Capital Budgeting
For 9.220, Term 1, 2002/03
02_Lecture8.ppt
Outline
 Introduction
 Discounted Cash Flow (DCF)
Techniques
 Net Present Value (NPV)
 Internal Rate of Return (IRR)
 Profitability Index (PI)
 Summary and Conclusions
Recall the Flows of funds and decisions
important to the financial manager
Financial
Manager
Financial
Markets
Real Assets
Financing
Decision
Investment
Decision
Returns from Investment Returns to Security Holders
Reinvestment Refinancing
Capital Budgeting is used to make the Investment Decision
Introduction
 Capital Budgeting is the process of determining which
real investment projects should be accepted and given
an allocation of funds from the firm.
 To evaluate capital budgeting processes, their
consistency with the goal of shareholder wealth
maximization is of utmost importance.
Discounted Cash Flow (DCF)
Techniques
 The main DCF techniques for capital budgeting
include: Net Present Value (NPV), Internal Rate of
Return (IRR), and Profitability Index (PI)
 Each requires estimates of expected cash flows (and
their timing) for the project.
 Including cash outflows (costs) and inflows (revenues or
savings) – normally tax effects are also considered.
 Each requires an estimate of the project’s risk so that
an appropriate discount rate (opportunity cost of
capital) can be determined.
 The discussion of risk will be deferred until later. For
now, we will assume we know the relevant opportunity
cost of capital or discount rate.
 Sometimes the above data is difficult to obtain –
this is the main weakness of all DCF techniques.
Net Present Value (NPV)
 Method: NPV = PVinflows – PVoutflows
 If NPV ≥ 0, then accept the project;
otherwise reject the project.
Example Project
 Initial investment
required: $100,000
 Opportunity cost of
capital: 15%
 The NPV is …
Year
Cash
Revenues
less Expenses
after tax
1 $20,000
2-9 $40,000
10 $10,000
NPV using the Calculator
 Use CFj key to enter the cash flows.
 Use Nj key to enter the number of times a
cash flow repeats.
 Enter the opportunity cost of capital in the
I/YR key.
 Use the NPV function to compute NPV
 Note: before starting the evaluation of a
new project, clear previous data and ensure
the calculator is set to 1 P/Yr.
NPV: Strengths and Weaknesses
 Strengths
 Resulting number is easy to interpret: shows how
wealth will change if the project is accepted.
 Acceptance criteria is consistent with shareholder
wealth maximization.
 Relatively straightforward to calculate
 Weaknesses
 Requires knowledge of finance to use.
 An improper NPV analysis may lead to the wrong
choices of projects when the firm has capital
rationing – this will be discussed later.
Internal Rate of Return (IRR)
 IRR is the rate of return that a project generates.
Algebraically, IRR can be determined by setting up an
NPV equation and solving for a discount rate that
makes the NPV = 0.
 Equivalently, IRR is solved by determining the rate
that equates the PV of cash inflows to the PV of cash
outflows.
 Method: Use your financial calculator or a
spreadsheet; IRR usually cannot be solved manually.
 If IRR ≥ opportunity cost of capital (or hurdle rate),
then accept the project; otherwise reject it.
Example Project
 Initial investment
required: $100,000
 Opportunity cost of
capital: 15%
 The IRR is …
Year
Cash
Revenues
less Expenses
after tax
1 $20,000
2-9 $40,000
10 $10,000
IRR using the Calculator
 Use CFj key to enter the cash flows.
 Use Nj key to enter the number of times a cash flow
repeats.
 Use the IRR function to compute IRR
 Note 1: before starting the evaluation of a new
project, clear previous data and ensure the calculator
is set to 1 P/Yr; however, if you have already entered
the cash flows for an NPV analysis, you do not need to
reenter them – they are in your calculator already and
can be used for the IRR calculation.
 Note 2: You do not need to input the opportunity cost
of capital to calculate the IRR, however, you need the
opportunity cost to make your accept/reject decision.
NPV Profile and the Solution for IRR
-$100,000
-$50,000
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Discount Rate
NPV
IRR: Strengths and Weaknesses
 Strengths
 IRR number is easy to interpret: shows the
return the project generates.
 Acceptance criteria is generally consistent with
shareholder wealth maximization.
 Weaknesses
 Requires knowledge of finance to use.
 Difficult to calculate – need financial calculator.
 It is possible that there exists no IRR or multiple
IRRs for a project and there are several special
cases when the IRR analysis needs to be
adjusted in order to make a correct decision
(these problems will be addressed later).
Profitability Index (PI)
 Method:
 Note: PI should always be expressed as a
positive number.
 If PI ≥ 1, then accept the real investment
project; otherwise, reject it.
Investment
Initial
PV
PI investment
initial
after the
flows
Cash

