Project Management Gaafar 2007 / 1
Time and Cost Estimation
Dr. Lotfi Gaafar
Source: PMBOK Guide 2000
Project Management Gaafar 2007 / 2
Importance of Time and Cost Estimation
 Estimates are needed to support good decisions.
 Estimates are needed to schedule work.
 Estimates are needed to determine how long the project
should take and its cost.
 Estimates are needed to determine whether the project is
worth doing.
 Estimates are needed to develop cash flow needs.
 Estimates are needed to determine how well the project is
progressing.
 Estimates are needed to develop time-phased budgets and
establish the project baseline
Project Management Gaafar 2007 / 3
Guidelines for Time and Cost Estimation
 Have people familiar with the tasks make the estimate.
 Use several people to make estimates.
 Base estimates on normal conditions, efficient methods, and
a normal level of resources.
 Use consistent time units in estimating task times.
 Treat each task as independent, don’t aggregate.
 Don’t make allowances for contingencies.
 Account for risks separately.
Project Management Gaafar 2007 / 4
Types of Estimates
– Top-down (macro) estimates: analogy, group
consensus, or mathematical relationships
– Bottom-up (micro) estimates: estimates of
elements of the work breakdown structure
Condition Macro Estimates Micro Estimates
Strategic decision making X
Cost and time important X
High uncertainty X
Internal, small project X
Fixed-price contract X
Customer wants details X
Unstable scope X
A brief comparison
Project Management Gaafar 2007 / 5
Estimation Methods
Top-down (macro) estimates: analogy, group consensus,
or mathematical relationships
– Consensus methods
– Ratio methods
– Apportion method
– Function point methods for software and system projects
Bottom-up (micro) estimates: estimates of elements of
the work breakdown structure
– Template method
– Parametric Procedures Applied to Specific Tasks
– Detailed Estimates for the WBS Work Packages
Project Management Gaafar 2007 / 6
Activity Definition
Project Management Gaafar 2007 / 7
Activity Sequencing
Project Management Gaafar 2007 / 8
Activity Duration Estimation
Project Management Gaafar 2007 / 9
Activity Duration Estimation
Project Management Gaafar 2007 / 10
Activity Duration Estimation- Inputs
Project Management Gaafar 2007 / 11
Activity Duration Estimation- Tools
Project Management Gaafar 2007 / 12
Activity Duration Estimation- Tools
Project Management Gaafar 2007 / 13
Schedule Development
Project Management Gaafar 2007 / 14
Schedule Control
Project Management Gaafar 2007 / 15
Activity Cost Estimation
Project Management Gaafar 2007 / 16
Activity Cost Estimation- Inputs
Project Management Gaafar 2007 / 17
Types of Costs
 Direct Costs
– Costs that are clearly chargeable to a specific work
package.
 Labor, materials, equipment, and other
 Direct (Project) Overhead Costs
– Costs incurred that are directly tied to an identifiable
project deliverable or work package.
 Salary, rents, supplies, specialized machinery
 General and Administrative Overhead Costs
– Organization costs indirectly linked to a specific
package that are apportioned to the project
Project Management Gaafar 2007 / 18
Refining Estimates
 Reasons for Adjusting Estimates
– Interaction costs are hidden in estimates.
– Normal conditions do not apply.
– Things go wrong on projects.
– Changes in project scope and plans.
 Adjusting Estimates
– Time and cost estimates of specific activities are
adjusted as the risks, resources, and situation
particulars become more clearly defined.
Project Management Gaafar 2007 / 19
Look at the history of similar projects to get a rough
estimate of costs. Make sure the scope and nature are
similar.
Determine the internal resources you have available to
use - people, equipment, etc., within your organization.
Determine the external resources - those not currently in
your organization - that you will need to get the job done.
Project Budget
Project Management Gaafar 2007 / 20
Sample Cost Estimation Tools
 Activity Based Costing
 Benchmarking
 Target Costing
Project Management Gaafar 2007 / 21
Activity Based Costing
 Description:
– Quantitatively measures the cost and
performance of activities
– It is the quantitative aspect of the Activity based
costing that makes it a more efficient tool that
improves the quality of the final decision.
 When to use it?
– Evaluate relative cost of various activities, and
