Cameron Engineering & Associates, LLP
Forge River Watershed Management PlanForge River Watershed Management Plan
Project Kick-Off Meeting
Prepared For:
Town of Brookhaven
Department of Planning
Division of Environment
April 5, 2010
Cameron Engineering & Associates, LLP
Project TeamProject Team
Town of Brookhaven
Department of Planning
Division of Environment
The Cameron Engineering Team has over 150 support staff members available to immediately assist the Team.
ROBERT SVADLENKA, AICP, GISC
TASK MANAGERS
Partner-in-Charge
JOSEPH R. AMATO, P.E., .LEED AP
Managing Partner
JOHN D. CAMERON, JR., P.E.
Scientific Advisor Project Manager Assistant Project Manager
JEFFREY LEVINTON, PHD MARK WAGNER, CEP, LEED AP WILLIAM MCMILLAN, JR, P.E., D.WRE
Technical Support Staff
Planning & Outreach Mapping & Data Compilation
DAVID BERG, AICP, LEED AP
Engineering & Infrastructure
NATALIE CLOUD JANICE JIJINA, P.E., AICP, LEED AP
SEQRA Compliance
JEFF KASSNER
US ARMY CORPS OF ENGINEERS
NYS DEPARTMENT OF STATE
NYS DEPT. OF ENV. CONSERVATION
SUFFOLK COUNTY DEPT. OF HEALTH SERVICES
AGENCIES
Cameron Engineering & Associates, LLP
Project BackgroundProject Background
1. Contract with CEA/CH2M executed in December 2009
2. Integration with the US Army Corps of Engineers
(USACE) planning process in early 2010
3. Data collection, literature review and agency coordination
has begun
4. Project team pre-kick-off held in late February 2010
Cameron Engineering & Associates, LLP
Project DeliverablesProject Deliverables
Forge River Watershed Management Plan (Plan):
Comprehensive existing conditions report
Watershed management strategies
Integration with USACE feasibility study
Prepare RFP for TMDL development
Cameron Engineering & Associates, LLP
Forge River: ReviewForge River: Review
Symptoms of the Problem
Water quality decline over many years
Hypoxia, fish kills, noxious odors
Fewer recreation and commercial opportunities
Source of the Problem - Nitrogen
Groundwater flow
On-site wastewater systems and fertilizer use
Forge River sediments
Accumulated duck farm waste and stormwater-borne silt & sediment
Decay of algae and aquatic plants
Atmospheric deposition
Surface Water Flow
Stormwater
Streamflow
Cameron Engineering & Associates, LLP
Forge River: ReviewForge River: Review
Solutions discussed
Remove or isolate sediment nitrogen
Reduce nitrogen input to groundwater
Reduce nitrogen input to stormwater
Improve estuarine circulation
Phased implementation strategy
Cameron Engineering & Associates, LLP
Forge River: ReviewForge River: Review
Study Approach
Engage/involve stakeholders
Watershed Advisory Committee
Town website, public workshops, other
Develop Watershed Management Plan
Characterize watershed and its problems
Understand nitrogen balance
Prioritize and rank sub-watersheds
Screen alternatives with stakeholders
Develop restoration & nitrogen management plan
Evaluate regulatory/programmatic solutions
Short (1-3 yrs), med (3-5 yrs), long term (>5 yrs)
Cameron Engineering & Associates, LLP
1. Project Scoping Meeting (completed)
2. Community Outreach Plan (submitted)
3. Watershed Characterization (in progress)
4. Subwatershed Prioritization
5. Evaluation of Regulatory & Programmatic Environment
6. TMDL (Background Research for Procurement)
7. SEQRA Compliance Outline
8. Management Strategies Screening
9. Community Meetings & Workshops
10. Final Report
Plan Components: 10 TasksPlan Components: 10 Tasks
Cameron Engineering & Associates, LLP
Pre-Kick-Off meeting held late February 2010
Agency coordination defined
Town of Brookhaven (Environment Division & District 6)
US Army Corps of Engineers
NY State Department of Environmental Conservation
Consultants (Cameron Engineering & CH2M HILL)
Note: Suffolk County will be a member of project team
Reports and project data provided to consultants
Formal Scoping Meeting April 5, 2010
Task 1. Project Scoping MeetingTask 1. Project Scoping Meeting
Cameron Engineering & Associates, LLP
Task 2. Community Outreach PlanTask 2. Community Outreach Plan
Elements
Identify all key individuals and organizations
Watershed Advisory Committee input and feedback
WAC meetings
Public workshops
Web pages
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
Task 3. Watershed Characterization
Literature Review
Comprehensive Inventory: Data collection, mapping & analysis
Task 4. Subwatershed Prioritization
Evaluate and rank subwatersheds per weighted criteria
Task 5. Evaluate Regulatory & Programmatic Environment
Define roles & responsibilities of agencies and NGOs
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
DATA
COMPILATION:
Bathymetric
Model
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
DATA
COMPILATION:
Bathymetric
Model
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
DATA
COMPILATION:
Bathymetric
Model
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
DATA
COMPILATION:
Water Quality Data
(Suffolk County DHS)
Cameron Engineering & Associates, LLP
Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis
DATA
COMPILATION:
Test Well Data
(Suffolk County DHS)
Cameron Engineering & Associates, LLP
Task 6. TMDL Procurement RFPTask 6. TMDL Procurement RFP
TMDL RFP development will be “fast-tracked”
Procurement process will be separate
Consultant team will:
Identify data gaps
Recommend model to be used
Estimate costs
Prepare Request for Proposals (RFP)
TMDL funding has been secured
Cameron Engineering & Associates, LLP
Task 7. SEQRA ComplianceTask 7. SEQRA Compliance
Identify potential adverse environmental impacts from
Plan implementation
Prepare Full Environmental Assessment Form Part I
Assist with Full EAF Parts II and III
Cameron Engineering & Associates, LLP
Task 8 -10. Strategies & Plan DevelopmentTask 8 -10. Strategies & Plan Development
Task 8. Identify and Describe Management Strategies
Watershed protection & restoration strategies
Phasing of strategies
Task 9. Public Meeting
Present strategies for public review and comment
Task 10. Final Forge River Watershed Management Plan
Incorporate comments from Public Meeting
Finalize plan with agency input
Cameron Engineering & Associates, LLP
ScheduleSchedule
July 2010: Watershed Characterization Report
Sept 2010: Subwatershed Prioritization, TMDL Update
Dec 2010: Draft Management Strategies, TMDL RFP
Jan 2011: Final Public Meeting
March 2011: Final Watershed Management Plan
Cameron Engineering & Associates, LLP
USACE Planning ProcessUSACE Planning Process
Implemented by two-phase plan (PMP)
Phase I – Existing Conditions / Alternative Screening
Phase II – Alternatives Design and Evaluation
PMP Phase I:
Assess existing conditions within project area to formulate
solutions, and ensure sustainability
• Partner with Town on feasibility study
Cameron Engineering & Associates, LLP
USACE Planning ProcessUSACE Planning Process
PMP Phase II:
Initiated when Town and Corps see sustainable solution
Evaluate and scale alternatives
Conceptual designs and preliminary costs
Preparation of draft environmental document
Public review process
Cameron Engineering & Associates, LLP
Forge River Watershed Management PlanForge River Watershed Management Plan
Discussion

