SlideShare a Scribd company logo
1 of 39
Telemark University College
Norway
Modelling the system dynamics of islanding asynchronous
generators
10th International Modelica Conference 2014
Håkon Molland Edvardsen Dietmar Winkler
Telemark University College
Norway
12th
March 2014
I. Introduction What is it about?
What is it about?
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
I. Introduction What is it about?
What is it about?
Figure : Broken surge arrester
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
I. Introduction What is it about?
What is it about?
Figure : Broken surge arrester
Figure : End-termination of supply cable
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
II. Practical Background Location
Location
Where in Europe?
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 3 / 18
II. Practical Background Location
Location
Locally
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 4 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Figure : Grunnåi (Synch - 15MW)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Grunnå and Sagbekken 1 and Sagbekken 2&3
Figure : Grunnåi (Synch - 15MW)
Figure : Sagbekken 2&3 (Asynch 75+75 &
75+250 kW)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
II. Practical Background The power stations
The power stations
Reinstul - 18kW (traditional Norwegian power station)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
II. Practical Background The power stations
The power stations
Reinstul - 18kW (traditional Norwegian power station)
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
II. Practical Background The power stations
The power stations
Total capacity
Grunnåi: 15MW - synchronous
Sagbekken 1: 2x100kW & 200kW - asynchronous
Sagbekken 2: 75kW & 250kW - asynchronous
Sagbekken 3: 75kW & 75kW - asynchronous
Total: 15.85MW
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 7 / 18
II. Practical Background What happend?
What happend?
Possible sequence
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 8 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
II. Practical Background Reconstruction of events
Reconstruction of events
Difficult...
1 Earth circuit fault in Grunnåi (Terminator)
2 The protection relay disconnected the Lønnestad radial
3 Result: heavy imbalance of active power and reactive power in the now
islanded radial.
4 Rapid frequency increase since Grunnåi did not correct for the
overproduction
5 The generator circuit breaker disconnected Grunnåi from the grid, due to
triggering of the over-frequency relay (51Hz and 0.1 seconds).
6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island.
7 Sufficient amount of reactive power in the grid to initiate self-excitation.
8 Successive voltage build-up, which resulted in significant over-voltages in
the grid.
9 Surge arresters to breakdown.
10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
IV. Modelling The Lønnestad radial
The Lønnestad radial
Using Electric Power Library
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 10 / 18
IV. Modelling The self-excitation
The self-excitation
Model of one asynchronous generator
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 11 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, no capacitance, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 12 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, influence of reactive and active load, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
IV. Modelling The self-excitation
The self-excitation
Simulation results, influence of reactive and active load, disconnection at t = 1s
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
IV. Modelling Ground fault
Ground fault
Sub-model Sagbekken 1
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 14 / 18
IV. Modelling Ground fault
Ground fault
Model of Lønnestad radial with phase to ground fault
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 15 / 18
IV. Modelling Ground fault
Ground fault
Simulation results
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
IV. Modelling Ground fault
Ground fault
Simulation results
Took 1.5 seconds from ground
fault until total disconnect
Maximum voltage reached:
53.36kV
Phase C over 30kV for
0.7 seconds
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Correct parameterisation of protection relays crucial
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Conclusions
Conclusions
Asynchronous generators can operate stand-alone when enough
capacitance available
Capacitance can come from long supply lines
Self-excitation leads to fast voltage build-ups
Simulations showed possible voltage build-up of 50kV within 0.4s!
Correct parameterisation of protection relays crucial
Need to take self-excitation effect into account
Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
Telemark University College
Norway Thank you for your attention!
Questions?
Dietmar.Winkler@hit.no
Acknowlegdements:

More Related Content

What's hot

High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul EdwardsNSW Environment and Planning
 
Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...NSW Environment and Planning
 
Significant incident review 415 v arc flash - Michael Wood
Significant incident review   415 v arc flash - Michael WoodSignificant incident review   415 v arc flash - Michael Wood
Significant incident review 415 v arc flash - Michael WoodNSW Environment and Planning
 
