WELL INTERVENTION PRESSURE
CONTROL
WELL COMPLETION
Dr. Imre Federer
Associate Professor
COMPLETING THE WELL
General
• The well intervention well control is
– about the well control of working on live wells
– the well operations are conducted by
• wireline,
• coiled tubing
• snubbing unit.
• Well pressure control is the most critical consideration in the
planning and performing of any well servicing operation.
Completion Fluid Characteristics
Dense:
• enough to control well pressures but no frac. the formation
Cost-effective:
• Expensive fluids to prevent damage to sensitive formations.
Free of solid particles as possible:
• Solids can plug perforations as well as reduce production.
Noncorrosive :
• to prevent failure of tubular goods.
Stable:
• If the fluid is to be left in the hole for an extended period.
Filtered or cleaned:
• The low solids content can still cause plugging at formation.
Completion Fluid Density Ranges
Fluid Minimum Density
kg/l (ppg)
Practical Maximum Density
kg/l (ppg)
Oil 0.96 (8.0)
Diesel oil 0,84 (7.0)
Fresh water 1.0 (8.3) 1.0 (8.3)
Sea water 1.01 (8.4) 1.02 (8.5)
Brine-sodium chloride (NaCl) 1.0 (8.3) 1.18 (9.8)
Brine-potassium chloride 1.0 (8.3) 1.17 (9.7)
Brine-calcium chloride 1.32 (11.0) 1.38 (11.5)
Brine-calcium bromide 1.38 (11.5) 1.80 (15.0)
Brine-zinc bromide (ZnBr2) 1.68 (14.0) 2.18 (18.1)
Crystallization
Point of Brines
Weight Crystallization Point
kg/l ppg oC oF
Sodium Chloride (NaCl)
1,02 8.5 -2 29
1,08 9.0 -7 19
1,14 9.5 -16 6
1,2 10.0 -4 25
Calcium Chloride (CaCl2)
1,02 8.5 -1 30
1,08 9.0 -0,5 31
1,14 9.5 -13 9
1,2 10.0 -22 -8
1,26 10.5 -37 -36
1,32 11.0 -30 -22
1,38 11.5 +2 35
Calcium Chloride/Bromide (CaCl2/Br2)
1,44 12.0 12 54
1,56 13.0 15 59
1,68 14.0 17,7 64
1,74 14.5 18,3 65
1,8 15.0 19,4 67
Density Loss due to Temperature
Brine Factors
NaCl or KCl 0.0024
CaCl2 0.0027
NaBr or NaBr/NaCl 0.0033
CaBr2 or CaBr2 /CaCl2 0.0033
ZnBr2 / CaBr2 / CaCl2< 2.1 kg/l (17.5 lb/gal) 0.0036
0.0048
Calculate density loss due to temperature.
ATI = Average temperature increase, oF
Cf = Correction factor for temperature from Table
DL = Density loss, ppg
Cf
*
ATI
DL =
WELL COMPLETION EQUIPMENT
Conventional Wellhead and Christmas Tree
Christmas tree
30000 psi
Conventional Tree
• Advantages: Made up of interchangeable
standard parts cheapest option.
• Disadvantages: more potential leak paths due to
the large number of connections.
Master Valve Block
Tree Cap
Tree Connector
Tubing Hanger
Wellhead
Solid Block Tree
• Their working parts incorporated into a solid,
• Single piece steel block
– with no connections between the individual valves.
• Advantages: - Contain fewer potential leak paths,
- Much shorter than conventional trees.
• Disadvantages: - More expensive.
• Completion can be pulled through the
tree without removing it.
• These trees are finding favor with
operators of ESP completion,
• No valves in vertical bore of tree,
• Two valves are on the production or flow
wing
• Two retrievable plugs set in the top of
the tree below the cap.
Horizontal Tree
Tee Cap
Crown Plugs
Tubing Hanger
Treehead
Tee Connector
Wellhead
Conventional Wellhead
API test pressures for all wellhead
testing by manufacturers, (including
the surface pressure control
equipment and downhole equipment):
• Twice the rated working pressure
up to 5,000 psi,
• 1 1/2 times working pressure
for 5,000 psi and above.
Spool type casing head.
• Wellhead is built up until the casing strings has been run.
• BOPs must be removed after cementing a casing string to
install the casing spool.
• Each casing string has it’s own casing hanger spool.
• Casing spool outlets are flanged or studs (cheaper).
• Outlets name: A, B or C (‘A’ internal annulus)
• ‘A’ annulus may be used for monitoring pressures
– gas lift inlet, chemical injection inlet, kill circuit,
– equalising pressure downhole before opening SSD’s.
– tubing, packer seal or wellhead seal leak.
Disadvantages:
• 1) Vertical clearance between rigfloor is excessive,
• 2) Each flange connection is a potential leak path.
Conventional
Wellhead
A
B
C
Compact (Unihead, Multibowl) Wellhead
• Each successive casing hanger is landed in the same bowl.
• BOPs do not need to be nippled down and up again (saves rig time).
• Developed in response to the needs of offshore operators.
• Compact wellhead overcomes the potential leak each flange connections.
• API 6A certified, API PR1, PR2
• Rated for 2,000 to 15,000 PSI and -75 ° F to
400 ° F .
• Material classes AA to HH.
• Elastomeric or metal-to-metal sealing.
• Accommodates casing sizes up to 26
inches.
• Reduces number of BOP connection
breakage.
• Available for both vertical and horizontal
production.
• Compact design decreases height and
weight.
• The wellhead sits on top of the conductor
(outer most pipe is the conductor).
Compact
Wellhead
Compact
Wellhead
Compact
Wellhead
Pack-off Bushing
• The MBS Wellhead pack-off bushing lands on the casing hanger to
suspend and seal the intermediate casing string(s).
• The inner seal on the bushing is a D seal which is energized by plastic
packing.
• This seal can be reenergized, if necessary, throughout the life of the well.
• The outer seal is radially energized.
Casing
Hanger
Wellheadből kivenni!
Tubing
Hanger
Mechanically
Screwed plug type
Wireline plug type Dual Tubing hanger
wireline plug type
• Located at top of the completion string,
• Enable to run, hang-off, set and seal the completion string,
• It forms the load-bearing and supporting interface for tubing string,
• Accommodates the down hole control line connections.
• Have a screwed or nipple profile for a plug to be installed prior to
removing the X-mas tree,
• Have a function during the testing of the Xmas tree valves.
• Seal is typically a metal-to-metal seal,
• Tested both prior to and after releasing the tubing hanger running tool.
Secondary Barrier
Tubing Hanger Plugs
Tubing hanger usually has a place for locating a
– Tubing Hanger Plug or
– Back Pressure Valve or
– Two Way Check Valve.
Functions:
• Sealing off the top of the well below the Xmas tree.
• If using a DHSV control line(s), seals off the line(s).
• Devices can be run into the tubing hanger with the well still under pressure.
They are of two basic kinds:
• Wireline type plugs
• Mechanically screwed in plugs
QUESTIONS ?
WELL INTERVENTION PRESSURE
CONTROL
DOWNHOLE TOOLS
Well Training & Finance Ltd.
Dr. Imre Federer
Associate Professor
Downhole Tools
Tubing Hanger
Flow coupling
Safety Valve
Landing Nipple
Flow coupling
Side Pocket Mandrel
Flow coupling
Sliding Side Door
Packer
Millout Extension
Perforated Joint
Polished Bore Receptacle
Landing Nipple
Landing Nipple
Wireline Entry Guide
Wireline Entry Guide
It has a smooth, often tapered, inner profile,
To allow well servicing tools to re-enter with ease.
Bell Guide
45˚ lead in taper to allow easy re-entry wireline tools.
Mule Shoe
Has a 60o angle on the outside of the guide.
Tubing rotation will guide the tubing into the liner.
Flow coupling
Thick walled tubing designed to withstand erosion,
ID is drift of tubing but OD is collar OD.
Perforated joint
An entry path for reservoir fluids into the tubing,
Allowing accurate pressure/temperature recording.
Blast joints
The wall thickness is greater than tubing.
Installed in the tubing opposite perforations,
Prevent tubing damage from the jetting,
Nipples
• Nipples are to allow a wireline device to pass through an
