SlideShare ist ein Scribd-Unternehmen logo
1 von 42
Welcome to our
Presentation
Course No: IPE3600
Course Title: IPE Case Study
Submitted By
 Md. Abu Bakar Siddique
Roll: 125029
3rd Year, 6th Semester
Department of Industrial & Production Engineering
Rajshahi University of Engineering & Technology.
Submitted to
Sonia Akhter
Assistant Professor
Dept. of IPE
RUET, Bangladesh
Contents
Topics of our case study
Introduction
Objective
Problem Definition
Methodology
Methods of Line Balancing
Assembly Shop
Data
Calculations & Results
Improvement
Conclusion
1.
Topics of the case
study
“Study on improvement in Productivity
by developing an efficient Line Balancing
at Runner
Automobiles Ltd.
1.
Introduction
Introduction
Increasing productivity has become a buzz word nowadays
on the basis of industry. There are several methods for
increasing productivity and Line Balancing is one of them.
Increase in production volume by decreasing cycle time is
the main task of line balancing.
There are 12 model motor bikes are manufactured by RAL
and we chose Royal+ bike due to its attractive look and its
high customer demand in the present market.
Literature Review
The Comsoal algorithm method of sequencing operation for assembly lines (Comsoal)
was developed by Arcus. The production generates a large number of feasible solution
using a simulation method.
The general algorithm of line balancing that we use for the further improvement was
done by Panneerselvam, et, aL, 1993. This algorithm is used both in Rank positional
method as well as in Comsoal algorithm method. The term idle time and down time are
not included in this algorithm method which creates an error some results.
Swapnil T. Firake and Dr. K. H. Inamdar wrote a journal on the topics of “Productivity
Improvement of Automotive Assembly Line through Line Balancing” where idle time,
down time and a non-value added activity is taken into consideration.
Muthanna Jamil and Noraini Mohd Razali wrote an journal on the topics of “Simulation
of Assembly Line Balancing in Automotive Component Manufacturing” where an
assembly line is developed on the basis of line balancing efficiency and minimum
percentages idle time.
2.
Objectives
Objectives
 To study the current line balancing of Runner Automobiles Ltd.
 Subdivide the network into several sub-networks.
 Precedence relationship of that sub-networks are not violated.
 Allocating operation to each station without exceeding the cycle
time.
 Complete the assembly line with proper heuristics.
 Finding out the limitations of existing line and then give a proper
solution.
3.
Problem Definition
Based on a preliminary study of the current production line
there exist three major problems.
Firstly, the production rate is not in optimum level on the basis
of cycle time. Secondly, the line is experiencing moderate line
efficiency. Thirdly, the job rotation is very acute there and so
the line is stopped uncertainly as the worker are not 100%
expert.
We work for improvement in productivity by solving this
situation applying the knowledge of line balancing.
Problem Definition
4.
Methodology
Results & Analysis
Verify the alternative line
Developing an advance alternative line
Analysis of present assembly line
Chose suitable algorithm
Data collection
Observation of assembly shop
Objective
Problem statement
5.
Methods of Line
Balancing
• Rank Positional Method
• Comsoal Algorithm Method
Ways of finding
out Line
Balancing:
Rank Positional Method:
The ranked positional weight method was developed by Helgeson and Brinie. This
method assigned those jobs first whose follower have the largest total time. The
positional weight of a work element is its own processing time plus the processing
times of all the following work elements.
Comsoal Algorithm Method:
This computer method of sequencing operation for assembly lines was developed
by Arcus. The procedure generates a large number of feasible solutions using a
simulation method.
Why Comsoal Algorithm is better
than Rank positional method?
The two methods that mentioned are almost same in the sense of
general algorithm. But the difference is in their condition. The main
limitation of Rank Position Method is that the immediate
predecessor are already assigned to some station on the contrary
applying Comsoal Algorithm immediate predecessor are also
already assigned but not in some station. That could be assigned in
all stations or in no station. That’s the benefit of Comsoal Algorithm
Method and so we choose this method for the further calculations.
6.
Motor Bike
Elements
Basic elements of Motor Bike
Wheel
Hydraulic
plate of wheel
Saree guard
Muffler (Gas
exposer)Handle bar
Mad guard
Basic elements of Motor Bike
Shock absorberChassis (Frame) Gear lever
Chain Chain guard Head light
Basic elements of Motor Bike