1. electricity markets_ Transmission
1. electricity markets_ Transmission1. electricity markets_ Transmission
1. electricity markets_ TransmissionSilvester Van Koten
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transientsmichaeljmack
 
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC ApplicationIRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC ApplicationIRJET Journal
 
Review on Islanding Detection Methods for Photovoltaic Inverter
Review on Islanding Detection Methods for Photovoltaic InverterReview on Islanding Detection Methods for Photovoltaic Inverter
Review on Islanding Detection Methods for Photovoltaic InverterNooria Sukmaningtyas
 
Semikron data sheet_skkh_57_07897942
Semikron data sheet_skkh_57_07897942Semikron data sheet_skkh_57_07897942
Semikron data sheet_skkh_57_07897942Leomar Besen
 
Wide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and PreventionWide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and PreventionPower System Operation
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issuesRohil Kumar
 
Building service project2
Building service project2Building service project2
Building service project2limziahuei
 
Qeg user-manual-3-25-14
Qeg user-manual-3-25-14Qeg user-manual-3-25-14
Qeg user-manual-3-25-14John Hutchison
 
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...ARAVIND U
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentationDoug Frome
 
Quantum energy generator (qeg) new paradigm distribution guidelines
Quantum energy generator (qeg)   new paradigm distribution guidelinesQuantum energy generator (qeg)   new paradigm distribution guidelines
Quantum energy generator (qeg) new paradigm distribution guidelinesPublicLeaker
 

What's hot (20)

High voltage truck protection and fire prevention Paul Edwards
High voltage truck protection and fire prevention   Paul EdwardsHigh voltage truck protection and fire prevention   Paul Edwards
High voltage truck protection and fire prevention Paul Edwards
 
Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...Managing earthing hazards around pole top transformers at mines and quarries ...
Managing earthing hazards around pole top transformers at mines and quarries ...
 
Significant incident review 415 v arc flash - Michael Wood
Significant incident review   415 v arc flash - Michael WoodSignificant incident review   415 v arc flash - Michael Wood
Significant incident review 415 v arc flash - Michael Wood
 
1. electricity markets_ Transmission
1. electricity markets_ Transmission1. electricity markets_ Transmission
1. electricity markets_ Transmission
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
SCG APSS
SCG APSSSCG APSS
SCG APSS
 
Transformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching TransientsTransformer Failure Due to Circuit Breaker Induced Switching Transients
Transformer Failure Due to Circuit Breaker Induced Switching Transients
 
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC ApplicationIRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
IRJET- A New Thyristor Based DC Circuit Breaker Implemented on a DC Application
 
Review on Islanding Detection Methods for Photovoltaic Inverter
Review on Islanding Detection Methods for Photovoltaic InverterReview on Islanding Detection Methods for Photovoltaic Inverter
Review on Islanding Detection Methods for Photovoltaic Inverter
 
Semikron data sheet_skkh_57_07897942
Semikron data sheet_skkh_57_07897942Semikron data sheet_skkh_57_07897942
Semikron data sheet_skkh_57_07897942
 
Wide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and PreventionWide Area Blackouts Causes and Prevention
Wide Area Blackouts Causes and Prevention
 
Islands in power systems
Islands in power systemsIslands in power systems
Islands in power systems
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issues
 
energy harvesting though piezo
energy harvesting though piezoenergy harvesting though piezo
energy harvesting though piezo
 
Building service project2
Building service project2Building service project2
Building service project2
 
Qeg user-manual-3-25-14
Qeg user-manual-3-25-14Qeg user-manual-3-25-14
Qeg user-manual-3-25-14
 
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentation
 
QEG build-manual-25-mar-15
QEG build-manual-25-mar-15QEG build-manual-25-mar-15
QEG build-manual-25-mar-15
 
Quantum energy generator (qeg) new paradigm distribution guidelines
Quantum energy generator (qeg)   new paradigm distribution guidelinesQuantum energy generator (qeg)   new paradigm distribution guidelines
Quantum energy generator (qeg) new paradigm distribution guidelines
 

Viewers also liked

Study on Excitation system in Power sector
Study on Excitation system in Power sectorStudy on Excitation system in Power sector
Study on Excitation system in Power sectorBoben Anto Chemmannoor
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plantsFateh Singh
 
