6. www.bestppt.com
WHA
THOW
WHY
?
BIM Definition
US National BIM Standard v1, 2007
“A digital representation of physical and functional characteristics of
a facility. A BIM is a shared knowledge resource for information
about a facility forming a reliable basis for decisions during its life-
cycle; defined as existing from earliest conception to demolition.”
7. SUTTER CASTRO VALLEY
WHY: Sutter Health + OSHPD State Requirements
Seismic Fault Lines
San Francisco Bay, CA
10. 3D Detailing and Coordination in Tekla
Shop Drawing Generation is Direct Output from Tekla Model
BIM Use: Direct 3D to 2D Field Drawings
11. The First Discovery: Rebar vs. Precast Sleeve
• 200+ Facade penetrations or embed were coordinated with rebar and MEP.
• Precast subcontractor did not originally account for rebar spacing during design.
• Over 25% of Connection designs were changed due to BIM Coordination
BIM Use: Precast Façade Connections
14. A Coordinated BIM is only as valuable as the
deliverable that it produces!
Design Drawings
?
=
? Shop Drawings
The Question Becomes…Risk: Design to Fabrication Reliability
15. How do you check?Countermeasure: 2D Fabrication to BIM
Design Assist Subcontractors Provided CAD to Align in Tekla
16. From 2D Shop Drawings…..From 2D to 3D BIM ….. Not Lean, but Effective!
21. BIM + Lean: Last Responsible Moment
• OPTION #2: Roof Slope redesigned 4 weeks prior to roof concrete pour
• Required 3 new drains to be coordinated with existing MEP BIM
22. TRUST: CONSTRUCTABILITY INPUTHOW: Shared Risk & Reward with MEP Trades
• Routed 3 additional drains to a nearby riser in BIM
• New drainage calculation of the redesigned sloping
• Confirmed LEED requirements of roof still held
• Poured concrete roof slab on schedule
23. TRUST: TRADES INSTALL FROM BIMBIM Use: Automated Spool Fabrication from BIM
Courtesy of McClanahan Plumbing
24. SYNERGY: BIM + TOTAL STATIONBIM Use: Integrated Total Station Layout
Use of Robotic Total Station (RTS) in Conjunction
with Coordinated MEP Inserts in BIM
4X Productivity Compared to Conventional Layout
Courtesy of McClanahan Plumbing
33. Robotic Total Station
Better for model vs. field comparison
of large areas/entire site
Countermeasure: Digital As-Builting
Better for specific points (end of wall,
bottom of door threshold, etc)
Laser Scanning
34. Courtesy of Trimble Navigation ltd.
BIM Use: Modeling of Unforseen Conditions
35. Design allows for maximum 3” tolerance for placement of piles
As-Built pile layout showed deviations up to 12” in more difficult locations
Risk: Misplaced Piles & Rebar Design Changes
36. Robotic Total Station points were captured immediately following pile placement
to early identify misplaced piles and begin design change and approval process
Within Tolerance
Out of Tolerance – Change in Rebar
Out of Tolerance –No Rebar Changes
BIM Use: Digital Check for Deviations
37. BIM Use: Coordination of Rebar & Structural Steel
2D constructability markup
Steel Plate Penetrations Aligned
with new Rebar Design
38. The Process
2D Shop
Drawings
Shop Drawing
Review
Fabricate
Rebar
Install Rebar
3D Model
Lean Innovation: Cloud Rebar Submittal Reviews
52. =
Success Metric: Early Schedule Savings
Concrete Foundations
31 Days
Of Critical Path Schedule
Recovered over 10 Months
33%
Time Savings Per
Submittal Review
53.
54. A Tale of Two Projects: IPD Lessons Learned
Castro Valley Delivered
6 Weeks
Ahead of Schedule
Maintained
Target Cost
Alta Bates Delivered
6 Months
Behind Schedule
20 Million
Over Target Cost
56. The Castro Valley Difference: Culture
Team members chorus: Don’t try this with strangers.
Expect lengthy contract negotiations and endless
meetings.
Be vigilant about communicating.
“The actual effort required was underestimated on
both the design and construction sides,” says James
Mobley, a Devenney principal.
60. TOOL
SHIFTING THE INDUSTRY PARADIGM
PEOPLE PROCESS
BIM is just a Tool1
This Tool is only as good as
the People using It
2
The People can only be as
effective as the Process allows them to be
3
The Role of BIM in Design & Construction
61. Christian, D., Bredbury, J., Emdanat, S., Haase, F., Kunz, A., Rubel, Z. and Ballard, G. (2014). “Four-phase project delivery and the pathway to
perfection.” In: Proc. 22nd Ann. Conf. of the Int’l Group for Lean Construction, IGLC-22, Oslo, Norway, June 25- 27. Available at <www.iglc.net>
Trust in BIM Starts with Lean Handoffs
62. 3D Model 2D Drawings
DesignFabrication
62
Challenge: BIM Handoffs in the Real World
63. • Does this…..
• Equal this?
Design Model
Fabrication Model
Risk: Loss of Reliable BIM for Coordination
65. 3D Model 2D Drawings
DesignerDetailer
65
Risk: New Process, Old Contract?
66. “Virtually everyone in the
construction supply chain works
on contracts where the incentive
is to maximize their gain at the
expense of others”
Macomber, John D. 2003 ASCE Report:
“Follow the Money: What Really Drives
Technology Innovation In Construction”
Root Cause Analysis: Contract Incentives
67. Result: Insufficient Funding for Technology
0 1 2 3 4 5 6 7
Construction
Energy
Manufacturing
Transportation
Healthcare
Education
Finance
IT Spending as a % of Revenue, By Industry [Gartner 2014]
3.3%
Cross-Industry
Average
3.3x
Investment Gap
68. ARE WE RIPE FOR DISRUPTION?
“It’s more likely…that new firms with new business
models and new areas of focus will leverage the
financial and technological innovations that will
change the nature of competition”
-Clayton Christensen, 1997
The Future of BIM Adoption in USA
IPD Contract Relationship
-
Design-Build Contract Structure
-
?
=
?
Concrete shear walls along perimeter on L1-3
Congested reinforcing in boundary elements
500 wall embeds and penetrations for precast
As unforseen conditions were discovered, trimble total station was used to document as-built location of obstructions, so that we could bring them into the model to see what future construction it would impact
TRAINER NOTE:
We are shifting our mindset away from the notion that everyone needs to know everything about BIM. Instead, we should be thinking about BIM as a Construction Tool that needs to be used by the right people at the right time to input construction knowledge into the model. And we need to make sure that our BIM processes are aligned with our current roles, so that it doesn’t create additional work.
ADDITIONAL INFO:
Bullet point 3 can seem controversial at first. What we’re trying to say is that a poorly planned process (or no process at all) can limit a person’s ability to perform – regardless of experience, talent, knowledge, etc.
Example: Navisworks is a particular BIM tool. If I were an expert at using Navisworks, but had no idea how to apply that to coordinating building systems – my skills would be useless. The process can be “make or break”.
Animation describes the current process from a designer revit model to flattened 2D drawings for steel fabrication.