  1. Mohammed Abdul Moiz Feroze B.E, PMP, CCP Consultant Planning- Depots & Stations Hyderabad Metro Rail Project & Bharani Dharan B.E Asst. Manager - Planning Hyderabad Metro Rail Project
  2. Advantages of Planning:. 1) A thorough plan contains multiple solutions 2) Maintaining an ongoing "to-do" list for your business 3) Each item you complete represents a success for you and your business 4) Use the information to make a more realistic estimate for that type of project in the future. 5) All members have the same guideline to follow when working so they are all on the same page 6) Better utilization of Resources Influencing the future by making decisions based on missions, needs and objectives - Planning
  3. Advantages of Scheduling: 1)Level of Information 2) Delay Analysis 3) Earned Value Analysis 4) SPI 5) CPI 6) BAC & ETC Establish Start and finish dates – Activity, Phase, and Project- Scheduling
  4. Monitor & Control Project Phases: 1) Initiation 2) Planning 3) Execution 4) Monitor & Control 5) Closeout Initiation Planning Execution Closeout
  5. KNOWLEDGE AREA Initiation Planning Execution Monitor & Control Closeout PROJECT INITIATION PROJECT CHARTER PROJ.MGMT PLAN MANAGE MONITOR & CHANGE CNTRL CLSOE PROJECT PROJECT SCOPE REQT. SCOPE, WBS CONTROL SCOPE PROJECT TIME SCHEDULE CONTROL SCHEDULE PROJECT COST COST BUDGET CONTROL COST PROJECT QUALITY PLAN QUALITY PERFORM ASSURANCE QUALITY CONTROL PROJECT HUMAN RESOURCE HR PLAN TEAM BUILDING PROJECT COMMUNICATION STAKE HOLDERS PLAN COMMN DISTRIBUTE INFORMATI ON REPORT PERFORMAN CE PROJECT RISK PLAN RISK MONITOR RISK PROJECT PROCUREMENT PLAN PROC CONDUT PROCUREMT MONOTOR PROCUREMT CLOSE PROCRMNT
  6. ENTERPRISE / ORGANIZATION PORTFOLIO 1 PORTFOLIO 2 PROGRAM 1 PROGRAM 2 PROGRAM 1 PROGRAM 2 PROJECT 1 PROJECT 2 PROJECT 3 PROJECT 4 Typical Enterprise Breakdown Structure
  7. A . M . NAIK SNS M. V SATISH CSL Organization Breakdown Structure
  8. CSL V. MOORTHY RBK HSPS SHUKLA CS CS Anand JASON A. KHAN SANJEEV PRABHAKAR Resource Breakdown Structure NAVYATA RAJA
  9. Work Breakdown Structure: Decomposition of work into more manageable parts. Triple Constraints: 1) Scope 1) Time 2) Cost Scope Time Cost∞ ∞ Scope is the process of developing a detailed description of the project and product. (Two Methods of Decomposition). We Cannot deliver our project, if we do not know what is to be delivered (Scope), by what time and what cost.
  10. MIYAPUR DEPOT BUILDINGS EXTERNAL WORKS GUARD HOUSE ANNEX EARTH WORKS SUB-SRFACE ENGG PROC. CONS T&C Work Breakdown Structure (WBS) GFC DWG-10 GFC DWG- MEP- 5 GFC DWG ARCH - 5 CIVIL 5000 MEP 5000 BMS 1 CHILLER 4 PUMPS 5 EXCV 2000 FOUND 40 COLUMN 40 SLAB 1500 BLOCK 1600 PLSTR 3200 PAINT 3200 DOORS 20 WINDOW 12 LIGHT 60 CHILLER 4 PUMPS 5 BMS 1 PUMPS 5 CHILLER 4 BMS 1 Work package
  11. Method of Planning: Software's : Primavera, MSP, TILOS, EXCEL, Power Point Presentation Tools: Earned value Management, Forecasting, To-complete performance index (TCPI), Performance reviews, Reserve analysis Skills: Business Acumen, Communication, Leadership, Problem Solving
