Good Neighbourly Relations Committee
Meeting
City of Brossard : 25 january 2017
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
Please note that the English version is used
only for refernce purposes. In case of
disrepancy between the English and French
versions, the French version shall prevail.
Projet de corridor du nouveau pont Champlain 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Jaime Reis
Marc Turcotte – Representative from a community
organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
Projet de corridor du nouveau pont Champlain
1. Follow up on the various files under the responsibility of
Infrastructure Canada : anti-noise wall and DEL lightning
2. Provide information about the work that has been
completed, is underway and planned between now and
July 2017
3. Answer questions, find potential solutions and discuss the
issues
Objectives of the Meeting
3
Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Anti-noise wall : update 20 min. 19h10 à 19h30
3. Question period 10 min. 19h30 à 19h40
4. Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 19h40
à 20h20
5. Question period 20 min. 20h20 à 20h40
6. Varia 15 min. 20h40 à 20h55
7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00
Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
Projet de corridor du nouveau pont Champlain
Survol des travaux complétés
6
• Fall season: solid work progress in general on the
East Approach
 Construction of footings and pier bases completed
 Beginning of installation of prefabricated segments
of piers and pier caps
 Continue the construction of the east abutment
• Installation of the new construction site exit
• Very few complaints, mainly about the new
construction site exit (5 on 8)
Projet de corridor du nouveau pont Champlain
Impacts:
new construction site exit
7
Impact sonore
Visual impactMobility impact
Noise impactOpening of the new construction site exit
Duration : 3 years
Period : 2017 à 2019
• No incidents recorded or reported
• Flow rate : 75 to 150 car / day
10 à 30 car/ night
• Installation of a visual screen
• Visible beacon
• Below the 75 dBA criteria
• Exceedance caused by traffic on
the upper road network
Projet de corridor du nouveau pont Champlain
Noise Impact
8
Noise tracking at 7070 Place Turenne
in Brossard
Soundlevel(dBa)
Noise limit
Projet de corridor du nouveau pont Champlain
Community relations
9
• Presentation at the Club Optimiste Clamplain-Brossard:
1st November 2016
• Presentation in a primary school in Saint-Lambert : 2
December 2016
• Presentation at Association des gens d’affaires de Brossard :
7 December 2016
Projet de corridor du nouveau pont Champlain
A great achievement of our workers
›Dons
Projet de corridor du nouveau pont Champlain
Complaints Handling
(April 29 to September 20, 2016)
Thématique
Brossard
Fermées Ouvertes Total
Noise 2 1 3
Air Quality 2 - 2
Traffic 3 - 3
Vibrations - - -
Brightness 2 - 2
Other - - -
Total 9 1 10
11
Eight complaints in the previous period from April 30 to September 20, 2016
Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months-
South Shore
Projet de corridor du nouveau pont Champlain
Location of Work Areas
City of Brossard
Cable-stayed
bridge
Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management
• Preparatory works for the configuration of the highway 10
East Approch
• Installation of prefabricated segments of piers and pier caps
• Continue the construction of the east abutment, including the building housing the
electric systems
• Preparations for the construction of the span above Route 132
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore
Priorities : January to June 2017
14
Projet de corridor du nouveau pont Champlain
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
15
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Travaux en cours et à venir :
• Placement of prefabricated segments of piers and pier caps
• Continue the construction of the abutment, including the building housing the
electric systems
• Preparatory works for the construction of the span above Highway 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels)
are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are
too significant
East Approach Area
17
Projet de corridor du nouveau pont Champlain
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
18
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of piers and
pier caps
Assembly of
superstructure and deck
Finishing work
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
19
Placement of prefabricated segments
of piers and pier caps
Duration: eight months