Functions and performance requirements of excitation systems
Functions and performance requirements of excitation systemsFunctions and performance requirements of excitation systems
Functions and performance requirements of excitation systemsRajshekar Naregal
 
Brushless DC Excitation Systems
Brushless DC Excitation SystemsBrushless DC Excitation Systems
Brushless DC Excitation SystemsSharmili Palli
 
Alternatorexcitation
AlternatorexcitationAlternatorexcitation
AlternatorexcitationRanjan Naik
 
Alternator excitation systems
Alternator excitation systemsAlternator excitation systems
Alternator excitation systemsMD AlBeruni
 
Brushless excitation
Brushless excitationBrushless excitation
Brushless excitationsuperbhuppi
 
Excitation system for alternator
Excitation system for alternatorExcitation system for alternator
Excitation system for alternatorsantu sutradhar
 
Three Phase Synchonours Generator and AVR
Three Phase Synchonours Generator and AVR Three Phase Synchonours Generator and AVR
Three Phase Synchonours Generator and AVR Emre Öztoklu
 
Excitation System & capability curve of synchronous generator
Excitation System &  capability curve of synchronous generatorExcitation System &  capability curve of synchronous generator
Excitation System & capability curve of synchronous generatorMANOJ KUMAR MAHARANA
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitationNTPC
 

Viewers also liked (12)

Study on Excitation system in Power sector
Study on Excitation system in Power sectorStudy on Excitation system in Power sector
Study on Excitation system in Power sector
 
synchronous generator excitation
synchronous generator excitationsynchronous generator excitation
synchronous generator excitation
 
Major electrical equipment in power plants
Major electrical equipment in power plantsMajor electrical equipment in power plants
Major electrical equipment in power plants
 
Functions and performance requirements of excitation systems
Functions and performance requirements of excitation systemsFunctions and performance requirements of excitation systems
Functions and performance requirements of excitation systems
 
Brushless DC Excitation Systems
Brushless DC Excitation SystemsBrushless DC Excitation Systems
Brushless DC Excitation Systems
 
Alternatorexcitation
AlternatorexcitationAlternatorexcitation
Alternatorexcitation
 
Alternator excitation systems
Alternator excitation systemsAlternator excitation systems
Alternator excitation systems
 
Brushless excitation
Brushless excitationBrushless excitation
Brushless excitation
 
Excitation system for alternator
Excitation system for alternatorExcitation system for alternator
Excitation system for alternator
 
Three Phase Synchonours Generator and AVR
Three Phase Synchonours Generator and AVR Three Phase Synchonours Generator and AVR
Three Phase Synchonours Generator and AVR
 
Excitation System & capability curve of synchronous generator
Excitation System &  capability curve of synchronous generatorExcitation System &  capability curve of synchronous generator
Excitation System & capability curve of synchronous generator
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitation
 

Similar to Modelling the system dynamics of islanding asynchronous generators / Telemark University

Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...NSW Environment and Planning
 
Wireless power trans mission via solar satelite
Wireless power trans mission via solar sateliteWireless power trans mission via solar satelite
Wireless power trans mission via solar sateliteSaumya Mahapatra
 
wire less power transfer system
wire less power transfer systemwire less power transfer system
wire less power transfer systemsaiteja mosam
 
Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.YouTubeofficial
 
Seminar on nuclear battery
Seminar on nuclear batterySeminar on nuclear battery
Seminar on nuclear batteryPravin Nirukhe
 
final year project report
final year project reportfinal year project report
final year project reportAnuj Kumar
 
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Franco Moriconi
 
Projects done by Stokholm Engineering
Projects done by Stokholm EngineeringProjects done by Stokholm Engineering
Projects done by Stokholm EngineeringKurt Stokholm
 
powerqualityppt-130820010049-phpapp02.pdf
powerqualityppt-130820010049-phpapp02.pdfpowerqualityppt-130820010049-phpapp02.pdf
powerqualityppt-130820010049-phpapp02.pdfgiahuy646563
 
EMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftEMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftDutch Power
 
Electric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plantElectric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plantAbdul Soomro
 