Example Project
 Initial investment
required: $100,000
 Opportunity cost of
capital: 15%
 The PI is …
Year
Cash
Revenues
less Expenses
after tax
1 $20,000
2-9 $40,000
10 $10,000
PI using the Calculator
 If you also need to calculate NPV and IRR, then follow
the steps below:
 Use CFj key to enter ALL of the cash flows.
 Use Nj key to enter the number of times a cash flow
repeats.
 Enter the opportunity cost of capital in the I/YR key.
 Use the NPV function to compute NPV.
 Take the NPV result, add back the initial investment
and then divide the new result by the initial
investment to get the PI.
 Note: before starting the evaluation of a new project, clear
previous data and ensure the calculator is set to 1 P/Yr; however,
if you have already entered the cash flows for an NPV analysis, you
do not need to reenter them – they are in your calculator already
and can be used for the IRR calculation.
PI using the Calculator
 If you just need to calculate PI, then follow the steps
below:
 Enter 0 for CF0.
 Use CFj key to enter the cash flows that follow the
initial investment.
 Use Nj key to enter the number of times a cash flow
repeats.
 Enter the opportunity cost of capital in the I/YR key.
 Use the NPV function to compute NPV – gives the PV
of the cash flows after the initial investment.
 Take the NPV result and divide by the initial
investment to get the PI.
PI: Strengths and Weaknesses
 Strengths
 PI number is easy to interpret: shows how many $
(in PV terms) you get back per $ invested.
 Acceptance criteria is generally consistent with
shareholder wealth maximization.
 Relatively straightforward to calculate.
 Useful when there is capital rationing (to be
discussed later).
 Weaknesses
 Requires knowledge of finance to use.
 It is possible that PI cannot be used if the initial cash
flow is an inflow.
 Method needs to be adjusted when there are
mutually exclusive projects (to be discussed later).
Summary and Conclusion
 The DCF techniques, NPV, IRR, and PI, are
all good techniques for capital budgeting
and allow us to accept or reject investment
projects consistent with the goal of
shareholder wealth maximization.
 Beware, however, there are times when one
technique’s output is better for some
decisions or when a technique has to be
modified given certain circumstances –
these cases will be discussed in the next
lecture.
Midterm Exam 1 – Coverage and Grading
 Covers: All material from lectures including self-study parts
plus chapters 1, 3, 4, 5 (not 5.5-5.8), 5 Appendix, and the
following sections of Chapter 6: 6.1, 6.5, 6.7, 6.8. The rest
of chapter 6 will be covered after the midterm.
 Format: 40-60% multiple choice (15-25 questions);
remainder is problems (4-8 questions).
 No credit will be given for indicating which calculator
buttons you pushed.
 Full credit will be given for correct answers. Incorrect
answers with no work will receive no credit. Work to be
shown for partial credit should be the numbers in the
equations.
 Do not round intermediate results; store them in your
calculator. Final $ answers may be rounded to the cent (i.e.,
2 decimal places; e.g., $1,253.56); other answers such as
%, years, etc., may be rounded to 6 decimal places (e.g.,
34.123456%).
Midterm Exam 1 – Advice
 If in doubt of a question’s wording, ask for
clarification!
 Some questions will be similar to lecture examples,
assignments, and text questions, BUT, beware some
questions will be quite different from those you have
seen previously – to test whether you really
understand the concepts and can apply them to new
situations.
 Time management is important; don’t waste time on
questions – do easier ones first if think you are going
too slowly.
 Don’t forget your formula sheet – double sided 8.5 by
11 inches; no word-processed or photocopied info is
allowed; any hand-written content can be included.
9.220 Midterm Exam 1 – Locations
 If you are registered in Stangeland’s class,
L01 Tu/Th 10 a.m., you will write in Room
105.
 If you are registered in Zheng’s class, L02,
Tu/Th 1 p.m., you will write in Room 107.
 If you are registered in Eisenberg’s class,
L03, Tu/Th 2:30 p.m., you will write in
Room 122.
 Remember, the exam is Monday,
Oct. 7, from 7 p.m. to 9 p.m.