Weitere ähnliche Inhalte

Ähnlich wie Forge River Watershed Plan Project Kick-Off Meeting

Ray.ronald
Ray.ronaldRay.ronald
Ray.ronaldNASAPMC
 
Vikas_Tandon_Modeling Services Portfolio 02 03 11
Vikas_Tandon_Modeling Services Portfolio 02 03 11Vikas_Tandon_Modeling Services Portfolio 02 03 11
Vikas_Tandon_Modeling Services Portfolio 02 03 11vtandon
 
C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_finalpublicinvolvement
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelNC Military Business Center
 
Mark Johnson Resume (March 2017)
Mark Johnson Resume (March 2017) Mark Johnson Resume (March 2017)
Mark Johnson Resume (March 2017) Mark Johnson
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishmentsmckay
 
FDOT D1 Presentation
FDOT D1 PresentationFDOT D1 Presentation
FDOT D1 Presentationdarbonnejd
 
meadowridge rev Nov 9 2011
meadowridge rev Nov 9 2011meadowridge rev Nov 9 2011
meadowridge rev Nov 9 2011Danee McGee
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
 
Ed Baquerizo CV (Updated April 2015)
Ed Baquerizo CV (Updated April 2015)Ed Baquerizo CV (Updated April 2015)
Ed Baquerizo CV (Updated April 2015)Ed A. Baquerizo
 
ESP171-CEQA and Land Use Planning
ESP171-CEQA and Land Use PlanningESP171-CEQA and Land Use Planning
ESP171-CEQA and Land Use PlanningCEQAplanner
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management ProcessesDanee McGee
 
robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016Robert Mcgregor
 
Birch Rd Presentation 05-11-09 Tm
Birch Rd Presentation 05-11-09 TmBirch Rd Presentation 05-11-09 Tm
Birch Rd Presentation 05-11-09 TmGordon Fowler
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshoppublicinvolvement
 

Ähnlich wie Forge River Watershed Plan Project Kick-Off Meeting (20)

Ray.ronald
Ray.ronaldRay.ronald
Ray.ronald
 
EWRES-Group Statement Of Qualifications
EWRES-Group Statement Of QualificationsEWRES-Group Statement Of Qualifications
EWRES-Group Statement Of Qualifications
 