upper nipple and be set in a lower one.
• The most common locations for nipples are:
– Just above the packer/seal assembly/circulating device for
pressure testing.
– Just below the packer/millout extension/seal bore
extension for pressure setting of the packer.
– At the bottom of the completion to enable gauges to be
hung and left in the well for a time to monitor the
reservoir.
Nipples
No-Go Nipple
• Has a No-Go restriction below the packing bore.
• The primary plugging point below the packer
• Receptacle for test plug to set the packer and test the
tubing.
• Used for plugging with locking device,
– when tubing has to be pulled and leaving the
packer in the hole.
Landing Nipple
• Has not a No-Go shoulder,
• It has a recess for locking dogs.
• Positive shoulder for locating the flow control device,
• Provides maximum through bore for completion.
Downhole Safety Valve
Commonly flapper valves which open downwards,
• It will isolate the reservoir fluids from surface.
It should be deep enough:
• to be unaffected by damage due to wellhead sabotage (explosions),
• to be unaffected by surface impact damage to the wellhead (collisions),
• to be unaffected by the crater that is formed by a major blowout,
• on closely spaced wellheads to be unaffected by another well being drilled
into it.
• In a single land well, the DHSV is often placed about 2-5 joints below the
ground level.
• There are offshore wells with the DHSV at 2500 ft below the tree.
• Allow the DHSV to be used as a barrier, when it has been closed and inflow
tested to prove that it is holding pressure.
Surface Controlled Sub-Surface Safety Valves (SCSSV)
• It is a downhole safety device that can shut in a well in an emergency or
provide a barrier .
• It can be controlled from the surface by hydraulic pressure through control
line to the SCSSV.
• It is held open by hydraulic pressure supplied by a manifold at the surface.
• Damage to the wellhead or flowlines causes a low operating pressure. When
this pressure is lost, the safety valve automatically closes.
• It is failsafe and will isolate the wellbore in the event of a loss of the
wellhead pressure control.
Two main categories:
• Wireline Retrievable SCSSV
• Tubing Retrievable SCSSV.
Tubing Retrievable SCSSV
• This is run and pulled as an integral part of
the tubing string.
• All components are incorporated in one
assembly which is installed in the completion
string.
• If the control line leaks it may be possible to
run with wireline a ‘Storm Choke’ to
production until to conduct workover
Damage can be happened:
• Running into the open DHSV with an item of
well servicing equipment (wear, mechanical
damage).
• Allowing the DHSV to close on the well
servicing equipment that is running through.
.
Tubing Retrievable SCSSV
Disadvantage:
• It can be removed for repair only with doing a workover.
• For this reason, should a tubing retrievable DHSV fail, the facility exists to
permanently lock it open and insert another – wireline retrievable – safety
valve inside it.
Advantage:
• It has a much larger bore and hence flow through it,
• There is no facility for removing it before commencing intervention operations,
• No potential flow path up the control line of the risk of damage to the DHSV,
• It is possible to run it open with an installed straddle across the valve.
• This straddle is pulled with wireline after the completion is set and the tree is
on.
Wireline Retrievable SCSSV
• It is locked and sealed off in a special landing nipple
• Which has a side connection for the control line,
• Between two packing stacks allowed control pressure to open
the valve.
• DHSV in intervention work requires the removal.
• There is then a flow path from the inside of the tubing, up the
control line, to the surface.
• Isolation sleeve can be installed in nipple to isolate this flow
path
Disadvantage:
• It is reduced bore since the DHSV must pass through the tubing
above it.
• Designing the well so that the size of the tubing above the DHSV
is larger than the tubing size below.
Advantage:
• It is quick, easy and cheap to regularly replace, serviced.
• It is run in the well in open position by a special prong.
TOP VIEW
HRP SAFETY VALVE
LANDING NIPPLE
LOCK
MANDREL
SAFETY
VALVE
Annulus Safety Valves
• For gas lift well, it is often a requirement to install the annular safety valve.
• Annular safety valve system provides a retrievable safety valve and packer.
• This is usually combined with the tubing safety valve in one unit and
resembles a packer.
• It is placed at the same depth as an ordinary safety valve would be placed.
• This is generally a packer type installation,
• But may also be a casing polished bore nipple into which a packing
mandrel will seal.
• In the sealing device there is a valve mechanism operated by hydraulic
pressure similar to an SCSSV.
• The valve mechanism opens the communication path from the annulus
below to the annulus above the valve and is fail-safe closed.
Sub-Surface Controlled
Sub-Surface Safety Valves
(SSSV)
• Storm Choke valves are restrictions in the flow
path held open by a spring.
• The well can be reopened by pumping.
• SSSV placed in a nipple in the completion.
• They are run and pulled by wireline.
• Popular in land operations due to its min.price.
Two Types:
• Excess flow (pressure differential). If the flow
rate increase significantly, the pressure
differential across a choke changes and a spring
closes the valve.
• Pressure activated (ambient pressure). The
well hydrostatic pressure keeps the valve open.
If the well starts to blow out, the tubing
pressure drops and the valve is closed by a
spring and pre-charged nitrogen chamber.
Spring
Open Close
Side Pocket Mandrel (SMP)
• In Gas Lift wells, high pressure gas injected
into the annulus flows through the ports of
the pocket in gas lift valve and into the tubing.
• The standard pocket is ported between the
seal bores to communicate with the casing
annulus.
• The SPM are used for tubing flow applications.
• SPM are available in sizes from 2-3/8” to 4-
1/2” tubing and they will work with 1” and 1-
1/2” O. D. gas lift valves.
• Side pocket mandrels have a position
orienting sleeve and tool guard of the kick-
over tool with the pocket.
Gas Lift Completion
Tubing Retrievable Safety Valve
Packer
Landing Nipple
VII GLC 1
CN00049F
Side Pocket Mandrels with
Gas Lift Valves
Side Pocket Mandrel
(SMP)
SPM is most commonly used in two ways.
• Used as a means of gas lifting the well,
• By using a Kick-Over Tool, a plug or valve can be
run/pulled from the side pocket.
• Good practice to run a „valve catcher” below the SPM
before pulling/running devices in the pocket.
• This is so that, if they drop off the Kick-Over Tool, they
will not fall to the bottom of the well.
Devices that can be installed in a SPM are:
• Gas Lift Valve - gas injection into the tubing.
• Shear kill valve - pressuring up annulus opens valve.
• Circulation valve - for protecting the pocket.
• Injection valve - for injecting inhibitor.
• Gauges - for recording pressure and temperature.
• Dummy Valve - plug the SPM (positive plug).
Orienting Kickover Tool
Sliding Sleeve (SS)
• Circulating device which allows communication
between tubing and annulus, without unseating the
packer.
• Installed in the tubing string a SS has a port that can be
opened and closed by wireline.
• Shifting Tool is run on wireline and engages a profile