Head Speedometer (Tachometer) Side cover
Fuel tank
Seat
Engine
7.
Functions
Operation Number Functions
Pre-assembly – 01 Unpacking & placing of all parts.
Pre-assembly – 02 Joining hydraulic plate to wheel.
Pre-assembly – 03 Blowing air to wheel.
Pre-assembly – 04 Joining rubber to the mat-guard.
Pre-assembly – 05 Joining light to the mat-guard.
Pre-assembly – 06 Joining parts of handle bar.
Pre-assembly – 07 Joining parts of speedometer.
Pre-assembly – 08 Joining light to head.
Pre-assembly – 09 Preparation of chassis.
Pre-assembly – 10 Assembling engine to chassis.
Assigned tasks
in pre assembly
Assigned tasks
in assembly
Operation Number Function
Assembly – 01 Assembling shock absorber & front wheel.
Assembly – 02 Assembling chain & chain guard.
Assembly – 03 Assembling back wheel.
Assembly – 04 Assembling mat-guard Screw tightening.
Assembly – 05 Assembling handle bar.
Assembly – 06 Assembling muffler.
Assembly – 07 Assembling gear lever.
Assembly – 08 Assembling speedometer.
Assembly – 09 Assembling electric wire.
Assembly – 10 Assembling Head & pumping point.
Assembly – 11 Assembling seat lock and saree guard.
Assembly – 12 Assembling fuel tank cover.
Assembly – 13 Assembling side cover and seat.
8.
Line Layout
Line Layout
Pre Assembly
Section
Assembly
Section
Precedence diagram
9.
Operation time
with predecessor
Operation No
Duration
(Sec)
Immediate predecessor
PA 1 190 --
PA 2 55 PA 1
PA 3 32 PA 1, PA 2
PA 4 145 PA 1
PA 5 150 PA 1, PA 4
PA 6 137 PA 1
PA 7 90 PA 1
PA 8 100 PA 1
PA 9 180 PA 1
PA 10 196 PA 1, PA 9
A 1 210 PA 1, PA 2, PA 3
A 2 60 PA 1
A 3 120 PA 1, PA 2, PA 3
A 4 118 PA 1, PA 4, PA 5
A 5 140 PA 1, PA 6
A 6 215 PA 1
A 7 160 PA 1
A 8 180 PA 1, PA 7
A 9 193 PA 1
A 10 222 PA 1, PA 8
A 11 167 PA 1
A 12 130 PA 1
A 13 109 PA 1
PA = Pre Assembly
A = Assembly
10.
Calculation
Production time = 6 hour 30 minute = 23400 sec
Production volume = 100 unit/day for Royal+ bike
Cycle Time =
Production Time
Production Volume
=
23400
100
= 234 Second
SUACT = 44 + 19 + 41 + 54 + 38 + 12 +
14 + 4 + 22 + 24 + 84 +
94 + 4 + 12 + 108 + 5 + 116
= 695 Sec
Station Number = 17
Cycle Time = 234 Sec
∴ Balancing efficiency
= (1 -
𝑆𝑈𝐴𝐶𝑇
𝐶𝑇∗𝑆𝑁
) * 100%
= (1 -
591
234 ∗ 17
) * 100%
= 85%
11.
Improvement
Proposed Model 1
On the basis of interchanging in assemble point
0
100
2 7
13 13
7
30
21
0
150
2 0 0
55 55
37
21
0
20
40
60
80
100
120
140
160
Assembly
line
A2 A4 A9 A8 A11 A7 A12 A13
Time
Assembly points
Idle time vs Assembly line
Graphical representation
Idle time of present assembly line
Idle time of proposed assembly line
Figure: Difference of idle between present and proposed Assembly line.
There is a chance of reduction of work station. Work station 17 is used for only Assembly point
A4 (Assembling mat-guard Screw tightening). It takes in average 118 sec. if we could reduce it
to 108 sec by involving an extra worker
Assembly point Operation duration
(Sec)
Corresponding sub-assembly
A4 118 PA1, PA4, PA5
This A4 assembly can be done in workstation 15 instead of workstation 17, if A4 = 108 seconds.
If A4 = 108, then it can be carried in workstation 15, because workstation 15 has 108 SUACT.
So let, A4 = 108 then
Balancing efficiency = (1 -
𝑆𝑈𝐴𝐶𝑇
𝐶𝑇∗𝑆𝑁
) * 100%
= (1 -
591−108
234 ∗ 16
) * 100%
= 87%
Proposed Model 2
11.
Overview of the
proposed model
Items Details Efficiency Maximum Idle time
Proposed model 1
Three unites of workstation
added
In A1 assembly point,
assembly line is redesigned.
94% 6%
Proposed model 2
Faster production in A4
assembly point.
87% 13%
Overview on proposed models
12.
Conclusion
Conclusion
The goal of the line balancing is to make an efficient line to
improve production volume from the existing production
line. The assembly line needs to balance so that the line
has the high value of efficiency. Higher value of line
efficiency indicates that the line have the approximately
equal cycle time between operators along the line. Besides
that, the workload between operators also distributed
equally which make the higher line efficiency. As Runner
Automobiles Ltd is in premature age so the line balancing
can bring a great help to increase the profit of the company.
Finally the case study is successfully completed with the
help of our honourable adviser Assistant Professor Sonia
Akhter and we are really thankful to her.
13.
Reference
References
 Pannerselvam, R. 2013, Production and Operation
Management, 3rd ed, PHI Learning Private Limited, Delhi –
110092, 219 – 240.
 Firake, S.T & Dr. Inamdar, K.H, 2014, Productivity
Improvement of Automotive Assembly Line Through Line
Balancing, Volume 2, Issue 3 (May-June 2014), PP. 124-
128
 Jamil, M. & Rajali, N.M., 2015, Simulation of Assembly
Line Balancing in Automotive Component Manufacturing
Thanks to all…
For contact: http://bit.ly/2fy1aiz
Email: mabs.ipe12@yahoo.com

