4. project cost management

Mohamed Salah Eldien Mohamed Ali
Mohamed Salah Eldien Mohamed AliPMPÂź, M.Sc.Eng., Six Sigma, B.Mgt., Training Projects Manager / Academic Manager / Training & Development Consultant um Taleem Educational Services and Consultations
‱‱

- Cost is one of 3 Triple constraints of the project. Managing costs of the project is very crucial and hardest part of the project. It spans across all phases of the project right from conception to closure of the project. - Cost Management is not just controlling “Costs”; it involves definitive planning and preparing budgets. Collecting cost associated data. Comparing the data to prepared budgets and taking appropriate actions when needed. - The process involved in estimating, budgeting, and controlling cost so that the project can be completed within approved budget. - Value analysis (value engineering) ‱ Looking at less costly way to do the same work within the same scope

4. Project Cost Management
-

Cost is one of 3 Triple constraints of the project. Managing costs of the project is
very crucial and hardest part of the project. It spans across all phases of the project
right from conception to closure of the project.

-

Cost Management is not just controlling “Costs”; it involves definitive planning and
preparing budgets. Collecting cost associated data. Comparing the data to prepared
budgets and taking appropriate actions when needed.

-

The process involved in estimating, budgeting, and controlling cost so that the
project can be completed within approved budget.
Value analysis (value engineering)
 Looking at less costly way to do the same work within the same scope
Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5
Process Groups'

-

5 Process
Groups

Initiation

Planning

Executi
on

Monitoring and
control

Closing

4.1. Cost Estimating
Processes

4.3. Cost Control
4.2. Cost Budgeting

4.1 Estimate Cost
- The process of developing approximation of the monetary resources needed to complete
project activities
 Cost trade-offs & risk must be considered


Cost estimates should be refined

Inputs

-

-

Scope baseline
Project schedule
Human resource plan
Risk register
Enterprise
environmental
factors
Organizational
process assets

Tools

-

Expert judgment
Analogous estimating
Parametric estimating
Bottom-up estimating
Three-point estimates
Reserve analysis
Cost of quality
Project management
estimating software
Vendor bid analysis

Outputs

- Activity cost estimates
- Basis of estimates
- Project document updates

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
There are 3 different types of estimation techniques listed over here under Tools section of Cost
Estimation.
- Analogous Estimation techniques
- Bottom-up approach technique
- Parametric approach technique
Analogous estimation
-It is mainly based on Expert Judgment or based on similar previous Projects. This approach is
very useful in early stages of the project where WBS and work packets are completely defined.
The expert judgment success factor depends on similarity of previous projects too. The main
disadvantage is that it is good for ball-park figures but not for precise project cost.
Parametric Estimation
- It considers different project characteristics to calculate total costs of the project. For example,
in the Telephone wire digging project, if we know cost per meter we can estimate it to whole
project. For a house construction, if we know cost to construct per square feet, we can estimate
total house project. For complex projects there will be multi dimensional parameters involved.
When historic information is available these parametric estimation will be more accurate.
Bottom-up approach
- It is elaborative estimation technique. We start estimating from the bottom most part of WBS
hierarchy which is work package. Work packages are divided into activities. Summing up work
packages to modules or groups, summing up different modules to stages, summing up different
stages to project is the bottom-up approach method. The people who will actually do this work
should create the estimates.
Types of Cost;

-

-

Variable Costs
 Change with the amount of production/work
 e.g. material, supplies, wages
Fixed Costs
 Do not change as production change


-

Direct Costs
 Directly attributable to the work of project


-

e.g. set-up, rental

e.g. team travel, recognition, team wages

Indirect Costs
 overhead or cost incurred for benefit of more than one project


e.g. taxes, fringe benefit, janitorial services

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
-

It is very important to understand “Cost Variability” that focuses on changing of
cost over time as well as over volume;


Inflation; cost of some items increase over time.



Deflation; cost of technology items decrease over time.

Direct Costs vs. Indirect Costs

-

when talking about “a new project team member”, the direct cost will be his salary
while the indirect costs may be the insurance premiums given to him, the paid pill
for his telephone calls, computer internet access cost, his disk or disk space that have
been given to him.

-

When talking about “a specific material needed”, the direct cost will be its price
while the indirect cost will be the transportation cost paid to receive such material as
well as the storing cost...etc.

