Pharmaceutical HVAC (Heating, ventilating, and air conditioning; also heating, ventilation, and air conditioning) system
1. What is HVAC ?
Heating,Ventilation, and
Air Conditioning
5/2/2015 1PALASH CHANDRA DAS (www.uscgmp.com)
By Palash Chandra Das
http://www.uscgmp.com
2. Introduction
The HVAC system is one of the more critical systems affecting
the ability of a pharmaceutical facility to meet its key
objectives. HVAC systems which are properly designed, built,
operated, and maintained can help ensure the quality of
product manufactured in that facility, improve reliability, and
reduce both first cost and ongoing operating costs of the
facility.
The design of HVAC systems for the pharmaceutical industry
requires special considerations beyond those for most other
industries, particularly in regards to cleanroom applications.
5/2/2015 2PALASH CHANDRA DAS (www.uscgmp.com)
3. How the concept came?
Most people live in homes with equipment incorporated into
the building to keep them comfortable.They have windows to
allow natural ventilation and heating and cooling s
We have the same goal in our pharmaceutical manufacturing
workplace – to make people comfortable, but we also have
the more exacting requirement to control the impact of the
environment on the finished product. systems to maintain
desired temperatures.
5/2/2015 3PALASH CHANDRA DAS (www.uscgmp.com)
4. Why is the requirement?
Air temperature at the critical location may affect
product or product contact surfaces
Relative humidity of the air at the critical location
may affect product moisture content, or may affect
product contact surfaces (via corrosion, etc.)
Airborne contamination at the critical location (may
affect product purity or product contact surfaces)
“Some variables, such as local contaminants, depend
on other HVAC variables such as room pressure, air
changes, airflow volume, airflow direction and
velocity, and air filter efficiency”
5/2/2015 4PALASH CHANDRA DAS (www.uscgmp.com)
5. Background of design:
Operational feature
How to Design?
Major component?
How it is works?
Automation with BMS/EMS
5/2/2015 5PALASH CHANDRA DAS (www.uscgmp.com)
6. Operational feature
It provides the conditioning of the environment through the
control of
Temperature, Relative Humidity, Air Movement and air quality
- including fresh air, airborne particles, and vapors.
HVAC systems can increase or decrease temperature, increase
or reduce the moisture or humidity in the air, decrease the
level of particulate or gaseous contaminants in the air.
These abilities are employed for comfort and to protect people
and product.
5/2/2015 6PALASH CHANDRA DAS (www.uscgmp.com)
7. How to Design?
Once through
Recirculating systems
Exhaust (Extract) system
5/2/2015 7PALASH CHANDRA DAS (www.uscgmp.com)
11. How many AHU’s should be used?
Use of multiple units improves reliability of the area – it would
be unusual for all of the units to fail.
The use of multiple smaller units might make air balancing
easier
The use of multiple smaller units means that the main
distribution ducts are smaller, making then easier to route in
small ceiling voids.
It is easier to make modifications to parts of the facility in
future and upgrade a small unit than change a large single unit
Use of multiple units allows for easier separation of areas
within a multi-product concurrent manufacturing plant.
5/2/2015 11PALASH CHANDRA DAS (www.uscgmp.com)
13. How it is works?
5/2/2015 13PALASH CHANDRA DAS (www.uscgmp.com)
14. How it auto controls
5/2/2015 14PALASH CHANDRA DAS (www.uscgmp.com)
15. Key feature of BMS
Monitor, control and display the room parameter of HVAC
system like temperature, relative humidity and room pressure as
applicable
Operation of AHU’s
Time scheduling of AHU’s.
Preventive maintenance scheduling.
Differential pressure monitoring across filters ( F-6, F-9 and H-13)
Alarm and audit log features
5/2/2015 15PALASH CHANDRA DAS (www.uscgmp.com)
16. Qualification:
Concept of Design aspect: From URS to DQ
Concept of Qualification
BMS integration and CVS?
Operational aspects
Operation
Maintenance
5/2/2015 16PALASH CHANDRA DAS (www.uscgmp.com)
17. Concept of Design aspect
For HVAC systems in a pharmaceutical environment, user
requirements are developed as a result of gathering relevant
data with regards to the following:
Process – Critical environmental parameters that must be
achieved and maintained.
