From:    Brandon Valdez                   To: David Ficklin - OnGoal
                                                                            Rory O’Connor – OnGoal
                              Office: Kansas City                           Lee Turner – OnGoal
                              Date:    4/7/2010                             Andy Heitmann – Turner
                                                                            Dave Dudzik - Turner
                              Re:      Wizards Stadium Project
                                       Update – Week of
                                       4/5/2010



 Current Activities this Week:

 Mass Excavation:
 Remaining Mass Excavation Activities are nearly
 complete. Removal of the Haul Road to Area C has
 started.
 .
 Site Utilities:
 Installation of the new electrical ductbank is ongoing.       Haul Road – Removal of the temporary haul
 Approximately 150 linear feet is installed.                   road to Area C has commenced.

 Boring for the service line for Sanitary Main Line
 D is ongoing. The boring and installation of pipe for
 the Sanitary Lateral line is complete.


 Foundations:
 Area 1 Field Level – Column Pads excavation and
 Concrete placement is complete to Column Line 24.

                                                               Concourse Level Area 2 – Electrical Duct
 Soil Nail Wall:                                               bank installation ongoing.
 Area 1 – Shotcrete installation is complete.

 Area 2 – Shotcrete installation is complete on the 4th lift
 up to approximately Column Line 14.




                                                               Field Level Area 1 – Isolated Footing
                                                               installation completed to 24-Line.

Building the Future
Projected Activities occurring next Week:

 Mass Excavation:
 Removal of the haul road will be nearing completion with
 installation of sodding and seeding commencing.

 Site Utilities:
 Installation of the new electrical ductback will continue.
                                                              Field Level Area 1 – Excavation for A-Line
 Installation of the Sanitary Manhole at the North end of     Footing from Column Line 24 to Column Line
 Area 1 will begin.                                           22.

 Installation of the Storm Line on the East Side (France
 Family Drive) of the site will begin.

 Foundations:
 Area 1 Mezzanine Level – Layout and Excavation for
 Footings for E-Line will begin.

 Area 1 Field Level – A-Line footing will be completed.

 Soil Nail Wall:                                              Field Level Area 1 – Concrete placement at
 Area 2 – Excavation for remaining remaining lift of          Player Field Entrance to the Pitch is
 Soil Nail Wall will begin, east of Column Line 14.           complete.

 Structural Steel Erection:
 Delivery and Installation of the Crane will begin
 mid-week.




                                                              Area 2 – Drilling for Soil Nails on 4th Lift on
                                                              South Wall.




Building the Future
Additional Photos:




Field Level Area 3 – Mass excavation, south   Field Level Area 1 – Backfill at SSB-Line Wall
of Haul Road.                                 is complete.




Concourse Level Area 2 – Capped water         Field Level Area 1 – Waterproofing
main.                                         installation on Elevator Pit for Elevators 2/3.




Field Level Area 1 – Hydrotherapy Pit         Area 1 – Shot of Area 1 looking North from
Excavation.                                   Concourse Level.




Building the Future

Weitere ähnliche Inhalte

Was ist angesagt?

Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...Crosstown TO
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main ReplacementFairfax County
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectFairfax County
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectFairfax County
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationFairfax County
 
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Fairfax County
 
Paul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingPaul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingFairfax County
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINTThomas Bryce
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
 

Was ist angesagt? (13)

Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream Restoration
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main Replacement
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Huntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation ProjectHuntsman Lake Dam Rehabilitation Project
Huntsman Lake Dam Rehabilitation Project
 
V Wright Sess2 102109
V Wright Sess2 102109V Wright Sess2 102109
V Wright Sess2 102109
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
 
W Wright Sess8 102709
W Wright Sess8 102709W Wright Sess8 102709
W Wright Sess8 102709
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream Restoration
 
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
Paul Spring Segment 2 at Hollin Hills Stream Restoration Community Meeting Ma...
 