Projected period: October 2016 to Summer 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
20
Construction of East Abutment’s building
Duration: four months
Projected period: April to July 2017
Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
Preparatory works for the construction of the span
above Highway 132
Duration : four months
Projected period: april to july 2017
21
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Highway 10
Conception et planification en développement
donc des modifications sont possibles
Projet de corridor du nouveau pont Champlain
Highway 10 Area
23
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Work underway:
• Soil storage
• Earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
Upcoming Works
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Soil management and creation of a retaining basin
Duration: throughout the project
Projected period: 2016 to 2019
24
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Earthworks at the eastern abutment
Duration: one year
Projected period: April 2016 to Spring 2017
25
Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Installation of permanent anti-noise walls
Duration : three months
Projected period: summer / fall 2017
26
Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
28
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
7. Main span
March 2017 to
September 2018
3. Rear span
November 2015 to July 2017
6. Upper pylon
February to December
2017
4. Lower pylon
May to October 2016
5. Lower crossbeam
October to February 2017
Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
29
Construction of the lower pylon and the rear span
Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
Installation of the lower crossbeam
Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the
seaway dike
31
Ponctual closing of variable duration for the seasons 2017 and 2018
et, if necessary, long term closing
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
Projet de corridor du nouveau pont Champlain
Anticipated Impacts
Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
• Air quality
33
Projet de corridor du nouveau pont Champlain
Traffic
• Disruptions to come
• Upcoming major disruptions for the Spring / Summer 2017 : installation
of superstructure and deck above Highway 132 traffic lanes
34
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary
scaffolding
March / April
2017
1 week
Passage of pier caps pieces May 2017 8 nights
Route Deviation from route 132 & boul.
Marie-Victorin
May 2017 2 years
Projet de corridor du nouveau pont Champlain
Passage of Pier Caps Pieces
35
Projet de corridor du nouveau pont Champlain
Steel Pier Caps
36
Projet de corridor du nouveau pont Champlain 37
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Area
Activity
Period
D/E/N
Exposed
sensitive
area
Ambient
noise
dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
D B1/B2 60/62 75 62/63 Not required
Construction
of building (east abutment)
D B2 62 75 66 Not required
Placement of prefabricated
segments of piers and
pier caps
D/E-N B2 62 75/67 To come
A10
Earthworks at the Eastern
Abutment
D B2 62 75
Cable-
stayed
Miscellaneous work D B1/B2 60/62 75 61/64 Not required
EastApproach
D B2 62 75
Preparatory works Highway
132
To come
Installation of permanent anti-
noise walls
Monitoring
required
73
Monitoring
required
75
Projet de corridor du nouveau pont Champlain
Air Quality Management
• Migitation measures : increased environmental monitoring + Frequent
water spaying and cleaning
• Regulatory framework : Contractual environmental obligations and
Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
38
Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
39
SSL
• Follow-up on the impacts of the new site exit
• Date for the installations of anti-noise walls
• Landscaping and building of the east abutment
Ville de Brossard
• Communications regarding the detour for cyclists during the
reconstruction of Panama
INFC (discuss previously)
• Follow-up on the anti-noise walls
• LED lighting tracking
Projet de corridor du nouveau pont Champlain
Next meetings
Projet de corridor du nouveau pont Champlain
Good Neighbourly Relations
Committee :
 10 or 17 may (to be confirmed)
 Topics:
 Mobility
 Landscaping
A site visit is planned for Friday 5 May in
the afternoon
Next meetings
41
Projet de corridor du nouveau pont Champlain
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and
notices in local newspapers
• Sign up / contact us:
 Website: www.newchamplain.ca
 Email: info@sslc.ca
 Phone us at: (514) 876-1020
 Twitter: @NOUV_CHAMPLAIN
Communication
42

