Towards the BAT based permitting
in Poland
Marcin Wiśniewski
Department of Environmental Instruments
Ministry of Climate and Environment
Regional meeting with Eastern Partnership countries
16 November 2020
Institutions
Supervising Authority
 Ministry of Climate and Environment
Permitting Authority
 Voivodship Marshal
 Starost
Inspection Authority
 Environmental Protection Inspectorate (Voivodship Inspectorates)
Appeals Authority
 Minister of Climate and Environment (for decisions issued by
voivodship marshals) and appeals boards (for decisions issued by
starosts)
3
Administrative Division
Number of the IED installations in PL
403
426
332
540
890
1804
0
200
400
600
800
1000
1200
1400
1600
1800
2000
BAT conclusions published
BAT conclusions not published
Number of the IED installations in the EU
5
≈ 4300
History of the integrated approach
Single media
permits (air,
water, noise) IPPCD IED
Since 1970 2001/2004 20142010
End of compliance
programs
implementation
• Integrated permits had to be issued
until 2007
• Deadlines differentiated according
to the activity types
Revised IED ?
2022/2023
Challenges under the IPPCD
 Shift from the „command and control” approach into a BAT approach
 Significant size of documentation to be prepared (operator) and assessed (CA)
 Required high level of expertise regarding technological processes (CA)
 Proper understanding of the role of BAT
• BREFs being a guidance documents
• Neither prescriptive nor exhaustive character of BATs
 Financing
• Activities in the field of collecting and sharing information about BAT
 Interpretation issues e.g.:
• Determination of the installation boundaries (facility > installation > unit),
• How to determine production/processing capacity
• Differences between activities e.g.:
2.3c: application of protective fused metal coats with an input exceeding 2 t of
crude steel per hour, and
2.6: Surface treatment of metals or plastic materials using an electrolytic or
chemical process where the volume of the treatment vats exceeds 30 m
3
Applied measures and activities
• Pilot projects,
• Trainings for administration and industry,
• Guidelines and folders concerning integrated permits,
• Translation of reference documents (BREFs),
• Establishing of Polish Technical Working Groups
• Polish IPPC website,
• Registration fee
Registration fee = B x Wr / Wp however not higher than 12 000 EUR
Where
B – base-fee rate for each activity type (defined in the Regulation)
Wr - parameter chractreising maximum scale of the activity (deifined by the opertors)
Wp - parameter charcterising average scale of the activity (defined in the Regulation)
Industrial emissions Directive (IED)
Changes introduced by the IED:
 New activities e.g. WBP or IWWTP
 Improved identification of BAT
 BAT conclusions on the key environmental issues
 Quantification of BAT performance, especially via BAT-AELs
 Also address prevention of emissions at source by using process-
integrated techniques
 Stricter ELVs for LCP, WI, VOC and TiO2, since 2016
 Additional elements of the permit e.g. baseline reports
Challenges under the IED
 Active involvement into the BREFs revision/elaboration process
 Activation of the industry and competent authorities
 Data collection
 Meaningful contribution to Sevilla Process
Challenges with permitting under the IED
 Implementation of the BAT conclusions,
 How to translate the BATc into the permit conditions,
 How to properly set the ELVs (based on BAT),
 How to asses if the art. 15.4 derogation is sufficiently justified,
 Compliance check criteria for the ELVs,
 Measurement uncertainty.
Implementation of the BAT conclusions
 No transposition of the BATc into national law
 No general binding rules
 The BATc applies directly using a framework given in the national
legislation
Instead
 National guidance documents produced to almost each
Implementing Decision
 Meetings with the competent authorities (usually the most relevant
for a given sector)
How to translate the BATc into the permit
conditions
Publication of decision on BAT Conclusions
Start up of the analysis
Results of the analysis
Full compliance Permit needs to
be updated
Announcement
RAI
Reconsideration of
previously granted
derogations
Information for the
operator
Request to submit an application for
updating the permit conditions
6m
4years
Competentauthorities
Elaboration of application
Submission of an application
Is 15.4 needed ?
Request to submit an application for
updating the permit conditions
For how long ?
Granting a permit
Compliance with the BAT
Conclusions
Lack of an application
Limitation of the permit by
law
12m
4yearsafterpublicationofBATConclusions
How to properly set the ELVs (based on BAT)
 In national legislation the BAT AELs are defined as the highest
value from the AELs range - what doesn’t mean that upper end of
the range needs to be applied
because:
 The obligation that permit needs to be always based on BAT
 The emission limit set out in the permit results from the techniques
installed – but cannot be higher than the upper end of the BAT
AELs
 Still one of the biggest challenges – which value from the range
fits best
 In addition the environmental quality standards can not be
breached
How to assess if derogation is sufficiently justified
 Derogation from BAT-AELs is only allowed in specific and justified cases:
 costs are disproportionately higher than benefits due to
local / installation-specific situation – IED Article 15(4)
 without jeopardy to Environmental Quality Standards
 not exceed the ELVs in the IED Annexes
Guidance document available at: https://ekoportal.gov.pl/pozwolenia-
zintegrowane/poradniki-branzowe
16
𝑵𝑷𝑽 =
𝒕=𝟎
𝒏
𝑶𝒕
𝟏 + 𝒓 𝒕
−
𝒕=𝟎
𝒏
𝑰𝒕
𝟏 + 𝒓 𝒕
Sum of discounted
financial expenditures
(CAPEX+OPEX)
Sum of discounted
environmental benefits
17
Compliance check criteria
Basic assumption that BAT AELs will replace IED Annex V ELVs was not
accurate because:
 The BAT AELs (where CEMS is used) refer usually to daily and yearly
averages
 No directly defined averaging periods for the Annex V ELVs
 Compliance check based on specific rules from the IED (Annex V Part
4):
 no validated monthly average value exceeds the relevant emission
limit values set out in Parts 1 and 2;
 no validated daily average value exceeds 110 % of the relevant
emission limit values set out in Parts 1 and 2;
 95 % of all the validated hour average values over the year do not
exceed 200 % of the relevant emission limit values set out in Parts
1 and 2.
 Therefore compliance with the BAT AELs is verified differently than with
the IED Annex V ELVs - without paying attention to hourly averages;
Mv 90 110 120
Rv Sv Rv Sv Rv Sv Max
A 20% MV 72 18 88 22 96 24 125
B 20% ELV 70 20 90 20 100 20 120
C 20% MV
lub 20%
ELV gdy
niższy od
MV
72 18 90 20 100 20 120
D SD 85,5 4,5 104,5 5,5 114 6 105,
26
NOx – ELV = 100 mg/Nm3
Mv – measured value, Rv – reported value, ELV – Subtracted value, SD – Standard deviation
Measurement uncertainty
Thank you

