2. A fast food chain wants to build four stores. In the past, the chain has
used six different construction companies and, having been satisfied
with each, has invited each to bid on each job. The final bids (in
thousands of rupees) are shown in the following table. Since the fast
food chain wants to have each of the new stores ready as quickly as
possible, it will award at most one job to a construction company. What
assignment results in minimum total cost to the fast food chain?
Construction Companies
1 2 3 4 5 6
Store 1 85.3 88 87.5 82.4 89.1 86.7
Store 2 78.9 77.4 77.4 76.5 79.3 78.3
Store 3 82 81.3 82.4 80.6 83.5 81.7
Store 4 84.3 84.6 86.2 83.3 84.4 85.5
15. Subtracting the minimum uncut
element from other uncut elements,
and adding it to elements at the
intersections
SI NC E MINI MUM NUM BER OF LI NE S
REQUI RED IS LE SS THA N THE NUM BER OF
ROWS/ COLUMNS
20. Subtracting the minimum uncut
element from other uncut elements,
and adding it to elements at the
intersections
SI NC E MINI MUM NUM BER OF LI NE S
REQUI RED IS LE SS THA N THE NUM BER OF
ROWS/ COLUMNS
25. Subtracting the minimum uncut
element from other uncut elements,
and adding it to elements at the
intersections
SI NC E MINI MUM NUM BER OF LI NE S
REQUI RED IS LE SS THA N THE NUM BER OF
ROWS/ COLUMNS
47. Ans: Optimum Assignment & TotalCost
Construction Company Store Cost
1 4 Rs.84300
2 3 Rs.81300
3 2 Rs.77400
4 1 Rs.82400
5 - -
6 - -
Total Cost Rs.325400
57. A firm wants to purchase three different types of equipment and five
manufacturers have come forward to supply these machines. However,
the firm’s policy is not to accept more than one machine from any of the
manufacturers. The data relating to the price (in lakhs of rupees) quoted
by the different manufacturers are given below. Determine how best the
firm can purchase the three machines.
Machines
1 2 3
Manufacturers
A 2.99 3.11 2.68
B 2.78 2.87 2.57
C 2.92 3.05 2.80
D 2.82 3.10 2.74
E 3.11 2.90 2.64
58. A management consulting firm has a backlog of 4 contracts.
Work on these contracts must be started immediately. 3 project
leaders are available for assignment to the contracts. Because
of varying work experience of the project leaders the profit of
the consulting firm would vary based on the assignments as
shown below. The unassigned contract can be completed by
subcontracting it to an outside consultant. The profit from the
subcontract is zero. Determine the assignment of project
leaders to the contracts so as to maximise profits.
Contracts
1 2 3 4
Project
Leaders
A 13 10 9 11
B 15 17 13 20
C 6 8 11 7