potential effects of modifications
– Analyze alternative process flows with
comparative economic evaluation
Project Management Gaafar 2007 / 22
Activity Based Costing
 Procedure:
– Analyze Activities
– Gather Costs
– Trace Costs to Activities
– Analyze Costs
Project Management Gaafar 2007 / 23
Activity Based Costing
Example
Total expenses $365.7
Activity Division
A1 $109.8
A11 $54.9
A12 $18.3
A13 $36.6
A2 $182.9
A21 $128
A22 $36.6
A23 $18.3
A3 $73.1
A31 $14.6
A32 $43.9
A33 $14.6
Project Management Gaafar 2007 / 24
Benchmarking
 Description:
– It is the continuous and systematic process of measuring
and assessing products, services, practices against
those of high performing organizations to improve
performance.
– Two types of benchmarking:
- Benchmarking prices
- Benchmarking processes
 When to use it ?
– Benchmarking is used when a company is suffering
losses in a certain area and wants to improve its
performance to overcome these losses.
Project Management Gaafar 2007 / 25
Benchmarking
 Procedure:
– Identify the work process or area to be improved
– Analyze the work process
– Measure your own performance
– Identify benchmarking partners
– Determine data collection method
– Collect data
– Determine performance gap
– Develop action plan
– Implement action plan
– Monitor results
– Recalibrate benchmarks (Repeat process)
Project Management Gaafar 2007 / 26
Target Costing
 Description4
:
– Is the cost that can be incurred while still gaining
profit.
Target Cost = Estimated Selling Price (Target Price) – Desired Profit
 When to use it1
?
– Dominantly with new products and services
– Improve existing products
Project Management Gaafar 2007 / 27
Target Costing
Example (The Montclair Paper Mill)5
Setting the target price: Per Ton
Competitor’s selling price to the merchant $1466
Less: freight paid by the mill (30)
Normal sales returns & allowances (60)
Montclair capital charge (120)
Ship to the DC (11)
DC operating cost (25)
DC capital charge (58)
Target Manufacturing Cost $1162
Project Management Gaafar 2007 / 28
Refining Estimates
 Contingency Funds and Time Buffers
– Are created independently to offset uncertainty.
– Reduce the likelihood of cost and completion time
overruns for a project.
– Can be added to the overall project or to specific
activities or work packages.
– Can be determined from previous similar projects.
 Changing Baseline Schedule and Budget
– Unforeseen events may dictate a reformulation of
the budget and schedule.
Project Management Gaafar 2007 / 29
* This Presentation is Based on information from PMBOK Guide 2000
Project Management
Cost Management*
Dr. Lotfi Gaafar
Project Management Gaafar 2007 / 30
Project Cost Management Processes
 Resource planning: determining what
resources and quantities of them should be
used
 Cost estimating: developing an estimate of
the costs and resources needed to complete
a project
 Cost budgeting: allocating the overall cost
estimate to individual work items to establish
a baseline for measuring performance
 Cost control: controlling changes to the
project budget
Project Management Gaafar 2007 / 31
Resource Planning
Cost Estimating
Project Management Gaafar 2007 / 32
Cost Budgeting
Cost Control
Project Management Gaafar 2007 / 33
Resource Planning
 The nature of the project and the organization will
affect resource planning
 Some questions to consider:
– How difficult will it be to do specific tasks on the project?
– Is there anything unique in this project’s scope
statement that will affect resources?
– What is the organization’s history in doing similar tasks?
– Does the organization have or can they acquire the
people, equipment, and materials that are capable and
available for performing the work?
Project Management Gaafar 2007 / 34
Cost Control
 Project cost control includes
– monitoring cost performance
– ensuring that only appropriate project changes are
included in a revised cost baseline
– informing project stakeholders of authorized changes
to the project that will affect costs
 Earned value management is an important tool
for cost control
Project Management Gaafar 2007 / 35
Using Software to Assist in Cost
Management
 Spreadsheets are a common tool for
resource planning, cost estimating, cost
budgeting, and cost control
 Many companies use more sophisticated and
centralized financial applications software for
cost information
 Project management software has many cost-
related features
1 von 35

