Practice notes for_quantity_surveyors_fi

Paraskevi (Evi) Alexopoulou
Paraskevi (Evi) AlexopoulouM.Sc. Civil Engineer/Design, Planning, Consulting um Freelance Engineering Practice

Educational Notes

PRACTICE
NOTES
FOR
QUANTITY
SURVEYORS
Final Accounts
21
Final AccountsPreface
General
The Final Account is a summary of the financial effect of all activities
carried out under the Contract. Clause 32.6 of the HKIS Standard Form
of Building Contract (2005 Edition) requires the Quantity Surveyor
to prepare the final account within the period stated in the Appendix
(normally 12 months from substantial completion of the whole of the
Works).
To provide effective post contract cost control and to expedite the
settlement of final accounts, Quantity Surveyors shall aim at having
periodic cost review meetings with the Contractors to settle the
valuation of instructed variations.
Variations
(A)	General
	 The Quantity Surveyor should conduct early evaluations of issued
variations for the following reasons:
	 (a)	 To enable close monitoring of the final contract sum;
	 (b)	 To identify early any potential claims related to the
		 variations;
	 (c)	 To provide the Contractor as early as possible with the
		 Quantity Surveyor’s assessed amount of the variation
		 to allow him to carry out cost control of his own
		 domestic sub-contracts; and
1.
	