Fixed Costs vs. Variable Costs

-

A fixed cost is like the cost of a unit has a certain nature which maybe a resource
such as a specific material or equipment used for the project. If you need to buy a
piece of equipment to allow the project to continue, that is simply a fixed cost
regardless it will be used for once or hundreds of times.

-

Variable costs are directly related to the level of work with each and every element
of the WBS. It is like the cost of water needed to drink or Gasoline needed to some
machinery.

Quality/Accuracy of Cost Estimation

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
4.2 Determine Budget
- Process of aggregating the estimated cost of individual activities or work packages to
establish an authorized cost baseline.
Inputs

- Activity cost estimates
- Basis of estimates
- Scope baselines
- Project schedule
- Resource calendars
- Contracts
- Organizational process
assets

Tools

-

Cost aggregation
Reserve analysis
Expert judgment
Historical relationship
Funding limit
reconciliation

Outputs

-

Cost performance
baseline
Project funding
requirements
Project document
updates

- The main goal of this process is to develop Cost Baseline. At the starting point of this Process,
you should have finished Project Cost Estimation and have a complete list of estimates of
individual
activities.
Cost Aggregation;
-

We use Cost Aggregation tools to sum up those low level activity costs to Work package to
higher levels of WBS hierarchy.

-

Reserves & risk management are important while estimating!



Contingency reserves/Cost Baseline (the cost impacts of the remaining risk)



Management reserves/Cost Budget (extra fund to cover surprising risks or
changes to the project).

The cost baseline
-

It is a reference point for the project to compare time to time. You will monitor and control
project costs comparing to the baseline and report any variations. Costs at work package
level are tied to financial systems using Chart of Accounts. Chart of accounts show cost
allocation categories.

Project manager is allowed to allocate extra resources (time or money) as a buffer for known
unknowns; we call it as Contingency Reserve.
Determines Budget: Other considerations

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
- High level parametric estimate as a rule of thumb
 E.g. testing cost 50% of development cost
- Funding limit reconciliation = checking cash flow
 When the money will be available?
- Reconciliation needed before proposed cost baseline and cost budget become final
 Such reconciliation is part of integration management

4.3 Control Cost
- The process of monitoring the status of the project to update the project budget and
managing changes to the cost baseline.
Inputs

- Project management
plan
- Project funding
requirement
- Work performance
information
- Organizational process
assets

Tools

-

Earned value
management
Forecasting
To-complete
performance index
Performance reviews
Variance analysis
Project management
software

Outputs

-

Work performance
measurement
Budget forecast
Organizational process
updates
Change requests
Project management plan
updates
Project document updates

Cost control:
Once you estimate Project costs as well as cost baseline and prepare a Budget, you will
be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at
all. You have to monitor your cost so closely. Your work performance information is key
input for this process. You should have clear set templates to report the work progress.
Otherwise all unwanted junk data might ruin the soup.

How to control cost?

-

Follow the cost management plan

-

Look at any organizational process asset that are available

-

Manage change


Recording all appropriate change

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD



Ensuring requested changes are agreed upon


-

Preventing incorrect change

Managing the actual changes when and as they occur

Measure and measure and measure (monitoring)

Project performance review is another Tools & Techniques provided. You will review

project progress with your baseline plans and will provide what you’ve earned against
what you have planned. This is known as Earned Value Analysis and helps you to track
your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that
means you are getting more than what you have planned, or progress is as per the plan or
not getting enough worth for your investment. Based on these 3 scenarios you can take
according corrective actions. Corrective actions are what you are supposed to do in this
process.

You can use Project Management software of your choice to help you in this regard. MS
Project is popular one or even you can simply use well planned out Excel sheets to track
those costs.

First you will find variances and report those using Variance analysis. The terms you use
over here are Cost Variance (CV) and Schedule Variance (SV). From that point you
might required to forecast rest of the project. This involves estimating rest of the work.
You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC).
Those names are telling what you have to Estimate.
Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule
Performance Index)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Earned Value Technique
Ex;

Cont. Earned Value Technique

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Earned Value Management
-

Method to measure project performance against scope, schedule and cost baseline
(performance measurement baseline).

-

Interpretation of basic EVM performance measures



Cost Performance Index (CPI)



Schedule Performance Index (SPI)

Exercise;

-

You have a project to build a box. The box is six sided. Each side is to take one day to
build and is budgeted for $1000 per side. The sides are planned to be completed one
after the other. Today is the end of day three.

