PROJECT MANAGEMENTPROJECT MANAGEMENT
CPM/PERT
V P B Chakravarthi . K
Abhijeet Kumar
ProjectProject
 “A project is a series of activities directed
to accomplishment of a desired objective.”
Plan your work first…..then work
your plan
Network analysis
Introduction
Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects.
One definition of a project:
“A project is a temporary endeavour undertaken to create a "unique"
product or service”
HistoryHistory
 Developed in 1950’s
 CPM by DuPont for chemical plants
 PERT by U.S. Navy for Polaris missile
PERT was developed by the US Navy for the planning and control of
the Polaris missile program and the emphasis was on completing the
program in the shortest possible time. In addition PERT had the
ability to cope with uncertain activity completion times (e.g. for a
particular activity the most likely completion time is 4 weeks but it
could be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on the
trade-off between the cost of the project and its overall
completion time (e.g. for certain activities it may be possible
to decrease their completion times by spending more money -
how does this affect the overall completion time of the
project?)
CPM - Critical Path MethodCPM - Critical Path Method
 Definition: In CPM activities are shown as a network of
precedence relationships using activity-on-node network
construction
– Single estimate of activity time
– Deterministic activity times
USED IN : Production management - for the jobs of
repetitive in nature where the activity time estimates can
be predicted with considerable certainty due to the
existence of past experience.
PERT -PERT -
Project Evaluation & Review TechniquesProject Evaluation & Review Techniques
 Definition: In PERT activities are shown as a network of
precedence relationships using activity-on-arrow network
construction
– Multiple time estimates
– Probabilistic activity times
USED IN : Project management - for non-repetitive jobs
(research and development work), where the time and cost
estimates tend to be quite uncertain. This technique uses
probabilistic time estimates.
Originated by H.L.Gantt in 1918
Gantt chart
Advantages
- Gantt charts are quite commonly used.
They provide an easy graphical
representation of when activities (might)
take place.
Limitations
- Do not clearly indicate details regarding
the progress of activities
- Do not give a clear indication of
interrelation ship between the separate
activities
CPM/PERTCPM/PERT
These deficiencies can be eliminated to a large extent by
showing the interdependence of various activities by means of
connecting arrows called network technique.
 Overtime CPM and PERT became one technique
 ADVANTAGES:
– Precedence relationships
– large projects
– more efficient
The Project NetworkThe Project Network
 Use of nodes and arrows
Arrows An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to
perform a part of the work.
Nodes  A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start
and/or finish.
Activity on Node & Activity on ArrowActivity on Node & Activity on Arrow
Activity on Node
- A completion of an activity
is represented by a node
Activity on Arrow
- An arrow represents a task,
while a node is the
completion of a task
- Arrows represent order of
events
Activity SlackActivity Slack
Each event has two important times associated with it :
- Earliest time , Te , which is a calendar time when a event can
occur when all the predecessor events completed at the earliest
possible times
- Latest time , TL , which is the latest time the event can occur with
out delaying the subsequent events and completion of project.
 Difference between the latest time and the earliest time of an event
is the slack time for that event
Positive slack : Slack is the amount of time an event can be delayed
without delaying the project completion
Critical PathCritical Path
 Is that the sequence of activities and events where there is no
“slack” i.e.. Zero slack
 Longest path through a network
 minimum project completion time
Benefits of CPM/PERTBenefits of CPM/PERT
 Useful at many stages of project management
 Mathematically simple
 Give critical path and slack time
 Provide project documentation
 Useful in monitoring costs
Questions Answered by CPM & PERTQuestions Answered by CPM & PERT
 Completion date?
 On Schedule?
 Within Budget?
 Critical Activities?
 How can the project be finished early at the least cost?
exampleexample
Illustration of network analysis of a minor redesign of a product and
its associated packaging.
The key question is: How long will it take to complete this project ?
For clarity, this list is kept to a minimum by specifying only
immediate relationships, that is relationships involving activities
that "occur near to each other in time".
•"What activities must be finished before this activity can start"
•could we complete this project in 30 weeks?
•could we complete this project in 2 weeks?
One answer could be, if we first do activity 1, then activity 2, then activity
3, ...., then activity 10, then activity 11 and the project would then take the sum
of the activity completion times, 30 weeks.
“What is the minimum possible time in which we can complete this project ? “
Before starting any of the above activity, the questions
asked would be
We shall see below how the network analysis diagram/picture we construct
helps us to answer this question.
CRITICAL PATH TAKES 24 WEEKS FOR THE COMPLETION OF THE PROJECT
Packages are available to determine the shortest path
and other relevant information.
Data entry window
Output of the package
Limitations to CPM/PERTLimitations to CPM/PERT
 Clearly defined, independent and stable activities
 Specified precedence relationships
 Over emphasis on critical paths
Thank you

Weitere ähnliche Inhalte

Was ist angesagt?

مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةM Maged Hegazy, LLM, MBA, CCP, P3O
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a projectSailish Cephas
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industryRubnawaz Bhatti
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 

Was ist angesagt? (20)

مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافية
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Risk management in a construction projects between knowledge and application ...
Risk management in a construction projects between knowledge and application ...Risk management in a construction projects between knowledge and application ...
Risk management in a construction projects between knowledge and application ...
 
Evolution of project management
Evolution of project managementEvolution of project management
Evolution of project management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
PM using P6
PM using P6PM using P6
PM using P6
 
Roles of project managers in oe
Roles of project managers in oeRoles of project managers in oe
Roles of project managers in oe
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Contract management
Contract managementContract management
Contract management
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 

Ähnlich wie 06 pert cpm (20)

time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Pert
PertPert
Pert
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
3...06 pert cpm
3...06 pert cpm3...06 pert cpm
3...06 pert cpm
 
porject management
porject managementporject management
porject management
 
S pert cpm
S pert cpmS pert cpm
S pert cpm
 
06 pert cpm (1)
06 pert cpm (1)06 pert cpm (1)
06 pert cpm (1)
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
Pert cpm
Pert  cpmPert  cpm
Pert cpm
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
project network
project networkproject network
project network
 

Kürzlich hochgeladen

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 

Kürzlich hochgeladen (20)

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 

06 pert cpm

  • 1. PROJECT MANAGEMENTPROJECT MANAGEMENT CPM/PERT V P B Chakravarthi . K Abhijeet Kumar
  • 2. ProjectProject  “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan
  • 3. Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project: “A project is a temporary endeavour undertaken to create a "unique" product or service”
  • 4. HistoryHistory  Developed in 1950’s  CPM by DuPont for chemical plants  PERT by U.S. Navy for Polaris missile PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks). CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)
  • 5. CPM - Critical Path MethodCPM - Critical Path Method  Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 6. PERT -PERT - Project Evaluation & Review TechniquesProject Evaluation & Review Techniques  Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 7. Originated by H.L.Gantt in 1918 Gantt chart Advantages - Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place. Limitations - Do not clearly indicate details regarding the progress of activities - Do not give a clear indication of interrelation ship between the separate activities
  • 8. CPM/PERTCPM/PERT These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique.  Overtime CPM and PERT became one technique  ADVANTAGES: – Precedence relationships – large projects – more efficient
  • 9. The Project NetworkThe Project Network  Use of nodes and arrows Arrows An arrow leads from tail to head directionally – Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish.
  • 10. Activity on Node & Activity on ArrowActivity on Node & Activity on Arrow Activity on Node - A completion of an activity is represented by a node Activity on Arrow - An arrow represents a task, while a node is the completion of a task - Arrows represent order of events
  • 11. Activity SlackActivity Slack Each event has two important times associated with it : - Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times - Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project.  Difference between the latest time and the earliest time of an event is the slack time for that event Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion
  • 12. Critical PathCritical Path  Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack  Longest path through a network  minimum project completion time
  • 13. Benefits of CPM/PERTBenefits of CPM/PERT  Useful at many stages of project management  Mathematically simple  Give critical path and slack time  Provide project documentation  Useful in monitoring costs
  • 14. Questions Answered by CPM & PERTQuestions Answered by CPM & PERT  Completion date?  On Schedule?  Within Budget?  Critical Activities?  How can the project be finished early at the least cost?
  • 15. exampleexample Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 16. For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
  • 17. •"What activities must be finished before this activity can start" •could we complete this project in 30 weeks? •could we complete this project in 2 weeks? One answer could be, if we first do activity 1, then activity 2, then activity 3, ...., then activity 10, then activity 11 and the project would then take the sum of the activity completion times, 30 weeks. “What is the minimum possible time in which we can complete this project ? “ Before starting any of the above activity, the questions asked would be
  • 18. We shall see below how the network analysis diagram/picture we construct helps us to answer this question.
  • 19. CRITICAL PATH TAKES 24 WEEKS FOR THE COMPLETION OF THE PROJECT
  • 20. Packages are available to determine the shortest path and other relevant information.
  • 22. Output of the package
  • 23. Limitations to CPM/PERTLimitations to CPM/PERT  Clearly defined, independent and stable activities  Specified precedence relationships  Over emphasis on critical paths