Canterbury earthquake response – key questions
1. How big is the rebuild expected to be? • $35 bn in 2012 dollars (15% of annual
national GDP)
2. How long do we expect activity to
continue?
• Peak in 2015/16, long tail for
non-residential activity
3. What is the profile for activity? • Construction has increased, further
increases expected over the coming year
• Construction to remain elevated through
to 2017
• Shift towards higher value residential
construction, increases in non-residential
spending
4. What are some of the key challenges? • Costs of construction
• Availability of labour
• Prices and rents
• Duration of demand
How big is the rebuild expected to be?
• Westpac estimate: $35 bn (2012 dollars,
i.e. excluding cost increases)
• Lower estimate than government
• Cost increases will make some
planned spending uneconomic,
especially in the commercial sphere
• Spending will still occur, but at a
later date (BAU vs. rebuild)
• Around half of spend is residential, half
non-residential (breakdown over page).
Reconstruction profile
Westpac forecasts
How big is the rebuild expected to be?
$bn
(2012 dollars)
Estimated spend to date
(% complete)
Comment
Residential Land
Westpac’s assumption
$5 Assumed $1 to $3 bil
(20 to 60%)
• As of January EQC had completed around 77% of land settlements.
Some of this will relate to cash settlements.
Repairs (properties with damage
less than $100k)
Source: EQC/Fletchers
$2.5 $2.2
+ Privately funded repairs
(95%)
• Around 69,000 properties in the repair program.
• As of 23 January, Fletchers EQR had completed 64,802 repairs.
• Completion targeted in early 2015.
Rebuilds/major repairs
(damage over $100k, funded
privately or through insurance)
Source: ICNZ and Westpac
estimates
$7 to $10 Insurers: $1.1 bil
+ Private: Around $1 bil
(10 to 20%)
• Around 24,000 properties, many are likely to be rebuilt to higher than
pre-quake standard. There will also be a number of new builds.
• As of 1 Jan 15: 2,890 homes fully rebuilt by insurers, work on
another 1,744 homes was underway and 5,700 in pre-construction.
TOTAL RESIDENTIAL $14.5 to $17.5 $5 to 7 bil
Non-residential Public and infrastructure
SCIRT (Horizontal)
Source: CERA/SCIRT
>$2.5 Around $1.6 bil
(65%)
• At the 12 February 2015 around 65% of the total SCRIT program
was complete
• Targeted completion at end of 2016.
Other including councils
and community assets
Source: CERA/CCDU
$7.5 to $8.5 $0.9 to 1.1 bil
(~13%)
• Design and construction has begun on a number of projects.
• Spending to remain elevated over 2015/16.
Commercial
Westpac’s assumption based on
insurance payouts
Around $7.5 to
$10
$1.3 to 2 bil
(around 20%)
• Includes replacement of damaged assets, and significant betterment,
excludes costs acceleration
• $8 bil in commercial claims paid (current dollars)
TOTAL NON-RESIDENTIAL $17.5 to $21 $4 to 5 bil
TOTAL
Around $35
$9 to 12 bil
(around 30%)
How long do we expect activity to continue?
• Total rebuild spending projected to peak over 2015/2016, 80% completion around
2018.
• Residential construction has been increasing strongly
• Peak projected over 2015/16, 80% completion by end of 2017
• Completion around 2020
• SCIRT (horizontal infrastructure) peak spend of around $40 mil month, completion
in 2016 targeted,
• Public/social asset spending ramping up now, planned spending to remain at high
level through 2015 and 2016 before tapering off through to 2020
• Commercial spending ramping up more gradually, projected peak over 2016/2017,
long tail
Profile of activity - Residential
• Work to date has predominantly related
to EQC’s repair program. The vast
majority of spending in this program will
be complete in early-2015.
• Residential construction is shifting