-

Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV,
SPI, EAC, ETC, VAC.

-

Describe your interpretation based on the calculation!

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Solution;

Hence, based on the result table;
‱ Over budget, getting 0.88 dollar for every spent dollar,
‱ Ahead schedule, progressing 101% of the rate planned,
‱ Probably will spend $6818 at the end (estimation),
‱ need $3368 to complete,
‱ Over budget at the end for about $818 (estimation)
Performance Metrics;

-

Budget At Completion (BAC) “Total cost of the project.”

-

Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)



-

The amount expressed in Pounds (or hours) of work to be performed as
per the schedule plan.
PV = BAC * % of planned work.

Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)



-

The amount expressed in Pounds (or hours) on the actual worked
performed.
EV = BAC * % of Actual work

Actual Cost of Work Performed (ACWP) / Actual Cost (AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Cost Forecasting:

-

Estimate At Completion (EAC)

-

The expected TOTAL cost required to finish complete work.

-

EAC = BAC / CPI
= AC + (BAC - EV) (at typical case)
= AC + ((BAC - EV) / CPI) (The same performance will remain)
= AC + (BAC - EV) / (CPI* SPI) (The same performance will remain +
Extra loss due to delay in time)

* Here “typical” means it is assumed that similar variances will not occur in the future.

-

Estimate to complete (ETC)

-

The expected cost required to finish all the Remaining work.

-

ETC

= EAC - AC
= (BAC - EV) / CPI

Variances:


Cost Variances (CV)
Determine “How much under or over budget?”
CV = EV-AC
NEGATIVE is over budget, POSITIVE is under budget.



Schedule Variances (SV)
Determine “How much ahead or behind schedule?”.
SV = EV-PV
NEGATIVE is behind schedule, POSITIVE is ahead of schedule.



Variance At Completion (VAC)
Variance of “TOTAL” cost of the work and expected cost.
VAC = BAC - EAC

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Performance Indices:


Cost Performance Index
CPI = EV / AC
“Over (< 1) or under (> 1) budget”.



Schedule Performance Index
SPI = EV / PV
“Ahead (> 1) or behind (< 1) schedule”.

To-Complete Performance Index (TCPI)

-

Helps the team determine the efficiency that must be achieved on the remaining
work for a project to meet a specified endpoint, such as BAC or the team’s revised
EAC.
TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC)

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Problem: A project has a budget of ÂŁ10M and schedule for 10 months. It is assumed that

the total budget will be spent equally each month until the 10th month is reached. After 2
months the project manager finds that only 5% of the work is finished and a total of ÂŁ1M
spent.
Solution:
PV = ÂŁ2M
EV = ÂŁ10M * 0.05 = ÂŁ0.5M
AV = ÂŁ1M
CV = EV-AC = 0.5-1 = -0.5M
CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun
SV = EV-PV = 0.5-2 = -1.5 months
SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = ÂŁ20M
ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = ÂŁ19M
Time to compete = (10-0.5)/0.25 = 38 Months

This project will take TOTAL ÂŁ20M (19+1) and 40 (38+2) Months to complete.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
Hints to remember;
-

EV comes in most of formulas specially regarding “Variance” & “Index”

-

If it’s variance, the formula is EV – something.

-

If it’s index, EV / something.

-

If it relates to cost, use Actual Cost.

-

If it relates to schedule, use PV.

-

Negative numbers are bad, positive is good.

By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD

Recomendados

PMP_Project Cost Management von
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost ManagementHisham Haridy MBA, PMPÂź, RMPÂź, SPÂź
5.4K views‱60 Folien
Project Management Methodologies von
Project Management MethodologiesProject Management Methodologies
Project Management MethodologiesMonief Eid,Prince2,Prosci, Lean Six Sigma &ITIL
3.9K views‱55 Folien
Construction Cost Control von
Construction Cost ControlConstruction Cost Control
Construction Cost ControlSunayana Miglani
5.8K views‱31 Folien
Project cost control von
Project cost controlProject cost control
Project cost controlSourabh Modgil
13.7K views‱16 Folien
Basic Principles of Project Management von
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Managementdanieljohn810
4.9K views‱12 Folien
Project cost management von
Project cost management Project cost management
Project cost management PALLA NARASIMHUDU
1.8K views‱12 Folien

MĂĄs contenido relacionado

Was ist angesagt?