Weitere ähnliche Inhalte

Ähnlich wie 02_lecture 8.ppt

Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Topic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment CreteriaTopic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment Creteriashengvn
 
Capital Budgeting PPT Of MBA Semister 2
Capital Budgeting PPT  Of MBA Semister 2Capital Budgeting PPT  Of MBA Semister 2
Capital Budgeting PPT Of MBA Semister 2VikasDighe6
 
Bsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxBsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxMohamoud9
 
Sesi 6 cap budgeting
Sesi 6 cap budgetingSesi 6 cap budgeting
Sesi 6 cap budgetingreran999
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Akhil Sabu
 
Powerpoint Presentation on Financial Management-G.REGIO.pptx
Powerpoint Presentation on Financial Management-G.REGIO.pptxPowerpoint Presentation on Financial Management-G.REGIO.pptx
Powerpoint Presentation on Financial Management-G.REGIO.pptxGENELYNREGIO1
 
Manajemen keuangan.lecture 4 min
Manajemen keuangan.lecture 4 minManajemen keuangan.lecture 4 min
Manajemen keuangan.lecture 4 minstanspmb
 
Iii. principles of_capital_budgeting
Iii. principles of_capital_budgetingIii. principles of_capital_budgeting
Iii. principles of_capital_budgetingEzgi Kurt
 
present worth analysis.ppt
present worth analysis.pptpresent worth analysis.ppt
present worth analysis.pptashwinigupta38
 
Project appraisal for financial markets
Project appraisal for financial marketsProject appraisal for financial markets
Project appraisal for financial marketskarangoyal972
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingKhalid Aziz
 
Ch12 cost
Ch12 costCh12 cost
Ch12 costMahii
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteriaAKSHAYA0000
 

Ähnlich wie 02_lecture 8.ppt (20)

Chapter iii capital budget
Chapter iii capital budgetChapter iii capital budget
Chapter iii capital budget
 
Npv n other invest cri lec 4
Npv n other invest cri lec 4Npv n other invest cri lec 4
Npv n other invest cri lec 4
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Topic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment CreteriaTopic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment Creteria
 
Cfd ppt
Cfd pptCfd ppt
Cfd ppt
 
Investment decision
Investment decisionInvestment decision
Investment decision
 
Capital Budgeting PPT Of MBA Semister 2
Capital Budgeting PPT  Of MBA Semister 2Capital Budgeting PPT  Of MBA Semister 2
Capital Budgeting PPT Of MBA Semister 2
 
Bsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptxBsics of Capital Budgeting.pptx
Bsics of Capital Budgeting.pptx
 
Sesi 6 cap budgeting
Sesi 6 cap budgetingSesi 6 cap budgeting
Sesi 6 cap budgeting
 
Financial Management- Making Capital Investment Decision
Financial Management- Making Capital Investment DecisionFinancial Management- Making Capital Investment Decision
Financial Management- Making Capital Investment Decision
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
 
Powerpoint Presentation on Financial Management-G.REGIO.pptx
Powerpoint Presentation on Financial Management-G.REGIO.pptxPowerpoint Presentation on Financial Management-G.REGIO.pptx
Powerpoint Presentation on Financial Management-G.REGIO.pptx
 
Manajemen keuangan.lecture 4 min
Manajemen keuangan.lecture 4 minManajemen keuangan.lecture 4 min
Manajemen keuangan.lecture 4 min
 
Iii. principles of_capital_budgeting
Iii. principles of_capital_budgetingIii. principles of_capital_budgeting
Iii. principles of_capital_budgeting
 
present worth analysis.ppt
present worth analysis.pptpresent worth analysis.ppt
present worth analysis.ppt
 
Project appraisal for financial markets
Project appraisal for financial marketsProject appraisal for financial markets
Project appraisal for financial markets
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Ch12 cost
Ch12 costCh12 cost
Ch12 cost
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 