Vikas_Tandon_Modeling Services Portfolio 02 03 11
Vikas_Tandon_Modeling Services Portfolio 02 03 11Vikas_Tandon_Modeling Services Portfolio 02 03 11
Vikas_Tandon_Modeling Services Portfolio 02 03 11
 
C5 council workshop 111128_final
C5 council workshop 111128_finalC5 council workshop 111128_final
C5 council workshop 111128_final
 
Fdot d1
Fdot d1Fdot d1
Fdot d1
 
Code Blue Implementation
Code Blue ImplementationCode Blue Implementation
Code Blue Implementation
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
 
Mark Johnson Resume (March 2017)
Mark Johnson Resume (March 2017) Mark Johnson Resume (March 2017)
Mark Johnson Resume (March 2017)
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments
 
FDOT D1 Presentation
FDOT D1 PresentationFDOT D1 Presentation
FDOT D1 Presentation
 
meadowridge rev Nov 9 2011
meadowridge rev Nov 9 2011meadowridge rev Nov 9 2011
meadowridge rev Nov 9 2011
 
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
 
Ed Baquerizo CV (Updated April 2015)
Ed Baquerizo CV (Updated April 2015)Ed Baquerizo CV (Updated April 2015)
Ed Baquerizo CV (Updated April 2015)
 
ESP171-CEQA and Land Use Planning
ESP171-CEQA and Land Use PlanningESP171-CEQA and Land Use Planning
ESP171-CEQA and Land Use Planning
 
Resume
ResumeResume
Resume
 
Local Government Management Processes
Local Government Management ProcessesLocal Government Management Processes
Local Government Management Processes
 
robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016
 
Mps cemp-final
Mps cemp-finalMps cemp-final
Mps cemp-final
 
Birch Rd Presentation 05-11-09 Tm
Birch Rd Presentation 05-11-09 TmBirch Rd Presentation 05-11-09 Tm
Birch Rd Presentation 05-11-09 Tm
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshop
 