2.
Preface
A Working Committee with representatives of the Hong Kong Institute of Surveyors,
the Association of Consultant Quantity Surveyors and the Hong Kong Construction
Association was set up in October 2010 to establish a set of Practice Notes for the benefit
of Quantity Surveying professionals in Hong Kong.
The Practice Notes are not intended to promulgate a standard of practice, but rather to
produce some basic guidelines for the following core practices :
1.	Tendering
2.	 Cost Control and Financial Statements
3.	 Valuation for Interim Payment Certificates
4.	 Valuation of Variations
5.	 Handling of Contractual Claims
6.	 Settlement of Final Account
As different client organisations will have their own procedures and requirements, the
Practice Notes, which are prepared mainly for private sector projects using the HKIA/HKIS
Standard Forms of Building Contract, should be adapted as appropriate.
The members of the Working Committee are: -
Representing the Hong Kong Institute of Surveyors
Mr. Raymond KONG
Mr. SO Chee Sing
Ms. Sandy TANG
Ms. Amelia FOK
Representing the Association of Consultant Quantity Surveyors
Mr. Kenneth POON
Mr. CHAN Choi Hing
Mr. Amen HOR
Representing the Hong Kong Construction Association
Mr. FUNG Chi Yiu
Mr. Patrick LO
Mr. YU Lap Chu
The Working Committee expresses its gratitude to the following HKIS members in the
Architectural Services Department and the Housing Authority for sharing their experience
in and knowledge of Quantity Surveying practice in the public sector for the improvement
of the document.
Professional Quantity Surveyor from the Architectural Services Department
Mr. Alvin CHAN
Professional Quantity Surveyor from the Housing Authority
Mr. James FUNG
Final Accounts
Final AccountsFinal Accounts
43
	 (d)	 To expedite final account settlement.
		 If the Quantity Surveyor does not issue an evaluation
		 for the issued variation, the Contractor should submit
		 his own assessment/claim to the Quantity Surveyor for
		 his notice and early processing.
(B)	Methodology
	 (a)	 Quantifying the changes
		 (i)	 the changes should be quantified by measuring
		 	 the “omissions” and the “additions” from the
		 	 drawings.
		 (ii)	 where changes are very substantial, a total
		 	 r e m e a s u r e m e n t o f t h e w o r k s a f f e c t e d m a y
		 	 be appropriate. In such cases, the Quantity
		 	 Surveyor and the Contractor should agree on
		 	 the set of drawings to be used.
	 (b)	 Assessing the rates
		 (i)	 the contract rates shall be used where the
		 	 works are of the same nature and are carried
		 	 out under the same circumstances;
		 (ii)	 If the works are similar but not the same, the
		 	 contract rate should be used as the basis for
		 	 forming a pro-rata rate;
		 (iii)	 If the works are of a different nature, a fair
		 	 valuation should be made for the variation
		 	 works using “star” rates.
(C)	 Verbal Instructions
	 Unless the Contract states otherwise, the Quantity Surveyor
	 should note that Confirmation of Verbal 	Instructions are also
	 variations and should be treated in the same manner as
	 Architect’s Instructions.
	 If all variations are to be covered only via written Architect’s
	 Instruction, the Quantity Surveyor should remind the Contractor
	 that those changes cannot be included in the final account
	 measurement and that he has to separately seek an appropriate
	 Architect’s Instruction.
(D)	 Taking Site Measurements
	 When visiting site to take measurements, the Quantity Surveyor
	 should :-
	 (a) record the Quantity Surveyor’s name, company, time of
		 arrival and departure in the site visitor’s book (if any).
	 (b)	 ensure that all measurements taken are properly recorded.
		 Each page entry must have the date of the 	m e a s u r e m e n t
		 recorded against it.
	 (c)	 if measurements are jointly taken with the Contractor,
		 request the Contractor to initial against the measurements.
Final AccountsFinal Accounts
65
(E)	 Cost Review Meetings
	 The Quantity Surveyor should arrange regular Cost Review
Meetings with the Contractor throughout the construction and
final account periods to discuss and finalise the financial effect of
the variations and other claims by the Contractor. The Architect,
Engineer or the Project Manager should be invited to attend the
Cost Review Meetings when necessary to resolve ambiguities as
to the scope of variations or disagreements on its actual effect on
the Works.
Remeasurements
The Quantity Surveyor should remeasure all provisional quantities in
the Bills of Quantities as soon as the “For Construction” drawings are
issued to the Contractor for implementation.
A copy of the remeasurement, duly priced should be issued to the
Contractor for his information as soon as it is available.
It is bad practice to wait for works to be completed before doing the
remeasurement. Early remeasurement once construction drawings
are available will give a chance to the Client to revise the design if the
remeasurement shows a budget over-run.
Contractual Claims
(A)	General
	 The validity of contractual claims depends a lot on the wording
of the contract conditions and specification clauses. Reference
should be made to the specific clauses of the contract being used
in order to approach a claim correctly.
	 A fundamental principle of any claim for a loss/expense claim by
a Contractor is that the onus lies with the Contractor to establish
the following facts in his submission to the Architect and Quantity
Surveyor :
	 (a) That an instruction amounting to a variation has been validly
		 issued and acted upon;
	 (b) The date of issue and receipt of the variation instruction;
	 (c) The nature of the variation;
	 (d) The time required to carry out the work pursuant to the
		 instruction;
	 (e) That the carrying out of the variation instruction affected
		 regular progress of the works which would not otherwise
		 have been affected;
	 (f) The extent to which the work was affected as a direct result
