1. PARTHA PRATIM GORAIN
: CBX-313, WARD-2A,ADIPUR, GUJARAT-370205
+91-7874935830,9978901240
; : Partha.svnit@gmail.com
CONSTRUCTION OPERATIONS MANAGEMENT PROFESSIONAL CIVIL
PROJECTS
Over 7.5 years of experience in delivering optimal results & Business value in high-growth environments
PROFILE
• CIVIL EXECUTION ,CHECKING REINFORCEMENT,SHUTTERING,CONCRETING WORKS
• PREPARATION OF BILL OF QUANTITY
• MANAGEMENT OF MANPOWER (SUB CONTRACTORS),MATERIAL AT SITE
• PREPARATION OF DAILY PROGRESS REPORT
• PREPARATION/CHECKING OF RA BILLS
• MATERIAL RECONCILATION
• RECORD KEEPING OF LATEST DRAWINGS
• ASSISTING QA/QC PERSONNEL IN CHECKING MEMBERS AND GET PROPER CORRECTION DONE.
• HANDING OVER OF STRUCTURES TO CLIENT.
PROFESSIONAL EXPERIENCE
• MAJOR PROJECTS HANDLED : WELSPUN CORP LIMITED ( CWC PIPE COATING PROJECT)
ESSAR REFINERY EXPANSION PROJECT
ESSAR SALAYA POWER PLANT
ESSAR BULK TERMINAL LIMITED
• STRUCTURES HANDLED: PIPERACKS, ISBL UNITS, CULVERTS,RCC CHIMNEY, SILO,
CONVEYOR STRUCTURE ETC.
• IT SKILLS: MS EXCEL, AUTOCAD
EDUCATIONAL DEVELOPMENT
B. Tech, (Civil Engineering), 2008
National Institute of Technology, Surat; 8.05 (CGPA)
XII, 2004
AISSCE; 81.33 %
X, 2002
AISSCE; 81.33 %
Date of Birth: 2nd October, 1986
Permanent Address: C/o Madhmita Gorai, At Manguria, P.o.-Manguria, Dist-Purulia (west Bengal)-723149
Languages Known: English, Hindi, Bengali & Gujarati
References: Available on Request
2. SL
NO.
ORGANISATION POSITION FROM
DATE
TO DATE JOB
DESCRIPTION
1 ESSAR PROJECTS (I)
LTD.
GET(CONFIRMATION-
PERIOD)
07-06-2008 06-12-2008 CIVIL JOBS AT
HMU
2 ESSAR PROJECTS (I)
LTD,
ASST MANAGER 07-12-2008 30-06-2010 PIPE RACK C,F
,HMU-1
3 ESSAR PROJECTS (I)
LTD.
DEPUTY MANAGER 01-07-2010 30-03-2012 RCC
CHIMNEY
SHELL
220MTRS
4 ESSAR PROJECTS (I)
LTD.
MANAGER 01-04-2012 30-04-2015 COAL
HANDLING
PLANT
5 Welspun Corp
limited
DEPUTY MANAGER 01-09-2015 PRESENT PIPE
COATING
PLANT
ANNEXURE
Project Concrete wet coating plant
Duration Since September 2015 to Present
Designation Deputy Manager
Responsibilities • Execution and supervised large amount of constructional Project, Records of measurement and
preparation of bill
• Implemented safety awareness, proper installation of safety equipment s and maintained safety
records.
• Administered site activities and ensured effective deployment of resources men, equipment and
materials-to maintain the desired pace of work execution
• Preparation of Detailed BOQ,
Project Coal Handling Plant, SALAYA Power Plant
Duration April 2012 TO April 2015
Designation Manager
Responsibilities • supervised large amount of constructional Project, Records of measurement and preparation of bill
• Implemented safety awareness, proper installation of safety equipment s and maintained safety
records.
• Administered site activities and ensured effective deployment of resources men, equipment and
materials-to maintain the desired pace of work execution
• Preparation of Detailed BOQ, Structural Fabrication and Erection
Project •220 Mtr Tall RCC chimney at VPCL.(power Plant Inside Refinery)
•SRU 83 Mtr Tall RCC chimney
•4 No s Fly ash Silo
•1 No s Intermediate Silo
•2 No s AOC and Salt water Silo at WWTF
•Lift Shaft at Electrical building
July 2010 to March 2012
Designation Deputy Manager
Responsibilities •Checked reinforcement of all the civil works like pile, pile cap, pier starter and retaining wall as per
3. BBS.
•Giving more importance to safety measures.
•Prepared the Client RA Bills, contractor billing &labor billing.
•Administered site activities and ensured effective deployment of resources men, equipment and
materials-to maintain the desired pace of work execution
•Civil Structural Erection, Painting and Refractory Jobs of 10 Slipform Structures.
Project Pipe Rack for Refinery Utility Area (800 Mtr length and 24 Mtr wide and 18 Mtr high)
Duration Dec 2008 to June 2010
Designation Asst. Manager
Responsibilities • Giving the quality of work to the client as per standards in all type of works.
• Overlooked the concrete work as per standards.
• Prepared the Contractor billing & labor billing.
• Prepared BBS for all type of works.
• Attended project review meetings
• Involved in civil works at Pipe Rack and ISBL unit For Refinery expansion Project.
Project EPC for ESSAR Oil Refinery Expansion Project at Vadinar, Gujarat.
Duration June 2008 to Dec 2008
Designation Graduate Engineer Trainee
Responsibilities • Checked Civil works at Mini HMU (hydrogen manufacturing unit)
• Checked the quality of interior works given to sub-contractor.
• Prepared the Contractor billing & labor billing