Project cost management von
Project cost managementProject cost management
Project cost managementProjectManager247
472 views‱17 Folien
Project Charter von
Project CharterProject Charter
Project CharterDeborah Obasogie
5.2K views‱8 Folien
Project integration management von
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
2K views‱51 Folien
crashing of project von
crashing of project crashing of project
crashing of project Mir Zafarullah
6.8K views‱15 Folien
Project management von
Project managementProject management
Project managementArsh Koul
1.3K views‱28 Folien
What are the Basic Principles of Project Management | AIMS, UK von
What are the Basic Principles of Project Management | AIMS, UK What are the Basic Principles of Project Management | AIMS, UK
What are the Basic Principles of Project Management | AIMS, UK Academy for International Modern Studies (AIMS)
1.6K views‱17 Folien

Was ist angesagt?(20)

Project integration management von Prabudh Dhingra
Project integration managementProject integration management
Project integration management
Prabudh Dhingra‱2K views
crashing of project von Mir Zafarullah
crashing of project crashing of project
crashing of project
Mir Zafarullah‱6.8K views
Project management von Arsh Koul
Project managementProject management
Project management
Arsh Koul‱1.3K views
Project Cost Management - PMBOK6 von Agus Suhanto
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto‱12.4K views
Project management life cycle von Amjad Idries
Project management life cycleProject management life cycle
Project management life cycle
Amjad Idries‱1.9K views
Project Management Fundamentals von Nishant Munjal
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
Nishant Munjal‱3.9K views
Termination.project management von Marius Miron
Termination.project managementTermination.project management
Termination.project management
Marius Miron‱39.1K views
Project Risk Management von Oleksa Stelmakh
Project Risk ManagementProject Risk Management
Project Risk Management
Oleksa Stelmakh‱9.1K views
Project planning and scheduling von adeel hamid
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
adeel hamid‱1.9K views
Project Management Principles and Process von Charles Cotter, PhD
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
Charles Cotter, PhD‱12K views
Project management (1) von Hetal Visaria
Project management (1)Project management (1)
Project management (1)
Hetal Visaria‱1.7K views
Chapter 1 An Overview Of Project Management von Mahesh Bendigeri
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
Mahesh Bendigeri‱34.1K views
Project Charter von CIToolkit
Project CharterProject Charter
Project Charter
CIToolkit‱1.1K views
Project Management - An Introductiuon von Graeme Smith
Project Management - An IntroductiuonProject Management - An Introductiuon
Project Management - An Introductiuon
Graeme Smith‱843 views

Similar a 4. project cost management

Cost management von
Cost managementCost management
Cost managementshkadry
18.3K views‱45 Folien
Constructiion cost estimating 2017 von
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017Peter Cholakis
111 views‱5 Folien
Term paper spm von
Term paper spmTerm paper spm
Term paper spmUDAY SHARMA
133 views‱16 Folien
con_mangt-lec4-project_costppt.ppt von
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
8 views‱33 Folien
con_mangt-lec4-project_costppt.ppt von
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
6 views‱33 Folien
This is a two step process.First write a one-page paper in which von
This is a two step process.First write a one-page paper in whichThis is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in whichGrazynaBroyles24
2 views‱5 Folien

Similar a 4. project cost management(20)

Cost management von shkadry
Cost managementCost management
Cost management
shkadry‱18.3K views
Constructiion cost estimating 2017 von Peter Cholakis
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
Peter Cholakis‱111 views
Term paper spm von UDAY SHARMA
Term paper spmTerm paper spm
Term paper spm
UDAY SHARMA‱133 views
con_mangt-lec4-project_costppt.ppt von sheryl90
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90‱8 views
con_mangt-lec4-project_costppt.ppt von sheryl90
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90‱6 views
This is a two step process.First write a one-page paper in which von GrazynaBroyles24
This is a two step process.First write a one-page paper in whichThis is a two step process.First write a one-page paper in which
This is a two step process.First write a one-page paper in which
GrazynaBroyles24‱2 views
Project Cost Management von Hayat Denzi
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi‱6.1K views
Project Cost Management von mohamed elashri
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri‱55.2K views
Quality metrics in project management von selinasimpson1601
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601‱3.1K views
Lect-5: Work Breakdown Structure and Project Cost Estimation von Mubashir Ali
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
Mubashir Ali‱13.1K views
Most Popular 20 Evergreen Project Management Terms von SHAZEBALIKHAN1
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1‱30 views
03costestimation-140930114902-phpapp01.pdf von zohir khellouf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
zohir khellouf‱26 views
A brief on project cost management von Imran Jamil
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil‱2.2K views
Chap005 von maisuradi
Chap005Chap005
Chap005
maisuradi‱1.7K views
advanced project management mod 5 von POOJA UDAYAN
advanced project management mod 5advanced project management mod 5
advanced project management mod 5
POOJA UDAYAN‱611 views