		 of the carrying out of the variation;
	 (g) Sufficient particulars of the direct loss and/or expense
		 suffered or incurred directly resulting from the variation;
	 (h) That the Contractor made a proper and timely application to
		 the Architect in respect of direct loss and/or expense.
	 The above list is not exhaustive and claims can always be made
under other contractual grounds. (See also Good Practice Notes
on Handling Contractual Claims for more details.)
3.
4.
Final AccountsFinal Accounts
87
(B)	 Extension of Time
	 Claims for extensions to the contract time are considered and
decided by the Architect. However, it is not uncommon for the
Architect to request the Quantity Surveyor to advise on the
contractual validity of the claims.
	 The following principles should be observed :
	 (a) The Contractor should "upon it becoming apparent that the
		 progress of the Works is delayed" give written notice of the
		 cause of delay to the Architect.
	 (b) The event delayed must be "critical" (i.e. the activity in
		 question must lie on the project’s critical path).
	 (c) Whether an event caused a delay or not should be decided
		 by reference to the actual progress on Site, not to the
		 original programme prepared at commencement of work.
	 Whether or not a Contractor is entitled to an extension of time
is to be decided by the Architect. The Quantity Surveyor should
only make suggestions for consideration if requested by the
Architect to do so.
(C)	 Prolongation Claims
	 When assessing prolongation claims, the Quantity Surveyor
should differentiate the extension of time granted under certain
events (commonly known as neutral events) for which the
Contractor may be entitled to an extension of time, but not
prolongation costs, such as the following:
	 •	 force majeure;
	 •	 inclement weather;
	 •	 fire;
	 •	 civil commotion, etc.;
	 As a general rule the Employer will only be liable for loss and
expense incurred by the Contractor when it is caused by acts for
which the Employer or his agents are responsible.
Nominated Sub-Contracts/Supply Contracts
If it is within his scope of services, the Quantity Surveyor should
prepare the final account statements for the Nominated Sub-contracts
and Nominated Supply Contracts for incorporation within the
Contractor’s final account for the whole of the works.
The Quantity Surveyor should follow the same guidelines given for
preparing the Contractor’s final account when handling the final
accounts for the Nominated Sub-contracts and Nominated Supply
Contracts.
Agreement of the Final Account
During the cost review meetings, the Quantity Surveyor and the
Contractor will exchange comments on each other’s assessment and
try to reach agreement on the appropriate financial figure for each
item of change.
Assessments done by the Quantity Surveyor should be issued to the
Contractor in advance of the meeting with a request that they mark
in red their comments and return to the Quantity Surveyor before
the meetings are held. Vice versa, the Quantity Surveyor should
check quotations submitted by the Contractor and mark in red their
comments and return to them before the meetings for their advance
information.
It should be noted that the Quantity Surveyor’s duty regarding the
Final Account is primarily to make fair and proper assessments of all
changes made in accordance with the contract provisions. Whether
the assessments are agreeable to the Contractor should not be a factor
influencing the Quantity Surveyor’s assessment.
5.
6.
Final AccountsFinal Accounts
109
Most Standard Forms of Contract have a provision that the Contractor
should submit all his claims and substantiations within a certain
period. The Quantity Surveyor should check this period and formally
write to the Contractor advising him to comply with it as the Quantity
Surveyor may refuse to accept any further submissions after this date.
When all claims and substantiations made have been taken into
consideration by the Quantity Surveyor and negotiations held with the
Contractor prove to be of no avail, the Quantity Surveyor may seek the
Client’s consent and support before proceeding to unilaterally close
out the final account.
A report on the non-agreed items should be prepared listing the items,
the Contractor’s figures versus the Quantity Surveyor’s assessed
figures, the arguments given by the Contractor and the Quantity
Surveyor’s judgments on why their arguments were not accepted.
Note that it is not normally a contractual requirement that the Final
Account needs to be agreed by the Contractor. This is only good
practice. In situations where agreement cannot be reached, the
Quantity Surveyor should prepare a Recommended Final Account
incorporating a report on non-agreed items and issue it to the Client
with a recommendation to either intervene to reach a settlement with
the Contractor or unilaterally close out the Final Account by issuing
the Final Certificate.
Final Account Format
The Final Account should clearly list all items that have a financial
effect on the original contract sum.
Extra care should be taken in writing the item descriptions to give a
brief indication of what changes were actually involved. Do not just
copy the headings of the Architect’s Instructions as these tend to be
very general.
The common headings to be found in a Final Account will include :
1. Architect’s Instructions
2. Confirmation of Verbal Instructions
3. Prime Cost Rates Adjustment
4. Prime Cost Sums Adjustment
5. Provisional Sums Adjustment
6. Provisional Quantities Adjustment
7. Fluctuations Adjustment
8. Contractual Claims
9. Others
The Agreement and Issuance of the Final Account
Under normal circumstances, the Final Account should either be
agreed between the Contractor and the Quantity Surveyor or the
Quantity Surveyor should issue their Final Account Recommendation
within 12 months of substantial completion of the whole of the Works.
7.
8.
Nov. 2012