More Related Content

What's hot

Eu f gas 7 lessons learned
Eu f gas 7 lessons learnedEu f gas 7 lessons learned
Eu f gas 7 lessons learnedAndrea Voigt
 
tew (10.10.18) - Towards new distribution tariffs in ukraine
tew (10.10.18) - Towards new distribution tariffs in ukrainetew (10.10.18) - Towards new distribution tariffs in ukraine
tew (10.10.18) - Towards new distribution tariffs in ukraineДенис Киркач
 
Development of the UK ETS - Danial Sturge
Development of the UK ETS - Danial SturgeDevelopment of the UK ETS - Danial Sturge
Development of the UK ETS - Danial SturgeOECD Environment
 
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...Chris Hamans
 
ETS revenues - Dr Stefano de Clara, ICAP
ETS revenues - Dr Stefano de Clara, ICAPETS revenues - Dr Stefano de Clara, ICAP
ETS revenues - Dr Stefano de Clara, ICAPOECD Environment
 
Experience from the EU ETS - Peter Vis, European University Institute
Experience from the EU ETS - Peter Vis, European University InstituteExperience from the EU ETS - Peter Vis, European University Institute
Experience from the EU ETS - Peter Vis, European University InstituteOECD Environment
 
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...OECD Environment
 
Allocation Methods of Emission allowance
Allocation Methods of Emission allowanceAllocation Methods of Emission allowance
Allocation Methods of Emission allowanceRenato Roldao
 
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...ESCCON2019 Update on REACH and its Impact on Availability of Components for S...
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...Paavo Heiskanen
 
ETS implementation - Kieran McNamara, IEA
ETS implementation - Kieran McNamara, IEAETS implementation - Kieran McNamara, IEA
ETS implementation - Kieran McNamara, IEAOECD Environment
 