Kürzlich hochgeladen

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 

Kürzlich hochgeladen (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 

02_lecture 8.ppt

  • 1. Capital Budgeting For 9.220, Term 1, 2002/03 02_Lecture8.ppt
  • 2. Outline  Introduction  Discounted Cash Flow (DCF) Techniques  Net Present Value (NPV)  Internal Rate of Return (IRR)  Profitability Index (PI)  Summary and Conclusions
  • 3. Recall the Flows of funds and decisions important to the financial manager Financial Manager Financial Markets Real Assets Financing Decision Investment Decision Returns from Investment Returns to Security Holders Reinvestment Refinancing Capital Budgeting is used to make the Investment Decision
  • 4. Introduction  Capital Budgeting is the process of determining which real investment projects should be accepted and given an allocation of funds from the firm.  To evaluate capital budgeting processes, their consistency with the goal of shareholder wealth maximization is of utmost importance.
  • 5. Discounted Cash Flow (DCF) Techniques  The main DCF techniques for capital budgeting include: Net Present Value (NPV), Internal Rate of Return (IRR), and Profitability Index (PI)  Each requires estimates of expected cash flows (and their timing) for the project.  Including cash outflows (costs) and inflows (revenues or savings) – normally tax effects are also considered.  Each requires an estimate of the project’s risk so that an appropriate discount rate (opportunity cost of capital) can be determined.  The discussion of risk will be deferred until later. For now, we will assume we know the relevant opportunity cost of capital or discount rate.  Sometimes the above data is difficult to obtain – this is the main weakness of all DCF techniques.
  • 6. Net Present Value (NPV)  Method: NPV = PVinflows – PVoutflows  If NPV ≥ 0, then accept the project; otherwise reject the project.
  • 7. Example Project  Initial investment required: $100,000  Opportunity cost of capital: 15%  The NPV is … Year Cash Revenues less Expenses after tax 1 $20,000 2-9 $40,000 10 $10,000
  • 8. NPV using the Calculator  Use CFj key to enter the cash flows.  Use Nj key to enter the number of times a cash flow repeats.  Enter the opportunity cost of capital in the I/YR key.  Use the NPV function to compute NPV  Note: before starting the evaluation of a new project, clear previous data and ensure the calculator is set to 1 P/Yr.
  • 9. NPV: Strengths and Weaknesses  Strengths  Resulting number is easy to interpret: shows how wealth will change if the project is accepted.  Acceptance criteria is consistent with shareholder wealth maximization.  Relatively straightforward to calculate  Weaknesses  Requires knowledge of finance to use.  An improper NPV analysis may lead to the wrong choices of projects when the firm has capital rationing – this will be discussed later.
  • 10. Internal Rate of Return (IRR)  IRR is the rate of return that a project generates. Algebraically, IRR can be determined by setting up an NPV equation and solving for a discount rate that makes the NPV = 0.  Equivalently, IRR is solved by determining the rate that equates the PV of cash inflows to the PV of cash outflows.  Method: Use your financial calculator or a spreadsheet; IRR usually cannot be solved manually.  If IRR ≥ opportunity cost of capital (or hurdle rate), then accept the project; otherwise reject it.
  • 11. Example Project  Initial investment required: $100,000  Opportunity cost of capital: 15%  The IRR is … Year Cash Revenues less Expenses after tax 1 $20,000 2-9 $40,000 10 $10,000
  • 12. IRR using the Calculator  Use CFj key to enter the cash flows.  Use Nj key to enter the number of times a cash flow repeats.  Use the IRR function to compute IRR  Note 1: before starting the evaluation of a new project, clear previous data and ensure the calculator is set to 1 P/Yr; however, if you have already entered the cash flows for an NPV analysis, you do not need to reenter them – they are in your calculator already and can be used for the IRR calculation.  Note 2: You do not need to input the opportunity cost of capital to calculate the IRR, however, you need the opportunity cost to make your accept/reject decision.
  • 13. NPV Profile and the Solution for IRR -$100,000 -$50,000 $0 $50,000 $100,000 $150,000 $200,000 $250,000 $300,000 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Discount Rate NPV
  • 14. IRR: Strengths and Weaknesses  Strengths  IRR number is easy to interpret: shows the return the project generates.  Acceptance criteria is generally consistent with shareholder wealth maximization.  Weaknesses  Requires knowledge of finance to use.  Difficult to calculate – need financial calculator.  It is possible that there exists no IRR or multiple IRRs for a project and there are several special cases when the IRR analysis needs to be adjusted in order to make a correct decision (these problems will be addressed later).