  12. LABOR (MEN & MACHINES) DIRECT INDIRECT FIXED VARIABLE (80%) FIXED VARIABLE PRIMAVERA: LABOUR, NON-LABOUR, MATERIAL MSP: WORK, MATERIAL, COST OTHERS: SKILLED, SEMI SKILLED, UN-SKILLED
  13. Construction Work Flow: Activity Based Costing Division 01 — General Requirements Division 02 — Site Construction Division 03 — Concrete Division 04 — Masonry Division 05 — Metals Division 06 — Wood and Plastics Division 07 — Thermal and Moisture Protection Division 08 — Doors and Windows Division 09 — Finishes Division 10 — Specialties Division 11 — Equipment Division 12 — Furnishings Division 13 — Special Construction Division 14 — Conveying Systems Division 15 — Mechanical Division 16 — Electrical These are used for BOQ preparation & Accounting People:
  14. Sno. Description Unit Qty cost Amount HM-DP-01-01-00 General Requirements Lot 1 6,30,000 6,30,000.00 HM-DP-01-02-00 Site Construction Lot 1 5,70,000 5,70,000.00 HM-DP-01-03-00 Concrete Lot 1 3,50,00,000 3,50,00,000.00 HM-DP-01-04-00 Masonry Lot 1 2,30,000 2,30,000.00 HM-DP-01-08-00 Doors and Windows Lot 1 2,80,000 2,80,000.00 HM-DP-01-09-00 Finishes Lot 1 33,00,000 33,00,000.00 HM-DP-01-15-00 Mechanical Lot 1 26,00,000 26,00,000.00 HM-DP-01-16-00 Electrical Lot 1 33,00,000 33,00,000.00 TOTAL 4,59,10,000.00 Typical BOQ Preparation:
  15. HM-DP-01-09-00 Finishes LOT Qty Cost 33,00,000.00 HM-DP-01-09-01 Matt Finished Vitrified Tiles (598mm x 598mmx 9mm SQM 6500 360 23,40,000.00 HM-DP-01-09-02 Matt Finished Vitrified Tiles for Concourse Level Toilet (Male, Female & Physically Handicapped) SQM 700 600 4,20,000.00 HM-DP-01-09-03 Vitrified Tiles for Dado SQM 750 700 5,25,000.00 HM-DP-01-09-04 Vitrified Tiles SQM 30 500 5,000.00 Typical Finishes BOQ Items:
  16. ID DESCRIPTION GANTT CHART / BAR CHART TYPICAL PRIMAVERA BAR CHART
  17. Item 01-Jan-1408-Jan-14 15-Jan-14 22-Jan-1429-Jan-14 05-Feb-14 12-Feb-14 19-Feb-14 26-Feb-1405-Mar-14 12-Mar-14 19-Mar-1426-Mar-1402-Apr-1409-Apr-14 Excavation PCC Form Work Rebar Concrete Dismantle FM Wall Planning by Henry Gantt:
  18. Flow of Work: Water Fall Method The waterfall model is a sequential process, in which progress is seen as flowing steadily downwards (like a waterfall) through the phases of Conception, Initiation, Analysis, Design, Construction, Testing, Production/Implementation and Maintenance.
  19. Network Diagram: Activity on Node and Activity on Arrow:
  20. CPM, PERT & CCM: CPM: The Shortest Duration to complete a project in a Networking Path. The critical path is the path where the float is zero. Developed by Dupont and Remington Rand in the 1950’s to manage plant maintenance projects PERT: Progress Evaluation Review Technique: 3 Point Analysis Estimation (Triangular Distribution). Developed by Frederick Taylor and Henry Ford in the 1950’s to manage Polaris Submarine System. CCM: Critical Chain Method proposed by Eliyahu Goldratt in his book Goal.