Recomendados

Session 9 4th edition PMP von
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMPمحمد عصمت عبد الرازق
1.7K views36 Folien
PMP-Cost Management area von
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management areaZaur Ahmadov, PMP
120 views34 Folien
7 cost managmenet von
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
131 views49 Folien
A brief on project cost management von
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
2.2K views29 Folien
7.2 Estimate Cost von
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate CostDavidMcLachlan1
177 views21 Folien
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd. von
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.iFour Institute - Sustainable Learning
703 views26 Folien

Más contenido relacionado

Similar a 005810603.pdf

cost Management V4 von
cost Management V4cost Management V4
cost Management V4Qussay Karam
52 views100 Folien
Cost Management PMBOK von
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOKWasis Witjaksono
376 views28 Folien
Term paper spm von
Term paper spmTerm paper spm
Term paper spmUDAY SHARMA
133 views16 Folien
07 project cost management von
07 project cost management07 project cost management
07 project cost managementOmer Alsayed PhD,MBA, PMP®
10.1K views50 Folien
Cost managment von
Cost managmentCost managment
Cost managmentHassan Sardar
165 views46 Folien
4. project cost management von
4. project cost management4. project cost management
4. project cost managementMohamed Salah Eldien Mohamed Ali
2.2K views13 Folien

Similar a 005810603.pdf(20)

C03.08-09-ExecutionMonitoringControl.key.pdf von ssuser8babb7
C03.08-09-ExecutionMonitoringControl.key.pdfC03.08-09-ExecutionMonitoringControl.key.pdf
C03.08-09-ExecutionMonitoringControl.key.pdf
ssuser8babb716 views
Chap005 von maisuradi
Chap005Chap005
Chap005
maisuradi1.7K views
con_mangt-lec4-project_costppt.ppt von sheryl90
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl907 views
con_mangt-lec4-project_costppt.ppt von sheryl90
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl906 views
Monitor and control process group part two von Hossam Maghrabi
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
Hossam Maghrabi2.3K views
Pmbok 5th executing process group von Hossam Maghrabi
Pmbok 5th executing process groupPmbok 5th executing process group
Pmbok 5th executing process group
Hossam Maghrabi2.1K views
ادارة تكلفة المشروع von Mohamed Dahi
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
Mohamed Dahi7.1K views
Cost management von shkadry
Cost managementCost management
Cost management
shkadry18.3K views
Topic 12 - Project Cost Management.pdf von HuyNguyen657394
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen65739416 views

Más de KalsoomTahir2

005813616.pdf von
005813616.pdf005813616.pdf
005813616.pdfKalsoomTahir2
1 view17 Folien
009576860.pdf von
009576860.pdf009576860.pdf
009576860.pdfKalsoomTahir2
1 view29 Folien
005813185.pdf von
005813185.pdf005813185.pdf
005813185.pdfKalsoomTahir2
1 view45 Folien
HASH FUNCTIONS.pdf von
HASH FUNCTIONS.pdfHASH FUNCTIONS.pdf
HASH FUNCTIONS.pdfKalsoomTahir2
1 view21 Folien
6. McCall's Model.pptx von
6. McCall's Model.pptx6. McCall's Model.pptx
6. McCall's Model.pptxKalsoomTahir2
4 views13 Folien
ch02-Database System Concepts and Architecture.ppt von
ch02-Database System Concepts and Architecture.pptch02-Database System Concepts and Architecture.ppt
ch02-Database System Concepts and Architecture.pptKalsoomTahir2
12 views53 Folien

Más de KalsoomTahir2(20)

ch02-Database System Concepts and Architecture.ppt von KalsoomTahir2
ch02-Database System Concepts and Architecture.pptch02-Database System Concepts and Architecture.ppt
ch02-Database System Concepts and Architecture.ppt
KalsoomTahir212 views
Lecture 19 - Dynamic Web - JAVA - Part 1.ppt von KalsoomTahir2
Lecture 19 - Dynamic Web - JAVA - Part 1.pptLecture 19 - Dynamic Web - JAVA - Part 1.ppt
Lecture 19 - Dynamic Web - JAVA - Part 1.ppt
KalsoomTahir23 views

