  1. 1. National Aeronautics and Space Administration A Project Management Toolkit for Space Flight Projects Vincent J. Bilardo, Jr., PMP Susan E. Kolibas, PMP NASA Glenn Research Center Presented at NASA Project Management Challenge Conference February 23, 2012 www.nasa.gov
  2. 2. Content • Context • Toolkit Current State • Toolkit Data Flow • Demonstration • Lessons Learned • Toolkit Future State • Payoff National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 2
  3. 3. Context Toolkit development driven by NASA Glenn Research Center’s Strategic Action Plan Strategic Goal 3: Deliver Program and Center Governance Structure Project Management Established Operating Rigorous Excellence (PPME) Cadence (Monthly Processes (NPR, GLPR, HBK, that results in Reviews, PPBE, Mile stone Calendar) etc) successful missions PPME Framework for our customers and Execution Standardized Metrics Tools challenging, long-term (EVM, Budget (Project Execution, Procure Management assignments for ment Execution, etc) Trained Proficient Toolkit) continued Staff (PMs, PP&C Staff, achievements. Team Members) National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 3
  4. 4. A Little History… What is the Project Manager’s Toolkit? PROJECT MANAGER’S TOOLKIT A web-served collection of user friendly tools that enable rigorous project planning! • Incorporates NASA standards and best practices: •NPR 7120.5c and 7123 •Competency Mgt System • Fully tailorable to user’s unique project needs • Puts powerful project formulation tools at user’s fingertips: •Historical Program Database NASA SimVision® models people at work •Design Structure Matrix Organization Simulation Technology •Analytical Hierarchy Process •Project Simulation Organizational norms shape their work, communications, 2006 Page 5 Meeting decisions, and leadership Decision Meeting Rework Twenty-five years of Stanford Rework Communication Direct Work University research and ten Direct Work Decision years of commercial application Communication Direct Work validate its accuracy and Delivering an reliability We have modeled NASA's VAMS (Virtual Airspace Modeling operational Rework System) project and the Constellation Systems Coordination Engineering organization 2011 Toolkit is not SimVision is part of the NASA Project Manager’s Toolkit easy! 2008 2/13/2012 PMC 2008 Ares I-X Upper Stage Simulator Team 12 National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 4
  5. 5. Current Toolkit Portal – Feb 2012 The PPME Toolkit is an online one-stop portal developed to facilitate rigorous, compliant, life cycle-based: - Proposal Development - Project Planning - Project Execution - Project Control & Reporting National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 5
  6. 6. Current Toolkit Portal GLenn Procedural Requirements (GLPRs) developed to implement NASA Procedural Requirements 7120.5, 7123.1, 7150.2, 8700.X National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 6
  7. 7. Current Toolkit Portal Toolkit brings GLPRs “to life” by serving up the process flows and templates via mouse clicks National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 7
  8. 8. Toolkit Standardizes Project Planning WBS: • Standard Work X Level 0 Top Level Project Life Cycle Milestones Breakdown WBS: X.Y Structure Project Level 1 WBS Elements / through each Control Accounts Team defines WBS: project phase X.Y.Z the Level 2 Work / Planning Packages Resource Loaded Schedule WBS: • Facilitates X.Y.Z.A (RLS) Level 3 communication Tasks / Deliverable Products between Performi WBS: ng Orgs X.Y.Z.A.B Projects and assign Level 4 Staffing Assignments Performing Orgs staff by name to project tasks National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 8
  9. 9. Toolkit Data Flow PPBE Cycle Planning Mode Execution Mode (prior to FY start) (after FY start) Project Planning & Estimating (PP&E) EVM System Obs, Costs Actuals Template Baseline Plan, Cobra / Winsight .xlw Enterprise Schedule, Budget Server Updates Resource Loaded Reporting Data Translator Schedule (RLS) Templates .mpp .xlw , .pdf, .ppt GRC ICA Financial Data Translator Template Systems .xlw or .pdf e.g. SAP/BW Data GRC Cost Translator Model .xlw Agency Data Phasing Plan Budget Translator Template Systems .xlw e.g. PMT Schedule PPME Toolkit Status Legacy Tools/Systems Schedule Updates Reports National Aeronautics and Space Administration
  10. 10. Project Planning & Estimating (PP&E) Template Demo • PP&E to Resource Loaded Schedule (RLS) Data Translation National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 10
  11. 11. Demo: Project Planning & Estimating Template enables single point of entry WBS definition and resource estimating, automatically translated into Microsoft Project Define the WBS Elements National Aeronautics and Space Administration Space Flight Systems Project Forum 09/26/2011 11