Similar to Modelling the system dynamics of islanding asynchronous generators / Telemark University (20)

ELECTRIC FAULTS
ELECTRIC FAULTSELECTRIC FAULTS
ELECTRIC FAULTS
 
Paul Stride - Electrical earth safety
Paul Stride  - Electrical earth safetyPaul Stride  - Electrical earth safety
Paul Stride - Electrical earth safety
 
Chapter4
Chapter4Chapter4
Chapter4
 
Major incidents throughout the world
Major incidents throughout the worldMajor incidents throughout the world
Major incidents throughout the world
 
Major incidents throughout the world
Major incidents throughout the worldMajor incidents throughout the world
Major incidents throughout the world
 
Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...Brett Roberts - Some aspects of electrical power system protection in undergr...
Brett Roberts - Some aspects of electrical power system protection in undergr...
 
Thermoelectricity
ThermoelectricityThermoelectricity
Thermoelectricity
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Power System Restoration
Power System RestorationPower System Restoration
Power System Restoration
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Wireless power trans mission via solar satelite
Wireless power trans mission via solar sateliteWireless power trans mission via solar satelite
Wireless power trans mission via solar satelite
 
wire less power transfer system
wire less power transfer systemwire less power transfer system
wire less power transfer system
 
Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.Ppt on chilla hydropower plant.
Ppt on chilla hydropower plant.
 
Seminar on nuclear battery
Seminar on nuclear batterySeminar on nuclear battery
Seminar on nuclear battery
 
final year project report
final year project reportfinal year project report
final year project report
 
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
Design, Test and Demonstration of Saturable- Core Reactor HTS Fault Current L...
 
Projects done by Stokholm Engineering
Projects done by Stokholm EngineeringProjects done by Stokholm Engineering
Projects done by Stokholm Engineering
 
powerqualityppt-130820010049-phpapp02.pdf
powerqualityppt-130820010049-phpapp02.pdfpowerqualityppt-130820010049-phpapp02.pdf
powerqualityppt-130820010049-phpapp02.pdf
 
EMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftEMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU Delft
 
Electric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plantElectric fault at forsmark nuclear power plant
Electric fault at forsmark nuclear power plant
 

More from Modelon

Vehicle Dynamics Library - Overview
Vehicle Dynamics Library - OverviewVehicle Dynamics Library - Overview
Vehicle Dynamics Library - OverviewModelon
 
Vapor Cycle Library - Overview
Vapor Cycle Library - OverviewVapor Cycle Library - Overview
Vapor Cycle Library - OverviewModelon
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - OverviewModelon
 
Pneumatics Library - Overview
Pneumatics Library - OverviewPneumatics Library - Overview
Pneumatics Library - OverviewModelon
 
Liquid Cooling Library - Overview
Liquid Cooling Library - OverviewLiquid Cooling Library - Overview
Liquid Cooling Library - OverviewModelon
 
Jet Propulsion Library - Overview
Jet Propulsion Library - OverviewJet Propulsion Library - Overview
Jet Propulsion Library - OverviewModelon
 
Heat Exchanger Library - Overview
Heat Exchanger Library - OverviewHeat Exchanger Library - Overview
Heat Exchanger Library - OverviewModelon
 
Hydro Power Library - Overview
Hydro Power Library - OverviewHydro Power Library - Overview
Hydro Power Library - OverviewModelon
 
Hydraulics Library - Overview
Hydraulics Library - OverviewHydraulics Library - Overview
Hydraulics Library - OverviewModelon
 
Fuel System Library Overview
Fuel System Library OverviewFuel System Library Overview
Fuel System Library OverviewModelon
 
Fuel Cell Library - Overview
Fuel Cell Library - OverviewFuel Cell Library - Overview
Fuel Cell Library - OverviewModelon
 
Electric Power Library - Overview
Electric Power Library - OverviewElectric Power Library - Overview
Electric Power Library - OverviewModelon
 
Electrification Library - Overview
Electrification Library - OverviewElectrification Library - Overview
Electrification Library - OverviewModelon
 