Recomendados

1 regatta quay rehab boq 20120420 blank von
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank Thomas Magatu
2.9K views15 Folien
Professional practice 2 von
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
1K views17 Folien
Boq of khadeja storage tank, well, and booster pumping station von
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
9.3K views27 Folien
Standard bill of quantities von
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
117K views554 Folien
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS von
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSLenson Mhango
18.2K views29 Folien
Measuring tendering and estimating for CBE von
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBESahl Buhary
4.5K views33 Folien

Más contenido relacionado

Was ist angesagt?

Bills of quantities von
Bills of quantitiesBills of quantities
Bills of quantitiesAr.Vijay Kumar
28.3K views8 Folien
Commercial Management Scenarios von
Commercial Management ScenariosCommercial Management Scenarios
Commercial Management ScenariosCKMCforstudents
2K views12 Folien
Questions in notes von
Questions in notesQuestions in notes
Questions in notesCKMCforstudents
3.8K views13 Folien
DD STAGE COST ESTIMATE SECTION 1 (J102) (1) von
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)Gayan Kalpitha Perera
2.5K views331 Folien
WORKS MANAGEMENT IN CPWD PART-I von
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IAvinash Kumar Gupta
9.1K views64 Folien
PP2 - Assignment von
PP2 - Assignment PP2 - Assignment
PP2 - Assignment lucaschinsheng
1.5K views22 Folien

Was ist angesagt?(18)

Pp2 group assignment von lohwenjun
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
lohwenjun635 views
Preparation of bill sandeep von Sandeep Yadav
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
Sandeep Yadav4.7K views
General notes to BSR BUILDING SCHEDULE OF RATES von R.R.G.S Bandara
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
R.R.G.S Bandara42.5K views
Pp1 seminar von wendyteosy
Pp1 seminarPp1 seminar
Pp1 seminar
wendyteosy1.5K views
Bo Q Preamble Td2 3 Jan 20 von guest5980d0
Bo Q Preamble Td2 3  Jan 20Bo Q Preamble Td2 3  Jan 20
Bo Q Preamble Td2 3 Jan 20
guest5980d07.3K views
Estimation (power point) von Waqas Aslam
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam32.3K views
Cost estimates & contract documents ce224 pdf von Saqib Imran
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
Saqib Imran755 views

Similar a Practice notes for_quantity_surveyors_fi

PP Seminar Tutorial 7 von
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
118 views28 Folien
Seminar Presentation Slides (Chapter 2) von
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
426 views17 Folien
Cbb512 examination november_2011 von
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
237 views6 Folien
Key terms to consider when negotiating cm at-risk agreements + gmp amendments von
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
841 views37 Folien
Types of contracts von
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
412 views24 Folien
MODULE 5.pptx von
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptxNithyaPotterhead
10 views25 Folien

Similar a Practice notes for_quantity_surveyors_fi(20)

PP Seminar Tutorial 7 von Farah Sham
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham118 views
Seminar Presentation Slides (Chapter 2) von Melvin Lim
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim426 views
Cbb512 examination november_2011 von Maatla Moadi
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
Maatla Moadi237 views
Types of contracts von MANNU KUMAR
Types of contracts   Types of contracts
Types of contracts
MANNU KUMAR412 views
Contract payment and variation von Vj NiroSh
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh1.6K views
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1 von Antonio Coladarce
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce10K views
CFW Supply Chain Development von Rae Davies
CFW Supply Chain DevelopmentCFW Supply Chain Development
CFW Supply Chain Development
Rae Davies594 views
MEASUREMENT PDF von IDHAMUKI
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
IDHAMUKI93.9K views
Effective contract administration may 2014 von SHKLaw
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw1.5K views

Último

Stone Masonry and Brick Masonry.pdf von
Stone Masonry and Brick Masonry.pdfStone Masonry and Brick Masonry.pdf
Stone Masonry and Brick Masonry.pdfMohammed Abdullah Laskar
19 views6 Folien
What is Unit Testing von
What is Unit TestingWhat is Unit Testing
What is Unit TestingSadaaki Emura
23 views25 Folien
Electrical Crimping von
Electrical CrimpingElectrical Crimping
Electrical CrimpingIwiss Tools Co.,Ltd
20 views22 Folien
How I learned to stop worrying and love the dark silicon apocalypse.pdf von
How I learned to stop worrying and love the dark silicon apocalypse.pdfHow I learned to stop worrying and love the dark silicon apocalypse.pdf
How I learned to stop worrying and love the dark silicon apocalypse.pdfTomasz Kowalczewski
23 views66 Folien
Update 42 models(Diode/General ) in SPICE PARK(DEC2023) von
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Tsuyoshi Horigome
18 views16 Folien
NEW SUPPLIERS SUPPLIES (copie).pdf von
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdfgeorgesradjou
7 views30 Folien