MĂĄs de Mohamed Salah Eldien Mohamed Ali

Series_Certificate von
Series_CertificateSeries_Certificate
Series_CertificateMohamed Salah Eldien Mohamed Ali
389 views‱1 Folie
Business Management Cert. von
Business Management Cert.Business Management Cert.
Business Management Cert.Mohamed Salah Eldien Mohamed Ali
277 views‱1 Folie
Business Management Cert. von
Business Management Cert.Business Management Cert.
Business Management Cert.Mohamed Salah Eldien Mohamed Ali
202 views‱1 Folie
9. project procurement management von
9. project procurement management9. project procurement management
9. project procurement managementMohamed Salah Eldien Mohamed Ali
5.2K views‱9 Folien
8. project risk management von
8. project risk management8. project risk management
8. project risk managementMohamed Salah Eldien Mohamed Ali
3K views‱8 Folien
7. project communications management von
7. project communications management7. project communications management
7. project communications managementMohamed Salah Eldien Mohamed Ali
1.5K views‱6 Folien

MĂĄs de Mohamed Salah Eldien Mohamed Ali(12)

Último

DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptx von
DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptxDEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptx
DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptxbradgallagher6
30 views‱24 Folien
Quandoo - Passion - Matthias M.pptx von
Quandoo - Passion - Matthias M.pptxQuandoo - Passion - Matthias M.pptx
Quandoo - Passion - Matthias M.pptxMatthias Maximilian
25 views‱5 Folien
port23_2023121_resize2.pdf von
port23_2023121_resize2.pdfport23_2023121_resize2.pdf
port23_2023121_resize2.pdfSivaphan Wuttingam
38 views‱64 Folien
auto dialer aegis.pdf von
auto dialer aegis.pdfauto dialer aegis.pdf
auto dialer aegis.pdfVoiceLogger1
16 views‱1 Folie
SWOT Analysis of MBM Group von
SWOT Analysis of MBM GroupSWOT Analysis of MBM Group
SWOT Analysis of MBM GroupAriful Saimon
22 views‱4 Folien
TMG Venue Catalog von
TMG Venue CatalogTMG Venue Catalog
TMG Venue CatalogKeizahAponte1
12 views‱11 Folien

Último(20)

DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptx von bradgallagher6
DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptxDEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptx
DEUTSER-03188 Salt Lake Nov 30 Talk with speaker notes[13].pptx
bradgallagher6‱30 views
auto dialer aegis.pdf von VoiceLogger1
auto dialer aegis.pdfauto dialer aegis.pdf
auto dialer aegis.pdf
VoiceLogger1‱16 views
SWOT Analysis of MBM Group von Ariful Saimon
SWOT Analysis of MBM GroupSWOT Analysis of MBM Group
SWOT Analysis of MBM Group
Ariful Saimon‱22 views
December 2023 - Meat on the Bones von NZSG
December 2023 - Meat on the BonesDecember 2023 - Meat on the Bones
December 2023 - Meat on the Bones
NZSG‱32 views
The Talent Management Navigator Performance Management von Seta Wicaksana
The Talent Management Navigator Performance ManagementThe Talent Management Navigator Performance Management
The Talent Management Navigator Performance Management
Seta Wicaksana‱39 views
Taryn_Stejskal_The 5 Practices of Highly Resilient People 30 Nov 2023 Officer... von bradgallagher6
Taryn_Stejskal_The 5 Practices of Highly Resilient People 30 Nov 2023 Officer...Taryn_Stejskal_The 5 Practices of Highly Resilient People 30 Nov 2023 Officer...
Taryn_Stejskal_The 5 Practices of Highly Resilient People 30 Nov 2023 Officer...
bradgallagher6‱25 views
Steele_D&O Summit Keynote.pptx von bradgallagher6
Steele_D&O Summit Keynote.pptxSteele_D&O Summit Keynote.pptx
Steele_D&O Summit Keynote.pptx
bradgallagher6‱12 views
Nevigating Sucess.pdf von TEWMAGAZINE
Nevigating Sucess.pdfNevigating Sucess.pdf
Nevigating Sucess.pdf
TEWMAGAZINE‱28 views
Promoting the SEO to the C-Suite von Ash Nallawalla
Promoting the SEO to the C-SuitePromoting the SEO to the C-Suite
Promoting the SEO to the C-Suite
Ash Nallawalla‱14 views
2023 Tracking Volunteers in Bloomerang.pdf von Bloomerang
2023 Tracking Volunteers in Bloomerang.pdf2023 Tracking Volunteers in Bloomerang.pdf
2023 Tracking Volunteers in Bloomerang.pdf
Bloomerang‱25 views
2024-cio-agenda-ebook.pdf von Alex446314
2024-cio-agenda-ebook.pdf2024-cio-agenda-ebook.pdf
2024-cio-agenda-ebook.pdf
Alex446314‱13 views
Hoole_Summit 2023 - Opening Remarks.pptx von bradgallagher6
Hoole_Summit 2023 - Opening Remarks.pptxHoole_Summit 2023 - Opening Remarks.pptx
Hoole_Summit 2023 - Opening Remarks.pptx
bradgallagher6‱11 views
Navigating the Complexity of Derivatives Valuation 📈 von ValAdvisor
Navigating the Complexity of Derivatives Valuation 📈Navigating the Complexity of Derivatives Valuation 📈
Navigating the Complexity of Derivatives Valuation 📈
ValAdvisor‱17 views