  • 15. Profitability Index (PI)  Method:  Note: PI should always be expressed as a positive number.  If PI ≥ 1, then accept the real investment project; otherwise, reject it. Investment Initial PV PI investment initial after the flows Cash 
  • 16. Example Project  Initial investment required: $100,000  Opportunity cost of capital: 15%  The PI is … Year Cash Revenues less Expenses after tax 1 $20,000 2-9 $40,000 10 $10,000
  • 17. PI using the Calculator  If you also need to calculate NPV and IRR, then follow the steps below:  Use CFj key to enter ALL of the cash flows.  Use Nj key to enter the number of times a cash flow repeats.  Enter the opportunity cost of capital in the I/YR key.  Use the NPV function to compute NPV.  Take the NPV result, add back the initial investment and then divide the new result by the initial investment to get the PI.  Note: before starting the evaluation of a new project, clear previous data and ensure the calculator is set to 1 P/Yr; however, if you have already entered the cash flows for an NPV analysis, you do not need to reenter them – they are in your calculator already and can be used for the IRR calculation.
  • 18. PI using the Calculator  If you just need to calculate PI, then follow the steps below:  Enter 0 for CF0.  Use CFj key to enter the cash flows that follow the initial investment.  Use Nj key to enter the number of times a cash flow repeats.  Enter the opportunity cost of capital in the I/YR key.  Use the NPV function to compute NPV – gives the PV of the cash flows after the initial investment.  Take the NPV result and divide by the initial investment to get the PI.
  • 19. PI: Strengths and Weaknesses  Strengths  PI number is easy to interpret: shows how many $ (in PV terms) you get back per $ invested.  Acceptance criteria is generally consistent with shareholder wealth maximization.  Relatively straightforward to calculate.  Useful when there is capital rationing (to be discussed later).  Weaknesses  Requires knowledge of finance to use.  It is possible that PI cannot be used if the initial cash flow is an inflow.  Method needs to be adjusted when there are mutually exclusive projects (to be discussed later).
  • 20. Summary and Conclusion  The DCF techniques, NPV, IRR, and PI, are all good techniques for capital budgeting and allow us to accept or reject investment projects consistent with the goal of shareholder wealth maximization.  Beware, however, there are times when one technique’s output is better for some decisions or when a technique has to be modified given certain circumstances – these cases will be discussed in the next lecture.
  • 21. Midterm Exam 1 – Coverage and Grading  Covers: All material from lectures including self-study parts plus chapters 1, 3, 4, 5 (not 5.5-5.8), 5 Appendix, and the following sections of Chapter 6: 6.1, 6.5, 6.7, 6.8. The rest of chapter 6 will be covered after the midterm.  Format: 40-60% multiple choice (15-25 questions); remainder is problems (4-8 questions).  No credit will be given for indicating which calculator buttons you pushed.  Full credit will be given for correct answers. Incorrect answers with no work will receive no credit. Work to be shown for partial credit should be the numbers in the equations.  Do not round intermediate results; store them in your calculator. Final $ answers may be rounded to the cent (i.e., 2 decimal places; e.g., $1,253.56); other answers such as %, years, etc., may be rounded to 6 decimal places (e.g., 34.123456%).
  • 22. Midterm Exam 1 – Advice  If in doubt of a question’s wording, ask for clarification!  Some questions will be similar to lecture examples, assignments, and text questions, BUT, beware some questions will be quite different from those you have seen previously – to test whether you really understand the concepts and can apply them to new situations.  Time management is important; don’t waste time on questions – do easier ones first if think you are going too slowly.  Don’t forget your formula sheet – double sided 8.5 by 11 inches; no word-processed or photocopied info is allowed; any hand-written content can be included.
  • 23. 9.220 Midterm Exam 1 – Locations  If you are registered in Stangeland’s class, L01 Tu/Th 10 a.m., you will write in Room 105.  If you are registered in Zheng’s class, L02, Tu/Th 1 p.m., you will write in Room 107.  If you are registered in Eisenberg’s class, L03, Tu/Th 2:30 p.m., you will write in Room 122.  Remember, the exam is Monday, Oct. 7, from 7 p.m. to 9 p.m.