on the inside of the inner sleeve.
• By jarring the inner sleeve is moved.
• To close the Sliding Sleeve after it has been opened,
the shifting tool is run the other way up and again it
engages in the profile.
• By jarring in the opposite direction to opening, the
inner sleeve moves to closed position.
• Such sleeves can either open upward and close
downward or open downward and close upward.
Downhole Tools
Packers
• A packer seals the annular space between the casing and the tubing.
• It prevents the wellbore fluids from contacting the casing above the
packer and isolates the annulus from the pressure inside the tubing.
• It protects the casing from high production or stimulation pressures
and corrosive fluids.
• Multiple packers isolate dual or triple completion.
• Special packers are also available for squeeze cementing, acidizing, and
fracturing.
There are two main groups:
• Retrievable Packers
• Permanent Packers
Downhole Tools
Packers
Retrievable Packer
• Packers setting mechanisms: hydraulic or mechanical
• Tension packers require an upstrain and compression
packers require a set down weight.
• The mechanism which controls whether the packer is
in the setting position is usually a „J” slot.
Disadvantage :
• During the life of the well, the downhole pressure and
temperature can change sufficiently to remove enough
weight from the packer to unseat it.
Advantage:
• The retrievable packer can remove, unseat and pull it
the service person can redress most retrievable
packers with seals and slips at the job site.
„J” slot
Mechanical Set
Retrievable Packer
Downhole Tools
Packers
Permanent Packers
• The packer may or may not be attached to the tubing
above it
• It can only be retrieved by milling.
The most common way they are set is either
• mechanically or explosively with wireline,
• hydraulically by applying pressure inside them.
Permanent
Seal Bore Packer
Permanent Packers
Removing these packers is in two stages:
• First: the tubing above the packer must be
removed. It may require that the tubing be cut
just above the packer.
• Second: a special mill is run to mill up the top
set of slips, which allows the packer to release
from the casing wall.
Millout Extension:
• It is a pup joint with a slightly larger I.D than
the packer.
• It may be attached to the bottom of packers
to enable to retrieved after it has had the top
slips milled off.
• It is used to accommodate a spear during
packer milling operations retrieved the packer
and tail-pipe in same run.
Permanent
Seal Bore
Packer
Downhole Tools
Packers
Seal Assemblies
• Seal Assemblies are installed in packers to prevent pressure from escaping
between the tubing and the packer.
• It run on the bottom of the tubing string and inserted into the packer.
• A latch-type seal nipple is also available that locks into the packer so that
tension may be pulled on the tubing if desired.
• There is a set of seals that are able to slide up and down inside or outside
another section.
• This maintains isolation of the tubing and its annulus whilst allowing for
tubing movement.
Downhole Tools
Packers
Different types of sealing:
•Tubing Seal Assembly: seals are able to move up and down inside a seal bore
in the packer itself.
•Seal Bore Extension: attached to the bottom of the packer, it can be very
much longer allowing for greater tubing movement.
•Slick joint: may be run above the packer.
– This is a single unit designed for running the tubing attached to the
packer.
– Once the packer has been set, the pins are sheared, the hanger landed
and the slick joint is able to allow tubing movement.
•Tubing anchor: If the tubing is not screwed directly into the top of the
permanent packer, it may be attached by means of a tubing anchor.
– This is a device that stabs into the top of the packer and seals off
inside the top of the packer.
Downhole Tools
Packers
The Polished Bore Receptacle (PBR) may be attached to the top
of the packer.
• This is a housing into which seals on the bottom of the tubing
can be stabbed.
• These can be 40 ft to 50 ft long. It allow for tubing movement.
The Extra Long Tubing Seal Receptacle (ELTSR) has the seals
inside the enlarged bottom section of tubing being run.
• This is stabbed over a mandrel with a polished external surface
attached to the top of the packer.
• Again this may be up to 60 ft long to allow for up to 30 ft of
movement up or down.
Downhole Tools
Flow Control Devices
Blanking Plugs (Positive plugs)
• They seal off in the nipple and hold pressure from both
directions.
• The pressure rating of plug should always be checked if it is
planned to pressure up against it from above.
Flow Control Devices
Check Valve
•Seal off in the nipple and hold pressure from above only.
•Usually used for pressure testing the completion above the
valve.
•Often used for setting packers.
•Check valves are also available which hold pressure from
below only.
•They can be pumped through by applying tubing pressure
above.
•Sometimes called Pump Through Plugs they can be used to
isolate the well below a certain point while retaining the
ability to pump into or kill the well.
Pump Through Plug
Flow Control Devices
Pump Open Plug
• It is a positive plug that holds pressure from either
direction.
• But can be pumped open by applying excess surface
pressure, the inside of the plug shears, which allows flow
from below.
• It is used for production without retrieving by slickline.
• It serve as temporary tubing plugs.
• It is useful for conventional plugging applications in sandy
conditions where equalizing through small bore equalizing
devices might be difficult.
• They can be run pre-installed in the nipple.
Flow Control Devices
Pressure Cycle Plugs
•The overbalance pressure above the plug must be cycled from zero to a pre-
set value of perhaps 2500 psi a fixed number of times before the plug opens.
•The number of cycles can be pre-set to anything up to 20.
•The pressure cycle plug offers more flexibility and security before the plug is
opened.
Pump Out Plugs
•When the correct pressure is applied above the plug, the bottom of the plug
shears off and is left downhole.
•They can give a greater flow path than pump open plugs although they have
the same disadvantage of leaving a restriction in the nipple.
Flow Control Devices
Retrievable Bridge Plugs
•It can be set anywhere in the tubing
•It is usually set by an explosive force, having been run on electric line.
•In this respect they are like a miniature packer in that they have slips and
packing elements.
•Slickline or Coiled Tubing can however pull them.
Pump Out Subs
•Same principle as the pump out plug, they are attached to the bottom of a
completion.
•When pressured up on and sheared, they leave a smooth full-bore end on
the pipe.
•They can be used when running completions in the same way as a pump
open plug.
Flow Control Devices
Ice Plugs
•When all other methods of plugging a well are not possible, an ice plug may
be made in a piece of surface equipment.
•Freeze jobs were originally done by surrounding the item to be frozen.
•In a special coil through which chemicals like glycol are passed that have
been cooled to a pre-determined level in a heat exchanger by liquid nitrogen.
•It is necessary to have still fresh water at the point where the plug is to be
formed.
•The process can be slow with plugs taking up to 18 hrs or more to form.
Questions?