Forge River Watershed Plan Project Kick-Off Meeting

  • 1. Cameron Engineering & Associates, LLP Forge River Watershed Management PlanForge River Watershed Management Plan Project Kick-Off Meeting Prepared For: Town of Brookhaven Department of Planning Division of Environment April 5, 2010
  • 2. Cameron Engineering & Associates, LLP Project TeamProject Team Town of Brookhaven Department of Planning Division of Environment The Cameron Engineering Team has over 150 support staff members available to immediately assist the Team. ROBERT SVADLENKA, AICP, GISC TASK MANAGERS Partner-in-Charge JOSEPH R. AMATO, P.E., .LEED AP Managing Partner JOHN D. CAMERON, JR., P.E. Scientific Advisor Project Manager Assistant Project Manager JEFFREY LEVINTON, PHD MARK WAGNER, CEP, LEED AP WILLIAM MCMILLAN, JR, P.E., D.WRE Technical Support Staff Planning & Outreach Mapping & Data Compilation DAVID BERG, AICP, LEED AP Engineering & Infrastructure NATALIE CLOUD JANICE JIJINA, P.E., AICP, LEED AP SEQRA Compliance JEFF KASSNER US ARMY CORPS OF ENGINEERS NYS DEPARTMENT OF STATE NYS DEPT. OF ENV. CONSERVATION SUFFOLK COUNTY DEPT. OF HEALTH SERVICES AGENCIES
  • 3. Cameron Engineering & Associates, LLP Project BackgroundProject Background 1. Contract with CEA/CH2M executed in December 2009 2. Integration with the US Army Corps of Engineers (USACE) planning process in early 2010 3. Data collection, literature review and agency coordination has begun 4. Project team pre-kick-off held in late February 2010
  • 4. Cameron Engineering & Associates, LLP Project DeliverablesProject Deliverables Forge River Watershed Management Plan (Plan): Comprehensive existing conditions report Watershed management strategies Integration with USACE feasibility study Prepare RFP for TMDL development
  • 5. Cameron Engineering & Associates, LLP Forge River: ReviewForge River: Review Symptoms of the Problem Water quality decline over many years Hypoxia, fish kills, noxious odors Fewer recreation and commercial opportunities Source of the Problem - Nitrogen Groundwater flow On-site wastewater systems and fertilizer use Forge River sediments Accumulated duck farm waste and stormwater-borne silt & sediment Decay of algae and aquatic plants Atmospheric deposition Surface Water Flow Stormwater Streamflow
  • 6. Cameron Engineering & Associates, LLP Forge River: ReviewForge River: Review Solutions discussed Remove or isolate sediment nitrogen Reduce nitrogen input to groundwater Reduce nitrogen input to stormwater Improve estuarine circulation Phased implementation strategy
  • 7. Cameron Engineering & Associates, LLP Forge River: ReviewForge River: Review Study Approach Engage/involve stakeholders Watershed Advisory Committee Town website, public workshops, other Develop Watershed Management Plan Characterize watershed and its problems Understand nitrogen balance Prioritize and rank sub-watersheds Screen alternatives with stakeholders Develop restoration & nitrogen management plan Evaluate regulatory/programmatic solutions Short (1-3 yrs), med (3-5 yrs), long term (>5 yrs)
  • 8. Cameron Engineering & Associates, LLP 1. Project Scoping Meeting (completed) 2. Community Outreach Plan (submitted) 3. Watershed Characterization (in progress) 4. Subwatershed Prioritization 5. Evaluation of Regulatory & Programmatic Environment 6. TMDL (Background Research for Procurement) 7. SEQRA Compliance Outline 8. Management Strategies Screening 9. Community Meetings & Workshops 10. Final Report Plan Components: 10 TasksPlan Components: 10 Tasks
  • 9. Cameron Engineering & Associates, LLP Pre-Kick-Off meeting held late February 2010 Agency coordination defined Town of Brookhaven (Environment Division & District 6) US Army Corps of Engineers NY State Department of Environmental Conservation Consultants (Cameron Engineering & CH2M HILL) Note: Suffolk County will be a member of project team Reports and project data provided to consultants Formal Scoping Meeting April 5, 2010 Task 1. Project Scoping MeetingTask 1. Project Scoping Meeting
  • 10. Cameron Engineering & Associates, LLP Task 2. Community Outreach PlanTask 2. Community Outreach Plan Elements Identify all key individuals and organizations Watershed Advisory Committee input and feedback WAC meetings Public workshops Web pages
  • 11. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis Task 3. Watershed Characterization Literature Review Comprehensive Inventory: Data collection, mapping & analysis Task 4. Subwatershed Prioritization Evaluate and rank subwatersheds per weighted criteria Task 5. Evaluate Regulatory & Programmatic Environment Define roles & responsibilities of agencies and NGOs
  • 12. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis DATA COMPILATION: Bathymetric Model
  • 13. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis DATA COMPILATION: Bathymetric Model
  • 14. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis DATA COMPILATION: Bathymetric Model
  • 15. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis DATA COMPILATION: Water Quality Data (Suffolk County DHS)
  • 16. Cameron Engineering & Associates, LLP Tasks 3, 4, & 5. Watershed AnalysisTasks 3, 4, & 5. Watershed Analysis DATA COMPILATION: Test Well Data (Suffolk County DHS)
  • 17. Cameron Engineering & Associates, LLP Task 6. TMDL Procurement RFPTask 6. TMDL Procurement RFP TMDL RFP development will be “fast-tracked” Procurement process will be separate Consultant team will: Identify data gaps Recommend model to be used Estimate costs Prepare Request for Proposals (RFP) TMDL funding has been secured
  • 18. Cameron Engineering & Associates, LLP Task 7. SEQRA ComplianceTask 7. SEQRA Compliance Identify potential adverse environmental impacts from Plan implementation Prepare Full Environmental Assessment Form Part I Assist with Full EAF Parts II and III
  • 19. Cameron Engineering & Associates, LLP Task 8 -10. Strategies & Plan DevelopmentTask 8 -10. Strategies & Plan Development Task 8. Identify and Describe Management Strategies Watershed protection & restoration strategies Phasing of strategies Task 9. Public Meeting Present strategies for public review and comment Task 10. Final Forge River Watershed Management Plan Incorporate comments from Public Meeting Finalize plan with agency input
  • 20. Cameron Engineering & Associates, LLP ScheduleSchedule July 2010: Watershed Characterization Report Sept 2010: Subwatershed Prioritization, TMDL Update Dec 2010: Draft Management Strategies, TMDL RFP Jan 2011: Final Public Meeting March 2011: Final Watershed Management Plan
  • 21. Cameron Engineering & Associates, LLP USACE Planning ProcessUSACE Planning Process Implemented by two-phase plan (PMP) Phase I – Existing Conditions / Alternative Screening Phase II – Alternatives Design and Evaluation PMP Phase I: Assess existing conditions within project area to formulate solutions, and ensure sustainability • Partner with Town on feasibility study
  • 22. Cameron Engineering & Associates, LLP USACE Planning ProcessUSACE Planning Process PMP Phase II: Initiated when Town and Corps see sustainable solution Evaluate and scale alternatives Conceptual designs and preliminary costs Preparation of draft environmental document Public review process
  • 23. Cameron Engineering & Associates, LLP Forge River Watershed Management PlanForge River Watershed Management Plan Discussion