Earned value analysis - presentation

“PMP® Certification Readiness”
Training Program
Module:Module:
Earned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget Forecasting
Ravikumar Kalose N, PMP®
http://www.propmacademy.com
1
ProPM Academy - 2011
"PMP® Exam Prep Course"
Understanding –
• Measurements - Subjective Vs Objective
• What is Earned Value (EV)
• Work Performance MeasurementsWork Performance Measurements
• Budget Forecasts
• Performance measurement parameters
• Various formulae and their interpretation
2
ProPM Academy - 2011
"PMP® Exam Prep Course"
Green
OR Red
?
What
IF…??
?
Can defend the
current Project
StatusAssertive
Relies on assumptions, interpretations based on
high level work status
Lack of any measured data and facts
Project Health (Red/Amber/Green) is debatable
and subjective
Relies on measured values derived from triple
constraints – Scope, Time and Cost
Project Status reported based on defined matrix
Unambiguous, No Assumptions
Easily understandable by Stakeholders
ProPM Academy - 2011
"PMP® Exam Prep Course" 3
An objective method to measure project progress based on triple
constraints (Scope, Time, Cost)
EV measurements helps to determine if a project is on track
EV is an indicator of current project performance
Provides early warnings and trends on any cost, schedule over runs
Earned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value Characteristics
Earned value indicates how much of “value” you have “earned” on
the project at any given point of time.
Helps determine variance against Planned Value (PV).
ProPM Academy - 2011
"PMP® Exam Prep Course" 4
Let us consider the following example to understand the
concepts better
An ERP implementation project for ABC company is estimated
to cost $500,000 with an estimated duration of 40 weeks.At
the end of 10 weeks the project is 20% complete withthe end of 10 weeks the project is 20% complete with
$150,000 being already spent on the project.
BAC =500,000,AC = 150,000
PV = 10/40*500,000 = 125,000
EV = 20/100*500,000 = 100,000
ProPM Academy - 2011
"PMP® Exam Prep Course" 5
ProPM Academy - 2011
"PMP® Exam Prep Course" 6
BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000
MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis
CV EV-AC -50,000 This indicates $50,000 has already been
additionally spent in excess of the project worth of
work up-to this point
ProPM Academy - 2011
"PMP® Exam Prep Course" 7
SV EV-PV -25000 The negative value indicates the project is lagging
behind its planned schedule.
CPI EV/AC 0.67 A value less than 1 indicates over utilization of
funds against the actual work. In this case the
project is earning $0.67 worth value for every $
spent, not a good sign.
SPI EV/PV 0.80 A value less than 1 indicates that the project is
behind planned schedule and progress has only
been at 80% .
SV
CV
ProPM Academy - 2011
"PMP® Exam Prep Course" 8
MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis
EAC BAC/CPI 746,268.65 The revised estimates now for project
completion based on current performance is
$746,268.65 as against planned $500,000.
BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000
CV = -50,000 SV = -25,000 CPI = 0.67 SPI = 0.80
ETC EAC-AC 596,268.65 The project would now require $596,268.65
to complete
VAC BAC-EAC -246,268.65 There is an additional $246,268.65 required
to complete the project compared to original
estimates
TCPI (BAC-EV)/(BAC-AC)
(WORK LEFT TO
DO)/ MONEY
REMAINING)
1.14 The project need to now perform at 1.14 times
in order to stay within the estimated budget
ProPM Academy - 2011
"PMP® Exam Prep Course" 9
Terminology Description Formula
Budget At CompletionBudget At CompletionBudget At CompletionBudget At Completion
(BAC)(BAC)(BAC)(BAC)
The original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project Cost NoneNoneNoneNone
Planned Value (PV)Planned Value (PV)Planned Value (PV)Planned Value (PV) Indicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD have
been completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work for
completion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any point
PV=Planned %PV=Planned %PV=Planned %PV=Planned %
complete X BACcomplete X BACcomplete X BACcomplete X BAC
Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual %
ProPM Academy - 2011
"PMP® Exam Prep Course" 10
Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual %
complete X BACcomplete X BACcomplete X BACcomplete X BAC
Actual Cost (AC)Actual Cost (AC)Actual Cost (AC)Actual Cost (AC) The actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of time AC= CumulativeAC= CumulativeAC= CumulativeAC= Cumulative
money spent till datemoney spent till datemoney spent till datemoney spent till date