Weitere ähnliche Inhalte

Was ist angesagt?

Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipplesElsayed Amer
 
Scsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valveScsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valveElsayed Amer
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operationsAbdulkadir Tekin
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & AbandonmentStatoil
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Tubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industryTubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industryPE Mahmoud Jad
 
7'' liner running and cementing
7'' liner running and cementing7'' liner running and cementing
7'' liner running and cementingKamel Elsayed
 
4th Presentation
4th Presentation4th Presentation
4th PresentationBarun
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN Elsayed Amer
 
Well_Intervention_Presentation
Well_Intervention_PresentationWell_Intervention_Presentation
Well_Intervention_PresentationMuhammad Hassaan
 
Production Packer setting and types
Production Packer setting and typesProduction Packer setting and types
Production Packer setting and typesElsayed Amer
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1Elsayed Amer
 
02 wireline
02 wireline02 wireline
02 wirelineJohan RC
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 

Was ist angesagt? (20)

Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipples
 
Wellhead basics
Wellhead basicsWellhead basics
Wellhead basics
 
Wellheads Training .pdf
Wellheads Training .pdfWellheads Training .pdf
Wellheads Training .pdf
 
Coiled tubing Equipments .pdf
Coiled tubing Equipments .pdfCoiled tubing Equipments .pdf
Coiled tubing Equipments .pdf
 
Scsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valveScsssv surface control subsurface safety valve
Scsssv surface control subsurface safety valve
 
Liner hanger design and operations
Liner hanger design and operationsLiner hanger design and operations
Liner hanger design and operations
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & Abandonment
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Tubing string
Tubing stringTubing string
Tubing string
 
Ssd spm
Ssd   spmSsd   spm
Ssd spm
 
Tubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industryTubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industry
 
7'' liner running and cementing
7'' liner running and cementing7'' liner running and cementing
7'' liner running and cementing
 
Casing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger systemCasing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger system
 
4th Presentation
4th Presentation4th Presentation
4th Presentation
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN
 
Well_Intervention_Presentation
Well_Intervention_PresentationWell_Intervention_Presentation
Well_Intervention_Presentation
 
Production Packer setting and types
Production Packer setting and typesProduction Packer setting and types
Production Packer setting and types
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
 
02 wireline
02 wireline02 wireline
02 wireline
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 

Ähnlich wie Wen_Design.ppt

Balancing Cost, Performance and Reliability when Choosing Solenoid Valves
Balancing Cost, Performance and Reliability when Choosing Solenoid ValvesBalancing Cost, Performance and Reliability when Choosing Solenoid Valves
Balancing Cost, Performance and Reliability when Choosing Solenoid ValvesDesign World
 
wellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfwellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfAZLANAiyub
 
05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007yudi05
 
Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training ProgramArul Balan
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaAnand Prithviraj
 
The humble check_valve
The humble check_valveThe humble check_valve
The humble check_valveUsama Khan
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxholegajendra
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPTMahadev Kovalli
 
4 primary parts Butterfly valve manufacturer comprises
4 primary parts Butterfly valve manufacturer comprises4 primary parts Butterfly valve manufacturer comprises
4 primary parts Butterfly valve manufacturer comprisesG M Engineering Pvt Ltd
 

Ähnlich wie Wen_Design.ppt (20)

Balancing Cost, Performance and Reliability when Choosing Solenoid Valves
Balancing Cost, Performance and Reliability when Choosing Solenoid ValvesBalancing Cost, Performance and Reliability when Choosing Solenoid Valves
Balancing Cost, Performance and Reliability when Choosing Solenoid Valves
 
wellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfwellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdf
 
Valve
ValveValve
Valve
 
05 well testing trisakti 25 nov 2007
05 well testing   trisakti 25 nov 200705 well testing   trisakti 25 nov 2007
05 well testing trisakti 25 nov 2007
 
Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training Program
 
Fluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteriaFluid conductors: Design and selection criteria
Fluid conductors: Design and selection criteria
 
BOP
BOPBOP
BOP
 
Mechanical seals
Mechanical sealsMechanical seals
Mechanical seals
 
The humble check_valve
The humble check_valveThe humble check_valve
The humble check_valve
 