  12. 12. The Project Planning & Estimating Template enables single point of entry WBS definition and resource estimating, automatically translated into Microsoft Project Define the WBS Elements Add Tasks, Durations , and Resource Document Estimates Basis of Estimate National Aeronautics and Space Administration Space Flight Systems Project Forum 09/26/2011 12
  13. 13. The Project Planning & Estimating Template enables single point of entry WBS definition and resource estimating, automatically translated into Microsoft Project Define the WBS Elements Add Tasks and Resource Estimates Import into Microsoft Project Resource Loaded Schedule template National Aeronautics and Space Administration Space Flight Systems Project Forum 09/26/2011 13
  14. 14. Resource Loaded Schedule (RLS) Demo • RLS to Cost Model Data Translation • RLS to Phasing Plan Data Translation National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 14
  15. 15. RLS to Cost Model Translation Scheduled resources generate cost via standard National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 15
  16. 16. RLS to Cost Model Translation Translator setup: Filter by date range, FY, or WBS Output by year, quarter, or month National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 16
  17. 17. RLS to Cost Model Translation Output to Excel Includes estimate per resource code (hours for labor, $K for National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 17
  18. 18. RLS to Cost Model Translation Output to Excel includes  Cost by FY of each WBS Element National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 18
  19. 19. RLS to Cost Model Translation Output to Excel-based GRC Cost Model includes:  Cost by FY of each WBS Element  Total National Aeronautics and Space Administration Project Management Challenge 2012 Project February 23, 2012 19
  20. 20. RLS to Phasing Plan Translation Output to Excel-based GRC Phasing Plan template includes:  FTE labor hours by month  Procurement cost or obs basis phasing by month for each discrete procurement Phasing Plan templates rolled together by GRC OCFO and loaded to Agency Program Management Tool (PMT) National Aeronautics and Space Administration Space Flight Systems Project Forum 09/26/2011 20
  21. 21. Lessons Learned to Date • Develop and baseline a standard GRC Resource Breakdown Structure for use in all Toolkit tools and templates. • Develop set of RLS templates with standardized WBS/task structures by project category. - Develop standardized list of typical project deliverables and associated BOEs based on mining historic project actuals. • Develop work instructions, guidance, and training for each of the Toolkit modules to assist project teams with successful adoption. • Define a CM process for establishing the integrated cost-schedule baseline, and controlling changes to it. • Provide tailored level of scheduling support for smaller projects. • Solve the detail-level issues to ensure the RLS captures the complete integrated cost-schedule baseline: - Cost basis scheduling vs. obligation basis planning - Prior year un-costed carry-in - Center assessments and service pools - Accounting for “overhead” (e.g. meetings, training, etc.) - Balance RLS standardization (e.g. custom data field use) vs. scheduling flexibility National Aeronautics and Space Administration Project Management Challenge 2012 February 23, 2012 21
  22. 22. PPME Toolkit Portal - Future State Transition current PPME Toolkit portal from .html to MS SharePoint to enable: • Management Dashboards • Project Budget, Schedule, Risk Reporting • User & Project Team file sharing • Improved file management & search National Aeronautics and Space Administration 22
  23. 23. Resource Loaded Schedules – Future State Activate Portfolio Management via MS Project Enterprise Server Importing An Existing Schedule Imports and Saves Works Schedule Publishes Manages Schedule Monitors Existing and Saves to Schedule and Executes Portfolio Schedule Draft Database when ready Subsequent Data Onto (Does NOT Publications on Project Publish) the Server Server Scheduler Portfolio Analyst Draft / Published Reporting Archive Working (PWA) Production National Aeronautics and Space Administration 23
  24. 24. The Payoff: Why are we doing this? • Improve up front project planning. • Integrate cost, schedule, and technical baselines. • Increase efficiency and hands-on labor savings. • Streamline PPBE process and enable rigorous and faster PPBE responses. • Enable rapid “what if” analysis in response to budget & schedule changes. • Enable rapid, accurate requirement/technical change impact assessments. • Enable quick, accurate, centrally handled data call responses. • Enable true Space Flight Portfolio Management. National Aeronautics and Space Administration 09/26/2011 24

×