Engine Dynamics Library - Overview
Engine Dynamics Library - OverviewEngine Dynamics Library - Overview
Engine Dynamics Library - OverviewModelon
 
Environmental Control Library - Overview
Environmental Control Library - OverviewEnvironmental Control Library - Overview
Environmental Control Library - OverviewModelon
 
Aircraft Dynamics Library - Overview
Aircraft Dynamics Library - OverviewAircraft Dynamics Library - Overview
Aircraft Dynamics Library - OverviewModelon
 
Air Conditioning Library - Overview
Air Conditioning Library - OverviewAir Conditioning Library - Overview
Air Conditioning Library - OverviewModelon
 
Fuel System Library - Overview
Fuel System Library - OverviewFuel System Library - Overview
Fuel System Library - OverviewModelon
 
FMI Composer Overview
FMI Composer OverviewFMI Composer Overview
FMI Composer OverviewModelon
 
Model Testing Toolkit - Overview
Model Testing Toolkit - OverviewModel Testing Toolkit - Overview
Model Testing Toolkit - OverviewModelon
 

More from Modelon (20)

Vehicle Dynamics Library - Overview
Vehicle Dynamics Library - OverviewVehicle Dynamics Library - Overview
Vehicle Dynamics Library - Overview
 
Vapor Cycle Library - Overview
Vapor Cycle Library - OverviewVapor Cycle Library - Overview
Vapor Cycle Library - Overview
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - Overview
 
Pneumatics Library - Overview
Pneumatics Library - OverviewPneumatics Library - Overview
Pneumatics Library - Overview
 
Liquid Cooling Library - Overview
Liquid Cooling Library - OverviewLiquid Cooling Library - Overview
Liquid Cooling Library - Overview
 
Jet Propulsion Library - Overview
Jet Propulsion Library - OverviewJet Propulsion Library - Overview
Jet Propulsion Library - Overview
 
Heat Exchanger Library - Overview
Heat Exchanger Library - OverviewHeat Exchanger Library - Overview
Heat Exchanger Library - Overview
 
Hydro Power Library - Overview
Hydro Power Library - OverviewHydro Power Library - Overview
Hydro Power Library - Overview
 
Hydraulics Library - Overview
Hydraulics Library - OverviewHydraulics Library - Overview
Hydraulics Library - Overview
 
Fuel System Library Overview
Fuel System Library OverviewFuel System Library Overview
Fuel System Library Overview
 
Fuel Cell Library - Overview
Fuel Cell Library - OverviewFuel Cell Library - Overview
Fuel Cell Library - Overview
 
Electric Power Library - Overview
Electric Power Library - OverviewElectric Power Library - Overview
Electric Power Library - Overview
 
Electrification Library - Overview
Electrification Library - OverviewElectrification Library - Overview
Electrification Library - Overview
 
Engine Dynamics Library - Overview
Engine Dynamics Library - OverviewEngine Dynamics Library - Overview
Engine Dynamics Library - Overview
 
Environmental Control Library - Overview
Environmental Control Library - OverviewEnvironmental Control Library - Overview
Environmental Control Library - Overview
 
Aircraft Dynamics Library - Overview
Aircraft Dynamics Library - OverviewAircraft Dynamics Library - Overview
Aircraft Dynamics Library - Overview
 
Air Conditioning Library - Overview
Air Conditioning Library - OverviewAir Conditioning Library - Overview
Air Conditioning Library - Overview
 
Fuel System Library - Overview
Fuel System Library - OverviewFuel System Library - Overview
Fuel System Library - Overview
 
FMI Composer Overview
FMI Composer OverviewFMI Composer Overview
FMI Composer Overview
 
Model Testing Toolkit - Overview
Model Testing Toolkit - OverviewModel Testing Toolkit - Overview
Model Testing Toolkit - Overview
 

Recently uploaded

Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 

Recently uploaded (20)

Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 

Modelling the system dynamics of islanding asynchronous generators / Telemark University

