SlideShare a Scribd company logo
1 of 23
Certified Associate Project Management
CAPM® Exam Prep – Week 2
Muzette Charles | mcharles2@pace.edu
Project Management
Process Overview
• Review 5 Process Groups
• Review 10 Knowledge Areas
• Identify each of the 47 Project Processes by their Process Group
Integration Management
Chapter 4
“Is the Project Manager’s core responsibilities”
“…. is a group of processes required to ensure that the
various elements of the project are properly coordinated.”
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Key Points
 A project charter formally authorizes the project
 Gives the objectives and business case
 Identifies & authorizes Project Manager use of organizational resources for project use
 Generic enough not to change often
 Written by a Manager higher in authority than Project Manager
 Includes name, description, deliverables
 A project does not start unless it has a Project charter
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
INPUTS
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
TOOLS
 Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page
when making a project decision
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Project Integration Management
Chapter 4
Develop Project Management Plan (PMP)
Process 2
Key Points
 Key benefit: creates the central document that defines all of the project work
 How the project will be executed, monitored & controlled
 All of the 10 subsidiary plans are integrated into ONE comprehensive PMP
 The PMP is developed by the Project Manager with inputs from the team, stakeholders & management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Kick-off meeting happens after the planning phase and before the project execution. It is typically used
to communicate responsibilities of key stakeholders.
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Key Points
 Key benefit of this process is to provide overall management of the project work
 To lead & perform work as defined in the PMP
 Create deliverables to meet planned project work
 Manage team members & provide them with training
 Obtain, manage & use resources ex. Materials, Equipment, Facilities
 Establish & manage communications internal & external channels
 Manage Stakeholders, Sellers, Risks, Change Requests
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 4
Key Points
 Key benefit: allows stakeholders to understand current state of the project, any steps taken
and budget, schedule & scope forecasts
 Tracks, reviews & reports actual progress & performance against the PMP objectives
 Is conducted from project inception through completion
 Control includes corrective & preventative actions
 Identify & analyze existing and new risks
 Work Authorization System - PM’s system to ensure work is performed at the right time & in
the right sequence (found in the EEF – PMIS)
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 4
Key Points
 Change Requests
 are submitted when issues are found while project work is being performed
 is a formal (written) proposal to modify any document, baseline, deliverable
 Change Log – all WRITTEN requests approved or not
 PM has authority to make changes IF constraints are not effected
 Types of Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 4
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 5
Key Points
 Key benefit: allows documented changes to be considered in an integrated manner to the
overall project while reducing risks to other areas of the project
 Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc
 Is conducted from project inception through completion
 Is the ultimate responsibility of the Project Manager to carefully & continuously manage
changes
 Changes can be requested by any stakeholder involved in the project
 Every “documented” change must be approved or rejected by a “responsible person”
 Or by the CCB – Change Control Board
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 5
Project Integration Management
Chapter 4
Close Project or Phase
Process 6
Project Integration Management
Chapter 4
Close Project or Phase
Process 6
Key Points
 Provides lessons learned, formal ending of the project work & release of the organization’s
resources to pursue new endeavors
 Finalizes all activities across all PM Process Groups
 PM measures the scope baseline against the PMP
 Complete & close all contracts, procurement agreements, financials
 Archive OPA historical records, reports, etc
 For projects terminated before completion, PM engages all stakeholders to investigate &
document reasons why
Key Points
 A project charter formally authorizes the project
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
 Expert Judgment – gaining advice from experts in other dept, outside consultants, industry
groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the
same page when making a project decision
 All of the 10 subsidiary plans are integrated into ONE comprehensive PMP
Project Integration Management
Chapter 4
Key Points
 The PMP is developed by the Project Manager with inputs from the team, stakeholders &
management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Monitor & Control is conducted from project inception through completion
 Control includes corrective & preventative Actions aka Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
 Changes can be made by Crashing or Fast Tracking
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4 - Summary

More Related Content

What's hot

13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
PMP Training Course - Project Management Framework
PMP Training Course - Project Management FrameworkPMP Training Course - Project Management Framework
PMP Training Course - Project Management FrameworkSkillogic Solutions
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...Shamil Habet
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP PreparationVladimir Vujovic
 
PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1Skillogic Solutions
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Managementjonash99
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2Skillogic Solutions
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management OverviewDavidMcLachlan1
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope ManagementSAJJAD KHUDHUR ABBAS
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Jeffrey Cheah
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder EngagementDavidMcLachlan1
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planningAbubeker mukemil
 

What's hot (19)

13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
PMP Training Course - Project Management Framework
PMP Training Course - Project Management FrameworkPMP Training Course - Project Management Framework
PMP Training Course - Project Management Framework
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
Episode 21 : Project Scope Management
Episode 21 :  Project Scope ManagementEpisode 21 :  Project Scope Management
Episode 21 : Project Scope Management
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement13.3 Manage Stakeholder Engagement
13.3 Manage Stakeholder Engagement
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planning
 
Pmp in summary
Pmp in summaryPmp in summary
Pmp in summary
 

Similar to CAPM Week 2 Chapter 4

PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration managementreddvise
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration MasterclassJeffrey Cheah
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approachMurali Venkatesh
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptxirrosennen
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptxAhmedKayed6
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Logitrain: New Zealand
 
04.integration management updated
04.integration management updated04.integration management updated
04.integration management updatedShraddha PMP
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptxHamzaMessaoudi10
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Fida Karim 🇵🇰
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...May Wong, PMP
 

Similar to CAPM Week 2 Chapter 4 (20)

PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
 
4 integration
4 integration4 integration
4 integration
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration Masterclass
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Prince2017 part 2
Prince2017   part 2Prince2017   part 2
Prince2017 part 2
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)Project Management for IT-related Projects (Logitrain)
Project Management for IT-related Projects (Logitrain)
 
04.integration management updated
04.integration management updated04.integration management updated
04.integration management updated
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
Pm training day 2
Pm training   day 2Pm training   day 2
Pm training day 2
 
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
Taking smaller bites with PMP-Bite series - 5 Process Groups to master and ac...
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Recently uploaded

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesShubhangi Sonawane
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIShubhangi Sonawane
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 

Recently uploaded (20)

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 

CAPM Week 2 Chapter 4

  • 1. Certified Associate Project Management CAPM® Exam Prep – Week 2 Muzette Charles | mcharles2@pace.edu
  • 2. Project Management Process Overview • Review 5 Process Groups • Review 10 Knowledge Areas • Identify each of the 47 Project Processes by their Process Group
  • 3. Integration Management Chapter 4 “Is the Project Manager’s core responsibilities” “…. is a group of processes required to ensure that the various elements of the project are properly coordinated.”
  • 5. Project Integration Management Chapter 4 Develop Project Charter Process 1 Key Points  A project charter formally authorizes the project  Gives the objectives and business case  Identifies & authorizes Project Manager use of organizational resources for project use  Generic enough not to change often  Written by a Manager higher in authority than Project Manager  Includes name, description, deliverables  A project does not start unless it has a Project charter
  • 6. Project Integration Management Chapter 4 Develop Project Charter Process 1 INPUTS  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense TOOLS  Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision
  • 7. Project Integration Management Chapter 4 Develop Project Charter Process 1
  • 8. Project Integration Management Chapter 4 Develop Project Management Plan (PMP) Process 2 Key Points  Key benefit: creates the central document that defines all of the project work  How the project will be executed, monitored & controlled  All of the 10 subsidiary plans are integrated into ONE comprehensive PMP  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
  • 9. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 10. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 11. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 12. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3 Key Points  Key benefit of this process is to provide overall management of the project work  To lead & perform work as defined in the PMP  Create deliverables to meet planned project work  Manage team members & provide them with training  Obtain, manage & use resources ex. Materials, Equipment, Facilities  Establish & manage communications internal & external channels  Manage Stakeholders, Sellers, Risks, Change Requests
  • 13. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3
  • 14. Project Integration Management Chapter 4 Monitor & Control Project Work Process 4 Key Points  Key benefit: allows stakeholders to understand current state of the project, any steps taken and budget, schedule & scope forecasts  Tracks, reviews & reports actual progress & performance against the PMP objectives  Is conducted from project inception through completion  Control includes corrective & preventative actions  Identify & analyze existing and new risks  Work Authorization System - PM’s system to ensure work is performed at the right time & in the right sequence (found in the EEF – PMIS)
  • 15. Project Integration Management Chapter 4 Monitor & Control Project Work Process 4 Key Points  Change Requests  are submitted when issues are found while project work is being performed  is a formal (written) proposal to modify any document, baseline, deliverable  Change Log – all WRITTEN requests approved or not  PM has authority to make changes IF constraints are not effected  Types of Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
  • 16. Project Integration Management Chapter 4 Monitor & Control Project Work Process 4
  • 17. Project Integration Management Chapter 4 Perform Integrated Change Control Process 5 Key Points  Key benefit: allows documented changes to be considered in an integrated manner to the overall project while reducing risks to other areas of the project  Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc  Is conducted from project inception through completion  Is the ultimate responsibility of the Project Manager to carefully & continuously manage changes  Changes can be requested by any stakeholder involved in the project  Every “documented” change must be approved or rejected by a “responsible person”  Or by the CCB – Change Control Board
  • 18. Project Integration Management Chapter 4 Perform Integrated Change Control Process 5
  • 19. Project Integration Management Chapter 4 Close Project or Phase Process 6
  • 20. Project Integration Management Chapter 4 Close Project or Phase Process 6 Key Points  Provides lessons learned, formal ending of the project work & release of the organization’s resources to pursue new endeavors  Finalizes all activities across all PM Process Groups  PM measures the scope baseline against the PMP  Complete & close all contracts, procurement agreements, financials  Archive OPA historical records, reports, etc  For projects terminated before completion, PM engages all stakeholders to investigate & document reasons why
  • 21. Key Points  A project charter formally authorizes the project  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense  Expert Judgment – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision  All of the 10 subsidiary plans are integrated into ONE comprehensive PMP Project Integration Management Chapter 4
  • 22. Key Points  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Monitor & Control is conducted from project inception through completion  Control includes corrective & preventative Actions aka Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong  Changes can be made by Crashing or Fast Tracking Project Integration Management Chapter 4