Quality – Regulatory guidance and quality principles to guide
decision making on HVAC parameters that can have product
impact.
Operations – Proper environment for the working conditions
that impact the HVAC design.
Maintenance – Provide input on critical aspects of the HVAC
design that would ensure a lowTCO
5/2/2015 17PALASH CHANDRA DAS (www.uscgmp.com)
19. CQA/CQP
Typical HVAC performance parameters that impact CQA/CQP are:
HEPA filter test data
Air change rates/airflow volumes
Area differential pressures
Temperature
Relative humidity
Particle count
Typical HVAC-related room performance parameters which impact CQA/CQP
are:
Clean up & Room recovery time
Total particle count (area classification)
MicrobialViable particulate test results – in air
MicrobialViable particulate test results – swab tests
5/2/2015 19PALASH CHANDRA DAS (www.uscgmp.com)
20. Critical Quality Attributes/Parameters
(CQA/CQP)
How to monitored. Some examples may be:
Humidity is monitored by an independent SCADA based
environmental monitoring system.
Temperature is monitored by an independent SCADA based
environmental monitoring system.
Air quality is monitored by a routine test using a particle
counter to per ISO CEN 14644 for all particles., and microbial
Microbial monitoring for viable particles is tested per local
SOP.
Room pressure differentials are monitored by an independent
SCADA based environmental monitoring system
5/2/2015 20PALASH CHANDRA DAS (www.uscgmp.com)
21. Critical Quality Attributes/Parameters
(CQA/CQP)
Define how the are achieved, and any associated equipment risks of failure and the probability
of detection of those failures. Some examples may be:
Humidity control is achieved by either dehumidifying the air through cooling below its dew
point to remove moisture, or by adding moisture with a steam humidifier.As humidity is
continuously monitored by a verified system it is considered adequate to commission the
humidifier/dehumidifier system, and maintain it under engineering change control
Temperature control is obtained through the use of the heating or cooling coils. As
temperature is continuously monitored by a verified system it is considered adequate to
commission the heat system, and maintain it under engineering change control.
Air quality is obtained through the final HEPA grade filter which is leak tested annually, with
a particle count conducted periodically. As the HEPA filter integrity is not continuously
monitored, and is directly responsible for this aspect of the system performance it will be
verified and maintained under quality change control.
Room pressure differentials are achieved through the leakage from and to the conditioned
space from adjacent areas and via the HVAC system balance. As pressure is continuously
monitored by a verified system it is considered adequate to commission the duct/damper
system and maintain it under engineering change control.
5/2/2015 21PALASH CHANDRA DAS (www.uscgmp.com)
24. Concept of Qualification
QUALIFICATION APPROACH
Following tests are to be carried out as a part of area qualification of
HVAC system:
Installed HEPA filter integrity
Air velocity and air changes per hour calculation
Air flow pattern visualization study using visible smoke
Room Differential Pressure monitoring
RoomTemperature and Relative Humidity Monitoring
Air Borne particle count (non-viable)
Active and passive Microbial Monitoring (By settle plate/Air sampling
Method)
Recovery Study
For all grade A equipments, HEPA filter integrity testing and air velocity are
carried out during operational qualification Moreover, room Differential
Pressure monitoring and recovery study is not applicable for Grade A units.
5/2/2015 24PALASH CHANDRA DAS (www.uscgmp.com)
25. Concept of Qualification
Air velocity and air changes per hour
calculation:
Average air velocity (FPM) =
A + B + C + D + E (FPM)
5
For unidirectional airflow units (LAF units, Biosafety cabinets and dynamic pass boxes) down flow and exhaust
HEPA filter air velocity shall be 0.45 meters/second (90 FPM ± 20%). However, higher velocities may be
appropriate in operations generating high levels of particulates.
5/2/2015 25PALASH CHANDRA DAS (www.uscgmp.com)
26. Concept of Qualification
Air Changes per hour:
To determine air changes of the cleanrooms, calculate the supply
air volume for each final HEPA filter as follows:
Qs =Vs x As
Where, Qs is the supply airflow volume from each final
filter (CFM)
Vs is the average supply airflow velocity at each final HEPA
filter (FPM)
As is the area of filter grill (sq. ft.)
