- Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning
- Provide information about the work that has been completed, is underway and planned between now and July 2017
- Answer questions, find potential solutions and discuss the issues
Good neighbourly relations committee meeting - Brossard - January 25, 2017
1. Good Neighbourly Relations Committee
Meeting
City of Brossard : 25 january 2017
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
Please note that the English version is used
only for refernce purposes. In case of
disrepancy between the English and French
versions, the French version shall prevail.
2. Projet de corridor du nouveau pont Champlain 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Jaime Reis
Marc Turcotte – Representative from a community
organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Vincent Jarry – Infrastructure Canada
3. Projet de corridor du nouveau pont Champlain
1. Follow up on the various files under the responsibility of
Infrastructure Canada : anti-noise wall and DEL lightning
2. Provide information about the work that has been
completed, is underway and planned between now and
July 2017
3. Answer questions, find potential solutions and discuss the
issues
Objectives of the Meeting
3
4. Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Anti-noise wall : update 20 min. 19h10 à 19h30
3. Question period 10 min. 19h30 à 19h40
4. Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 19h40
à 20h20
5. Question period 20 min. 20h20 à 20h40
6. Varia 15 min. 20h40 à 20h55
7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00
5. Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
6. Projet de corridor du nouveau pont Champlain
Survol des travaux complétés
6
• Fall season: solid work progress in general on the
East Approach
Construction of footings and pier bases completed
Beginning of installation of prefabricated segments
of piers and pier caps
Continue the construction of the east abutment
• Installation of the new construction site exit
• Very few complaints, mainly about the new
construction site exit (5 on 8)
7. Projet de corridor du nouveau pont Champlain
Impacts:
new construction site exit
7
Impact sonore
Visual impactMobility impact
Noise impactOpening of the new construction site exit
Duration : 3 years
Period : 2017 à 2019
• No incidents recorded or reported
• Flow rate : 75 to 150 car / day
10 à 30 car/ night
• Installation of a visual screen
• Visible beacon
• Below the 75 dBA criteria
• Exceedance caused by traffic on
the upper road network
8. Projet de corridor du nouveau pont Champlain
Noise Impact
8
Noise tracking at 7070 Place Turenne
in Brossard
Soundlevel(dBa)
Noise limit
9. Projet de corridor du nouveau pont Champlain
Community relations
9
• Presentation at the Club Optimiste Clamplain-Brossard:
1st November 2016
• Presentation in a primary school in Saint-Lambert : 2
December 2016
• Presentation at Association des gens d’affaires de Brossard :
7 December 2016
10. Projet de corridor du nouveau pont Champlain
A great achievement of our workers
›Dons
11. Projet de corridor du nouveau pont Champlain
Complaints Handling
(April 29 to September 20, 2016)
Thématique
Brossard
Fermées Ouvertes Total
Noise 2 1 3
Air Quality 2 - 2
Traffic 3 - 3
Vibrations - - -
Brightness 2 - 2
Other - - -
Total 9 1 10
11
Eight complaints in the previous period from April 30 to September 20, 2016
12. Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months-
South Shore
13. Projet de corridor du nouveau pont Champlain
Location of Work Areas
City of Brossard
Cable-stayed
bridge
14. Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management
• Preparatory works for the configuration of the highway 10
East Approch
• Installation of prefabricated segments of piers and pier caps
• Continue the construction of the east abutment, including the building housing the
electric systems
• Preparations for the construction of the span above Route 132
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore
Priorities : January to June 2017
14
15. Projet de corridor du nouveau pont Champlain
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
15
16. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
17. Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Travaux en cours et à venir :
• Placement of prefabricated segments of piers and pier caps
• Continue the construction of the abutment, including the building housing the
electric systems
• Preparatory works for the construction of the span above Highway 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels)
are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are
too significant
East Approach Area
17
18. Projet de corridor du nouveau pont Champlain
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
18
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of piers and
pier caps
Assembly of
superstructure and deck