Último

American Psychological Association 7th Edition.pptx von
American Psychological Association  7th Edition.pptxAmerican Psychological Association  7th Edition.pptx
American Psychological Association 7th Edition.pptxSamiullahAfridi4
82 views8 Folien
Drama KS5 Breakdown von
Drama KS5 BreakdownDrama KS5 Breakdown
Drama KS5 BreakdownWestHatch
71 views2 Folien
STERILITY TEST.pptx von
STERILITY TEST.pptxSTERILITY TEST.pptx
STERILITY TEST.pptxAnupkumar Sharma
125 views9 Folien
Lecture: Open Innovation von
Lecture: Open InnovationLecture: Open Innovation
Lecture: Open InnovationMichal Hron
96 views56 Folien
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptx von
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptxOEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptx
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptxInge de Waard
167 views29 Folien
Solar System and Galaxies.pptx von
Solar System and Galaxies.pptxSolar System and Galaxies.pptx
Solar System and Galaxies.pptxDrHafizKosar
85 views26 Folien

Último(20)

American Psychological Association 7th Edition.pptx von SamiullahAfridi4
American Psychological Association  7th Edition.pptxAmerican Psychological Association  7th Edition.pptx
American Psychological Association 7th Edition.pptx
SamiullahAfridi482 views
Drama KS5 Breakdown von WestHatch
Drama KS5 BreakdownDrama KS5 Breakdown
Drama KS5 Breakdown
WestHatch71 views
Lecture: Open Innovation von Michal Hron
Lecture: Open InnovationLecture: Open Innovation
Lecture: Open Innovation
Michal Hron96 views
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptx von Inge de Waard
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptxOEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptx
OEB 2023 Co-learning To Speed Up AI Implementation in Courses.pptx
Inge de Waard167 views
Solar System and Galaxies.pptx von DrHafizKosar
Solar System and Galaxies.pptxSolar System and Galaxies.pptx
Solar System and Galaxies.pptx
DrHafizKosar85 views
Are we onboard yet University of Sussex.pptx von Jisc
Are we onboard yet University of Sussex.pptxAre we onboard yet University of Sussex.pptx
Are we onboard yet University of Sussex.pptx
Jisc77 views
Compare the flora and fauna of Kerala and Chhattisgarh ( Charttabulation) von AnshulDewangan3
 Compare the flora and fauna of Kerala and Chhattisgarh ( Charttabulation) Compare the flora and fauna of Kerala and Chhattisgarh ( Charttabulation)
Compare the flora and fauna of Kerala and Chhattisgarh ( Charttabulation)
AnshulDewangan3316 views
Class 10 English notes 23-24.pptx von TARIQ KHAN
Class 10 English notes 23-24.pptxClass 10 English notes 23-24.pptx
Class 10 English notes 23-24.pptx
TARIQ KHAN107 views
Community-led Open Access Publishing webinar.pptx von Jisc
Community-led Open Access Publishing webinar.pptxCommunity-led Open Access Publishing webinar.pptx
Community-led Open Access Publishing webinar.pptx
Jisc74 views
Class 10 English lesson plans von TARIQ KHAN
Class 10 English  lesson plansClass 10 English  lesson plans
Class 10 English lesson plans
TARIQ KHAN257 views
JiscOAWeek_LAIR_slides_October2023.pptx von Jisc
JiscOAWeek_LAIR_slides_October2023.pptxJiscOAWeek_LAIR_slides_October2023.pptx
JiscOAWeek_LAIR_slides_October2023.pptx
Jisc79 views
ISO/IEC 27001 and ISO/IEC 27005: Managing AI Risks Effectively von PECB
ISO/IEC 27001 and ISO/IEC 27005: Managing AI Risks EffectivelyISO/IEC 27001 and ISO/IEC 27005: Managing AI Risks Effectively
ISO/IEC 27001 and ISO/IEC 27005: Managing AI Risks Effectively
PECB 545 views
Structure and Functions of Cell.pdf von Nithya Murugan
Structure and Functions of Cell.pdfStructure and Functions of Cell.pdf
Structure and Functions of Cell.pdf
Nithya Murugan368 views
Narration lesson plan.docx von TARIQ KHAN
Narration lesson plan.docxNarration lesson plan.docx
Narration lesson plan.docx
TARIQ KHAN104 views
Ch. 7 Political Participation and Elections.pptx von Rommel Regala
Ch. 7 Political Participation and Elections.pptxCh. 7 Political Participation and Elections.pptx
Ch. 7 Political Participation and Elections.pptx
Rommel Regala72 views