Take sum of airflow volume from all the supply air filters installed
for a single cleanroom or enclosure.This will lead to a total
airflow volume (Vt) for the cleanroom.
From the volume of the room, find out air changes per hour using
the formula:
ACPH =
Total airflow volume (CFM) x 60
Volume of the room (cu.ft.)
5/2/2015 26PALASH CHANDRA DAS (www.uscgmp.com)
27. Concept of Qualification
HEPA filter integrity test:
Aim:
This test is performed to confirm that the HEPA filters
are properly installed and leaks have not developed
during installation/use. The test verifies the absence of
leakage, relevant to the cleanliness performance of
the installation.
The test will detect small holes and other damages in
the filter medium and the frame sealant as well as
bypass air in the filter frame, in its gasket, in the grid
system and other fixtures.
Before filter integrity testing, ensure that the air flow
velocity of the HEPA filter is carried out and complies
as per test requirements.
5/2/2015 27PALASH CHANDRA DAS (www.uscgmp.com)
29. Concept of Qualification
Room Differential Pressure monitoring:
Aim:
The purpose of this test is to verify the capability
of the HVAC system to maintain the specified
pressure difference between the rooms and
associated environments.
Sampling frequency:
Carry out monitoring of differential pressure
thrice in a shift during environment monitoring
i.e, 3 consecutive days in at rest condition followed
by 7 consecutive working days in at operation
condition.
5/2/2015 29PALASH CHANDRA DAS (www.uscgmp.com)
30. Concept of Qualification
RoomTemperature and Relative Humidity
Monitoring:
Aim:
The purpose of this test is to demonstrate the
capability of the HVAC system to maintain the air
temperature and humidity level within the control
limits and over the time period.
Sampling frequency:
Carry out monitoring of temperature and relative
humidity thrice in a shift during environment
monitoring for 3 consecutive days in at rest condition
followed by 7 consecutive working days in at operation
condition.
5/2/2015 30PALASH CHANDRA DAS (www.uscgmp.com)
31. Concept of Qualification
Air flow pattern visualization/airflow direction
study:
Aim:
The purpose of flow visualization is to confirm spatial
and temporal characteristics of airflow in the clean
rooms, grade A equipments and controlled
environments. Appropriate procedure for flow
visualization should be performed to demonstrate
that the maintenance of cleanliness is effective.
The airflow pattern should be carried out in both at
rest and at operation conditions to assess the behavior
of the air flow with man and material interventions.
5/2/2015 31PALASH CHANDRA DAS (www.uscgmp.com)
32. Concept of Qualification
Air Borne particle count (non-viable) monitoring:
Aim:
This test method specifies the measurement of airborne
particle concentrations with size distributions having a
threshold size of 0.5 μm and 5.0 μm.
Establishment of sampling locations:
Derive the minimum number of sampling point locations
from following equation:
NL = √ A
Where, NL is the minimum number of sampling
locations (rounded up to a whole number).
A is the area of the cleanroom or clean
zone in square meters.
5/2/2015 32PALASH CHANDRA DAS (www.uscgmp.com)
33. Concept of Qualification
Establishment of single sample volume per location:
As per ISO-14644-1, sampling volume is calculated as below:
Where,Vs is the minimum sample volume per location (in
liters)
C n,m is the class limit (in number of particles per cubic meter)
for the largest considered particle size specified for the
relevant grade,
20 is the defined number of particles that could be counted if
the particle concentration is at the class limit.
To calculate the class level at multiple particle sizes, select a
sample volume for the largest size, this is also the largest
required volume.This will ensure the sample data is valid for all
sizes.
Vs =
20
x 1000
C n,m
5/2/2015 33PALASH CHANDRA DAS (www.uscgmp.com)
34. Concept of Qualification
ISO 4.8 = (20 / 20) x 1000 = 1000 liter
ISO 5 = (20 / 29) x 1000 = 690 liter
ISO 6 = (20 / 293) x 1000 = 69 liter
ISO 7 = (20 / 2930) x 1000 = 6.9 liter
ISO 8 = (20 / 29300) x 1000 = 0.69 liter
CLASS
Minimum
sampling
volume (Ltrs.)