towards full-rebuilds/overcap repairs
(around 24,000 homes), plus some new
builds
• Current consent issuance consistent
with around 7000 new homes a year
(around 21,000 new homes between
2015 and 2017)
• Questions around strength of activity
further ahead, and how many new
builds/medium-density projects will be
required
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0
500
1000
1500
2000
2500
2000 2003 2006 2009 2012 2015
Number$m
Number (RHS)
Value
Source: Statistics NZ, Westpac
Sept
2010
Residential consents
(annual totals)
Profile of activity – Infrastructure and public
• Spending to rise over 2015, remaining elevated though 2016, tail out to ~2020.
• CERA - $1.1 to 1.2 bn (e.g. Metro sports, stadium, convention centre)
• Councils - around $1.1 to 1.2 bn (e.g. art gallery, library)
• Education (Ministry of Education and tertiary providers) - $2.1 to 2.4 bn
• Lyttelton Port - around $1 bn
• Also health, justice, roading
Public sector construction profile (Source: CERA, MBIE)
Profile of activity - Commercial
• Around $800 mil of work was consented
in 2014 (roughly double the pre-quake
level), with a significant increase
expected over the coming year
• Extended period of strong activity
• Betterment of assets occurring
• Questions around timing of spending vs
cost (economics of investment
decisions)
• Rents
• Building size
• Cost increases
• When will spending occur? Is it rebuild
or BAU?
0
500
1000
1500
2000
2500
3000
0
200
400
600
800
1000
1200
1400
2000 2003 2006 2009 2012 2015
Number
$m
Floor area (RHS)
Value
Source: Statistics NZ, Westpac
Sept
2010
Non-residential consents
(annual totals)
Labour market
0
2
4
6
8
10
12
14
0
2
4
6
8
10
12
14
1990 1993 1996 1999 2002 2005 2008 2011 2014 2017
%%
Canterbury
Auckland
NZ
Source: Statistics NZ, Westpac
Sept 2010
• Unemployment in Canterbury is 3.5%,
not far from pre-recession levels
• Net immigration an important source of
labour
• Increases in construction and economic
activity more generally will absorb spare
capacity
• Increasing construction activity in other
regions, especially Auckland, will result
in increased competition for resources
• Between Dec 2011 and Dec 2014 base
rates for construction labour rose 10%
in Canterbury vs. 6% in the rest of NZ
Unemployment by region
Residential building costs
500
750
1000
1250
1500
1750
2000
500
750
1000
1250
1500
1750
2000
2000 2003 2006 2009 2012 2015
$/sq mtr$/sq mtr
Canterbury
Auckland
NZ
Source: Statistics NZ, Westpac
Sept 2010
Ave. build cost in Canterbury:
June 2011: $1307 sq mtr
Dec 2014: $1753 sq mtr (up 34%)
Non-residential building costs
0
500
1000
1500
2000
0
500
1000
1500
2000
2000 2003 2006 2009 2012 2015
$/sq mtr$/sq mtr
Canterbury
Auckland
NZ
Source: Statistics NZ, Westpac
Sept 2010
House prices and rents in Christchurch (s.a.)
500
1000
1500
2000
2500
3000
500
1000
1500
2000
2500
3000
2000 2003 2006 2009 2012 2015
Index
Index
House prices
Rents
Sept
20102012 2013 2014
House prices 11.8 7.1 3.7
Rents 16.4 8.9 1.7
Source: Statistics NZ, MBIE, Westpac
Year to Dec % change
Population growth and housing demand
• Most of the damaged housing stock forecast to be repaired or replaced by end of
2017.
• Rebuild estimates also include new builds.
• Stats NZ projections imply growth in Canterbury’s population of around 53,100
people between 2018 to 2028 (range of estimates: 13,400 to 92,800)
• Medium estimate implies the need for about 23,000 homes over 10 years (around
2,300 per year).
• Comparison
• Current: around 7000 new homes consented over the past year
• Pre-quake: around 2500 to 4500 new homes built per annum.
So, now what?
CLICK HERE
How can you best use this information?
If you’d like a one-on-one meeting with me to
discuss the implications for your business

