This document summarizes a final construction management project presentation for a 13500 square meter site in Tel Aviv, Israel. It details the site layout, preparation work including earthworks and structural preparations. It outlines the schedule and crews for concrete works including forming, steel placement, and concrete casting over 12 days. It describes the Baranovich system for exterior cladding and stonework. It analyzes the costs of concrete, steel, and formwork. It determines that concrete works must be completed within 2 weeks per floor to finish the project in the required 36 months and that a crew of 20 workers using the Peri Skydeck system is needed. Finally, it outlines the project management structure.