Long-term fiscal sustainability... -- Luisa Dressler, OECD
Long-term fiscal sustainability... -- Luisa Dressler, OECDLong-term fiscal sustainability... -- Luisa Dressler, OECD
Long-term fiscal sustainability... -- Luisa Dressler, OECDOECD Governance
 
Calculating the environmental impacts of public action -- Nils Axel Braathen,...
Calculating the environmental impacts of public action -- Nils Axel Braathen,...Calculating the environmental impacts of public action -- Nils Axel Braathen,...
Calculating the environmental impacts of public action -- Nils Axel Braathen,...OECD Governance
 
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...OECD Environment
 
9. carol day brexit and aarhus dublin presentation-4
9. carol day brexit and aarhus   dublin presentation-49. carol day brexit and aarhus   dublin presentation-4
9. carol day brexit and aarhus dublin presentation-4ELIGConference
 

What's hot (20)

Eu f gas 7 lessons learned
Eu f gas 7 lessons learnedEu f gas 7 lessons learned
Eu f gas 7 lessons learned
 
tew (10.10.18) - Towards new distribution tariffs in ukraine
tew (10.10.18) - Towards new distribution tariffs in ukrainetew (10.10.18) - Towards new distribution tariffs in ukraine
tew (10.10.18) - Towards new distribution tariffs in ukraine
 
The impact of Brexit on EU's environmental law
The impact of Brexit on EU's environmental lawThe impact of Brexit on EU's environmental law
The impact of Brexit on EU's environmental law
 
Development of the UK ETS - Danial Sturge
Development of the UK ETS - Danial SturgeDevelopment of the UK ETS - Danial Sturge
Development of the UK ETS - Danial Sturge
 
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...
WSB14 - Session 111-1 CEN presentation: overview Rules and Regulations and EN...
 
ETS revenues - Dr Stefano de Clara, ICAP
ETS revenues - Dr Stefano de Clara, ICAPETS revenues - Dr Stefano de Clara, ICAP
ETS revenues - Dr Stefano de Clara, ICAP
 
Experience from the EU ETS - Peter Vis, European University Institute
Experience from the EU ETS - Peter Vis, European University InstituteExperience from the EU ETS - Peter Vis, European University Institute
Experience from the EU ETS - Peter Vis, European University Institute
 
Waste Prevention Programmes in the EU - Overview
Waste Prevention Programmes in the EU - OverviewWaste Prevention Programmes in the EU - Overview
Waste Prevention Programmes in the EU - Overview
 
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...
The impact of an ETS in a system dominated by coal power - Marta Roslaniec, K...
 
Allocation Methods of Emission allowance
Allocation Methods of Emission allowanceAllocation Methods of Emission allowance
Allocation Methods of Emission allowance
 
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...ESCCON2019 Update on REACH and its Impact on Availability of Components for S...
ESCCON2019 Update on REACH and its Impact on Availability of Components for S...
 
ETS implementation - Kieran McNamara, IEA
ETS implementation - Kieran McNamara, IEAETS implementation - Kieran McNamara, IEA
ETS implementation - Kieran McNamara, IEA
 
tew (09.10.18) - Oshchepkova
tew (09.10.18) - Oshchepkovatew (09.10.18) - Oshchepkova
tew (09.10.18) - Oshchepkova
 
Long-term fiscal sustainability... -- Luisa Dressler, OECD
Long-term fiscal sustainability... -- Luisa Dressler, OECDLong-term fiscal sustainability... -- Luisa Dressler, OECD
Long-term fiscal sustainability... -- Luisa Dressler, OECD
 
Calculating the environmental impacts of public action -- Nils Axel Braathen,...
Calculating the environmental impacts of public action -- Nils Axel Braathen,...Calculating the environmental impacts of public action -- Nils Axel Braathen,...
Calculating the environmental impacts of public action -- Nils Axel Braathen,...
 
Matthews future for direct payments eur parl sept 2015
Matthews future for direct payments eur parl sept 2015Matthews future for direct payments eur parl sept 2015
Matthews future for direct payments eur parl sept 2015
 
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...
EaP GREEN: Experience of the implementation of EU Directives based on EPR pri...
 
