1. case study
PROJECT AT A GLANCE
• 43kWp system
• Annual savings of £12,700
• 20 tonnes of CO2 saved per year
M&M goes pole to pole
“Their dedication to working outside of AXA PPP hoursand
general commitment to the task in hand saw the installation run
smoothly and without adversely affecting working conditions for the
client and their employees”
S a v i n g E n e r g y T h r o u g h V i s i o n
2. A solar PV installation at private medical insurance group
AXA PPP’s Tunbridge Wells offices presented green energy
experts M&M with a scaffold pole problem.
web-based system that charts the
electricity generated by the solar PV
panels via a sim cardtechnology.
Laurence Gomersall, from
Douglas Moat consultants,
employed by AXA PPP to manage
theinstallation,said:“Wewerevery
impressed with everyone at M&M.
“Their engineers were as keen as
we were to ensure the installation
was carried out in a professional
manner and were happy to work
closelywithusthroughoutthe
three-week project.
The eco-energy specialists were
tasked with installing a major
43kWp solar photovoltaic system on
the roof of AXA’s tall, town centre
office block, working from an
enclosed central courtyard.
Simon Coomber, Contracts
Manager at M&M, said: “The biggest
challenge we faced was to get
scaffolding into the small interior
courtyard. This had to be brought in
through the main office and then
passed out of windows one pole at
atime.
“With the buildingcontaining
more than 500 members of staff, we
carefully programmed the work
around office hours, erecting the
scaffolding and carrying out thebulk
of the installation duringweekends,
early in the morning and in the
evenings.
“The project was carried out over
three weeks in a bid to restrict
disruption to the office complex and
the staff of AXA PPP.”
The 43kWp system, laid out over
two roof spaces, will provide annual
energy savings of £3,700 and tax-
free Feed-in Tariff and Export
returns of £9,000 – over 25 years
this will provide an income and
savingsofapproximately£472,000.
The solar system also boasts
stronggreencredentials,withCO2
savingsofover20tonnesperyear.
The installation is nowbeing
monitored through Meteronline, a
“Their dedication toworking
outside of AXA PPP hours and
general commitment to the task in
hand saw the installation run
smoothly and withoutadversely
affecting working conditions for the
client and their employees.”