4. project cost management

  • 1. 4. Project Cost Management - Cost is one of 3 Triple constraints of the project. Managing costs of the project is very crucial and hardest part of the project. It spans across all phases of the project right from conception to closure of the project. - Cost Management is not just controlling “Costs”; it involves definitive planning and preparing budgets. Collecting cost associated data. Comparing the data to prepared budgets and taking appropriate actions when needed. - The process involved in estimating, budgeting, and controlling cost so that the project can be completed within approved budget. Value analysis (value engineering)  Looking at less costly way to do the same work within the same scope Following table lists all 3 Processes in this Knowledge Area, spread across '2 out of 5 Process Groups' - 5 Process Groups Initiation Planning Executi on Monitoring and control Closing 4.1. Cost Estimating Processes 4.3. Cost Control 4.2. Cost Budgeting 4.1 Estimate Cost - The process of developing approximation of the monetary resources needed to complete project activities  Cost trade-offs & risk must be considered  Cost estimates should be refined Inputs - - Scope baseline Project schedule Human resource plan Risk register Enterprise environmental factors Organizational process assets Tools - Expert judgment Analogous estimating Parametric estimating Bottom-up estimating Three-point estimates Reserve analysis Cost of quality Project management estimating software Vendor bid analysis Outputs - Activity cost estimates - Basis of estimates - Project document updates By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 2. There are 3 different types of estimation techniques listed over here under Tools section of Cost Estimation. - Analogous Estimation techniques - Bottom-up approach technique - Parametric approach technique Analogous estimation -It is mainly based on Expert Judgment or based on similar previous Projects. This approach is very useful in early stages of the project where WBS and work packets are completely defined. The expert judgment success factor depends on similarity of previous projects too. The main disadvantage is that it is good for ball-park figures but not for precise project cost. Parametric Estimation - It considers different project characteristics to calculate total costs of the project. For example, in the Telephone wire digging project, if we know cost per meter we can estimate it to whole project. For a house construction, if we know cost to construct per square feet, we can estimate total house project. For complex projects there will be multi dimensional parameters involved. When historic information is available these parametric estimation will be more accurate. Bottom-up approach - It is elaborative estimation technique. We start estimating from the bottom most part of WBS hierarchy which is work package. Work packages are divided into activities. Summing up work packages to modules or groups, summing up different modules to stages, summing up different stages to project is the bottom-up approach method. The people who will actually do this work should create the estimates. Types of Cost; - - Variable Costs  Change with the amount of production/work  e.g. material, supplies, wages Fixed Costs  Do not change as production change  - Direct Costs  Directly attributable to the work of project  - e.g. set-up, rental e.g. team travel, recognition, team wages Indirect Costs  overhead or cost incurred for benefit of more than one project  e.g. taxes, fringe benefit, janitorial services By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 3. - It is very important to understand “Cost Variability” that focuses on changing of cost over time as well as over volume;  Inflation; cost of some items increase over time.  Deflation; cost of technology items decrease over time. Direct Costs vs. Indirect Costs - when talking about “a new project team member”, the direct cost will be his salary while the indirect costs may be the insurance premiums given to him, the paid pill for his telephone calls, computer internet access cost, his disk or disk space that have been given to him. - When talking about “a specific material needed”, the direct cost will be its price while the indirect cost will be the transportation cost paid to receive such material as well as the storing cost...etc. Fixed Costs vs. Variable Costs - A fixed cost is like the cost of a unit has a certain nature which maybe a resource such as a specific material or equipment used for the project. If you need to buy a piece of equipment to allow the project to continue, that is simply a fixed cost regardless it will be used for once or hundreds of times. - Variable costs are directly related to the level of work with each and every element of the WBS. It is like the cost of water needed to drink or Gasoline needed to some machinery. Quality/Accuracy of Cost Estimation By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 4. 4.2 Determine Budget - Process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline. Inputs - Activity cost estimates - Basis of estimates - Scope baselines - Project schedule - Resource calendars - Contracts - Organizational process assets Tools - Cost aggregation Reserve analysis Expert judgment Historical relationship Funding limit reconciliation Outputs - Cost performance baseline Project funding requirements Project document updates - The main goal of this process is to develop Cost Baseline. At the starting point of this Process, you should have finished Project Cost Estimation and have a complete list of estimates of individual activities. Cost Aggregation; - We use Cost Aggregation tools to sum up those low level activity costs to Work package to higher levels of WBS hierarchy. - Reserves & risk management are important while estimating!  Contingency reserves/Cost Baseline (the cost impacts of the remaining risk)  Management reserves/Cost Budget (extra fund to cover surprising risks or changes to the project). The cost baseline - It is a reference point for the project to compare time to time. You will monitor and control project costs comparing to the baseline and report any variations. Costs at work package level are tied to financial systems using Chart of Accounts. Chart of accounts show cost allocation categories. Project manager is allowed to allocate extra resources (time or money) as a buffer for known unknowns; we call it as Contingency Reserve. Determines Budget: Other considerations By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 5. - High level parametric estimate as a rule of thumb  E.g. testing cost 50% of development cost - Funding limit reconciliation = checking cash flow  When the money will be available? - Reconciliation needed before proposed cost baseline and cost budget become final  Such reconciliation is part of integration management 4.3 Control Cost - The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. Inputs - Project management plan - Project funding requirement - Work performance information - Organizational process assets Tools - Earned value management Forecasting To-complete performance index Performance reviews Variance analysis Project management software Outputs - Work performance measurement Budget forecast Organizational process updates Change requests Project management plan updates Project document updates Cost control: Once you estimate Project costs as well as cost baseline and prepare a Budget, you will be on cruise mode to control the costs. That doesn’t mean it is easy thereafter. No not at all. You have to monitor your cost so closely. Your work performance information is key input for this process. You should have clear set templates to report the work progress. Otherwise all unwanted junk data might ruin the soup. How to control cost? - Follow the cost management plan - Look at any organizational process asset that are available - Manage change  Recording all appropriate change By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 6.   Ensuring requested changes are agreed upon  - Preventing incorrect change Managing the actual changes when and as they occur Measure and measure and measure (monitoring) Project performance review is another Tools & Techniques provided. You will review project progress with your baseline plans and will provide what you’ve earned against what you have planned. This is known as Earned Value Analysis and helps you to track your day to day progress. 3 possible scenarios are: you are progressing ahead of plan that means you are getting more than what you have planned, or progress is as per the plan or not getting enough worth for your investment. Based on these 3 scenarios you can take according corrective actions. Corrective actions are what you are supposed to do in this process. You can use Project Management software of your choice to help you in this regard. MS Project is popular one or even you can simply use well planned out Excel sheets to track those costs. First you will find variances and report those using Variance analysis. The terms you use over here are Cost Variance (CV) and Schedule Variance (SV). From that point you might required to forecast rest of the project. This involves estimating rest of the work. You use terms like Estimation to Completion (ETC) and Estimate at Complete (EAC). Those names are telling what you have to Estimate. Other terms you use here are Cost Performance Index (CPI) and SPI (Schedule Performance Index) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 7. Earned Value Technique Ex; Cont. Earned Value Technique By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 8. Earned Value Management - Method to measure project performance against scope, schedule and cost baseline (performance measurement baseline). - Interpretation of basic EVM performance measures  Cost Performance Index (CPI)  Schedule Performance Index (SPI) Exercise; - You have a project to build a box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three. - Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC. - Describe your interpretation based on the calculation! By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 9. Solution; Hence, based on the result table; ‱ Over budget, getting 0.88 dollar for every spent dollar, ‱ Ahead schedule, progressing 101% of the rate planned, ‱ Probably will spend $6818 at the end (estimation), ‱ need $3368 to complete, ‱ Over budget at the end for about $818 (estimation) Performance Metrics; - Budget At Completion (BAC) “Total cost of the project.” - Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)   - The amount expressed in Pounds (or hours) of work to be performed as per the schedule plan. PV = BAC * % of planned work. Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)   - The amount expressed in Pounds (or hours) on the actual worked performed. EV = BAC * % of Actual work Actual Cost of Work Performed (ACWP) / Actual Cost (AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 10. Cost Forecasting: - Estimate At Completion (EAC) - The expected TOTAL cost required to finish complete work. - EAC = BAC / CPI = AC + (BAC - EV) (at typical case) = AC + ((BAC - EV) / CPI) (The same performance will remain) = AC + (BAC - EV) / (CPI* SPI) (The same performance will remain + Extra loss due to delay in time) * Here “typical” means it is assumed that similar variances will not occur in the future. - Estimate to complete (ETC) - The expected cost required to finish all the Remaining work. - ETC = EAC - AC = (BAC - EV) / CPI Variances:  Cost Variances (CV) Determine “How much under or over budget?” CV = EV-AC NEGATIVE is over budget, POSITIVE is under budget.  Schedule Variances (SV) Determine “How much ahead or behind schedule?”. SV = EV-PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule.  Variance At Completion (VAC) Variance of “TOTAL” cost of the work and expected cost. VAC = BAC - EAC By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 11. Performance Indices:  Cost Performance Index CPI = EV / AC “Over (< 1) or under (> 1) budget”.  Schedule Performance Index SPI = EV / PV “Ahead (> 1) or behind (< 1) schedule”. To-Complete Performance Index (TCPI) - Helps the team determine the efficiency that must be achieved on the remaining work for a project to meet a specified endpoint, such as BAC or the team’s revised EAC. TCPI = Remaining Work (BAC – EV) / Funds Remaining (EAC - AC) By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 12. Problem: A project has a budget of ÂŁ10M and schedule for 10 months. It is assumed that the total budget will be spent equally each month until the 10th month is reached. After 2 months the project manager finds that only 5% of the work is finished and a total of ÂŁ1M spent. Solution: PV = ÂŁ2M EV = ÂŁ10M * 0.05 = ÂŁ0.5M AV = ÂŁ1M CV = EV-AC = 0.5-1 = -0.5M CV% = 100 * (CV/EV) = 100*(-0.5/0.5) = -100% overrun SV = EV-PV = 0.5-2 = -1.5 months SV% = 100 * (SV/PV) = 100*(-1.5/2) = -75% behind CPI = EV/AC = 0.5/1 = 0.5 SPI = EV/PV = 0.5/2 = 0.25 EAC = BAC/CPI = 10/0.5 = ÂŁ20M ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = ÂŁ19M Time to compete = (10-0.5)/0.25 = 38 Months This project will take TOTAL ÂŁ20M (19+1) and 40 (38+2) Months to complete. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD
  • 13. Hints to remember; - EV comes in most of formulas specially regarding “Variance” & “Index” - If it’s variance, the formula is EV – something. - If it’s index, EV / something. - If it relates to cost, use Actual Cost. - If it relates to schedule, use PV. - Negative numbers are bad, positive is good. By: Mohamed Salah ElDien Mohamed Aly, MSc, PMPÂź, DIT, MCAD