ETS Handbook
ETS HandbookETS Handbook
ETS Handbook
 
AIB 2019 - disclosure workshop - Liesbeth Switten
AIB 2019 - disclosure workshop - Liesbeth SwittenAIB 2019 - disclosure workshop - Liesbeth Switten
AIB 2019 - disclosure workshop - Liesbeth Switten
 
9. carol day brexit and aarhus dublin presentation-4
9. carol day brexit and aarhus   dublin presentation-49. carol day brexit and aarhus   dublin presentation-4
9. carol day brexit and aarhus dublin presentation-4
 

Similar to Implementation of BAT approach

The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables DirectiveLeonardo ENERGY
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directivefernando nuño
 
Implementation of BAT approach: Experience of Georgia
Implementation of BAT approach: Experience of GeorgiaImplementation of BAT approach: Experience of Georgia
Implementation of BAT approach: Experience of GeorgiaOECD Environment
 
Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...OECD Environment
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Bill St. Arnaud
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Bill St. Arnaud
 
The Proposed new EU Renewables Directive
The Proposed new EU Renewables DirectiveThe Proposed new EU Renewables Directive
The Proposed new EU Renewables DirectiveLeonardo ENERGY
 
The potential impact of transitioning CDM units and activities to the Paris A...
The potential impact of transitioning CDM units and activities to the Paris A...The potential impact of transitioning CDM units and activities to the Paris A...
The potential impact of transitioning CDM units and activities to the Paris A...Oeko-Institut
 
Financing the water sector
Financing the water sectorFinancing the water sector
Financing the water sectorARERA
 
Understanding Carbon Credits Business
Understanding Carbon Credits BusinessUnderstanding Carbon Credits Business
Understanding Carbon Credits BusinessAmit Chauhan
 
Report on water services & waste management
Report on water services & waste managementReport on water services & waste management
Report on water services & waste managementARERA
 
Calculating the environmental impacts of public action -- Jonas Teusch, OECD
Calculating the environmental impacts of public action -- Jonas Teusch, OECDCalculating the environmental impacts of public action -- Jonas Teusch, OECD
Calculating the environmental impacts of public action -- Jonas Teusch, OECDOECD Governance
 
Transition of the CDM to Article 6.4
Transition of the CDM to Article 6.4Transition of the CDM to Article 6.4
Transition of the CDM to Article 6.4Oeko-Institut
 
Wis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationWis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationwispolitics
 
Wis. climate change legislation - 1/20/2010 presentation
Wis. climate change legislation - 1/20/2010 presentationWis. climate change legislation - 1/20/2010 presentation
Wis. climate change legislation - 1/20/2010 presentationiowapolitics
 
Flexibility Instruments of the Kyoto Protocol
Flexibility Instruments of the Kyoto Protocol  Flexibility Instruments of the Kyoto Protocol
Flexibility Instruments of the Kyoto Protocol Pallav Purohit
 
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Leonardo ENERGY
 

Similar to Implementation of BAT approach (20)

The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables Directive
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directive
 
Implementation of BAT approach: Experience of Georgia
Implementation of BAT approach: Experience of GeorgiaImplementation of BAT approach: Experience of Georgia
Implementation of BAT approach: Experience of Georgia
 
Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...
 
Evaluations of SEAPs: strengths and weaknesses - Melica
Evaluations of SEAPs: strengths and weaknesses - MelicaEvaluations of SEAPs: strengths and weaknesses - Melica
Evaluations of SEAPs: strengths and weaknesses - Melica
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4
 
Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4Climate Check Canarie Workshop March4
Climate Check Canarie Workshop March4
 
The Proposed new EU Renewables Directive
The Proposed new EU Renewables DirectiveThe Proposed new EU Renewables Directive
The Proposed new EU Renewables Directive
 
The potential impact of transitioning CDM units and activities to the Paris A...
The potential impact of transitioning CDM units and activities to the Paris A...The potential impact of transitioning CDM units and activities to the Paris A...
The potential impact of transitioning CDM units and activities to the Paris A...
 