More Related Content

What's hot

Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
Crosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 

What's hot (20)

Details of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlainDetails of anti noise walls - june 15 2016 - nouveau pont champlain
Details of anti noise walls - june 15 2016 - nouveau pont champlain
 
Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016
 
Presentation anti noise walls good neighbourly relations committee City of Br...
Presentation anti noise walls good neighbourly relations committee City of Br...Presentation anti noise walls good neighbourly relations committee City of Br...
Presentation anti noise walls good neighbourly relations committee City of Br...
 
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
 
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...Meeting of the verdun / le sud ouest - good neighbourly relations committee  ...
Meeting of the verdun / le sud ouest - good neighbourly relations committee ...
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
Meeting of the verdun le sud ouest good neighbourly relations committee - Jun...
 
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 BroadwayAlamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Plan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structuresPlan for major repairs and maintenance work on JCCBI structures
Plan for major repairs and maintenance work on JCCBI structures
 
2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Leaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingLeaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee Meeting
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
2018 Planning
2018 Planning2018 Planning
2018 Planning
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 

Similar to Good neighbourly relations committee meeting - Brossard - January 25, 2017

Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Crosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 

Similar to Good neighbourly relations committee meeting - Brossard - January 25, 2017 (20)

Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee - Apri...
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Review of work in 2016
Review of work in 2016Review of work in 2016
Review of work in 2016
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
JCCBI 2015 Project Report
JCCBI 2015 Project ReportJCCBI 2015 Project Report
JCCBI 2015 Project Report
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Queen street station tunnel or throat development rodger querns
Queen street station tunnel or throat development  rodger quernsQueen street station tunnel or throat development  rodger querns
Queen street station tunnel or throat development rodger querns
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Firas Abbawy CV - Atkins
Firas Abbawy CV - AtkinsFiras Abbawy CV - Atkins
Firas Abbawy CV - Atkins
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 

More from Pont Samuel-De Champlain Bridge

More from Pont Samuel-De Champlain Bridge (20)

Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
Virtual Public Information Meeting: Noise Barriers in Verdun / Le Sud-Ouest -...
 
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
Rencontre information publique virtuelle : murs anti-bruit dans les secteurs ...
 
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
Coulisses du pont Samuel-De Champlain - Chantier de l'emploi - Montreal - 12 ...
 
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
Boulevard René-Lévesque - Île-des-Soeurs - Mise a jour des travaux - 30 aout ...
 
Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019Mobilité Montreal - Document technique chantiers majeurs automne 2019
Mobilité Montreal - Document technique chantiers majeurs automne 2019
 
Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019Mobilité Montréal - Présentation chantiers majeurs automne 2019
Mobilité Montréal - Présentation chantiers majeurs automne 2019
 
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
Briefing media - Ouverture du pont samuel-de champlain - 17 juin 2018
 
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
Rencontre de comité de bon voisinage Brossard - 29 mai 2019 - Projet de corri...
 
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
Comité de bon voisinage Verdun / Île-des-Soeurs / Le Sud-Ouest - 16 mai 2019
 
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
En route vers l'ouverture du pont Samuel-De Champlain - 11 avril 2019 - aga b...
 
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
Scénarios de mobilité à L'Ile-des-soeurs - Rencontre avec les commerçants et ...
 
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
Scénarios de mobilité - Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fe...
 
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
Comité de bon voisinage Verdun / Le Sud-Ouest - 20 fevrier 2019
 
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
Compte rendu comite de bon voisinage brossard - nouveau pont champlain - 26 s...
 
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
Compte-rendu comité de bon voisinage Verdun - Le Sud-Ouest du 12 septembre 2018
 
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
Mobilité Montréal : chacun fait partie de la solution - Rencontre d'informati...
 
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
Mobilite verdun et ile des-soeurs - Mise à jour du 26 novembre 2018 - Nouveau...
 
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
Nouveau pont champlain : pas tres loin du but - Briefing technique et visite ...
 
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
Scénarios de mobilit. dans le secteur Île-des-Soeurs - Mise-à-jour du 8 octob...
 
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
Scénarios de mobilité dans le secteur de L'Île-des-Soeurs - Mise à jour du 27...
 

Recently uploaded

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Recently uploaded (20)

UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

Good neighbourly relations committee meeting - Brossard - January 25, 2017

  • 1. Good Neighbourly Relations Committee Meeting City of Brossard : 25 january 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.
  • 2. Projet de corridor du nouveau pont Champlain 2 Committee Members Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
  • 3. Projet de corridor du nouveau pont Champlain 1. Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning 2. Provide information about the work that has been completed, is underway and planned between now and July 2017 3. Answer questions, find potential solutions and discuss the issues Objectives of the Meeting 3
  • 4. Projet de corridor du nouveau pont Champlain Agenda 4 Série Item Durée Heure 1. Opening 10 min. 19h00 à 19h10 2. Anti-noise wall : update 20 min. 19h10 à 19h30 3. Question period 10 min. 19h30 à 19h40 4. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area 40 min. 19h40 à 20h20 5. Question period 20 min. 20h20 à 20h40 6. Varia 15 min. 20h40 à 20h55 7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00
  • 5. Projet de corridor du nouveau pont Champlain Work Completed over the Past Few Months
  • 6. Projet de corridor du nouveau pont Champlain Survol des travaux complétés 6 • Fall season: solid work progress in general on the East Approach  Construction of footings and pier bases completed  Beginning of installation of prefabricated segments of piers and pier caps  Continue the construction of the east abutment • Installation of the new construction site exit • Very few complaints, mainly about the new construction site exit (5 on 8)
  • 7. Projet de corridor du nouveau pont Champlain Impacts: new construction site exit 7 Impact sonore Visual impactMobility impact Noise impactOpening of the new construction site exit Duration : 3 years Period : 2017 à 2019 • No incidents recorded or reported • Flow rate : 75 to 150 car / day 10 à 30 car/ night • Installation of a visual screen • Visible beacon • Below the 75 dBA criteria • Exceedance caused by traffic on the upper road network
  • 8. Projet de corridor du nouveau pont Champlain Noise Impact 8 Noise tracking at 7070 Place Turenne in Brossard Soundlevel(dBa) Noise limit
  • 9. Projet de corridor du nouveau pont Champlain Community relations 9 • Presentation at the Club Optimiste Clamplain-Brossard: 1st November 2016 • Presentation in a primary school in Saint-Lambert : 2 December 2016 • Presentation at Association des gens d’affaires de Brossard : 7 December 2016
  • 10. Projet de corridor du nouveau pont Champlain A great achievement of our workers ›Dons
  • 11. Projet de corridor du nouveau pont Champlain Complaints Handling (April 29 to September 20, 2016) Thématique Brossard Fermées Ouvertes Total Noise 2 1 3 Air Quality 2 - 2 Traffic 3 - 3 Vibrations - - - Brightness 2 - 2 Other - - - Total 9 1 10 11 Eight complaints in the previous period from April 30 to September 20, 2016
  • 12. Projet de corridor du nouveau pont Champlain Main Priorities for the Upcoming Months- South Shore
  • 13. Projet de corridor du nouveau pont Champlain Location of Work Areas City of Brossard Cable-stayed bridge
  • 14. Projet de corridor du nouveau pont Champlain Highway 10 • Soil management • Preparatory works for the configuration of the highway 10 East Approch • Installation of prefabricated segments of piers and pier caps • Continue the construction of the east abutment, including the building housing the electric systems • Preparations for the construction of the span above Route 132 Cable-stayed bridge • Construction of main pylon and rear span South Shore Priorities : January to June 2017 14
  • 15. Projet de corridor du nouveau pont Champlain Description of Activity Approximate Duration of Works Planned Work Period Legend: Work and Impacts • Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths: Minor impact Medium impact Major impact Indication by level colour code 15
  • 16. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come - East Approach Design and planning underway so modifications are possible
  • 17. Projet de corridor du nouveau pont Champlain Objective: Construction of East Approach of the new Champlain Bridge Travaux en cours et à venir : • Placement of prefabricated segments of piers and pier caps • Continue the construction of the abutment, including the building housing the electric systems • Preparatory works for the construction of the span above Highway 132 Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant East Approach Area 17
  • 18. Projet de corridor du nouveau pont Champlain Nov 2015 May Nov 2016 May Nov. 2017 Nov 2018 May East Approach: Timetable 18 Feb 2016 Aug Feb 2017 Aug. Feb. 2018 Aug. Construction of footings and pier bases Installation of piers and pier caps Assembly of superstructure and deck Finishing work
  • 19. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach 19 Placement of prefabricated segments of piers and pier caps Duration: eight months Projected period: October 2016 to Summer 2017