Paul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community MeetingPaul Spring Branch Stream Restoration Project Community Meeting
Paul Spring Branch Stream Restoration Project Community Meeting
 
4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT4P - CAPSTONE FINAL POWERPOINT
4P - CAPSTONE FINAL POWERPOINT
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 

Andere mochten auch (10)

Mass haul
Mass haulMass haul
Mass haul
 
Earth work
Earth workEarth work
Earth work
 
Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
 
Volume
VolumeVolume
Volume
 
Area & Volume
Area & VolumeArea & Volume
Area & Volume
 
Volume and Area Calculation
Volume and Area Calculation Volume and Area Calculation
Volume and Area Calculation
 
Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)Area and Volume Survey Engineering (RZ)
Area and Volume Survey Engineering (RZ)
 
Earthwork notes
Earthwork notesEarthwork notes
Earthwork notes
 
Earthwork
EarthworkEarthwork
Earthwork
 
Tutorial MHD
Tutorial MHDTutorial MHD
Tutorial MHD
 

Ähnlich wie Construction Update 4-7-2010

Memo wizards 05-12-2010
Memo wizards 05-12-2010Memo wizards 05-12-2010
Memo wizards 05-12-2010KyleLRogers
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Kansas City Wizards
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Kansas City Wizards
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Fairfax County
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Crosstown TO
 
Rockaway projectupdateapril2015
Rockaway projectupdateapril2015Rockaway projectupdateapril2015
Rockaway projectupdateapril2015Rose Klein
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Honolulu Civil Beat
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportHonolulu Civil Beat
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Fairfax County
 

Ähnlich wie Construction Update 4-7-2010 (20)

Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 
Memo wizards 05-12-2010
Memo wizards 05-12-2010Memo wizards 05-12-2010
Memo wizards 05-12-2010
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010Weekly Construction Update 06-06-2010
Weekly Construction Update 06-06-2010
 
Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
 
Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Rockaway projectupdateapril2015
Rockaway projectupdateapril2015Rockaway projectupdateapril2015
Rockaway projectupdateapril2015
 
Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report Feb. 16 Waste Management Daily Progress Report
Feb. 16 Waste Management Daily Progress Report
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 

Construction Update 4-7-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 4/7/2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 4/5/2010 Current Activities this Week: Mass Excavation: Remaining Mass Excavation Activities are nearly complete. Removal of the Haul Road to Area C has started. . Site Utilities: Installation of the new electrical ductbank is ongoing. Haul Road – Removal of the temporary haul Approximately 150 linear feet is installed. road to Area C has commenced. Boring for the service line for Sanitary Main Line D is ongoing. The boring and installation of pipe for the Sanitary Lateral line is complete. Foundations: Area 1 Field Level – Column Pads excavation and Concrete placement is complete to Column Line 24. Concourse Level Area 2 – Electrical Duct Soil Nail Wall: bank installation ongoing. Area 1 – Shotcrete installation is complete. Area 2 – Shotcrete installation is complete on the 4th lift up to approximately Column Line 14. Field Level Area 1 – Isolated Footing installation completed to 24-Line. Building the Future
  • 2. Projected Activities occurring next Week: Mass Excavation: Removal of the haul road will be nearing completion with installation of sodding and seeding commencing. Site Utilities: Installation of the new electrical ductback will continue. Field Level Area 1 – Excavation for A-Line Installation of the Sanitary Manhole at the North end of Footing from Column Line 24 to Column Line Area 1 will begin. 22. Installation of the Storm Line on the East Side (France Family Drive) of the site will begin. Foundations: Area 1 Mezzanine Level – Layout and Excavation for Footings for E-Line will begin. Area 1 Field Level – A-Line footing will be completed. Soil Nail Wall: Field Level Area 1 – Concrete placement at Area 2 – Excavation for remaining remaining lift of Player Field Entrance to the Pitch is Soil Nail Wall will begin, east of Column Line 14. complete. Structural Steel Erection: Delivery and Installation of the Crane will begin mid-week. Area 2 – Drilling for Soil Nails on 4th Lift on South Wall. Building the Future
  • 3. Additional Photos: Field Level Area 3 – Mass excavation, south Field Level Area 1 – Backfill at SSB-Line Wall of Haul Road. is complete. Concourse Level Area 2 – Capped water Field Level Area 1 – Waterproofing main. installation on Elevator Pit for Elevators 2/3. Field Level Area 1 – Hydrotherapy Pit Area 1 – Shot of Area 1 looking North from Excavation. Concourse Level. Building the Future