GRPE-82-35e.pptx
GRPE-82-35e.pptxGRPE-82-35e.pptx
GRPE-82-35e.pptx
 
Financing the water sector
Financing the water sectorFinancing the water sector
Financing the water sector
 
Understanding Carbon Credits Business
Understanding Carbon Credits BusinessUnderstanding Carbon Credits Business
Understanding Carbon Credits Business
 
Report on water services & waste management
Report on water services & waste managementReport on water services & waste management
Report on water services & waste management
 
Calculating the environmental impacts of public action -- Jonas Teusch, OECD
Calculating the environmental impacts of public action -- Jonas Teusch, OECDCalculating the environmental impacts of public action -- Jonas Teusch, OECD
Calculating the environmental impacts of public action -- Jonas Teusch, OECD
 
Transition of the CDM to Article 6.4
Transition of the CDM to Article 6.4Transition of the CDM to Article 6.4
Transition of the CDM to Article 6.4
 
Wis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentationWis. climate change bill - 1/20/2010 staff presentation
Wis. climate change bill - 1/20/2010 staff presentation
 
Wis. climate change legislation - 1/20/2010 presentation
Wis. climate change legislation - 1/20/2010 presentationWis. climate change legislation - 1/20/2010 presentation
Wis. climate change legislation - 1/20/2010 presentation
 
Flexibility Instruments of the Kyoto Protocol
Flexibility Instruments of the Kyoto Protocol  Flexibility Instruments of the Kyoto Protocol
Flexibility Instruments of the Kyoto Protocol
 
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
 
The EU F-Gas Regulation
The EU F-Gas RegulationThe EU F-Gas Regulation
The EU F-Gas Regulation
 

More from OECD Environment

GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfOECD Environment
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...OECD Environment
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...OECD Environment
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...OECD Environment
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...OECD Environment
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...OECD Environment
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...OECD Environment
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...OECD Environment
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESOECD Environment
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...OECD Environment
 
Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...OECD Environment
 
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijCanadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijOECD Environment
 
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...OECD Environment
 
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...OECD Environment
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysOECD Environment
 
CCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsCCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsOECD Environment
 
CCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoCCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoOECD Environment
 
CCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghCCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghOECD Environment
 
CCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngCCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngOECD Environment
 
CCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikCCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikOECD Environment
 

More from OECD Environment (20)

GREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdfGREEN Action Task Force - Full Presentations.pdf
GREEN Action Task Force - Full Presentations.pdf
 
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
Case Study: Peptides-based Plant Protection Product (harpin proteins*) by Ros...
 
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
CLE Contribution on the Assessment of Innovative Biochemicals in the EU Statu...
 
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...Additional Considerations for Pesticide Formulations Containing Microbial Pes...
Additional Considerations for Pesticide Formulations Containing Microbial Pes...
 
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
Role of genome sequencing (WGS) in microbial biopesticides safety assessment ...
 
Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...Considerations for Problem Formulation for Human Health Safety Assessments of...
Considerations for Problem Formulation for Human Health Safety Assessments of...
 
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
How to Identify and Quantify Mixtures What is Essential to Know for Risk Asse...
 
APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...APVMA outcome-focussed approach to data requirements to support registration ...
APVMA outcome-focussed approach to data requirements to support registration ...
 
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGESThe U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
The U.S. Perspective on Problem Formulation for Biopesticides: Shannon BORGES
 
Problem formulation for environmental risk assessment – Finnish case study: ...
Problem formulation for environmental risk assessment – Finnish case study:  ...Problem formulation for environmental risk assessment – Finnish case study:  ...
Problem formulation for environmental risk assessment – Finnish case study: ...
 
Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...Problem formulation for environmental risk assessment in the context of EC Re...
Problem formulation for environmental risk assessment in the context of EC Re...
 
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma BabijCanadian Perspective on Problem Formulation for Biopesticides: Emma Babij
Canadian Perspective on Problem Formulation for Biopesticides: Emma Babij
 
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
Problem Formulation as an Ecological Testing and Assessment Tool for Microbia...
 
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...History, principles and use for biopesticide risk assessment: Boet Glandorf a...
History, principles and use for biopesticide risk assessment: Boet Glandorf a...
 
CCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeawaysCCXG global forum, April 2025, Key takeaways
CCXG global forum, April 2025, Key takeaways
 
CCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter resultsCCXG global forum, April 2024, Mentimeter results
CCXG global forum, April 2024, Mentimeter results
 
CCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara FaldutoCCXG global forum, April 2024, Chiara Falduto
CCXG global forum, April 2024, Chiara Falduto
 
CCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth SinghCCXG global forum, April 2024, Siddharth Singh
CCXG global forum, April 2024, Siddharth Singh
 
CCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine AngCCXG global forum, April 2024, Geraldine Ang
CCXG global forum, April 2024, Geraldine Ang
 
CCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël JachnikCCXG global forum, April 2024, Raphaël Jachnik
CCXG global forum, April 2024, Raphaël Jachnik
 

Recently uploaded

Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...Call Girls in Nagpur High Profile
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Servicesdollysharma2066
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...tanu pandey
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Sapana Sha
 
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...kauryashika82
 
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...Escorts Call Girls
 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.cojitesh
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...rajputriyana310
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756dollysharma2066
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...Call Girls in Nagpur High Profile
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Bhosari ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
Call Girls In Okhla DELHI ~9654467111~ Short 1500 Night 6000
 
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
 
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...
Call Now ☎ Russian Call Girls Connaught Place @ 9899900591 # Russian Escorts ...
 
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.
 
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
VVIP Pune Call Girls Koregaon Park (7001035870) Pune Escorts Nearby with Comp...
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 

Implementation of BAT approach

  • 1. Towards the BAT based permitting in Poland Marcin Wiśniewski Department of Environmental Instruments Ministry of Climate and Environment Regional meeting with Eastern Partnership countries 16 November 2020
  • 2. Institutions Supervising Authority  Ministry of Climate and Environment Permitting Authority  Voivodship Marshal  Starost Inspection Authority  Environmental Protection Inspectorate (Voivodship Inspectorates) Appeals Authority  Minister of Climate and Environment (for decisions issued by voivodship marshals) and appeals boards (for decisions issued by starosts)
  • 4. Number of the IED installations in PL 403 426 332 540 890 1804 0 200 400 600 800 1000 1200 1400 1600 1800 2000 BAT conclusions published BAT conclusions not published
  • 5. Number of the IED installations in the EU 5 ≈ 4300
  • 6. History of the integrated approach Single media permits (air, water, noise) IPPCD IED Since 1970 2001/2004 20142010 End of compliance programs implementation • Integrated permits had to be issued until 2007 • Deadlines differentiated according to the activity types Revised IED ? 2022/2023
  • 7. Challenges under the IPPCD  Shift from the „command and control” approach into a BAT approach  Significant size of documentation to be prepared (operator) and assessed (CA)  Required high level of expertise regarding technological processes (CA)  Proper understanding of the role of BAT • BREFs being a guidance documents • Neither prescriptive nor exhaustive character of BATs  Financing • Activities in the field of collecting and sharing information about BAT  Interpretation issues e.g.: • Determination of the installation boundaries (facility > installation > unit), • How to determine production/processing capacity • Differences between activities e.g.: 2.3c: application of protective fused metal coats with an input exceeding 2 t of crude steel per hour, and 2.6: Surface treatment of metals or plastic materials using an electrolytic or chemical process where the volume of the treatment vats exceeds 30 m 3
  • 8. Applied measures and activities • Pilot projects, • Trainings for administration and industry, • Guidelines and folders concerning integrated permits, • Translation of reference documents (BREFs), • Establishing of Polish Technical Working Groups • Polish IPPC website, • Registration fee Registration fee = B x Wr / Wp however not higher than 12 000 EUR Where B – base-fee rate for each activity type (defined in the Regulation) Wr - parameter chractreising maximum scale of the activity (deifined by the opertors) Wp - parameter charcterising average scale of the activity (defined in the Regulation)
  • 9. Industrial emissions Directive (IED) Changes introduced by the IED:  New activities e.g. WBP or IWWTP  Improved identification of BAT  BAT conclusions on the key environmental issues  Quantification of BAT performance, especially via BAT-AELs  Also address prevention of emissions at source by using process- integrated techniques  Stricter ELVs for LCP, WI, VOC and TiO2, since 2016  Additional elements of the permit e.g. baseline reports