Minimum sampling time
(for particle counter with
50 LPM flow rate)
Minimum sampling time
(for particle counter with
100 LPM flow rate)
ISO 4.8 1000 20 minutes 10 minutes
ISO 5 1000 20 minutes 10 minutes
ISO 6 69 02 minute 01 minute
ISO 7 6.9 01 minute 01 minute
ISO 8 2.0 01 minute 01 minute
5/2/2015 34PALASH CHANDRA DAS (www.uscgmp.com)
35. Concept of Qualification
Sampling frequency:
As a part of initial qualification, monitoring of
the clean rooms for non-viable particle count
shall be done for at least 3 consecutive
working days in at rest condition, followed by 7
consecutive working days in at operation
condition, covering all the sampling points
each day.
5/2/2015 35PALASH CHANDRA DAS (www.uscgmp.com)
36. Concept of Qualification
Microbial Monitoring:
Aim:
To ascertain that the HVAC system under
consideration is capable of providing and
maintaining the required level of the
microbiological quality in the rooms supplied
by it.
For active sampling, 1000 Ltrs of air should be sampled from each
location. For passive air sampling, plates should be exposed for not less
than 4 hours.
5/2/2015 36PALASH CHANDRA DAS (www.uscgmp.com)
37. Concept of Qualification
Incubate all exposed plates in inverted position at 32.5 ±
2.5º C temperature for minimum of 48 hours duration.
Now transfer the plates to incubator with temperature of
22.5 ± 2.5º C and continue incubation for minimum of next
72 hours duration.
Also correlate the obtained CFUs at the end of 5-day
incubation period with the standard correction table
applicable to respective air sampler and enter the corrected
CFUs in the report.
Sampling frequency:
As a part of initial qualification, monitoring of the clean
rooms for viable monitoring shall be done for at least 3
consecutive working days in at rest condition, followed by 7
consecutive working days in at operation condition,
covering all the sampling points each day.
5/2/2015 37PALASH CHANDRA DAS (www.uscgmp.com)
38. Concept of Qualification
Area Recovery Study:
Aim:
This test is performed to determine the ability of the HVAC
system to eliminate airborne particulates from the clean
rooms from worst case condition to class limits.This test
should be carried out upon an installation in the at rest
state.
Recovery performance is evaluated using the rate of
change of particle concentration or 100:1 recovery time.
The 100:1 recovery time is defined as the time required for
decreasing the initial level of particle concentration by a
factor of 0.01 times
Acceptance criteria:
The recovery time for a particular area should not be more
than 15 minutes.
5/2/2015 38PALASH CHANDRA DAS (www.uscgmp.com)
39. BMS integration and CVS?
Supply air fan.
Return air fan
ChilledWater outletTemp.
HotWater outletTemp.
Fresh air ON/OFF damper.
Exhaust air ON/OFF damper
2-way modulating cooling valve.
3-way modulating heating valve.
Mixing ON/OFF damper
Fresh air connected throughTFA ON/OFF damper
Fine & Semi hepa Filter
A temperature and RH sensor installed in common return air duct.
RoomTemperature and Humidity Sensors(Monitoring).
Room differential pressure sensor’s.
Differential pressure sensor across hepa filters.
Differential pressure switch across hepa filters.
Room motorized dampers.
VFD’s trip status and software integration.
I/O verification
Alarms and
interlocks
Data restrorization
Software backup
Audit trial
Password
verification
Real time clock
verification
Screen shots
verifications
5/2/2015 39PALASH CHANDRA DAS (www.uscgmp.com)
41. Operation
For the manufacture of sterile pharmaceutical preparations, four grades
of clean areas are distinguished as follows:
Grade A:The local zone for high-risk operations, e.g. filling and making
aseptic connections. Normally such conditions are achieved by using
unidirectional airflow workstation. Unidirectional airflow systems should
provide a homogeneous air speed of 0.36–0.54 m/s (guidance value) at a
defined test position 15–30 cm below the terminal filter or air distributor
system.The velocity at working level should not be less than 0.36 m/s.
The uniformity and effectiveness of the unidirectional airflow should be
demonstrated by undertaking airflow visualization tests.