Weitere ähnliche Inhalte

Was ist angesagt?

Line balancing
Line balancingLine balancing
Line balancinggeetha_64
 
Chapter 2 line_balancing no pics
Chapter 2 line_balancing no picsChapter 2 line_balancing no pics
Chapter 2 line_balancing no picsNirav Jadav
 
Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)shady anwer
 
Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)Sohit Chauhan
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balanceSudhir Reddy
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarWakil Kumar
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)Inter Alliance Werardt
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment EffectivenessAnand Subramaniam
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxLakshayKumar504432
 

Was ist angesagt? (20)

Time study
Time studyTime study
Time study
 
Line balancing
Line balancingLine balancing
Line balancing
 
Line balancing
Line balancingLine balancing
Line balancing
 
Line balancing
Line balancingLine balancing
Line balancing
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
Chapter 2 line_balancing no pics
Chapter 2 line_balancing no picsChapter 2 line_balancing no pics
Chapter 2 line_balancing no pics
 
Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)
 
Line balancing
Line balancing Line balancing
Line balancing
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)Most (Maynard Operation Sequence Technique)
Most (Maynard Operation Sequence Technique)
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balance
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil Kumar
 
OEE
OEEOEE
OEE
 
Man and machine chart
Man and machine chartMan and machine chart
Man and machine chart
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
 

Ähnlich wie Assembly Line Balancing | Case Study

Project_Overview_ecopy
Project_Overview_ecopyProject_Overview_ecopy
Project_Overview_ecopyDavid Beck
 
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...IAEME Publication
 
Optimization_model_of the propsed kiiraEV assembly lineprstn
Optimization_model_of the propsed kiiraEV assembly lineprstnOptimization_model_of the propsed kiiraEV assembly lineprstn
Optimization_model_of the propsed kiiraEV assembly lineprstnRonald Kayiwa
 
Toyota Assembly Unit Simulation.pptx
Toyota  Assembly Unit Simulation.pptxToyota  Assembly Unit Simulation.pptx
Toyota Assembly Unit Simulation.pptxAjay Gangakhedkar
 
H0432045055
H0432045055H0432045055
H0432045055theijes
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET Journal
 
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...Optimization and Improvisation of Production Assembly Line of Two Valve Engin...
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...IJERA Editor
 