  21. Precedence Diagramming Method (PDM): With advancement of PERT & CPM the network logic diagramming was developed. a 10 ES EF LS LF b 22 ES EF LS LF c 6 ES EF LS LF e 25 ES EF LS LF d 8 ES EF LS LF f 25 ES EF LS LF g 12 ES EF LS LF h 14 ES EF LS LF i 16 ES EF LS LF j 6 ES EF LS LF k 7 ES EF LS LF L 10 ES EF LS LF m 5 ES EF LS LF
  22. a 10 1 10 LS LF b 22 11 32 LS LF c 6 33 38 LS LF e 25 11 35 LS LF d 8 39 46 LS LF f 25 36 60 LS LF g 12 61 72 LS LF h 14 73 86 LS LF i 16 11 27 LS LF j 6 28 33 LS LF k 7 34 40 LS LF L 10 41 50 LS LF m 5 47 51 86 52 55 91 LS LFForward Pass A+b+c+d+m a+e+f+g+h+m a+i+j+k+l+m
  23. a 10 1 10 1 10 b 22 11 32 51 72 c 6 33 38 73 78 e 25 11 35 11 35 d 8 39 46 79 86 f 25 36 60 36 60 g 12 61 72 61 72 h 14 73 86 73 86 i 16 11 27 47 63 j 6 28 33 64 69 k 7 34 40 70 76 L 10 41 50 77 86 m 5 87 91 LS LFBackward Pass m+d+c+b+a m+h+g+f+e+a m+l+k+j+i+a
  24. Scheduling in 5 steps: 1) Identify Activities 2) Establish Relationships 3) Identify Resources 4) Establish Duration 5) Schedule Identify Activities comes from Work Package Relationships : FS, SS, FF, SF along with Lags & Leads Resources Comes from Enterprise Establish Duration from Productivity Norms Schedule : F9 Activity Qty. Unit Crew Productivity Duration Mandays Manhours @ 10 hrs per day Unit Rate hr/cum Excavation 10000 CUM 10 500 20 200 2000 0.2 8 Labor qty/prod crew x 1600 lab 2 Machine duration 400 machine
  25. Level 1 Schedule Executive Summary, also called a Project Master Schedule (PMS). Level 2 Schedule Management Summary, also called a Summary Master Schedule (SMS). Level 3 Schedule Project Coordination Schedule (PCS) also called a Publication Schedule. Level 4 Schedule Execution Schedule, also called a Project Working Level Schedule. Level 5 Schedule Detail Schedule. The further breakdown of the activities of a Level 4 Schedule. Level of Schedule:
  26. Progress Measurement: There are 6 Types of Progress measurement: Units Method Supervisory Method Start – Finish Method Cost Factor Method Incremental Method Weight Factor Method
  27. Establishing Weights: Contribution Factor Method Description of Sub-System Cost in Crs Duration - Total No of Weeks Level of Effort (Scale of 5) Criticality (Scale of 5) Risk factor (Scale of 5) Percentage Round Figure ENGINEERING 12.00 30.00 3.00 3.00 5.00 9.16% 9.00% PROCUREMENT 60.00 40.00 5.00 5.00 5.00 25.10% 25.00% CONSTRUCTION 159.00 80.00 5.00 5.00 5.00 55.74% 56.00% TESTING & COMM. 15.00 12.00 5.00 5.00 3.00 10.01% 10.00% Total 246.00 162.00 18.00 18.00 18.00 Weitage Factor 70% 10% 5% 10% 5% 100.00% 100.00% Cost 70% Duration 10% Manhours (LOE) 5% Criticality 10% Risk Factor 5% LEVEL 1
  28. - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 - 100 200 300 400 500 600 700 800 900 Apr-12 Jun-12 Aug-12 Oct-12 Dec-12 Feb-13 Apr-13 Jun-13 Aug-13 Oct-13 Dec-13 Feb-14 Apr-14 Jun-14 Aug-14 Oct-14 Dec-14 Feb-15 Apr-15 Jun-15 Aug-15 Oct-15 Dec-15 Feb-16 Apr-16 Jun-16 CASTING Vs ERECTION - PLAN Vs ACTUAL- Month WisePlan Progress (Casting) Actual Progress (Casting) Casting Progress (Cum) Casting Actual (Cum) Erection Progress (Cum) GENERAL, -2.48% ENGINEERING , -0.95% PROCUREMENT, - 13.17% CONSTRUCTION, -19.23% T&C, -1.47% Overall Variance Analysis
  29. Difference in Primavera V/S MSP Item Primavera MSP Baseline Multiple 11 User Access Multiple Single Issues & Risk Available Not Included Web Support Yes. Html can be made Not Included Steps Available Not Included Custom Fields No Arithmetic Can define Columns 200 or more 40 Multiple Projects Yes No WBS Available Indent
  30. Duration Types Fixed Units/Time Fixed Duration and Units/Time Fixed Units Duration x Units/Time = Duration Fixed Duration and Units if your organization is more concerned about coming in on the schedule date and within the costs (which are usually associated with the units), you would select Fixed Durations and Units. If your organization is concerned with levelling resources and you assign resources specific hours per day on activities, you would select Fixed Units/Time.
  31. Activity Types Finish Milestone Level of Effort Resource Dependent Start Milestone Task Dependent WBS Summary Task Dependent: These Activity Types have a duration and will only calculate the duration using the assigned calendar even when one or more resources are assigned to an activity. Resource Dependent: These Activity Types have a duration and will calculate the duration only using the calendar assigned to the activity when NO resources are assigned to the activity.
  32. The Activity % Complete Field Duration % Complete = Original or Planned Duration – Remaining Duration = Percent Complete Physical % Complete Units % Complete
  33. Import & Export Database License Convertors
  34. User Preference
  35. View
  36. Project
  37. Baselines
  38. Enterprise
  39. Tools
  40. Admin
  41. Help
  42. End