Último(20)

How I learned to stop worrying and love the dark silicon apocalypse.pdf von Tomasz Kowalczewski
How I learned to stop worrying and love the dark silicon apocalypse.pdfHow I learned to stop worrying and love the dark silicon apocalypse.pdf
How I learned to stop worrying and love the dark silicon apocalypse.pdf
Update 42 models(Diode/General ) in SPICE PARK(DEC2023) von Tsuyoshi Horigome
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
NEW SUPPLIERS SUPPLIES (copie).pdf von georgesradjou
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdf
georgesradjou7 views
MSA Website Slideshow (16).pdf von msaucla
MSA Website Slideshow (16).pdfMSA Website Slideshow (16).pdf
MSA Website Slideshow (16).pdf
msaucla39 views
Design and analysis of a new undergraduate Computer Engineering degree – a me... von WaelBadawy6
Design and analysis of a new undergraduate Computer Engineering degree – a me...Design and analysis of a new undergraduate Computer Engineering degree – a me...
Design and analysis of a new undergraduate Computer Engineering degree – a me...
WaelBadawy652 views
fakenews_DBDA_Mar23.pptx von deepmitra8
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptx
deepmitra812 views
Machine Element II Course outline.pdf von odatadese1
Machine Element II Course outline.pdfMachine Element II Course outline.pdf
Machine Element II Course outline.pdf
odatadese16 views
2_DVD_ASIC_Design_FLow.pdf von Usha Mehta
2_DVD_ASIC_Design_FLow.pdf2_DVD_ASIC_Design_FLow.pdf
2_DVD_ASIC_Design_FLow.pdf
Usha Mehta14 views