Pigging Pipelines.pdf
Pigging Pipelines.pdfPigging Pipelines.pdf
Pigging Pipelines.pdf
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Control Valves
Control ValvesControl Valves
Control Valves
 
Valves and Testing .pdf
Valves and Testing .pdfValves and Testing .pdf
Valves and Testing .pdf
 
switching & control devices
switching & control devicesswitching & control devices
switching & control devices
 
Descon Presentation
Descon PresentationDescon Presentation
Descon Presentation
 
VALVE AND TESTING.pdf
VALVE AND TESTING.pdfVALVE AND TESTING.pdf
VALVE AND TESTING.pdf
 
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptxPRESENTATION ON SURGE ANTICIPATION VALVE.pptx
PRESENTATION ON SURGE ANTICIPATION VALVE.pptx
 
500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT500MW presentation - 11102006.PPT
500MW presentation - 11102006.PPT
 
4 primary parts Butterfly valve manufacturer comprises
4 primary parts Butterfly valve manufacturer comprises4 primary parts Butterfly valve manufacturer comprises
4 primary parts Butterfly valve manufacturer comprises
 
pool circulation
pool circulationpool circulation
pool circulation
 

Mehr von MOHAMMEDSalih117921

Mehr von MOHAMMEDSalih117921 (8)

عرض تقديمي خاص بقسم الانتاج 1.pptx
عرض تقديمي خاص بقسم الانتاج 1.pptxعرض تقديمي خاص بقسم الانتاج 1.pptx
عرض تقديمي خاص بقسم الانتاج 1.pptx
 
P-Difference between methods.pptx
P-Difference between methods.pptxP-Difference between methods.pptx
P-Difference between methods.pptx
 
I-Gas Migration.pptx
I-Gas Migration.pptxI-Gas Migration.pptx
I-Gas Migration.pptx
 
F-Fractures and MAASP.ppt
F-Fractures and MAASP.pptF-Fractures and MAASP.ppt
F-Fractures and MAASP.ppt
 
O-Gas Behavior during killing.pptx
O-Gas Behavior during killing.pptxO-Gas Behavior during killing.pptx
O-Gas Behavior during killing.pptx
 
ت.pptx
ت.pptxت.pptx
ت.pptx
 
Casing_Design(1).ppt
Casing_Design(1).pptCasing_Design(1).ppt
Casing_Design(1).ppt
 
Chapter_6hdhdvd-OCW.pdf
Chapter_6hdhdvd-OCW.pdfChapter_6hdhdvd-OCW.pdf
Chapter_6hdhdvd-OCW.pdf
 

Kürzlich hochgeladen

Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Apollo Techno Industries Pvt Ltd
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxjasonsedano2
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...sahb78428
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical SensorTanvir Moin
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxYogeshKumarKJMIT
 
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfsdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfJulia Kaye
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Projectreemakb03
 
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Amil baba
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technologyabdulkadirmukarram03
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Akarthi keyan
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptxSaiGouthamSunkara
 
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....santhyamuthu1
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfRedhwan Qasem Shaddad
 
Multicomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfMulticomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfGiovanaGhasary1
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Bahzad5
 

Kürzlich hochgeladen (20)

Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...Technology Features of Apollo HDD Machine, Its Technical Specification with C...
Technology Features of Apollo HDD Machine, Its Technical Specification with C...
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptx
 
Lecture 4 .pdf
Lecture 4                              .pdfLecture 4                              .pdf
Lecture 4 .pdf
 
Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...Clutches and brkesSelect any 3 position random motion out of real world and d...
Clutches and brkesSelect any 3 position random motion out of real world and d...
 
Litature Review: Research Paper work for Engineering
Litature Review: Research Paper work for EngineeringLitature Review: Research Paper work for Engineering
Litature Review: Research Paper work for Engineering
 
Basic Principle of Electrochemical Sensor
Basic Principle of  Electrochemical SensorBasic Principle of  Electrochemical Sensor
Basic Principle of Electrochemical Sensor
 
Design of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptxDesign of Clutches and Brakes in Design of Machine Elements.pptx
Design of Clutches and Brakes in Design of Machine Elements.pptx
 
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdfsdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
sdfsadopkjpiosufoiasdoifjasldkjfl a asldkjflaskdjflkjsdsdf
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Project
 
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
 
The relationship between iot and communication technology
The relationship between iot and communication technologyThe relationship between iot and communication technology
The relationship between iot and communication technology
 
me3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part Ame3493 manufacturing technology unit 1 Part A
me3493 manufacturing technology unit 1 Part A
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptx
 
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....
SATELITE COMMUNICATION UNIT 1 CEC352 REGULATION 2021 PPT BASICS OF SATELITE ....
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdf
 
Multicomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdfMulticomponent Spiral Wound Membrane Separation Model.pdf
Multicomponent Spiral Wound Membrane Separation Model.pdf
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
 
Lecture 2 .pdf
Lecture 2                           .pdfLecture 2                           .pdf
Lecture 2 .pdf
 