  • 20. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach 20 Construction of East Abutment’s building Duration: four months Projected period: April to July 2017
  • 21. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach Preparatory works for the construction of the span above Highway 132 Duration : four months Projected period: april to july 2017 21
  • 22. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Highway 10 Conception et planification en développement donc des modifications sont possibles
  • 23. Projet de corridor du nouveau pont Champlain Highway 10 Area 23 Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links Work underway: • Soil storage • Earthworks at the eastern abutment • Creation of a retaining basin for permanent drainage Upcoming Works • Installation of permanent anti-noise walls Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Night-time trucking from the West Approach to the East Approach
  • 24. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019 24
  • 25. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Earthworks at the eastern abutment Duration: one year Projected period: April 2016 to Spring 2017 25
  • 26. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Installation of permanent anti-noise walls Duration : three months Projected period: summer / fall 2017 26
  • 27. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Cable-stayed Bridge Design and planning underway so modifications are possible
  • 28. Projet de corridor du nouveau pont Champlain Cable-stayed Bridge: Timetable 28 2. Pylon foundations October 2015 to April 20161. Jetty August to October 2015 7. Main span March 2017 to September 2018 3. Rear span November 2015 to July 2017 6. Upper pylon February to December 2017 4. Lower pylon May to October 2016 5. Lower crossbeam October to February 2017
  • 29. Projet de corridor du nouveau pont Champlain Key activities since fall 2016 29 Construction of the lower pylon and the rear span
  • 30. Projet de corridor du nouveau pont Champlain Key activities since fall 2016 Installation of the lower crossbeam
  • 31. Projet de corridor du nouveau pont Champlain Works and impacts : Bike path of the seaway dike 31 Ponctual closing of variable duration for the seasons 2017 and 2018 et, if necessary, long term closing Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
  • 32. Projet de corridor du nouveau pont Champlain Anticipated Impacts
  • 33. Projet de corridor du nouveau pont Champlain Anticipated impacts • Road traffic • Noise • Air quality 33
  • 34. Projet de corridor du nouveau pont Champlain Traffic • Disruptions to come • Upcoming major disruptions for the Spring / Summer 2017 : installation of superstructure and deck above Highway 132 traffic lanes 34 Configuration – Disruptions Schedule Duration Installation of foundations and temporary scaffolding March / April 2017 1 week Passage of pier caps pieces May 2017 8 nights Route Deviation from route 132 & boul. Marie-Victorin May 2017 2 years
  • 35. Projet de corridor du nouveau pont Champlain Passage of Pier Caps Pieces 35
  • 36. Projet de corridor du nouveau pont Champlain Steel Pier Caps 36
  • 37. Projet de corridor du nouveau pont Champlain 37 B1: Turenne area B2: Voltaire area B3: Tisserand area Noise Management Area Activity Period D/E/N Exposed sensitive area Ambient noise dBA Criterion dBA Estimated noise dBA Required measures D B1/B2 60/62 75 62/63 Not required Construction of building (east abutment) D B2 62 75 66 Not required Placement of prefabricated segments of piers and pier caps D/E-N B2 62 75/67 To come A10 Earthworks at the Eastern Abutment D B2 62 75 Cable- stayed Miscellaneous work D B1/B2 60/62 75 61/64 Not required EastApproach D B2 62 75 Preparatory works Highway 132 To come Installation of permanent anti- noise walls Monitoring required 73 Monitoring required 75
  • 38. Projet de corridor du nouveau pont Champlain Air Quality Management • Migitation measures : increased environmental monitoring + Frequent water spaying and cleaning • Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR) Applicable MDDELCC standards MDDELCC CAR PMt PM2.5 120 ug/m3 30 ug/m3 38
  • 39. Projet de corridor du nouveau pont Champlain Follow-up on Interventions 39 SSL • Follow-up on the impacts of the new site exit • Date for the installations of anti-noise walls • Landscaping and building of the east abutment Ville de Brossard • Communications regarding the detour for cyclists during the reconstruction of Panama INFC (discuss previously) • Follow-up on the anti-noise walls • LED lighting tracking
  • 40. Projet de corridor du nouveau pont Champlain Next meetings
  • 41. Projet de corridor du nouveau pont Champlain Good Neighbourly Relations Committee :  10 or 17 may (to be confirmed)  Topics:  Mobility  Landscaping A site visit is planned for Friday 5 May in the afternoon Next meetings 41
  • 42. Projet de corridor du nouveau pont Champlain • Newsletter: sign up online • Information sheets delivered to residents’ homes, if required, and notices in local newspapers • Sign up / contact us:  Website: www.newchamplain.ca  Email: info@sslc.ca  Phone us at: (514) 876-1020  Twitter: @NOUV_CHAMPLAIN Communication 42