Practice notes for_quantity_surveyors_fi

  • 2. 21 Final AccountsPreface General The Final Account is a summary of the financial effect of all activities carried out under the Contract. Clause 32.6 of the HKIS Standard Form of Building Contract (2005 Edition) requires the Quantity Surveyor to prepare the final account within the period stated in the Appendix (normally 12 months from substantial completion of the whole of the Works). To provide effective post contract cost control and to expedite the settlement of final accounts, Quantity Surveyors shall aim at having periodic cost review meetings with the Contractors to settle the valuation of instructed variations. Variations (A) General The Quantity Surveyor should conduct early evaluations of issued variations for the following reasons: (a) To enable close monitoring of the final contract sum; (b) To identify early any potential claims related to the variations; (c) To provide the Contractor as early as possible with the Quantity Surveyor’s assessed amount of the variation to allow him to carry out cost control of his own domestic sub-contracts; and 1. 2. Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong Construction Association was set up in October 2010 to establish a set of Practice Notes for the benefit of Quantity Surveying professionals in Hong Kong. The Practice Notes are not intended to promulgate a standard of practice, but rather to produce some basic guidelines for the following core practices : 1. Tendering 2. Cost Control and Financial Statements 3. Valuation for Interim Payment Certificates 4. Valuation of Variations 5. Handling of Contractual Claims 6. Settlement of Final Account As different client organisations will have their own procedures and requirements, the Practice Notes, which are prepared mainly for private sector projects using the HKIA/HKIS Standard Forms of Building Contract, should be adapted as appropriate. The members of the Working Committee are: - Representing the Hong Kong Institute of Surveyors Mr. Raymond KONG Mr. SO Chee Sing Ms. Sandy TANG Ms. Amelia FOK Representing the Association of Consultant Quantity Surveyors Mr. Kenneth POON Mr. CHAN Choi Hing Mr. Amen HOR Representing the Hong Kong Construction Association Mr. FUNG Chi Yiu Mr. Patrick LO Mr. YU Lap Chu The Working Committee expresses its gratitude to the following HKIS members in the Architectural Services Department and the Housing Authority for sharing their experience in and knowledge of Quantity Surveying practice in the public sector for the improvement of the document. Professional Quantity Surveyor from the Architectural Services Department Mr. Alvin CHAN Professional Quantity Surveyor from the Housing Authority Mr. James FUNG Final Accounts
  • 3. Final AccountsFinal Accounts 43 (d) To expedite final account settlement. If the Quantity Surveyor does not issue an evaluation for the issued variation, the Contractor should submit his own assessment/claim to the Quantity Surveyor for his notice and early processing. (B) Methodology (a) Quantifying the changes (i) the changes should be quantified by measuring the “omissions” and the “additions” from the drawings. (ii) where changes are very substantial, a total r e m e a s u r e m e n t o f t h e w o r k s a f f e c t e d m a y be appropriate. In such cases, the Quantity Surveyor and the Contractor should agree on the set of drawings to be used. (b) Assessing the rates (i) the contract rates shall be used where the works are of the same nature and are carried out under the same circumstances; (ii) If the works are similar but not the same, the contract rate should be used as the basis for forming a pro-rata rate; (iii) If the works are of a different nature, a fair valuation should be made for the variation works using “star” rates. (C) Verbal Instructions Unless the Contract states otherwise, the Quantity Surveyor should note that Confirmation of Verbal Instructions are also variations and should be treated in the same manner as Architect’s Instructions. If all variations are to be covered only via written Architect’s Instruction, the Quantity Surveyor should remind the Contractor that those changes cannot be included in the final account measurement and that he has to separately seek an appropriate Architect’s Instruction. (D) Taking Site Measurements When visiting site to take measurements, the Quantity Surveyor should :- (a) record the Quantity Surveyor’s name, company, time of arrival and departure in the site visitor’s book (if any). (b) ensure that all measurements taken are properly recorded. Each page entry must have the date of the m e a s u r e m e n t recorded against it. (c) if measurements are jointly taken with the Contractor, request the Contractor to initial against the measurements.
  • 4. Final AccountsFinal Accounts 65 (E) Cost Review Meetings The Quantity Surveyor should arrange regular Cost Review Meetings with the Contractor throughout the construction and final account periods to discuss and finalise the financial effect of the variations and other claims by the Contractor. The Architect, Engineer or the Project Manager should be invited to attend the Cost Review Meetings when necessary to resolve ambiguities as to the scope of variations or disagreements on its actual effect on the Works. Remeasurements The Quantity Surveyor should remeasure all provisional quantities in the Bills of Quantities as soon as the “For Construction” drawings are issued to the Contractor for implementation. A copy of the remeasurement, duly priced should be issued to the Contractor for his information as soon as it is available. It is bad practice to wait for works to be completed before doing the remeasurement. Early remeasurement once construction drawings are available will give a chance to the Client to revise the design if the remeasurement shows a budget over-run. Contractual Claims (A) General The validity of contractual claims depends a lot on the wording of the contract conditions and specification clauses. Reference should be made to the specific clauses of the contract being used in order to approach a claim correctly. A fundamental principle of any claim for a loss/expense claim by a Contractor is that the onus lies with the Contractor to establish the following facts in his submission to the Architect and Quantity Surveyor : (a) That an instruction amounting to a variation has been validly issued and acted upon; (b) The date of issue and receipt of the variation instruction; (c) The nature of the variation; (d) The time required to carry out the work pursuant to the instruction; (e) That the carrying out of the variation instruction affected regular progress of the works which would not otherwise have been affected; (f) The extent to which the work was affected as a direct result of the carrying out of the variation; (g) Sufficient particulars of the direct loss and/or expense suffered or incurred directly resulting from the variation; (h) That the Contractor made a proper and timely application to the Architect in respect of direct loss and/or expense. The above list is not exhaustive and claims can always be made under other contractual grounds. (See also Good Practice Notes on Handling Contractual Claims for more details.) 3. 4.