Weitere ähnliche Inhalte

Ähnlich wie New Zealand Economic Update - Construction March 2015

Housing in Ireland: From Crisis to Crisis
Housing in Ireland: From Crisis to CrisisHousing in Ireland: From Crisis to Crisis
Housing in Ireland: From Crisis to Crisisrobkitchin
 
Municipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingMunicipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingShaun Wilson
 
Funding our future community information session nov 2013
Funding our future community information session nov 2013Funding our future community information session nov 2013
Funding our future community information session nov 2013maitlandyoursay
 
Merseyside Development Update: Mark Kitts, Liverpool City Council
Merseyside Development Update: Mark Kitts, Liverpool City CouncilMerseyside Development Update: Mark Kitts, Liverpool City Council
Merseyside Development Update: Mark Kitts, Liverpool City CouncilPlace North West
 
Ontario construction labour assessment 2012 2020
  Ontario construction labour assessment 2012 2020  Ontario construction labour assessment 2012 2020
Ontario construction labour assessment 2012 2020Shawna Henderson
 
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014Roger Sutton CEO, CERA - speaking at Seismics and the City 2014
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014SmartNet
 
Aspe presentation april 21 2014
Aspe presentation april 21 2014Aspe presentation april 21 2014
Aspe presentation april 21 2014Michael Miller
 
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...The Business Council of Mongolia
 
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...Nat Rojanasathira
 
Stfc presentation feb 2013
Stfc presentation feb 2013Stfc presentation feb 2013
Stfc presentation feb 2013Peter Coles
 
Funding our future community presentation 21012014 fina_lpptx
Funding our future community presentation 21012014 fina_lpptxFunding our future community presentation 21012014 fina_lpptx
Funding our future community presentation 21012014 fina_lpptxmaitlandyoursay
 
The Built Environment PCNZ Presentation
The Built Environment PCNZ PresentationThe Built Environment PCNZ Presentation
The Built Environment PCNZ PresentationAlex Voutratzis
 
Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21CityofGalveston
 
2015 nawic presentation final.ptx
2015 nawic presentation final.ptx2015 nawic presentation final.ptx
2015 nawic presentation final.ptxMichael Miller
 
2015 construction economic forecast
2015 construction economic forecast2015 construction economic forecast
2015 construction economic forecastMichael Miller
 
ONS Local presents: Growth in the low carbon & renewable energy economy, link...
ONS Local presents: Growth in the low carbon & renewable energy economy, link...ONS Local presents: Growth in the low carbon & renewable energy economy, link...
ONS Local presents: Growth in the low carbon & renewable energy economy, link...Office for National Statistics
 
Funding our future community presentation
Funding our future community presentationFunding our future community presentation
Funding our future community presentationmaitlandyoursay
 

Ähnlich wie New Zealand Economic Update - Construction March 2015 (20)

Housing in Ireland: From Crisis to Crisis
Housing in Ireland: From Crisis to CrisisHousing in Ireland: From Crisis to Crisis
Housing in Ireland: From Crisis to Crisis
 
Municipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingMunicipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public Funding
 
Funding our future community information session nov 2013
Funding our future community information session nov 2013Funding our future community information session nov 2013
Funding our future community information session nov 2013
 
Merseyside Development Update: Mark Kitts, Liverpool City Council
Merseyside Development Update: Mark Kitts, Liverpool City CouncilMerseyside Development Update: Mark Kitts, Liverpool City Council
Merseyside Development Update: Mark Kitts, Liverpool City Council
 
Ontario construction labour assessment 2012 2020
  Ontario construction labour assessment 2012 2020  Ontario construction labour assessment 2012 2020
Ontario construction labour assessment 2012 2020
 
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014Roger Sutton CEO, CERA - speaking at Seismics and the City 2014
Roger Sutton CEO, CERA - speaking at Seismics and the City 2014
 
Aspe presentation april 21 2014
Aspe presentation april 21 2014Aspe presentation april 21 2014
Aspe presentation april 21 2014
 
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...
11.16-17.2015, PRESENTATION, Challenges and Opportunities for Growth, Randolp...
 
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...
Overview of the Town of Danville Proposed 2015/16 Operating Budget & Capita...
 
Stfc presentation feb 2013
Stfc presentation feb 2013Stfc presentation feb 2013
Stfc presentation feb 2013
 
Funding our future community presentation 21012014 fina_lpptx
Funding our future community presentation 21012014 fina_lpptxFunding our future community presentation 21012014 fina_lpptx
Funding our future community presentation 21012014 fina_lpptx
 
F3 Village Development
F3 Village DevelopmentF3 Village Development
F3 Village Development
 
2017 Altus Cost Guide (FINAL)
2017 Altus Cost Guide (FINAL)2017 Altus Cost Guide (FINAL)
2017 Altus Cost Guide (FINAL)
 
The Built Environment PCNZ Presentation
The Built Environment PCNZ PresentationThe Built Environment PCNZ Presentation
The Built Environment PCNZ Presentation
 
Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21Wkshp Item 3.C. Discussion of FY 17-21
Wkshp Item 3.C. Discussion of FY 17-21
 
2015 nawic presentation final.ptx
2015 nawic presentation final.ptx2015 nawic presentation final.ptx
2015 nawic presentation final.ptx
 
2015 construction economic forecast
2015 construction economic forecast2015 construction economic forecast
2015 construction economic forecast
 
Triple Bottom Line Calculator
Triple Bottom Line CalculatorTriple Bottom Line Calculator
Triple Bottom Line Calculator
 
ONS Local presents: Growth in the low carbon & renewable energy economy, link...
ONS Local presents: Growth in the low carbon & renewable energy economy, link...ONS Local presents: Growth in the low carbon & renewable energy economy, link...
ONS Local presents: Growth in the low carbon & renewable energy economy, link...
 
Funding our future community presentation
Funding our future community presentationFunding our future community presentation
Funding our future community presentation
 

New Zealand Economic Update - Construction March 2015

  • 2. Canterbury earthquake response – key questions 1. How big is the rebuild expected to be? • $35 bn in 2012 dollars (15% of annual national GDP) 2. How long do we expect activity to continue? • Peak in 2015/16, long tail for non-residential activity 3. What is the profile for activity? • Construction has increased, further increases expected over the coming year • Construction to remain elevated through to 2017 • Shift towards higher value residential construction, increases in non-residential spending 4. What are some of the key challenges? • Costs of construction • Availability of labour • Prices and rents • Duration of demand
  • 3. How big is the rebuild expected to be? • Westpac estimate: $35 bn (2012 dollars, i.e. excluding cost increases) • Lower estimate than government • Cost increases will make some planned spending uneconomic, especially in the commercial sphere • Spending will still occur, but at a later date (BAU vs. rebuild) • Around half of spend is residential, half non-residential (breakdown over page). Reconstruction profile Westpac forecasts
  • 4. How big is the rebuild expected to be? $bn (2012 dollars) Estimated spend to date (% complete) Comment Residential Land Westpac’s assumption $5 Assumed $1 to $3 bil (20 to 60%) • As of January EQC had completed around 77% of land settlements. Some of this will relate to cash settlements. Repairs (properties with damage less than $100k) Source: EQC/Fletchers $2.5 $2.2 + Privately funded repairs (95%) • Around 69,000 properties in the repair program. • As of 23 January, Fletchers EQR had completed 64,802 repairs. • Completion targeted in early 2015. Rebuilds/major repairs (damage over $100k, funded privately or through insurance) Source: ICNZ and Westpac estimates $7 to $10 Insurers: $1.1 bil + Private: Around $1 bil (10 to 20%) • Around 24,000 properties, many are likely to be rebuilt to higher than pre-quake standard. There will also be a number of new builds. • As of 1 Jan 15: 2,890 homes fully rebuilt by insurers, work on another 1,744 homes was underway and 5,700 in pre-construction. TOTAL RESIDENTIAL $14.5 to $17.5 $5 to 7 bil Non-residential Public and infrastructure SCIRT (Horizontal) Source: CERA/SCIRT >$2.5 Around $1.6 bil (65%) • At the 12 February 2015 around 65% of the total SCRIT program was complete • Targeted completion at end of 2016. Other including councils and community assets Source: CERA/CCDU $7.5 to $8.5 $0.9 to 1.1 bil (~13%) • Design and construction has begun on a number of projects. • Spending to remain elevated over 2015/16. Commercial Westpac’s assumption based on insurance payouts Around $7.5 to $10 $1.3 to 2 bil (around 20%) • Includes replacement of damaged assets, and significant betterment, excludes costs acceleration • $8 bil in commercial claims paid (current dollars) TOTAL NON-RESIDENTIAL $17.5 to $21 $4 to 5 bil TOTAL Around $35 $9 to 12 bil (around 30%)
  • 5. How long do we expect activity to continue? • Total rebuild spending projected to peak over 2015/2016, 80% completion around 2018. • Residential construction has been increasing strongly • Peak projected over 2015/16, 80% completion by end of 2017 • Completion around 2020 • SCIRT (horizontal infrastructure) peak spend of around $40 mil month, completion in 2016 targeted, • Public/social asset spending ramping up now, planned spending to remain at high level through 2015 and 2016 before tapering off through to 2020 • Commercial spending ramping up more gradually, projected peak over 2016/2017, long tail