Wen_Design.ppt

  • 1. WELL INTERVENTION PRESSURE CONTROL WELL COMPLETION Dr. Imre Federer Associate Professor
  • 2. COMPLETING THE WELL General • The well intervention well control is – about the well control of working on live wells – the well operations are conducted by • wireline, • coiled tubing • snubbing unit. • Well pressure control is the most critical consideration in the planning and performing of any well servicing operation.
  • 3. Completion Fluid Characteristics Dense: • enough to control well pressures but no frac. the formation Cost-effective: • Expensive fluids to prevent damage to sensitive formations. Free of solid particles as possible: • Solids can plug perforations as well as reduce production. Noncorrosive : • to prevent failure of tubular goods. Stable: • If the fluid is to be left in the hole for an extended period. Filtered or cleaned: • The low solids content can still cause plugging at formation.
  • 4. Completion Fluid Density Ranges Fluid Minimum Density kg/l (ppg) Practical Maximum Density kg/l (ppg) Oil 0.96 (8.0) Diesel oil 0,84 (7.0) Fresh water 1.0 (8.3) 1.0 (8.3) Sea water 1.01 (8.4) 1.02 (8.5) Brine-sodium chloride (NaCl) 1.0 (8.3) 1.18 (9.8) Brine-potassium chloride 1.0 (8.3) 1.17 (9.7) Brine-calcium chloride 1.32 (11.0) 1.38 (11.5) Brine-calcium bromide 1.38 (11.5) 1.80 (15.0) Brine-zinc bromide (ZnBr2) 1.68 (14.0) 2.18 (18.1)
  • 5. Crystallization Point of Brines Weight Crystallization Point kg/l ppg oC oF Sodium Chloride (NaCl) 1,02 8.5 -2 29 1,08 9.0 -7 19 1,14 9.5 -16 6 1,2 10.0 -4 25 Calcium Chloride (CaCl2) 1,02 8.5 -1 30 1,08 9.0 -0,5 31 1,14 9.5 -13 9 1,2 10.0 -22 -8 1,26 10.5 -37 -36 1,32 11.0 -30 -22 1,38 11.5 +2 35 Calcium Chloride/Bromide (CaCl2/Br2) 1,44 12.0 12 54 1,56 13.0 15 59 1,68 14.0 17,7 64 1,74 14.5 18,3 65 1,8 15.0 19,4 67
  • 6. Density Loss due to Temperature Brine Factors NaCl or KCl 0.0024 CaCl2 0.0027 NaBr or NaBr/NaCl 0.0033 CaBr2 or CaBr2 /CaCl2 0.0033 ZnBr2 / CaBr2 / CaCl2< 2.1 kg/l (17.5 lb/gal) 0.0036 0.0048 Calculate density loss due to temperature. ATI = Average temperature increase, oF Cf = Correction factor for temperature from Table DL = Density loss, ppg Cf * ATI DL =
  • 8. Conventional Wellhead and Christmas Tree
  • 10. Conventional Tree • Advantages: Made up of interchangeable standard parts cheapest option. • Disadvantages: more potential leak paths due to the large number of connections. Master Valve Block Tree Cap Tree Connector Tubing Hanger Wellhead
  • 11. Solid Block Tree • Their working parts incorporated into a solid, • Single piece steel block – with no connections between the individual valves. • Advantages: - Contain fewer potential leak paths, - Much shorter than conventional trees. • Disadvantages: - More expensive.
  • 12. • Completion can be pulled through the tree without removing it. • These trees are finding favor with operators of ESP completion, • No valves in vertical bore of tree, • Two valves are on the production or flow wing • Two retrievable plugs set in the top of the tree below the cap. Horizontal Tree Tee Cap Crown Plugs Tubing Hanger Treehead Tee Connector Wellhead
  • 13. Conventional Wellhead API test pressures for all wellhead testing by manufacturers, (including the surface pressure control equipment and downhole equipment): • Twice the rated working pressure up to 5,000 psi, • 1 1/2 times working pressure for 5,000 psi and above.
  • 14. Spool type casing head. • Wellhead is built up until the casing strings has been run. • BOPs must be removed after cementing a casing string to install the casing spool. • Each casing string has it’s own casing hanger spool. • Casing spool outlets are flanged or studs (cheaper). • Outlets name: A, B or C (‘A’ internal annulus) • ‘A’ annulus may be used for monitoring pressures – gas lift inlet, chemical injection inlet, kill circuit, – equalising pressure downhole before opening SSD’s. – tubing, packer seal or wellhead seal leak. Disadvantages: • 1) Vertical clearance between rigfloor is excessive, • 2) Each flange connection is a potential leak path. Conventional Wellhead A B C
  • 15. Compact (Unihead, Multibowl) Wellhead • Each successive casing hanger is landed in the same bowl. • BOPs do not need to be nippled down and up again (saves rig time). • Developed in response to the needs of offshore operators. • Compact wellhead overcomes the potential leak each flange connections. • API 6A certified, API PR1, PR2 • Rated for 2,000 to 15,000 PSI and -75 ° F to 400 ° F . • Material classes AA to HH. • Elastomeric or metal-to-metal sealing. • Accommodates casing sizes up to 26 inches. • Reduces number of BOP connection breakage. • Available for both vertical and horizontal production. • Compact design decreases height and weight. • The wellhead sits on top of the conductor (outer most pipe is the conductor).
  • 19. Pack-off Bushing • The MBS Wellhead pack-off bushing lands on the casing hanger to suspend and seal the intermediate casing string(s). • The inner seal on the bushing is a D seal which is energized by plastic packing. • This seal can be reenergized, if necessary, throughout the life of the well. • The outer seal is radially energized. Casing Hanger Wellheadből kivenni!
  • 20. Tubing Hanger Mechanically Screwed plug type Wireline plug type Dual Tubing hanger wireline plug type • Located at top of the completion string, • Enable to run, hang-off, set and seal the completion string, • It forms the load-bearing and supporting interface for tubing string, • Accommodates the down hole control line connections. • Have a screwed or nipple profile for a plug to be installed prior to removing the X-mas tree, • Have a function during the testing of the Xmas tree valves. • Seal is typically a metal-to-metal seal, • Tested both prior to and after releasing the tubing hanger running tool. Secondary Barrier
  • 21. Tubing Hanger Plugs Tubing hanger usually has a place for locating a – Tubing Hanger Plug or – Back Pressure Valve or – Two Way Check Valve. Functions: • Sealing off the top of the well below the Xmas tree. • If using a DHSV control line(s), seals off the line(s). • Devices can be run into the tubing hanger with the well still under pressure. They are of two basic kinds: • Wireline type plugs • Mechanically screwed in plugs
  • 23. WELL INTERVENTION PRESSURE CONTROL DOWNHOLE TOOLS Well Training & Finance Ltd. Dr. Imre Federer Associate Professor
  • 24. Downhole Tools Tubing Hanger Flow coupling Safety Valve Landing Nipple Flow coupling Side Pocket Mandrel Flow coupling Sliding Side Door Packer Millout Extension Perforated Joint Polished Bore Receptacle Landing Nipple Landing Nipple Wireline Entry Guide Wireline Entry Guide It has a smooth, often tapered, inner profile, To allow well servicing tools to re-enter with ease. Bell Guide 45˚ lead in taper to allow easy re-entry wireline tools. Mule Shoe Has a 60o angle on the outside of the guide. Tubing rotation will guide the tubing into the liner. Flow coupling Thick walled tubing designed to withstand erosion, ID is drift of tubing but OD is collar OD. Perforated joint An entry path for reservoir fluids into the tubing, Allowing accurate pressure/temperature recording. Blast joints The wall thickness is greater than tubing. Installed in the tubing opposite perforations, Prevent tubing damage from the jetting,