  • 5. Final AccountsFinal Accounts 87 (B) Extension of Time Claims for extensions to the contract time are considered and decided by the Architect. However, it is not uncommon for the Architect to request the Quantity Surveyor to advise on the contractual validity of the claims. The following principles should be observed : (a) The Contractor should "upon it becoming apparent that the progress of the Works is delayed" give written notice of the cause of delay to the Architect. (b) The event delayed must be "critical" (i.e. the activity in question must lie on the project’s critical path). (c) Whether an event caused a delay or not should be decided by reference to the actual progress on Site, not to the original programme prepared at commencement of work. Whether or not a Contractor is entitled to an extension of time is to be decided by the Architect. The Quantity Surveyor should only make suggestions for consideration if requested by the Architect to do so. (C) Prolongation Claims When assessing prolongation claims, the Quantity Surveyor should differentiate the extension of time granted under certain events (commonly known as neutral events) for which the Contractor may be entitled to an extension of time, but not prolongation costs, such as the following: • force majeure; • inclement weather; • fire; • civil commotion, etc.; As a general rule the Employer will only be liable for loss and expense incurred by the Contractor when it is caused by acts for which the Employer or his agents are responsible. Nominated Sub-Contracts/Supply Contracts If it is within his scope of services, the Quantity Surveyor should prepare the final account statements for the Nominated Sub-contracts and Nominated Supply Contracts for incorporation within the Contractor’s final account for the whole of the works. The Quantity Surveyor should follow the same guidelines given for preparing the Contractor’s final account when handling the final accounts for the Nominated Sub-contracts and Nominated Supply Contracts. Agreement of the Final Account During the cost review meetings, the Quantity Surveyor and the Contractor will exchange comments on each other’s assessment and try to reach agreement on the appropriate financial figure for each item of change. Assessments done by the Quantity Surveyor should be issued to the Contractor in advance of the meeting with a request that they mark in red their comments and return to the Quantity Surveyor before the meetings are held. Vice versa, the Quantity Surveyor should check quotations submitted by the Contractor and mark in red their comments and return to them before the meetings for their advance information. It should be noted that the Quantity Surveyor’s duty regarding the Final Account is primarily to make fair and proper assessments of all changes made in accordance with the contract provisions. Whether the assessments are agreeable to the Contractor should not be a factor influencing the Quantity Surveyor’s assessment. 5. 6.
  • 6. Final AccountsFinal Accounts 109 Most Standard Forms of Contract have a provision that the Contractor should submit all his claims and substantiations within a certain period. The Quantity Surveyor should check this period and formally write to the Contractor advising him to comply with it as the Quantity Surveyor may refuse to accept any further submissions after this date. When all claims and substantiations made have been taken into consideration by the Quantity Surveyor and negotiations held with the Contractor prove to be of no avail, the Quantity Surveyor may seek the Client’s consent and support before proceeding to unilaterally close out the final account. A report on the non-agreed items should be prepared listing the items, the Contractor’s figures versus the Quantity Surveyor’s assessed figures, the arguments given by the Contractor and the Quantity Surveyor’s judgments on why their arguments were not accepted. Note that it is not normally a contractual requirement that the Final Account needs to be agreed by the Contractor. This is only good practice. In situations where agreement cannot be reached, the Quantity Surveyor should prepare a Recommended Final Account incorporating a report on non-agreed items and issue it to the Client with a recommendation to either intervene to reach a settlement with the Contractor or unilaterally close out the Final Account by issuing the Final Certificate. Final Account Format The Final Account should clearly list all items that have a financial effect on the original contract sum. Extra care should be taken in writing the item descriptions to give a brief indication of what changes were actually involved. Do not just copy the headings of the Architect’s Instructions as these tend to be very general. The common headings to be found in a Final Account will include : 1. Architect’s Instructions 2. Confirmation of Verbal Instructions 3. Prime Cost Rates Adjustment 4. Prime Cost Sums Adjustment 5. Provisional Sums Adjustment 6. Provisional Quantities Adjustment 7. Fluctuations Adjustment 8. Contractual Claims 9. Others The Agreement and Issuance of the Final Account Under normal circumstances, the Final Account should either be agreed between the Contractor and the Quantity Surveyor or the Quantity Surveyor should issue their Final Account Recommendation within 12 months of substantial completion of the whole of the Works. 7. 8.