Case study final presentation ashish
Case study final presentation ashishCase study final presentation ashish
Case study final presentation ashishashish sinha
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyeSAT Journals
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systemschethan kumar
 
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...IRJET Journal
 
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEyosefhadiwibowo
 
presentation on Toyota Assembly Unit Simulation
presentation on Toyota Assembly Unit Simulationpresentation on Toyota Assembly Unit Simulation
presentation on Toyota Assembly Unit Simulationsandeepbags2004
 
IRJET- Design, Development and Manufacturing of CVT for ATV through Real ...
IRJET-  	  Design, Development and Manufacturing of CVT for ATV through Real ...IRJET-  	  Design, Development and Manufacturing of CVT for ATV through Real ...
IRJET- Design, Development and Manufacturing of CVT for ATV through Real ...IRJET Journal
 
Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...eSAT Journals
 
Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...eSAT Publishing House
 

Ähnlich wie Assembly Line Balancing | Case Study (20)

Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Project_Overview_ecopy
Project_Overview_ecopyProject_Overview_ecopy
Project_Overview_ecopy
 
Internship Report
Internship ReportInternship Report
Internship Report
 
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
 
Optimization_model_of the propsed kiiraEV assembly lineprstn
Optimization_model_of the propsed kiiraEV assembly lineprstnOptimization_model_of the propsed kiiraEV assembly lineprstn
Optimization_model_of the propsed kiiraEV assembly lineprstn
 
Toyota Assembly Unit Simulation.pptx
Toyota  Assembly Unit Simulation.pptxToyota  Assembly Unit Simulation.pptx
Toyota Assembly Unit Simulation.pptx
 
H0432045055
H0432045055H0432045055
H0432045055
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
 
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...Optimization and Improvisation of Production Assembly Line of Two Valve Engin...
Optimization and Improvisation of Production Assembly Line of Two Valve Engin...
 
Case study final presentation ashish
Case study final presentation ashishCase study final presentation ashish
Case study final presentation ashish
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
 
Ijariie1167
Ijariie1167Ijariie1167
Ijariie1167
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systems
 
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...
IRJET- Finite Element Analysis of Winch Machine for Erection of Transmission ...
 
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
 
presentation on Toyota Assembly Unit Simulation
presentation on Toyota Assembly Unit Simulationpresentation on Toyota Assembly Unit Simulation
presentation on Toyota Assembly Unit Simulation
 
IRJET- Design, Development and Manufacturing of CVT for ATV through Real ...
IRJET-  	  Design, Development and Manufacturing of CVT for ATV through Real ...IRJET-  	  Design, Development and Manufacturing of CVT for ATV through Real ...
IRJET- Design, Development and Manufacturing of CVT for ATV through Real ...
 
Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...
 
Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...Modeling, simulation and optimization analysis of steering knuckle component ...
Modeling, simulation and optimization analysis of steering knuckle component ...
 

Kürzlich hochgeladen

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsRommel Regala
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxruthvilladarez
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 

Kürzlich hochgeladen (20)

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World Politics
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 