Grade B: In aseptic preparation and filling, this is the background
environment for the Grade A zone.
Grades C and D: Clean areas for carrying out less critical stages in the
manufacture of sterile products or carrying out activities during which
the product is not directly exposed (i.e. aseptic connection with aseptic
connectors and operations in a closed system).
5/2/2015 41PALASH CHANDRA DAS (www.uscgmp.com)
45. Maintenance
There should be a planned preventive maintenance programme,
procedures and records for the HVAC system. Records should be kept.
Operating and maintenance (O&M) manuals, schematic drawings,
protocols and reports should be maintained as reference documents for
any future changes and upgrades to the system.These documents
should be kept up to date, containing any system revisions made.
Maintenance personnel should receive appropriate training.
HEPA filters should be changed either by a specialist or a trained person,
and then followed by installed filter leakage testing.
Any maintenance activity should be assessed critically to determine any
Maintenance activities should normally be scheduled to take place
outside production hours, and any system stoppage should be assessed
with a view to the possible need for requalification of an area as a result
of an interruption of the service. impact on product quality including
possible contamination.
5/2/2015 45PALASH CHANDRA DAS (www.uscgmp.com)
47. Schedule M
Appropriate action shall be taken
immediately if the result of particulate
and microbiological monitoring indicates that
the counts exceed the limits.The Standard
Operating Procedures shall contain corrective
action. After major engineering
modification to the HVAC system of any area,
all monitoring shall be re-performed
before production commences.
5/2/2015 47PALASH CHANDRA DAS (www.uscgmp.com)
48. USFDA
CFR211.46 states that “
a) Adequate ventilation shall be provided.
b) Equipment for adequate control over air pressure, micro-
organisms, dust,
humidity, and temperature shall be provided when appropriate
for the manufacture,
processing, packaging, or holding of a drug product.
c) Air filtration system ,including prefilters and particulate matter
air filters, shall be used when appropriate on air suppliers to
production areas.”
5/2/2015 48PALASH CHANDRA DAS (www.uscgmp.com)
51. Annex 15: Qualification and
Validation
A risk assessment should be carried out
where there may be direct contact with the
product, e.g. heating, ventilation and air-
conditioning (HVAC) systems, or indirect
contact such as through heat exchangers to
mitigate any risks of failure
5/2/2015 51PALASH CHANDRA DAS (www.uscgmp.com)
53. Reference
ASHRAE handbook 2000. HVAC Systems and Equipment. Atlanta, GA, ASHRAE, 2008.
http://www.ashrae.org/technology/page/548.
ICH. Good Manufacturing PracticeGuide for Active Pharmaceutical Ingredients.Q7A (March 15, 2000).
FDA. FDA’s proposed current good manufacturing practices (GMP) for regs. For large volume parenterals (LVP).
Fed Reg (June 1, 1976). PreliminaryConcept Paper of Sterile Drug Products Produced byAseptic Processing, draft
paper, Sept. 27, 2002.
Pharmaceutical EngineeringGuideVol. 4:Water and Steam Guide.Tampa, FL: ISPE, (1997).
Code of Federal RegulationTitle 21, Part 211. Current good manufacturing practice for finished pharmaceuticals
(2002).
General information <1116>: Microbiological evaluation of clean rooms and other controlled environments. U.S.
Pharmacopeia. vol. 25. Rockville, MD: U.S. Pharmacopeial Convention, p. 2206–2212 (2002).
EU.GMP annex: Manufacturing of sterile products (1996).
Federal Standard 209E. Airborne ParticulateCleanliness Classes in Cleanroom and Clean Zone (Sept. 11, 1992).
Pharmaceutical EngineeringGuideVol. 3: Sterile Manufacturing Facilities.Tampa, FL: ISPE, (1997).
FDA/ISPE. Pharmaceutical Engineering Guide. vol. 1.Tampa, FL.
Classification of Airborne Particulates, in Cleanrooms andAssociated Controlled Environments—Part 1, ISO 14644-
1, Geneva: InternationalOrganization for Standardization (1999).
WHO GMP. Good Practices in Manufacturing of Pharmaceutical Products in WHO ExpertCommittee on
Specifications for Pharmaceutical Preparations, 32 edition,Geneva (1992).