005810603.pdf

  • 1. Project Management Gaafar 2007 / 1 Time and Cost Estimation Dr. Lotfi Gaafar Source: PMBOK Guide 2000
  • 2. Project Management Gaafar 2007 / 2 Importance of Time and Cost Estimation  Estimates are needed to support good decisions.  Estimates are needed to schedule work.  Estimates are needed to determine how long the project should take and its cost.  Estimates are needed to determine whether the project is worth doing.  Estimates are needed to develop cash flow needs.  Estimates are needed to determine how well the project is progressing.  Estimates are needed to develop time-phased budgets and establish the project baseline
  • 3. Project Management Gaafar 2007 / 3 Guidelines for Time and Cost Estimation  Have people familiar with the tasks make the estimate.  Use several people to make estimates.  Base estimates on normal conditions, efficient methods, and a normal level of resources.  Use consistent time units in estimating task times.  Treat each task as independent, don’t aggregate.  Don’t make allowances for contingencies.  Account for risks separately.
  • 4. Project Management Gaafar 2007 / 4 Types of Estimates – Top-down (macro) estimates: analogy, group consensus, or mathematical relationships – Bottom-up (micro) estimates: estimates of elements of the work breakdown structure Condition Macro Estimates Micro Estimates Strategic decision making X Cost and time important X High uncertainty X Internal, small project X Fixed-price contract X Customer wants details X Unstable scope X A brief comparison
  • 5. Project Management Gaafar 2007 / 5 Estimation Methods Top-down (macro) estimates: analogy, group consensus, or mathematical relationships – Consensus methods – Ratio methods – Apportion method – Function point methods for software and system projects Bottom-up (micro) estimates: estimates of elements of the work breakdown structure – Template method – Parametric Procedures Applied to Specific Tasks – Detailed Estimates for the WBS Work Packages
  • 6. Project Management Gaafar 2007 / 6 Activity Definition
  • 7. Project Management Gaafar 2007 / 7 Activity Sequencing
  • 8. Project Management Gaafar 2007 / 8 Activity Duration Estimation
  • 9. Project Management Gaafar 2007 / 9 Activity Duration Estimation
  • 10. Project Management Gaafar 2007 / 10 Activity Duration Estimation- Inputs
  • 11. Project Management Gaafar 2007 / 11 Activity Duration Estimation- Tools
  • 12. Project Management Gaafar 2007 / 12 Activity Duration Estimation- Tools
  • 13. Project Management Gaafar 2007 / 13 Schedule Development
  • 14. Project Management Gaafar 2007 / 14 Schedule Control
  • 15. Project Management Gaafar 2007 / 15 Activity Cost Estimation
  • 16. Project Management Gaafar 2007 / 16 Activity Cost Estimation- Inputs
  • 17. Project Management Gaafar 2007 / 17 Types of Costs  Direct Costs – Costs that are clearly chargeable to a specific work package.  Labor, materials, equipment, and other  Direct (Project) Overhead Costs – Costs incurred that are directly tied to an identifiable project deliverable or work package.  Salary, rents, supplies, specialized machinery  General and Administrative Overhead Costs – Organization costs indirectly linked to a specific package that are apportioned to the project
  • 18. Project Management Gaafar 2007 / 18 Refining Estimates  Reasons for Adjusting Estimates – Interaction costs are hidden in estimates. – Normal conditions do not apply. – Things go wrong on projects. – Changes in project scope and plans.  Adjusting Estimates – Time and cost estimates of specific activities are adjusted as the risks, resources, and situation particulars become more clearly defined.
  • 19. Project Management Gaafar 2007 / 19 Look at the history of similar projects to get a rough estimate of costs. Make sure the scope and nature are similar. Determine the internal resources you have available to use - people, equipment, etc., within your organization. Determine the external resources - those not currently in your organization - that you will need to get the job done. Project Budget
  • 20. Project Management Gaafar 2007 / 20 Sample Cost Estimation Tools  Activity Based Costing  Benchmarking  Target Costing
  • 21. Project Management Gaafar 2007 / 21 Activity Based Costing  Description: – Quantitatively measures the cost and performance of activities – It is the quantitative aspect of the Activity based costing that makes it a more efficient tool that improves the quality of the final decision.  When to use it? – Evaluate relative cost of various activities, and potential effects of modifications – Analyze alternative process flows with comparative economic evaluation