Cost Variance (CV)Cost Variance (CV)Cost Variance (CV)Cost Variance (CV) The difference between howThe difference between howThe difference between howThe difference between how much was actuallymuch was actuallymuch was actuallymuch was actually
EarnedEarnedEarnedEarned and how muchand how muchand how muchand how much was awas awas awas actually spentctually spentctually spentctually spent
CV=EVCV=EVCV=EVCV=EV----ACACACAC
ScheduleScheduleScheduleSchedule Variance (SV)Variance (SV)Variance (SV)Variance (SV) The difference between plannedThe difference between plannedThe difference between plannedThe difference between planned schedule Vsschedule Vsschedule Vsschedule Vs
Actual ScheduleActual ScheduleActual ScheduleActual Schedule
SV = EVSV = EVSV = EVSV = EV----PVPVPVPV
TerminologyTerminologyTerminologyTerminology DescriptionDescriptionDescriptionDescription FormulaFormulaFormulaFormula
CostCostCostCost Performance IndexPerformance IndexPerformance IndexPerformance Index
(CPI)(CPI)(CPI)(CPI)
Indicates the projectIndicates the projectIndicates the projectIndicates the project performance for every $performance for every $performance for every $performance for every $
spentspentspentspent
CPCPCPCPI = EV / ACI = EV / ACI = EV / ACI = EV / AC
Schedule PerformanceSchedule PerformanceSchedule PerformanceSchedule Performance
Index (SPI)Index (SPI)Index (SPI)Index (SPI)
Indicate actualIndicate actualIndicate actualIndicate actual schedule progress of theschedule progress of theschedule progress of theschedule progress of the
against the planned scheduleagainst the planned scheduleagainst the planned scheduleagainst the planned schedule
SPI = EV / PVSPI = EV / PVSPI = EV / PVSPI = EV / PV
Estimate At CompletionEstimate At CompletionEstimate At CompletionEstimate At Completion
(EAC)(EAC)(EAC)(EAC)
TheTheTheThe revised project Budget for completionrevised project Budget for completionrevised project Budget for completionrevised project Budget for completion
based on current performance indicatorsbased on current performance indicatorsbased on current performance indicatorsbased on current performance indicators
EAC = BAC /EAC = BAC /EAC = BAC /EAC = BAC /
Cumulative CPICumulative CPICumulative CPICumulative CPI
Estimate To CompleteEstimate To CompleteEstimate To CompleteEstimate To Complete
(ETC)(ETC)(ETC)(ETC)
How much more (cost)How much more (cost)How much more (cost)How much more (cost) would be needed towould be needed towould be needed towould be needed to
complete the project based on currentcomplete the project based on currentcomplete the project based on currentcomplete the project based on current
performance indicatorsperformance indicatorsperformance indicatorsperformance indicators
ETC = EACETC = EACETC = EACETC = EAC –––– ACACACAC
Variance At CompletionVariance At CompletionVariance At CompletionVariance At Completion
(VAC)(VAC)(VAC)(VAC)
TheTheTheThe difference between the budgeted costdifference between the budgeted costdifference between the budgeted costdifference between the budgeted cost
and revised estimates based on currentand revised estimates based on currentand revised estimates based on currentand revised estimates based on current
performance indicatorsperformance indicatorsperformance indicatorsperformance indicators
VAC = BACVAC = BACVAC = BACVAC = BAC –––– EACEACEACEAC
ToToToTo----CompleteCompleteCompleteComplete
Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)
ProjectProjectProjectProject Performance required to be achievedPerformance required to be achievedPerformance required to be achievedPerformance required to be achieved
in order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budget
using the remaining fundsusing the remaining fundsusing the remaining fundsusing the remaining funds
TCPI = (BACTCPI = (BACTCPI = (BACTCPI = (BAC----EV) /EV) /EV) /EV) /
(BAC(BAC(BAC(BAC----AC)AC)AC)AC)
ProPM Academy - 2011
"PMP® Exam Prep Course" 11
Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) : If Negative, it is below planned performance,
If Positive, it is above planned performance
If Zero, it is exactly meeting the planned
performance
Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI): If the Value is less than 1, it is below planned
performance
If the Value is more than 1, it is above
planned performance
ProPM Academy - 2011
"PMP® Exam Prep Course" 12
planned performance
If the Value is equal to 1, it is exactly meeting
the planned performance
TCPI:TCPI:TCPI:TCPI: If the Value is Less than 1, it is above
planned performance
If the Value is more than 1, it is below
planned performance
If the Value is Equal to 1, it is exactly meeting
the planned performance
ProPM Academy - 2011
"PMP® Exam Prep Course" 13
http://www.propmacademy.com
Learn, Apply, Deliver, Succeed
Thank You
ProPM Academy - 2011
"PMP® Exam Prep Course" 14
Thank You
1 von 14