  • 25. Nipples • Nipples are to allow a wireline device to pass through an upper nipple and be set in a lower one. • The most common locations for nipples are: – Just above the packer/seal assembly/circulating device for pressure testing. – Just below the packer/millout extension/seal bore extension for pressure setting of the packer. – At the bottom of the completion to enable gauges to be hung and left in the well for a time to monitor the reservoir.
  • 26. Nipples No-Go Nipple • Has a No-Go restriction below the packing bore. • The primary plugging point below the packer • Receptacle for test plug to set the packer and test the tubing. • Used for plugging with locking device, – when tubing has to be pulled and leaving the packer in the hole. Landing Nipple • Has not a No-Go shoulder, • It has a recess for locking dogs. • Positive shoulder for locating the flow control device, • Provides maximum through bore for completion.
  • 27. Downhole Safety Valve Commonly flapper valves which open downwards, • It will isolate the reservoir fluids from surface. It should be deep enough: • to be unaffected by damage due to wellhead sabotage (explosions), • to be unaffected by surface impact damage to the wellhead (collisions), • to be unaffected by the crater that is formed by a major blowout, • on closely spaced wellheads to be unaffected by another well being drilled into it. • In a single land well, the DHSV is often placed about 2-5 joints below the ground level. • There are offshore wells with the DHSV at 2500 ft below the tree. • Allow the DHSV to be used as a barrier, when it has been closed and inflow tested to prove that it is holding pressure.
  • 28. Surface Controlled Sub-Surface Safety Valves (SCSSV) • It is a downhole safety device that can shut in a well in an emergency or provide a barrier . • It can be controlled from the surface by hydraulic pressure through control line to the SCSSV. • It is held open by hydraulic pressure supplied by a manifold at the surface. • Damage to the wellhead or flowlines causes a low operating pressure. When this pressure is lost, the safety valve automatically closes. • It is failsafe and will isolate the wellbore in the event of a loss of the wellhead pressure control. Two main categories: • Wireline Retrievable SCSSV • Tubing Retrievable SCSSV.
  • 29. Tubing Retrievable SCSSV • This is run and pulled as an integral part of the tubing string. • All components are incorporated in one assembly which is installed in the completion string. • If the control line leaks it may be possible to run with wireline a ‘Storm Choke’ to production until to conduct workover Damage can be happened: • Running into the open DHSV with an item of well servicing equipment (wear, mechanical damage). • Allowing the DHSV to close on the well servicing equipment that is running through. .
  • 30. Tubing Retrievable SCSSV Disadvantage: • It can be removed for repair only with doing a workover. • For this reason, should a tubing retrievable DHSV fail, the facility exists to permanently lock it open and insert another – wireline retrievable – safety valve inside it. Advantage: • It has a much larger bore and hence flow through it, • There is no facility for removing it before commencing intervention operations, • No potential flow path up the control line of the risk of damage to the DHSV, • It is possible to run it open with an installed straddle across the valve. • This straddle is pulled with wireline after the completion is set and the tree is on.
  • 31. Wireline Retrievable SCSSV • It is locked and sealed off in a special landing nipple • Which has a side connection for the control line, • Between two packing stacks allowed control pressure to open the valve. • DHSV in intervention work requires the removal. • There is then a flow path from the inside of the tubing, up the control line, to the surface. • Isolation sleeve can be installed in nipple to isolate this flow path Disadvantage: • It is reduced bore since the DHSV must pass through the tubing above it. • Designing the well so that the size of the tubing above the DHSV is larger than the tubing size below. Advantage: • It is quick, easy and cheap to regularly replace, serviced. • It is run in the well in open position by a special prong. TOP VIEW HRP SAFETY VALVE LANDING NIPPLE LOCK MANDREL SAFETY VALVE
  • 32. Annulus Safety Valves • For gas lift well, it is often a requirement to install the annular safety valve. • Annular safety valve system provides a retrievable safety valve and packer. • This is usually combined with the tubing safety valve in one unit and resembles a packer. • It is placed at the same depth as an ordinary safety valve would be placed. • This is generally a packer type installation, • But may also be a casing polished bore nipple into which a packing mandrel will seal. • In the sealing device there is a valve mechanism operated by hydraulic pressure similar to an SCSSV. • The valve mechanism opens the communication path from the annulus below to the annulus above the valve and is fail-safe closed.
  • 33. Sub-Surface Controlled Sub-Surface Safety Valves (SSSV) • Storm Choke valves are restrictions in the flow path held open by a spring. • The well can be reopened by pumping. • SSSV placed in a nipple in the completion. • They are run and pulled by wireline. • Popular in land operations due to its min.price. Two Types: • Excess flow (pressure differential). If the flow rate increase significantly, the pressure differential across a choke changes and a spring closes the valve. • Pressure activated (ambient pressure). The well hydrostatic pressure keeps the valve open. If the well starts to blow out, the tubing pressure drops and the valve is closed by a spring and pre-charged nitrogen chamber. Spring Open Close
  • 34. Side Pocket Mandrel (SMP) • In Gas Lift wells, high pressure gas injected into the annulus flows through the ports of the pocket in gas lift valve and into the tubing. • The standard pocket is ported between the seal bores to communicate with the casing annulus. • The SPM are used for tubing flow applications. • SPM are available in sizes from 2-3/8” to 4- 1/2” tubing and they will work with 1” and 1- 1/2” O. D. gas lift valves. • Side pocket mandrels have a position orienting sleeve and tool guard of the kick- over tool with the pocket. Gas Lift Completion Tubing Retrievable Safety Valve Packer Landing Nipple VII GLC 1 CN00049F Side Pocket Mandrels with Gas Lift Valves
  • 35. Side Pocket Mandrel (SMP) SPM is most commonly used in two ways. • Used as a means of gas lifting the well, • By using a Kick-Over Tool, a plug or valve can be run/pulled from the side pocket. • Good practice to run a „valve catcher” below the SPM before pulling/running devices in the pocket. • This is so that, if they drop off the Kick-Over Tool, they will not fall to the bottom of the well. Devices that can be installed in a SPM are: • Gas Lift Valve - gas injection into the tubing. • Shear kill valve - pressuring up annulus opens valve. • Circulation valve - for protecting the pocket. • Injection valve - for injecting inhibitor. • Gauges - for recording pressure and temperature. • Dummy Valve - plug the SPM (positive plug). Orienting Kickover Tool