Assembly Line Balancing | Case Study

  • 1. Welcome to our Presentation Course No: IPE3600 Course Title: IPE Case Study
  • 2. Submitted By  Md. Abu Bakar Siddique Roll: 125029 3rd Year, 6th Semester Department of Industrial & Production Engineering Rajshahi University of Engineering & Technology. Submitted to Sonia Akhter Assistant Professor Dept. of IPE RUET, Bangladesh
  • 3. Contents Topics of our case study Introduction Objective Problem Definition Methodology Methods of Line Balancing Assembly Shop Data Calculations & Results Improvement Conclusion
  • 4. 1. Topics of the case study
  • 5. “Study on improvement in Productivity by developing an efficient Line Balancing at Runner Automobiles Ltd.
  • 7. Introduction Increasing productivity has become a buzz word nowadays on the basis of industry. There are several methods for increasing productivity and Line Balancing is one of them. Increase in production volume by decreasing cycle time is the main task of line balancing. There are 12 model motor bikes are manufactured by RAL and we chose Royal+ bike due to its attractive look and its high customer demand in the present market.
  • 8. Literature Review The Comsoal algorithm method of sequencing operation for assembly lines (Comsoal) was developed by Arcus. The production generates a large number of feasible solution using a simulation method. The general algorithm of line balancing that we use for the further improvement was done by Panneerselvam, et, aL, 1993. This algorithm is used both in Rank positional method as well as in Comsoal algorithm method. The term idle time and down time are not included in this algorithm method which creates an error some results. Swapnil T. Firake and Dr. K. H. Inamdar wrote a journal on the topics of “Productivity Improvement of Automotive Assembly Line through Line Balancing” where idle time, down time and a non-value added activity is taken into consideration. Muthanna Jamil and Noraini Mohd Razali wrote an journal on the topics of “Simulation of Assembly Line Balancing in Automotive Component Manufacturing” where an assembly line is developed on the basis of line balancing efficiency and minimum percentages idle time.
  • 10. Objectives  To study the current line balancing of Runner Automobiles Ltd.  Subdivide the network into several sub-networks.  Precedence relationship of that sub-networks are not violated.  Allocating operation to each station without exceeding the cycle time.  Complete the assembly line with proper heuristics.  Finding out the limitations of existing line and then give a proper solution.
  • 12. Based on a preliminary study of the current production line there exist three major problems. Firstly, the production rate is not in optimum level on the basis of cycle time. Secondly, the line is experiencing moderate line efficiency. Thirdly, the job rotation is very acute there and so the line is stopped uncertainly as the worker are not 100% expert. We work for improvement in productivity by solving this situation applying the knowledge of line balancing. Problem Definition
  • 14. Results & Analysis Verify the alternative line Developing an advance alternative line Analysis of present assembly line Chose suitable algorithm Data collection Observation of assembly shop Objective Problem statement
  • 16. • Rank Positional Method • Comsoal Algorithm Method Ways of finding out Line Balancing: Rank Positional Method: The ranked positional weight method was developed by Helgeson and Brinie. This method assigned those jobs first whose follower have the largest total time. The positional weight of a work element is its own processing time plus the processing times of all the following work elements. Comsoal Algorithm Method: This computer method of sequencing operation for assembly lines was developed by Arcus. The procedure generates a large number of feasible solutions using a simulation method.
  • 17. Why Comsoal Algorithm is better than Rank positional method? The two methods that mentioned are almost same in the sense of general algorithm. But the difference is in their condition. The main limitation of Rank Position Method is that the immediate predecessor are already assigned to some station on the contrary applying Comsoal Algorithm immediate predecessor are also already assigned but not in some station. That could be assigned in all stations or in no station. That’s the benefit of Comsoal Algorithm Method and so we choose this method for the further calculations.
  • 19. Basic elements of Motor Bike Wheel Hydraulic plate of wheel Saree guard Muffler (Gas exposer)Handle bar Mad guard
  • 20. Basic elements of Motor Bike Shock absorberChassis (Frame) Gear lever Chain Chain guard Head light