Recomendados

Earned Value Analysis von
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisDavid Edgeworth
509 views18 Folien
Earned Value Management von
Earned Value ManagementEarned Value Management
Earned Value ManagementAnand Subramaniam
40.3K views37 Folien
EVM of Project Management... von
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
4.2K views48 Folien
A simple approach to understanding Earned Value Management von
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
1.2K views15 Folien
Project cost control von
Project cost controlProject cost control
Project cost controlSourabh Modgil
13.7K views16 Folien
Earned value management von
Earned value managementEarned value management
Earned value managementAshif AR
1.5K views22 Folien

Más contenido relacionado

Was ist angesagt?

Earned value management (EVM) von
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
780 views19 Folien
7.4 Earned Value Analysis von
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
235 views8 Folien
Project Cost Management von
Project Cost ManagementProject Cost Management
Project Cost ManagementKateri Manglicmot
658 views42 Folien
Earned Value Analysis von
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
1.4K views17 Folien
Earned value analysis von
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
1.3K views12 Folien
Project controls von
Project controlsProject controls
Project controlsAshok Kumar
4K views57 Folien

Was ist angesagt?(20)

Earned value management (EVM) von Joshua Render
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
Joshua Render780 views
Earned Value Analysis von Saqib Raza
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza1.4K views
Earned value analysis von Nikhil Raj
Earned value analysisEarned value analysis
Earned value analysis
Nikhil Raj1.3K views
PMP Training - 07 project cost management von ejlp12
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp1232.6K views
Earned value management for Beginners von Shenin Hassan
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
Shenin Hassan 1.3K views
Introduce Project Management von guest90bddb
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
guest90bddb7K views
Project Management and Process von Muhammad Rehman
Project Management and ProcessProject Management and Process
Project Management and Process
Muhammad Rehman11.3K views
Project planning and scheduling techniques von Shivangi Saini
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini15.6K views

Similar a Earned value analysis - presentation

EVM+Formulas+for+Exam.pdf von
EVM+Formulas+for+Exam.pdfEVM+Formulas+for+Exam.pdf
EVM+Formulas+for+Exam.pdfManuelSilva202590
3 views1 Folie
PM - EVM - Dr Najam Abbas - OHT 1.pdf von
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
11 views14 Folien
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b... von
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
769 views1 Folie
Earned Value AnalysisTracking Project ProgressWh.docx von
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
7 views13 Folien
Track Project Performance - Earned Value Management von
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
8K views20 Folien
Project Health.doc von
Project Health.docProject Health.doc
Project Health.docPatricia Benedict, PMP
104 views1 Folie

Similar a Earned value analysis - presentation(20)

PM - EVM - Dr Najam Abbas - OHT 1.pdf von Najm Naqvi
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi11 views
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b... von Tipsographic . com
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com769 views
Earned Value AnalysisTracking Project ProgressWh.docx von sagarlesley
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley7 views
Track Project Performance - Earned Value Management von Baroness PM
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM8K views
PMP Key Exam Concepts - Formulas von Anand Bobade
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade5.9K views
A gentle introduction to earned value management systems (neutral) von Glen Alleman
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman9.2K views
A gentle introduction to earned value management systems (neutral) von Glen Alleman
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman2 views
Project Monitoring and Control von guy_davis
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
guy_davis14.8K views
The simple problem of schedule performance indices von Glen Alleman
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
Glen Alleman1.6K views
Cost Controlling And Forecasting of Project.pdf von Nabeel Ahmad
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad8 views
PMP - Math Formulas von gijoeusa
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
gijoeusa6.9K views

Último

PRELIMS ANSWER.pptx von
PRELIMS ANSWER.pptxPRELIMS ANSWER.pptx
PRELIMS ANSWER.pptxsouravkrpodder
50 views60 Folien
Education of marginalized and socially disadvantages segments.pptx von
Education of marginalized and socially disadvantages segments.pptxEducation of marginalized and socially disadvantages segments.pptx
Education of marginalized and socially disadvantages segments.pptxGarimaBhati5
43 views36 Folien
The Accursed House by Émile Gaboriau von
The Accursed House  by Émile GaboriauThe Accursed House  by Émile Gaboriau
The Accursed House by Émile GaboriauDivyaSheta
251 views15 Folien
Guess Papers ADC 1, Karachi University von
Guess Papers ADC 1, Karachi UniversityGuess Papers ADC 1, Karachi University
Guess Papers ADC 1, Karachi UniversityKhalid Aziz
99 views17 Folien
MercerJesse2.1Doc.pdf von
MercerJesse2.1Doc.pdfMercerJesse2.1Doc.pdf
MercerJesse2.1Doc.pdfjessemercerail
314 views5 Folien
unidad 3.pdf von
unidad 3.pdfunidad 3.pdf
unidad 3.pdfMarcosRodriguezUcedo
134 views38 Folien

Último(20)

Education of marginalized and socially disadvantages segments.pptx von GarimaBhati5
Education of marginalized and socially disadvantages segments.pptxEducation of marginalized and socially disadvantages segments.pptx
Education of marginalized and socially disadvantages segments.pptx
GarimaBhati543 views
The Accursed House by Émile Gaboriau von DivyaSheta
The Accursed House  by Émile GaboriauThe Accursed House  by Émile Gaboriau
The Accursed House by Émile Gaboriau
DivyaSheta251 views
Guess Papers ADC 1, Karachi University von Khalid Aziz
Guess Papers ADC 1, Karachi UniversityGuess Papers ADC 1, Karachi University
Guess Papers ADC 1, Karachi University
Khalid Aziz99 views
Career Building in AI - Technologies, Trends and Opportunities von WebStackAcademy
Career Building in AI - Technologies, Trends and OpportunitiesCareer Building in AI - Technologies, Trends and Opportunities
Career Building in AI - Technologies, Trends and Opportunities
WebStackAcademy45 views
Retail Store Scavenger Hunt.pptx von jmurphy154
Retail Store Scavenger Hunt.pptxRetail Store Scavenger Hunt.pptx
Retail Store Scavenger Hunt.pptx
jmurphy15452 views
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (FRIE... von Nguyen Thanh Tu Collection
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (FRIE...BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (FRIE...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (FRIE...
JRN 362 - Lecture Twenty-Three (Epilogue) von Rich Hanley
JRN 362 - Lecture Twenty-Three (Epilogue)JRN 362 - Lecture Twenty-Three (Epilogue)
JRN 362 - Lecture Twenty-Three (Epilogue)
Rich Hanley41 views
EILO EXCURSION PROGRAMME 2023 von info33492
EILO EXCURSION PROGRAMME 2023EILO EXCURSION PROGRAMME 2023
EILO EXCURSION PROGRAMME 2023
info33492202 views
Nelson_RecordStore.pdf von BrynNelson5
Nelson_RecordStore.pdfNelson_RecordStore.pdf
Nelson_RecordStore.pdf
BrynNelson546 views
Narration lesson plan von TARIQ KHAN
Narration lesson planNarration lesson plan
Narration lesson plan
TARIQ KHAN75 views

Earned value analysis - presentation

  • 1. “PMP® Certification Readiness” Training Program Module:Module: Earned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget ForecastingEarned Value and Budget Forecasting Ravikumar Kalose N, PMP® http://www.propmacademy.com 1 ProPM Academy - 2011 "PMP® Exam Prep Course"
  • 2. Understanding – • Measurements - Subjective Vs Objective • What is Earned Value (EV) • Work Performance MeasurementsWork Performance Measurements • Budget Forecasts • Performance measurement parameters • Various formulae and their interpretation 2 ProPM Academy - 2011 "PMP® Exam Prep Course"
  • 3. Green OR Red ? What IF…?? ? Can defend the current Project StatusAssertive Relies on assumptions, interpretations based on high level work status Lack of any measured data and facts Project Health (Red/Amber/Green) is debatable and subjective Relies on measured values derived from triple constraints – Scope, Time and Cost Project Status reported based on defined matrix Unambiguous, No Assumptions Easily understandable by Stakeholders ProPM Academy - 2011 "PMP® Exam Prep Course" 3
  • 4. An objective method to measure project progress based on triple constraints (Scope, Time, Cost) EV measurements helps to determine if a project is on track EV is an indicator of current project performance Provides early warnings and trends on any cost, schedule over runs Earned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value CharacteristicsEarned Value Characteristics Earned value indicates how much of “value” you have “earned” on the project at any given point of time. Helps determine variance against Planned Value (PV). ProPM Academy - 2011 "PMP® Exam Prep Course" 4
  • 5. Let us consider the following example to understand the concepts better An ERP implementation project for ABC company is estimated to cost $500,000 with an estimated duration of 40 weeks.At the end of 10 weeks the project is 20% complete withthe end of 10 weeks the project is 20% complete with $150,000 being already spent on the project. BAC =500,000,AC = 150,000 PV = 10/40*500,000 = 125,000 EV = 20/100*500,000 = 100,000 ProPM Academy - 2011 "PMP® Exam Prep Course" 5
  • 6. ProPM Academy - 2011 "PMP® Exam Prep Course" 6
  • 7. BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000 MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis CV EV-AC -50,000 This indicates $50,000 has already been additionally spent in excess of the project worth of work up-to this point ProPM Academy - 2011 "PMP® Exam Prep Course" 7 SV EV-PV -25000 The negative value indicates the project is lagging behind its planned schedule. CPI EV/AC 0.67 A value less than 1 indicates over utilization of funds against the actual work. In this case the project is earning $0.67 worth value for every $ spent, not a good sign. SPI EV/PV 0.80 A value less than 1 indicates that the project is behind planned schedule and progress has only been at 80% .
  • 8. SV CV ProPM Academy - 2011 "PMP® Exam Prep Course" 8
  • 9. MetricMetricMetricMetric FormulaFormulaFormulaFormula ValueValueValueValue AnalysisAnalysisAnalysisAnalysis EAC BAC/CPI 746,268.65 The revised estimates now for project completion based on current performance is $746,268.65 as against planned $500,000. BAC = 500,000BAC = 500,000BAC = 500,000BAC = 500,000 PV = 125,000PV = 125,000PV = 125,000PV = 125,000 EV = 100,000EV = 100,000EV = 100,000EV = 100,000 AC = 150,000AC = 150,000AC = 150,000AC = 150,000 CV = -50,000 SV = -25,000 CPI = 0.67 SPI = 0.80 ETC EAC-AC 596,268.65 The project would now require $596,268.65 to complete VAC BAC-EAC -246,268.65 There is an additional $246,268.65 required to complete the project compared to original estimates TCPI (BAC-EV)/(BAC-AC) (WORK LEFT TO DO)/ MONEY REMAINING) 1.14 The project need to now perform at 1.14 times in order to stay within the estimated budget ProPM Academy - 2011 "PMP® Exam Prep Course" 9
  • 10. Terminology Description Formula Budget At CompletionBudget At CompletionBudget At CompletionBudget At Completion (BAC)(BAC)(BAC)(BAC) The original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project CostThe original estimated (planned) project Cost NoneNoneNoneNone Planned Value (PV)Planned Value (PV)Planned Value (PV)Planned Value (PV) Indicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD haveIndicates amount of work which “SHOULD have been completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work forbeen completed” or “Authorized work for completion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any pointcompletion” as per plan at any point PV=Planned %PV=Planned %PV=Planned %PV=Planned % complete X BACcomplete X BACcomplete X BACcomplete X BAC Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual % ProPM Academy - 2011 "PMP® Exam Prep Course" 10 Earned Value (EV)Earned Value (EV)Earned Value (EV)Earned Value (EV) Actual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any pointActual work that is accomplished at any point EV= Actual %EV= Actual %EV= Actual %EV= Actual % complete X BACcomplete X BACcomplete X BACcomplete X BAC Actual Cost (AC)Actual Cost (AC)Actual Cost (AC)Actual Cost (AC) The actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of