  • 36. Sliding Sleeve (SS) • Circulating device which allows communication between tubing and annulus, without unseating the packer. • Installed in the tubing string a SS has a port that can be opened and closed by wireline. • Shifting Tool is run on wireline and engages a profile on the inside of the inner sleeve. • By jarring the inner sleeve is moved. • To close the Sliding Sleeve after it has been opened, the shifting tool is run the other way up and again it engages in the profile. • By jarring in the opposite direction to opening, the inner sleeve moves to closed position. • Such sleeves can either open upward and close downward or open downward and close upward.
  • 37. Downhole Tools Packers • A packer seals the annular space between the casing and the tubing. • It prevents the wellbore fluids from contacting the casing above the packer and isolates the annulus from the pressure inside the tubing. • It protects the casing from high production or stimulation pressures and corrosive fluids. • Multiple packers isolate dual or triple completion. • Special packers are also available for squeeze cementing, acidizing, and fracturing. There are two main groups: • Retrievable Packers • Permanent Packers
  • 38. Downhole Tools Packers Retrievable Packer • Packers setting mechanisms: hydraulic or mechanical • Tension packers require an upstrain and compression packers require a set down weight. • The mechanism which controls whether the packer is in the setting position is usually a „J” slot. Disadvantage : • During the life of the well, the downhole pressure and temperature can change sufficiently to remove enough weight from the packer to unseat it. Advantage: • The retrievable packer can remove, unseat and pull it the service person can redress most retrievable packers with seals and slips at the job site. „J” slot Mechanical Set Retrievable Packer
  • 39. Downhole Tools Packers Permanent Packers • The packer may or may not be attached to the tubing above it • It can only be retrieved by milling. The most common way they are set is either • mechanically or explosively with wireline, • hydraulically by applying pressure inside them. Permanent Seal Bore Packer
  • 40. Permanent Packers Removing these packers is in two stages: • First: the tubing above the packer must be removed. It may require that the tubing be cut just above the packer. • Second: a special mill is run to mill up the top set of slips, which allows the packer to release from the casing wall. Millout Extension: • It is a pup joint with a slightly larger I.D than the packer. • It may be attached to the bottom of packers to enable to retrieved after it has had the top slips milled off. • It is used to accommodate a spear during packer milling operations retrieved the packer and tail-pipe in same run. Permanent Seal Bore Packer
  • 41. Downhole Tools Packers Seal Assemblies • Seal Assemblies are installed in packers to prevent pressure from escaping between the tubing and the packer. • It run on the bottom of the tubing string and inserted into the packer. • A latch-type seal nipple is also available that locks into the packer so that tension may be pulled on the tubing if desired. • There is a set of seals that are able to slide up and down inside or outside another section. • This maintains isolation of the tubing and its annulus whilst allowing for tubing movement.
  • 42. Downhole Tools Packers Different types of sealing: •Tubing Seal Assembly: seals are able to move up and down inside a seal bore in the packer itself. •Seal Bore Extension: attached to the bottom of the packer, it can be very much longer allowing for greater tubing movement. •Slick joint: may be run above the packer. – This is a single unit designed for running the tubing attached to the packer. – Once the packer has been set, the pins are sheared, the hanger landed and the slick joint is able to allow tubing movement. •Tubing anchor: If the tubing is not screwed directly into the top of the permanent packer, it may be attached by means of a tubing anchor. – This is a device that stabs into the top of the packer and seals off inside the top of the packer.
  • 43. Downhole Tools Packers The Polished Bore Receptacle (PBR) may be attached to the top of the packer. • This is a housing into which seals on the bottom of the tubing can be stabbed. • These can be 40 ft to 50 ft long. It allow for tubing movement. The Extra Long Tubing Seal Receptacle (ELTSR) has the seals inside the enlarged bottom section of tubing being run. • This is stabbed over a mandrel with a polished external surface attached to the top of the packer. • Again this may be up to 60 ft long to allow for up to 30 ft of movement up or down.
  • 44. Downhole Tools Flow Control Devices Blanking Plugs (Positive plugs) • They seal off in the nipple and hold pressure from both directions. • The pressure rating of plug should always be checked if it is planned to pressure up against it from above.
  • 45. Flow Control Devices Check Valve •Seal off in the nipple and hold pressure from above only. •Usually used for pressure testing the completion above the valve. •Often used for setting packers. •Check valves are also available which hold pressure from below only. •They can be pumped through by applying tubing pressure above. •Sometimes called Pump Through Plugs they can be used to isolate the well below a certain point while retaining the ability to pump into or kill the well. Pump Through Plug
  • 46. Flow Control Devices Pump Open Plug • It is a positive plug that holds pressure from either direction. • But can be pumped open by applying excess surface pressure, the inside of the plug shears, which allows flow from below. • It is used for production without retrieving by slickline. • It serve as temporary tubing plugs. • It is useful for conventional plugging applications in sandy conditions where equalizing through small bore equalizing devices might be difficult. • They can be run pre-installed in the nipple.
  • 47. Flow Control Devices Pressure Cycle Plugs •The overbalance pressure above the plug must be cycled from zero to a pre- set value of perhaps 2500 psi a fixed number of times before the plug opens. •The number of cycles can be pre-set to anything up to 20. •The pressure cycle plug offers more flexibility and security before the plug is opened. Pump Out Plugs •When the correct pressure is applied above the plug, the bottom of the plug shears off and is left downhole. •They can give a greater flow path than pump open plugs although they have the same disadvantage of leaving a restriction in the nipple.
  • 48. Flow Control Devices Retrievable Bridge Plugs •It can be set anywhere in the tubing •It is usually set by an explosive force, having been run on electric line. •In this respect they are like a miniature packer in that they have slips and packing elements. •Slickline or Coiled Tubing can however pull them. Pump Out Subs •Same principle as the pump out plug, they are attached to the bottom of a completion. •When pressured up on and sheared, they leave a smooth full-bore end on the pipe. •They can be used when running completions in the same way as a pump open plug.
  • 49. Flow Control Devices Ice Plugs •When all other methods of plugging a well are not possible, an ice plug may be made in a piece of surface equipment. •Freeze jobs were originally done by surrounding the item to be frozen. •In a special coil through which chemicals like glycol are passed that have been cooled to a pre-determined level in a heat exchanger by liquid nitrogen. •It is necessary to have still fresh water at the point where the plug is to be formed. •The process can be slow with plugs taking up to 18 hrs or more to form.