  • 22. Project Management Gaafar 2007 / 22 Activity Based Costing  Procedure: – Analyze Activities – Gather Costs – Trace Costs to Activities – Analyze Costs
  • 23. Project Management Gaafar 2007 / 23 Activity Based Costing Example Total expenses $365.7 Activity Division A1 $109.8 A11 $54.9 A12 $18.3 A13 $36.6 A2 $182.9 A21 $128 A22 $36.6 A23 $18.3 A3 $73.1 A31 $14.6 A32 $43.9 A33 $14.6
  • 24. Project Management Gaafar 2007 / 24 Benchmarking  Description: – It is the continuous and systematic process of measuring and assessing products, services, practices against those of high performing organizations to improve performance. – Two types of benchmarking: - Benchmarking prices - Benchmarking processes  When to use it ? – Benchmarking is used when a company is suffering losses in a certain area and wants to improve its performance to overcome these losses.
  • 25. Project Management Gaafar 2007 / 25 Benchmarking  Procedure: – Identify the work process or area to be improved – Analyze the work process – Measure your own performance – Identify benchmarking partners – Determine data collection method – Collect data – Determine performance gap – Develop action plan – Implement action plan – Monitor results – Recalibrate benchmarks (Repeat process)
  • 26. Project Management Gaafar 2007 / 26 Target Costing  Description4 : – Is the cost that can be incurred while still gaining profit. Target Cost = Estimated Selling Price (Target Price) – Desired Profit  When to use it1 ? – Dominantly with new products and services – Improve existing products
  • 27. Project Management Gaafar 2007 / 27 Target Costing Example (The Montclair Paper Mill)5 Setting the target price: Per Ton Competitor’s selling price to the merchant $1466 Less: freight paid by the mill (30) Normal sales returns & allowances (60) Montclair capital charge (120) Ship to the DC (11) DC operating cost (25) DC capital charge (58) Target Manufacturing Cost $1162
  • 28. Project Management Gaafar 2007 / 28 Refining Estimates  Contingency Funds and Time Buffers – Are created independently to offset uncertainty. – Reduce the likelihood of cost and completion time overruns for a project. – Can be added to the overall project or to specific activities or work packages. – Can be determined from previous similar projects.  Changing Baseline Schedule and Budget – Unforeseen events may dictate a reformulation of the budget and schedule.
  • 29. Project Management Gaafar 2007 / 29 * This Presentation is Based on information from PMBOK Guide 2000 Project Management Cost Management* Dr. Lotfi Gaafar
  • 30. Project Management Gaafar 2007 / 30 Project Cost Management Processes  Resource planning: determining what resources and quantities of them should be used  Cost estimating: developing an estimate of the costs and resources needed to complete a project  Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance  Cost control: controlling changes to the project budget
  • 31. Project Management Gaafar 2007 / 31 Resource Planning Cost Estimating
  • 32. Project Management Gaafar 2007 / 32 Cost Budgeting Cost Control
  • 33. Project Management Gaafar 2007 / 33 Resource Planning  The nature of the project and the organization will affect resource planning  Some questions to consider: – How difficult will it be to do specific tasks on the project? – Is there anything unique in this project’s scope statement that will affect resources? – What is the organization’s history in doing similar tasks? – Does the organization have or can they acquire the people, equipment, and materials that are capable and available for performing the work?
  • 34. Project Management Gaafar 2007 / 34 Cost Control  Project cost control includes – monitoring cost performance – ensuring that only appropriate project changes are included in a revised cost baseline – informing project stakeholders of authorized changes to the project that will affect costs  Earned value management is an important tool for cost control
  • 35. Project Management Gaafar 2007 / 35 Using Software to Assist in Cost Management  Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control  Many companies use more sophisticated and centralized financial applications software for cost information  Project management software has many cost- related features