  • 6. Profile of activity - Residential • Work to date has predominantly related to EQC’s repair program. The vast majority of spending in this program will be complete in early-2015. • Residential construction is shifting towards full-rebuilds/overcap repairs (around 24,000 homes), plus some new builds • Current consent issuance consistent with around 7000 new homes a year (around 21,000 new homes between 2015 and 2017) • Questions around strength of activity further ahead, and how many new builds/medium-density projects will be required 0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 0 500 1000 1500 2000 2500 2000 2003 2006 2009 2012 2015 Number$m Number (RHS) Value Source: Statistics NZ, Westpac Sept 2010 Residential consents (annual totals)
  • 7. Profile of activity – Infrastructure and public • Spending to rise over 2015, remaining elevated though 2016, tail out to ~2020. • CERA - $1.1 to 1.2 bn (e.g. Metro sports, stadium, convention centre) • Councils - around $1.1 to 1.2 bn (e.g. art gallery, library) • Education (Ministry of Education and tertiary providers) - $2.1 to 2.4 bn • Lyttelton Port - around $1 bn • Also health, justice, roading Public sector construction profile (Source: CERA, MBIE)
  • 8. Profile of activity - Commercial • Around $800 mil of work was consented in 2014 (roughly double the pre-quake level), with a significant increase expected over the coming year • Extended period of strong activity • Betterment of assets occurring • Questions around timing of spending vs cost (economics of investment decisions) • Rents • Building size • Cost increases • When will spending occur? Is it rebuild or BAU? 0 500 1000 1500 2000 2500 3000 0 200 400 600 800 1000 1200 1400 2000 2003 2006 2009 2012 2015 Number $m Floor area (RHS) Value Source: Statistics NZ, Westpac Sept 2010 Non-residential consents (annual totals)
  • 9. Labour market 0 2 4 6 8 10 12 14 0 2 4 6 8 10 12 14 1990 1993 1996 1999 2002 2005 2008 2011 2014 2017 %% Canterbury Auckland NZ Source: Statistics NZ, Westpac Sept 2010 • Unemployment in Canterbury is 3.5%, not far from pre-recession levels • Net immigration an important source of labour • Increases in construction and economic activity more generally will absorb spare capacity • Increasing construction activity in other regions, especially Auckland, will result in increased competition for resources • Between Dec 2011 and Dec 2014 base rates for construction labour rose 10% in Canterbury vs. 6% in the rest of NZ Unemployment by region
  • 10. Residential building costs 500 750 1000 1250 1500 1750 2000 500 750 1000 1250 1500 1750 2000 2000 2003 2006 2009 2012 2015 $/sq mtr$/sq mtr Canterbury Auckland NZ Source: Statistics NZ, Westpac Sept 2010 Ave. build cost in Canterbury: June 2011: $1307 sq mtr Dec 2014: $1753 sq mtr (up 34%)
  • 11. Non-residential building costs 0 500 1000 1500 2000 0 500 1000 1500 2000 2000 2003 2006 2009 2012 2015 $/sq mtr$/sq mtr Canterbury Auckland NZ Source: Statistics NZ, Westpac Sept 2010
  • 12. House prices and rents in Christchurch (s.a.) 500 1000 1500 2000 2500 3000 500 1000 1500 2000 2500 3000 2000 2003 2006 2009 2012 2015 Index Index House prices Rents Sept 20102012 2013 2014 House prices 11.8 7.1 3.7 Rents 16.4 8.9 1.7 Source: Statistics NZ, MBIE, Westpac Year to Dec % change
  • 13. Population growth and housing demand • Most of the damaged housing stock forecast to be repaired or replaced by end of 2017. • Rebuild estimates also include new builds. • Stats NZ projections imply growth in Canterbury’s population of around 53,100 people between 2018 to 2028 (range of estimates: 13,400 to 92,800) • Medium estimate implies the need for about 23,000 homes over 10 years (around 2,300 per year). • Comparison • Current: around 7000 new homes consented over the past year • Pre-quake: around 2500 to 4500 new homes built per annum.
  • 14. So, now what? CLICK HERE How can you best use this information? If you’d like a one-on-one meeting with me to discuss the implications for your business