Flatlick Sewer Rehabilitation Project Phase 1 and 2
Construction Update 4-7-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 4/7/2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
4/5/2010
Current Activities this Week:
Mass Excavation:
Remaining Mass Excavation Activities are nearly
complete. Removal of the Haul Road to Area C has
started.
.
Site Utilities:
Installation of the new electrical ductbank is ongoing. Haul Road – Removal of the temporary haul
Approximately 150 linear feet is installed. road to Area C has commenced.
Boring for the service line for Sanitary Main Line
D is ongoing. The boring and installation of pipe for
the Sanitary Lateral line is complete.
Foundations:
Area 1 Field Level – Column Pads excavation and
Concrete placement is complete to Column Line 24.
Concourse Level Area 2 – Electrical Duct
Soil Nail Wall: bank installation ongoing.
Area 1 – Shotcrete installation is complete.
Area 2 – Shotcrete installation is complete on the 4th lift
up to approximately Column Line 14.
Field Level Area 1 – Isolated Footing
installation completed to 24-Line.
Building the Future
2. Projected Activities occurring next Week:
Mass Excavation:
Removal of the haul road will be nearing completion with
installation of sodding and seeding commencing.
Site Utilities:
Installation of the new electrical ductback will continue.
Field Level Area 1 – Excavation for A-Line
Installation of the Sanitary Manhole at the North end of Footing from Column Line 24 to Column Line
Area 1 will begin. 22.
Installation of the Storm Line on the East Side (France
Family Drive) of the site will begin.
Foundations:
Area 1 Mezzanine Level – Layout and Excavation for
Footings for E-Line will begin.
Area 1 Field Level – A-Line footing will be completed.
Soil Nail Wall: Field Level Area 1 – Concrete placement at
Area 2 – Excavation for remaining remaining lift of Player Field Entrance to the Pitch is
Soil Nail Wall will begin, east of Column Line 14. complete.
Structural Steel Erection:
Delivery and Installation of the Crane will begin
mid-week.
Area 2 – Drilling for Soil Nails on 4th Lift on
South Wall.
Building the Future
3. Additional Photos:
Field Level Area 3 – Mass excavation, south Field Level Area 1 – Backfill at SSB-Line Wall
of Haul Road. is complete.
Concourse Level Area 2 – Capped water Field Level Area 1 – Waterproofing
main. installation on Elevator Pit for Elevators 2/3.
Field Level Area 1 – Hydrotherapy Pit Area 1 – Shot of Area 1 looking North from
Excavation. Concourse Level.
Building the Future