Finishing work
19. Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
19
Placement of prefabricated segments
of piers and pier caps
Duration: eight months
Projected period: October 2016 to Summer 2017
20. Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
20
Construction of East Abutment’s building
Duration: four months
Projected period: April to July 2017
21. Projet de corridor du nouveau pont Champlain
Works and Impacts: East Approach
Preparatory works for the construction of the span
above Highway 132
Duration : four months
Projected period: april to july 2017
21
22. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Highway 10
Conception et planification en développement
donc des modifications sont possibles
23. Projet de corridor du nouveau pont Champlain
Highway 10 Area
23
Objective: Area reserved for soil management for the work site and preparatory
work for the reconfiguration of highway links
Work underway:
• Soil storage
• Earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
Upcoming Works
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
24. Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Soil management and creation of a retaining basin
Duration: throughout the project
Projected period: 2016 to 2019
24
25. Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Earthworks at the eastern abutment
Duration: one year
Projected period: April 2016 to Spring 2017
25
26. Projet de corridor du nouveau pont Champlain
Works and Impacts: Highway 10
Installation of permanent anti-noise walls
Duration : three months
Projected period: summer / fall 2017
26
27. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
28. Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
28
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
7. Main span
March 2017 to
September 2018
3. Rear span
November 2015 to July 2017
6. Upper pylon
February to December
2017
4. Lower pylon
May to October 2016
5. Lower crossbeam
October to February 2017
29. Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
29
Construction of the lower pylon and the rear span
30. Projet de corridor du nouveau pont Champlain
Key activities since fall 2016
Installation of the lower crossbeam
31. Projet de corridor du nouveau pont Champlain
Works and impacts : Bike path of the
seaway dike
31
Ponctual closing of variable duration for the seasons 2017 and 2018
et, if necessary, long term closing
Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
33. Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
• Air quality
33
34. Projet de corridor du nouveau pont Champlain
Traffic
• Disruptions to come
• Upcoming major disruptions for the Spring / Summer 2017 : installation
of superstructure and deck above Highway 132 traffic lanes
34
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary
scaffolding
March / April
2017
1 week
Passage of pier caps pieces May 2017 8 nights
Route Deviation from route 132 & boul.
Marie-Victorin
May 2017 2 years
35. Projet de corridor du nouveau pont Champlain
Passage of Pier Caps Pieces
35
37. Projet de corridor du nouveau pont Champlain 37
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Area
Activity
Period
D/E/N
Exposed
sensitive
area
Ambient
noise
dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
D B1/B2 60/62 75 62/63 Not required
Construction
of building (east abutment)
D B2 62 75 66 Not required
Placement of prefabricated
segments of piers and
pier caps
D/E-N B2 62 75/67 To come
A10
Earthworks at the Eastern
Abutment
D B2 62 75
Cable-
stayed
Miscellaneous work D B1/B2 60/62 75 61/64 Not required
EastApproach
D B2 62 75
Preparatory works Highway
132
To come
Installation of permanent anti-
noise walls
Monitoring
required
73
Monitoring
required
75
38. Projet de corridor du nouveau pont Champlain
Air Quality Management
• Migitation measures : increased environmental monitoring + Frequent
water spaying and cleaning
• Regulatory framework : Contractual environmental obligations and
Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
38
39. Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
39
SSL
• Follow-up on the impacts of the new site exit
• Date for the installations of anti-noise walls
• Landscaping and building of the east abutment
Ville de Brossard
• Communications regarding the detour for cyclists during the
reconstruction of Panama
INFC (discuss previously)
• Follow-up on the anti-noise walls
• LED lighting tracking
41. Projet de corridor du nouveau pont Champlain
Good Neighbourly Relations
Committee :
10 or 17 may (to be confirmed)
Topics:
Mobility
Landscaping
A site visit is planned for Friday 5 May in
the afternoon
Next meetings
41
42. Projet de corridor du nouveau pont Champlain
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and
notices in local newspapers
• Sign up / contact us:
Website: www.newchamplain.ca
Email: info@sslc.ca
Phone us at: (514) 876-1020
Twitter: @NOUV_CHAMPLAIN
Communication
42