  • 21. Basic elements of Motor Bike Head Speedometer (Tachometer) Side cover Fuel tank Seat Engine
  • 23. Operation Number Functions Pre-assembly – 01 Unpacking & placing of all parts. Pre-assembly – 02 Joining hydraulic plate to wheel. Pre-assembly – 03 Blowing air to wheel. Pre-assembly – 04 Joining rubber to the mat-guard. Pre-assembly – 05 Joining light to the mat-guard. Pre-assembly – 06 Joining parts of handle bar. Pre-assembly – 07 Joining parts of speedometer. Pre-assembly – 08 Joining light to head. Pre-assembly – 09 Preparation of chassis. Pre-assembly – 10 Assembling engine to chassis. Assigned tasks in pre assembly
  • 24. Assigned tasks in assembly Operation Number Function Assembly – 01 Assembling shock absorber & front wheel. Assembly – 02 Assembling chain & chain guard. Assembly – 03 Assembling back wheel. Assembly – 04 Assembling mat-guard Screw tightening. Assembly – 05 Assembling handle bar. Assembly – 06 Assembling muffler. Assembly – 07 Assembling gear lever. Assembly – 08 Assembling speedometer. Assembly – 09 Assembling electric wire. Assembly – 10 Assembling Head & pumping point. Assembly – 11 Assembling seat lock and saree guard. Assembly – 12 Assembling fuel tank cover. Assembly – 13 Assembling side cover and seat.
  • 29. Operation No Duration (Sec) Immediate predecessor PA 1 190 -- PA 2 55 PA 1 PA 3 32 PA 1, PA 2 PA 4 145 PA 1 PA 5 150 PA 1, PA 4 PA 6 137 PA 1 PA 7 90 PA 1 PA 8 100 PA 1 PA 9 180 PA 1 PA 10 196 PA 1, PA 9 A 1 210 PA 1, PA 2, PA 3 A 2 60 PA 1 A 3 120 PA 1, PA 2, PA 3 A 4 118 PA 1, PA 4, PA 5 A 5 140 PA 1, PA 6 A 6 215 PA 1 A 7 160 PA 1 A 8 180 PA 1, PA 7 A 9 193 PA 1 A 10 222 PA 1, PA 8 A 11 167 PA 1 A 12 130 PA 1 A 13 109 PA 1 PA = Pre Assembly A = Assembly
  • 31. Production time = 6 hour 30 minute = 23400 sec Production volume = 100 unit/day for Royal+ bike Cycle Time = Production Time Production Volume = 23400 100 = 234 Second SUACT = 44 + 19 + 41 + 54 + 38 + 12 + 14 + 4 + 22 + 24 + 84 + 94 + 4 + 12 + 108 + 5 + 116 = 695 Sec Station Number = 17 Cycle Time = 234 Sec ∴ Balancing efficiency = (1 - 𝑆𝑈𝐴𝐶𝑇 𝐶𝑇∗𝑆𝑁 ) * 100% = (1 - 591 234 ∗ 17 ) * 100% = 85%
  • 33. Proposed Model 1 On the basis of interchanging in assemble point
  • 34. 0 100 2 7 13 13 7 30 21 0 150 2 0 0 55 55 37 21 0 20 40 60 80 100 120 140 160 Assembly line A2 A4 A9 A8 A11 A7 A12 A13 Time Assembly points Idle time vs Assembly line Graphical representation Idle time of present assembly line Idle time of proposed assembly line Figure: Difference of idle between present and proposed Assembly line.
  • 35. There is a chance of reduction of work station. Work station 17 is used for only Assembly point A4 (Assembling mat-guard Screw tightening). It takes in average 118 sec. if we could reduce it to 108 sec by involving an extra worker Assembly point Operation duration (Sec) Corresponding sub-assembly A4 118 PA1, PA4, PA5 This A4 assembly can be done in workstation 15 instead of workstation 17, if A4 = 108 seconds. If A4 = 108, then it can be carried in workstation 15, because workstation 15 has 108 SUACT. So let, A4 = 108 then Balancing efficiency = (1 - 𝑆𝑈𝐴𝐶𝑇 𝐶𝑇∗𝑆𝑁 ) * 100% = (1 - 591−108 234 ∗ 16 ) * 100% = 87% Proposed Model 2
  • 37. Items Details Efficiency Maximum Idle time Proposed model 1 Three unites of workstation added In A1 assembly point, assembly line is redesigned. 94% 6% Proposed model 2 Faster production in A4 assembly point. 87% 13% Overview on proposed models
  • 39. Conclusion The goal of the line balancing is to make an efficient line to improve production volume from the existing production line. The assembly line needs to balance so that the line has the high value of efficiency. Higher value of line efficiency indicates that the line have the approximately equal cycle time between operators along the line. Besides that, the workload between operators also distributed equally which make the higher line efficiency. As Runner Automobiles Ltd is in premature age so the line balancing can bring a great help to increase the profit of the company. Finally the case study is successfully completed with the help of our honourable adviser Assistant Professor Sonia Akhter and we are really thankful to her.
  • 41. References  Pannerselvam, R. 2013, Production and Operation Management, 3rd ed, PHI Learning Private Limited, Delhi – 110092, 219 – 240.  Firake, S.T & Dr. Inamdar, K.H, 2014, Productivity Improvement of Automotive Assembly Line Through Line Balancing, Volume 2, Issue 3 (May-June 2014), PP. 124- 128  Jamil, M. & Rajali, N.M., 2015, Simulation of Assembly Line Balancing in Automotive Component Manufacturing
  • 42. Thanks to all… For contact: http://bit.ly/2fy1aiz Email: mabs.ipe12@yahoo.com