  • 10. Challenges under the IED  Active involvement into the BREFs revision/elaboration process  Activation of the industry and competent authorities  Data collection  Meaningful contribution to Sevilla Process
  • 11. Challenges with permitting under the IED  Implementation of the BAT conclusions,  How to translate the BATc into the permit conditions,  How to properly set the ELVs (based on BAT),  How to asses if the art. 15.4 derogation is sufficiently justified,  Compliance check criteria for the ELVs,  Measurement uncertainty.
  • 12. Implementation of the BAT conclusions  No transposition of the BATc into national law  No general binding rules  The BATc applies directly using a framework given in the national legislation Instead  National guidance documents produced to almost each Implementing Decision  Meetings with the competent authorities (usually the most relevant for a given sector)
  • 13. How to translate the BATc into the permit conditions Publication of decision on BAT Conclusions Start up of the analysis Results of the analysis Full compliance Permit needs to be updated Announcement RAI Reconsideration of previously granted derogations Information for the operator Request to submit an application for updating the permit conditions 6m 4years Competentauthorities
  • 14. Elaboration of application Submission of an application Is 15.4 needed ? Request to submit an application for updating the permit conditions For how long ? Granting a permit Compliance with the BAT Conclusions Lack of an application Limitation of the permit by law 12m 4yearsafterpublicationofBATConclusions
  • 15. How to properly set the ELVs (based on BAT)  In national legislation the BAT AELs are defined as the highest value from the AELs range - what doesn’t mean that upper end of the range needs to be applied because:  The obligation that permit needs to be always based on BAT  The emission limit set out in the permit results from the techniques installed – but cannot be higher than the upper end of the BAT AELs  Still one of the biggest challenges – which value from the range fits best  In addition the environmental quality standards can not be breached
  • 16. How to assess if derogation is sufficiently justified  Derogation from BAT-AELs is only allowed in specific and justified cases:  costs are disproportionately higher than benefits due to local / installation-specific situation – IED Article 15(4)  without jeopardy to Environmental Quality Standards  not exceed the ELVs in the IED Annexes Guidance document available at: https://ekoportal.gov.pl/pozwolenia- zintegrowane/poradniki-branzowe 16 𝑵𝑷𝑽 = 𝒕=𝟎 𝒏 𝑶𝒕 𝟏 + 𝒓 𝒕 − 𝒕=𝟎 𝒏 𝑰𝒕 𝟏 + 𝒓 𝒕 Sum of discounted financial expenditures (CAPEX+OPEX) Sum of discounted environmental benefits
  • 17. 17 Compliance check criteria Basic assumption that BAT AELs will replace IED Annex V ELVs was not accurate because:  The BAT AELs (where CEMS is used) refer usually to daily and yearly averages  No directly defined averaging periods for the Annex V ELVs  Compliance check based on specific rules from the IED (Annex V Part 4):  no validated monthly average value exceeds the relevant emission limit values set out in Parts 1 and 2;  no validated daily average value exceeds 110 % of the relevant emission limit values set out in Parts 1 and 2;  95 % of all the validated hour average values over the year do not exceed 200 % of the relevant emission limit values set out in Parts 1 and 2.  Therefore compliance with the BAT AELs is verified differently than with the IED Annex V ELVs - without paying attention to hourly averages;
  • 18. Mv 90 110 120 Rv Sv Rv Sv Rv Sv Max A 20% MV 72 18 88 22 96 24 125 B 20% ELV 70 20 90 20 100 20 120 C 20% MV lub 20% ELV gdy niższy od MV 72 18 90 20 100 20 120 D SD 85,5 4,5 104,5 5,5 114 6 105, 26 NOx – ELV = 100 mg/Nm3 Mv – measured value, Rv – reported value, ELV – Subtracted value, SD – Standard deviation Measurement uncertainty

Editor's Notes

  1. This slide is an example of a template: Numerical bullets
  2. This slide is an example of a template: Overview_02
  3. This slide is an example of a template: Chart_01
  4. This slide is an example of a template: Numerical bullets
  5. Foundaries
  6. This slide is an example of a template: Numerical bullets
  7. Merged and repealed 8 other directives
  8. 2.5 Processing of non-ferrous metals: (a) production of non-ferrous crude metals from ore, concentrates or secondary raw materials by metallurgical, chemical or electrolytic processes; (b) melting, including the alloyage, of non-ferrous metals, including recovered products and operation of non-ferrous metal foundries, with a melting capacity exceeding 4 tonnes per day for lead and cadmium or 20 tonnes per day for all other metals. 2.6. Surface treatment of metals or plastic materials using an electrolytic or chemical process where the volume of the treatment vats exceeds 30 m3
  9. Jest to przykładowy slajd do wzorca: Wypunktowanie Numeryczne
  10. Jest to przykładowy slajd do wzorca: Wypunktowanie Numeryczne