timeThe actual money spent at any point of time AC= CumulativeAC= CumulativeAC= CumulativeAC= Cumulative money spent till datemoney spent till datemoney spent till datemoney spent till date Cost Variance (CV)Cost Variance (CV)Cost Variance (CV)Cost Variance (CV) The difference between howThe difference between howThe difference between howThe difference between how much was actuallymuch was actuallymuch was actuallymuch was actually EarnedEarnedEarnedEarned and how muchand how muchand how muchand how much was awas awas awas actually spentctually spentctually spentctually spent CV=EVCV=EVCV=EVCV=EV----ACACACAC ScheduleScheduleScheduleSchedule Variance (SV)Variance (SV)Variance (SV)Variance (SV) The difference between plannedThe difference between plannedThe difference between plannedThe difference between planned schedule Vsschedule Vsschedule Vsschedule Vs Actual ScheduleActual ScheduleActual ScheduleActual Schedule SV = EVSV = EVSV = EVSV = EV----PVPVPVPV
  • 11. TerminologyTerminologyTerminologyTerminology DescriptionDescriptionDescriptionDescription FormulaFormulaFormulaFormula CostCostCostCost Performance IndexPerformance IndexPerformance IndexPerformance Index (CPI)(CPI)(CPI)(CPI) Indicates the projectIndicates the projectIndicates the projectIndicates the project performance for every $performance for every $performance for every $performance for every $ spentspentspentspent CPCPCPCPI = EV / ACI = EV / ACI = EV / ACI = EV / AC Schedule PerformanceSchedule PerformanceSchedule PerformanceSchedule Performance Index (SPI)Index (SPI)Index (SPI)Index (SPI) Indicate actualIndicate actualIndicate actualIndicate actual schedule progress of theschedule progress of theschedule progress of theschedule progress of the against the planned scheduleagainst the planned scheduleagainst the planned scheduleagainst the planned schedule SPI = EV / PVSPI = EV / PVSPI = EV / PVSPI = EV / PV Estimate At CompletionEstimate At CompletionEstimate At CompletionEstimate At Completion (EAC)(EAC)(EAC)(EAC) TheTheTheThe revised project Budget for completionrevised project Budget for completionrevised project Budget for completionrevised project Budget for completion based on current performance indicatorsbased on current performance indicatorsbased on current performance indicatorsbased on current performance indicators EAC = BAC /EAC = BAC /EAC = BAC /EAC = BAC / Cumulative CPICumulative CPICumulative CPICumulative CPI Estimate To CompleteEstimate To CompleteEstimate To CompleteEstimate To Complete (ETC)(ETC)(ETC)(ETC) How much more (cost)How much more (cost)How much more (cost)How much more (cost) would be needed towould be needed towould be needed towould be needed to complete the project based on currentcomplete the project based on currentcomplete the project based on currentcomplete the project based on current performance indicatorsperformance indicatorsperformance indicatorsperformance indicators ETC = EACETC = EACETC = EACETC = EAC –––– ACACACAC Variance At CompletionVariance At CompletionVariance At CompletionVariance At Completion (VAC)(VAC)(VAC)(VAC) TheTheTheThe difference between the budgeted costdifference between the budgeted costdifference between the budgeted costdifference between the budgeted cost and revised estimates based on currentand revised estimates based on currentand revised estimates based on currentand revised estimates based on current performance indicatorsperformance indicatorsperformance indicatorsperformance indicators VAC = BACVAC = BACVAC = BACVAC = BAC –––– EACEACEACEAC ToToToTo----CompleteCompleteCompleteComplete Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI)Performance Index (TCPI) ProjectProjectProjectProject Performance required to be achievedPerformance required to be achievedPerformance required to be achievedPerformance required to be achieved in order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budgetin order to stay within the original budget using the remaining fundsusing the remaining fundsusing the remaining fundsusing the remaining funds TCPI = (BACTCPI = (BACTCPI = (BACTCPI = (BAC----EV) /EV) /EV) /EV) / (BAC(BAC(BAC(BAC----AC)AC)AC)AC) ProPM Academy - 2011 "PMP® Exam Prep Course" 11
  • 12. Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) :Variance Value (SV, CV, VAC) : If Negative, it is below planned performance, If Positive, it is above planned performance If Zero, it is exactly meeting the planned performance Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI):Performance Index (CPI,SPI): If the Value is less than 1, it is below planned performance If the Value is more than 1, it is above planned performance ProPM Academy - 2011 "PMP® Exam Prep Course" 12 planned performance If the Value is equal to 1, it is exactly meeting the planned performance TCPI:TCPI:TCPI:TCPI: If the Value is Less than 1, it is above planned performance If the Value is more than 1, it is below planned performance If the Value is Equal to 1, it is exactly meeting the planned performance
  • 13. ProPM Academy - 2011 "PMP® Exam Prep Course" 13 http://www.propmacademy.com Learn, Apply, Deliver, Succeed
  • 14. Thank You ProPM Academy - 2011 "PMP® Exam Prep Course" 14 Thank You