Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
1. Development of stacking area
and Lighting facilities for
Automobile handling at
Bakshi ka Talab station.
2021-22 2.4746 0.8757 0 June 2022 Work awarded on 17.01.2022.
Work is in progress.
2. Gorakhpur Cantt.-
Remodeling of station for
developing as satellite
terminal.
2016-17 40.0415 0.8724 0 Dec. 2022 Platform surfacing & Station
building finishing work is in
progress. Existing service
buildings (except station & PI
building) have been dismantled
and relocated into newly
constructed buildings. Sheeting
work of pp shed on PF2/3 and 4/5
is in progress. NEW FOB
foundation works are under
progress.
3. Aishbagh-Manaknagar –
Independent bypass line.
2017-18 81.6300 21.4975 0 March2023 Estimate sanctioned By Rly.
Board on 01.08.2019. LOA issued
on 05.03.2020 for civil Engg.
work (All works except track
work). 3250 nos. protection pile,
construction of minor bridge no.3
and 35000 cum earth cutting
completed and work in progress.
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
4. Remodeling of Farrukhbad
yard by providing dead end
for isolation on loop line and
converting line no. 07 to
running line etc.
2021-22 2.3367 0 1.0000
CAP
June 2022 Engg-Work in progress.
S&T- For S&T work contract
awarded. Indoor wiring work yet
to be started due to non-
availability of circuit diagram by
HQ. Outdoor signalling work
85% completed. CRS sanction
applied & awaited. Tentative NI
will be taken in IInd week of
June-22.
TRD-90% Work completed.TDC
10.06.2022.
5. Layout correction in Bhatni
& Deoria Sadar yard to
remove PSR/TSR.
2017-18 2.6456 0.5159 2.1297
RRSK
Feb. 2023 Bhatni- Work completed. At
Deoria Sadar - Work is in
progress.
S&T: -LOA issued on
28.01.2020 Work completed at
BTT. Work at DEOS will be
taken up after Engg work."
6. At Kusmhi – Modification
of yard.
2019-20 2.1000 0 2.1000
DF3
Dec. 2022 The work comprises of
modification of yard, shifting
crossovers at BSB end of
Kusumhi. The work shall be
executed along with 3rd line
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
7. Improvement of approach
road of Rake handling
platform at Chhapra Gramin,
Siwan and Hathua.
2020-21 2.0020 0 2.0020
EBR
Feb. 2023 Work is in progress at Siwan.
Earth filling and brick soling in
stabling area done . Work at
Chhapra Gramin & Hathua will
be taken up.
8. Extension of line no. 8 and
shifting of Turn out at
Deoria Sadar yard.
2021-22 1.8873 0 1.8858
CAP
March2023 Scope- 50 m Extension of Line
no-8, Shifting of 1 T/O by 35
m and removal of 4 redundant
T/O.
Engg.- Material mobilization
under progress.
S&T: -LOA issued on 04.04.22.
Work under progress, SIP
approved, Selection table under
approval, CRS sanction application
will be sent up to 15.07.2022.
TDC-March’22.
9. Provision of 3rd running line
at Ghughli Station.
2021-22 8.8132 0 8.8131
DF3
Dec. 2023 Detailed estimate under
preparation.
S&T: -Detailed estimate given
to Engg dept for sanctioning.
Traffic Facility Works (PH-16) targeted for completion during 2022-23
S.No. Name of work Year of
Sanction
Total
Cost
(In Cr.)
Amount
spent till
30th June
(In Cr.)
Additional
funds required
[CAP/DPR/DF/
EBR]
(In Cr.)
Targeted
month of
completion
Status of Works/
Remarks
10. Bhatni-Peokol – Broad
gauge bypass line.
2012-13 49.1495 0.4808 5.0000
CAP
Dec. 2022 Ballast supply, Earthwork,
Blanketing work, Approach work
and Track linking work is in
progress.
11. Chhapra Jn – Interlocking of
goods lines 8, 9, 10, 11 and
provision of shunt signals
for stabling lines 12, 13, 14,
15 & pit lines.
2016-17 8.7367 1.9376 0 Dec. 2022 S&T-"LOA issued on 05.03.18
for outdoor work. Agency
awarded & work in progress,
Indoor execution work to be
done by BG/Con with EI. To be
commissioned by BG/Con
12. Chhapra- 2nd entry, 2nd home
platform, island platform, 3rd
new tracks & one stabling
line etc.
2017-18 24.6233 0 0 Dec. 2022 Work transferred to construction
on 30.03.2021. S&T and
SDEE/BSB : Electrical work to
be completed with civil work.