  • 1. Telemark University College Norway Modelling the system dynamics of islanding asynchronous generators 10th International Modelica Conference 2014 Håkon Molland Edvardsen Dietmar Winkler Telemark University College Norway 12th March 2014
  • 2. I. Introduction What is it about? What is it about? Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 3. I. Introduction What is it about? What is it about? Figure : Broken surge arrester Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 4. I. Introduction What is it about? What is it about? Figure : Broken surge arrester Figure : End-termination of supply cable Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 2 / 18
  • 5. II. Practical Background Location Location Where in Europe? Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 3 / 18
  • 6. II. Practical Background Location Location Locally Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 4 / 18
  • 7. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 8. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Figure : Grunnåi (Synch - 15MW) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 9. II. Practical Background The power stations The power stations Grunnå and Sagbekken 1 and Sagbekken 2&3 Figure : Grunnåi (Synch - 15MW) Figure : Sagbekken 2&3 (Asynch 75+75 & 75+250 kW) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 5 / 18
  • 10. II. Practical Background The power stations The power stations Reinstul - 18kW (traditional Norwegian power station) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
  • 11. II. Practical Background The power stations The power stations Reinstul - 18kW (traditional Norwegian power station) Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 6 / 18
  • 12. II. Practical Background The power stations The power stations Total capacity Grunnåi: 15MW - synchronous Sagbekken 1: 2x100kW & 200kW - asynchronous Sagbekken 2: 75kW & 250kW - asynchronous Sagbekken 3: 75kW & 75kW - asynchronous Total: 15.85MW Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 7 / 18
  • 13. II. Practical Background What happend? What happend? Possible sequence Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 8 / 18
  • 14. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 15. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 16. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 17. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 18. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 19. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 20. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 21. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 22. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 23. II. Practical Background Reconstruction of events Reconstruction of events Difficult... 1 Earth circuit fault in Grunnåi (Terminator) 2 The protection relay disconnected the Lønnestad radial 3 Result: heavy imbalance of active power and reactive power in the now islanded radial. 4 Rapid frequency increase since Grunnåi did not correct for the overproduction 5 The generator circuit breaker disconnected Grunnåi from the grid, due to triggering of the over-frequency relay (51Hz and 0.1 seconds). 6 Asynchronous generators in Sagbekken 1, 2 & 3 alone in the island. 7 Sufficient amount of reactive power in the grid to initiate self-excitation. 8 Successive voltage build-up, which resulted in significant over-voltages in the grid. 9 Surge arresters to breakdown. 10 Arcing ⇒ low impedance in the grid ⇒ stops self-excitation Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 9 / 18
  • 24. IV. Modelling The Lønnestad radial The Lønnestad radial Using Electric Power Library Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 10 / 18
  • 25. IV. Modelling The self-excitation The self-excitation Model of one asynchronous generator Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 11 / 18
  • 26. IV. Modelling The self-excitation The self-excitation Simulation results, no capacitance, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 12 / 18
  • 27. IV. Modelling The self-excitation The self-excitation Simulation results, influence of reactive and active load, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
  • 28. IV. Modelling The self-excitation The self-excitation Simulation results, influence of reactive and active load, disconnection at t = 1s Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 13 / 18
  • 29. IV. Modelling Ground fault Ground fault Sub-model Sagbekken 1 Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 14 / 18
  • 30. IV. Modelling Ground fault Ground fault Model of Lønnestad radial with phase to ground fault Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 15 / 18
  • 31. IV. Modelling Ground fault Ground fault Simulation results Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
  • 32. IV. Modelling Ground fault Ground fault Simulation results Took 1.5 seconds from ground fault until total disconnect Maximum voltage reached: 53.36kV Phase C over 30kV for 0.7 seconds Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 16 / 18
  • 33. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 34. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 35. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 36. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 37. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Correct parameterisation of protection relays crucial Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 38. Conclusions Conclusions Asynchronous generators can operate stand-alone when enough capacitance available Capacitance can come from long supply lines Self-excitation leads to fast voltage build-ups Simulations showed possible voltage build-up of 50kV within 0.4s! Correct parameterisation of protection relays crucial Need to take self-excitation effect into account Edvardsen & Winkler (TUC) Modelica’2014 12th March 2014 17 / 18
  • 39. Telemark University College Norway Thank you for your attention! Questions? Dietmar.Winkler@hit.no Acknowlegdements: