SlideShare a Scribd company logo
1 of 11
Download to read offline
Noble Fire Production Capacity
Report
Prepared by
Julian Kalac, P.Eng
10/9/2012
Page 2 of 11 Noble Fire Capacity Report 9 October 2012
To: Eric St-Amant, Kevin Paterson
C.C.: Kirk Daize
From: Julian Kalac, P.Eng License #90505462
Date: October 6, 2012
Re: Noble Fire Production Capacity
OBJECTIVE:
The objective of this report is to provide an initial assessment of the current Production
Capacity at Noble Fire, identify process bottlenecks, and develop a proposed plan to
increase Production Capacity.
This report contains detailed process descriptions, machine limitations, pictures, current
capacity and detailed recommendations for increased capacity.
REFRENCED STANDARDS:
 Ontario Building Code
 National Fire Protection Association (NFPA)
 National Standard for Sprinkler System Design (FC 403 )
The preliminary capacity assessment is based on observations from a 1 ½ day visit on
October 4th
& 5th
.
For clarification purposes, NO COSTS were provided nor used in this report on: Material &
Labour Costs/unit, Production/Sales Gross Margins, Machine Parts & Downtime costs
Since no Production KPI was available, and current capacity is not known, the capacity
assessment is based on WELDED “OUTLETS/Hr” & % Machine Utilization.
Overview:
Noble Fire, known as Don Park Fire, is a division of Noble that produces Fire Sprinkler
Systems for both residential and commercial industries as per the NFPA and Ontario
Building Code standards
Noble Fire has a VERY UNIQUE production process. Initially looking from the outside the
operation may appear to be simple and straight forward, but the actual production
complexity is hidden deep inside the machines & processes.
The plant has approximately 35,000 ft², which includes production, offices, warehouse
and pipe racks/storage (see Layout in Appendix).
Page 3 of 11 Noble Fire Capacity Report 9 October 2012
There are 8 skilled fabricator/welders & 1 foreman. There are no dedicated Maintenance
staff on site. The fabricators do their own maintenance and repairs.
The foreman Kirk is very experienced, knowledgeable and mechanically skilled. He “wears
many different hats”, i.e. reviews customer drawings, provides quotes on labour costs,
coordinates workloads, deals with customer calls/complaints/inquiries, orders material.
One thing that would make his job a little easier is for him to have a computer with a
hard-drive, printer and photocopier on the production floor instead in the front office.
Production Processes
There are 4 processes involved in completing a finished pipe:
1. Pipe cutting
2. Plasma Profile Burning
3. Circular welding (outlet onto pipe)
4. Pipe Threading
THERE ARE 3 BURN/WELD MACHINES:
 WB#1--Whirly-Bird style circular welder (—WITHOUT CUTTER)
 WB#2 --Whirly-Bird style circular welders (–WITH A DEDICATED CUTTER)
 Nogeo machine (1 1/4” to 3”)
Machine Design issues:
All 3 Machines are outdated in design and require a great deal of maintenance and
operator involvement to make them run. They are very much operator dependent, and
not everyone can operate each machine. For example the Nogeo Machine can only be
operated by either Sergey or Lead Hand Anthony. Each Machine is unique in it’s
limitations and capacity.
WB#1
WB#2
NOGEO M/C
Page 4 of 11 Noble Fire Capacity Report 9 October 2012
The major Machine and Process issues are:
1. Whirlybird M/C #1 (6 years old) has a Production Capacity of 14-16 outlets/hr
and is only 60% Utilized in Run Time and 40% with various downtime issues
a) Does NOT HAVE a CUTTER AT THE END, therefore requires Non-Value
Add activity of loading pipes onto manual cart, pushing the cart to the
Threader/Cutter machine ( up to 130ft distance) and back and unload pipes.
Estimated= 1-2 Hrs. downtime/shift.
b) By adding 2 additional pipe cutters to the plant, would improve machine
utilization by min. 15%
c) Material handling (loading/unloading) of pipes is done manually with carts
and is very labour intensive and time consuming.
d) Welding wire feed issues, causing misfeeds/jams and machine downtime.
(1hr/shift)
e) Both WHIRLY-BIRD machine(s) DO NOT have programming capability
therefore require the operator to manually to measure each pipe length,
outlet location/spacing, which are done with a tape measurer while the
machine is down (2 hr/day). Note: The tolerances on sprinkler head outlets
are designed within 1/32” in total variation per system (500+ pipe lines)
WB#1
WB#1 NO CUTTER
WB#2
Page 5 of 11 Noble Fire Capacity Report 9 October 2012
2. Whirlybird M/C #2 has a Machine Capacity of 16 Outlet/hr
a. Has the same issues as WB# 1 listed above, except for the wire feed issue
b. On top of that WB# 2 has machine alignment issues between the Burning & Welding
cycles and therefore has to work backwards and use welding as the main reference
and work backwards to set the burning position.
c. This is currently being compensated with the skill and experience of the main
operator, Dimitri, who is a very skilled MIG/TIG/GAS welder originally from Romania,
where the experience level is much higher than here
3. Nogeo Automated Machine has a Machine Capacity of 16 outlets/hr.
a) I personally timed the machine cycle time without interruption to be 3.49 min
b) The Machine Cycle time is directly related to the lack of process capability and
reliability. This machine needs major maintenance & repair to keep running
c) This machine is run only by 1 operator, (Sergey) who is the most experienced
welder. He has modified, repaired & kept this machine running with no spare parts.
d) Sergey has to manually center the welding adapter every single cycle prior to
the weld cycle. This is due to the lack of machine capability to adjust for different
outlets sizes and causes over 30% of the machine downtime.
e) This could easily be rectified by using a STANDARDIZED AISI 1020 UN-ILET
(see picture below)
f) Frequent Machine breakdowns are a major cause of the machine
downtime.
g) There are no spare parts and the manufacturer does not carry any of the parts
from this outdated model. This causes over 50% of major downtime and lost of
productivity (see pictures below and in appendix).
WB# 1 FRONT VIEW
Pipe Handling cartPlasma Burner
Page 6 of 11 Noble Fire Capacity Report 9 October 2012
THREADER PROBLEMS:
1. Oster threader (>30 years) only threads up to 2” pipes
2. Dies keep breaking causing downtime (40% downtime) YTD replaced over 10 sets
3. The material used to make the dies are only case hardened and not made out of
HSS—High Speed Steel (M-2) which is the proper tool steel for this application
4. Set-Up time on 1” – 2” Threader takes min 15min/set-up. (3-4 set-ups/day=
1hr M/C downtime)
Manually centering the weld
adapter prior to welding
AISI 1020 STD OUTLET
One of the repairs Sergey was showing me
he used rope to hold the weld unit together!
Problems due to lack of standardized outlets SOLUTION
Page 7 of 11 Noble Fire Capacity Report 9 October 2012
CURRENT PRODUCTION CAPABILITY AND SUGGESTED IMPROVEMENTS
Current Fire Capacity on the 3 burn/weld machines
M/C Pcs/Hr Daily Capacity Weekly Capacity
Monthly
capacity
Annual Capacity
WB #1 15 112.5 562.5 2250 27000
WB #2 16 120 600 2400 28800
NOGEO M/C 17 128 638 2550 30600
TOTAL CAPACITY 48 360 1800 7200 86400
AFTER IMPROVMENETS
1-ADDING 2 CUTTERS + 2 THREADER + IMPROVING WB #1 WIRE FEED (estimated cost < $15,000)
2-Replace all outlets with 1 STANDARD AISI 1020 UNI-LET 3/4" OUTLET
M/C Pcs/Hr Daily Capacity Weekly Capacity
Monthly
capacity
Annual Capacity
WB #1 20 150 750 3000 36000
WB #2 21 157.5 788 3150 37800
NOGEO M/C 23 172.5 863 3450 41400
TOTAL CAPACITY 64 480 2400 9600 115200
Productivity Improvement= 25.0%
SUGGESTED IMMEDIATE IMPROVEMENTS:
1. Add 2 PIPE CUTTERS (2”), for WB#1 and Main area. Estimated Cost=$ 2,000
2. Add 1 ROTHENBERGER 4” THREADER with automatic die heads (Max. $10,000)
3. IMPLEMENT AISI 1020 STANDARD UNI-LET outlet which will standardize all
welded outlets and significantly reduce machine downtime, especially on the
complex NOGEO.
4. Repair WB#1 WIRE FEED ISSUE. I have provided a wire feed troubleshooting
guide/checklist to Fernando, WB#1 operator.
5. Implement a PREVENTATIVE MAINTENANCE PLAN for the NOGEO machine
with a recommended SPARE PARTS list from the manufacturer in order to reduce
downtime
TOTAL NEW EQUIPMENT COST = $15,000
Note: These are only estimated improvements which need to be validated
Page 8 of 11 Noble Fire Capacity Report 9 October 2012
FURTHER OPTIONS
DEPENDING ON THE CONFIDENCE LEVEL OF FUTURE SALES
1. HIRE 2ND
SHIFT
Because of the equipment issues & limitations, I do not believe adding a 2nd
shift
would be a feasible option due to the frequent machine breakdowns, design
limitations, lack of process/machine capability & unique operator dependency.
Hiring & training new people on equipment which are NOT capable, have many
limitations, breakdowns and unreliable will only cause more issues and lost of
productivity.
These machines are not capable of mass production, and would need to retrofitted
to make them suitable for mass production.
2. PURCHASE NEW MACHINE(S):
This option would only be feasible if there were sufficient sales for the next 5-6
years in order to amortize the capital costs. The question then becomes the
confidence level in the projected future sales.
I strongly suggest to look into improving the current Whirly-Bird machine issues
listed above before purchasing another new machine with the same issues.
3. REPLACE NOGEO WELD UNIT WITH CYPRESS WHIRLYBIRD CW-5
If the Production Capacity after the IMMEDIATE IMPROVEMENTS listed above is still
not sufficient, then this would be the most feasible and most effective option.
Reason: in order to maximize the utilization of the NOGEO machine
The CW-5 model comes with programming capability to allow for individual and
combined operations.
By investing in this replacement weld unit, the production capacity can increase by
over 800% and allow capability for mass production.
The cost of 1 of these units needs to be verified, but I have found a used on for
$29,000 plus $3000 for carriage and set-up adapter. See the specifications and
pictures in the APPENDIX.
TOTAL COST USED UNIT = $33,000
Page 9 of 11 Noble Fire Capacity Report 9 October 2012
CYPRESS CW-5 CIRCULAR WELDERS
CAPACITY ANALYSIS COMPARISON (CW-5 vs NOGEO)
CURRENT NOGEO
M/C
Individual Operation Combined Operations Combined Operations
Cycle Time (Seconds) Cycle Time (Seconds) Cycle Time (Seconds)
Burn Cut 10 5 30
Weld Time 20 10 150
Loading/Unloading 20 10 10
Chuck Travel Time 10 5 39
Total M/C Cycle Time (Seconds) 60 30 229
Pipes/Min 1 2 0.26
Pipes/Hr 60 120 15.7
Total Available Time/Shift 8.5 8.5 8.5
Breaks & Lunches 1 1 1
RUN TIME 7.5 7.5 7.5
Max Pipes/Shift (8.5 Hrs) 510 1020 117.9
Maintenance Time/Downtime 1.0 1.0 2.0
RUN TIME 7.5 7.5 6.5
EXPECTED PIPES/SHIFT 450 900 102.2
Note:
The approximate time for a cut is 6-10 seconds, depending upon diameter and thickness.
The approximate time for a weld is 15-20 seconds
CYPRESS CIRCULAR WELDER CW-5
New Machine Utilization requires relieving for break and lunches
Page 10 of 11 Noble Fire Capacity Report 9 October 2012
Page 11 of 11 Noble Fire Capacity Report 9 October 2012
CONCLUSION
Based on the overall situation and current production capacity I recommend the
immediate suggestions be implemented right away.
An estimated 24% increased productivity is well worth the $15,000 cost.
I also strongly suggest a Preventative Maintenance Plan for the NOGEO
machine with SPARE PARTS ON HAND to reduce machine downtime.
I also suggest the manufacturer, NOGEO, come in and do an overall assessment of
the machine capability and to evaluate the proposed option of replacing the welding
unit with a more sophisticated as listed above or similar.
I have reviewed this report with Kirk, the plant foreman and he is in agreement
with the recommendations and suggested improvements.
If needed I can be of assistance to discuss the proposal with NOGEO
I also suggest Production to begin tracking & reporting machine downtime and
causes in order to accurately determine the machine efficiency.
I would like to thank Kirk and his group for their assistance during the visit.
Sincerely,
Julian Kalac, P.Eng.

More Related Content

What's hot

Advanced Lean Strategies for Office & Service Environments
Advanced Lean Strategies for Office & Service Environments Advanced Lean Strategies for Office & Service Environments
Advanced Lean Strategies for Office & Service Environments TKMG, Inc.
 
Process improvement techniques
Process improvement techniquesProcess improvement techniques
Process improvement techniquesHakeem-Ur- Rehman
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)Md.Muzahid Khan
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016W3 Group Canada Inc.
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing ToolsJagriti Prasad
 
Lean six sigma green belt project improvement
Lean six sigma  green belt project improvementLean six sigma  green belt project improvement
Lean six sigma green belt project improvementAnkurSharma820
 

What's hot (20)

My machine camp
My machine campMy machine camp
My machine camp
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
OEE
OEEOEE
OEE
 
Advanced Lean Strategies for Office & Service Environments
Advanced Lean Strategies for Office & Service Environments Advanced Lean Strategies for Office & Service Environments
Advanced Lean Strategies for Office & Service Environments
 
Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
Kanban system presentation
Kanban system presentationKanban system presentation
Kanban system presentation
 
Process improvement techniques
Process improvement techniquesProcess improvement techniques
Process improvement techniques
 
TPM Loss Analysis
TPM  Loss AnalysisTPM  Loss Analysis
TPM Loss Analysis
 
Lean Manufacturing Training
Lean Manufacturing TrainingLean Manufacturing Training
Lean Manufacturing Training
 
Kaizen
Kaizen Kaizen
Kaizen
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
 
Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016Lean Materials Management - Parts presentation at the line - November 2016
Lean Materials Management - Parts presentation at the line - November 2016
 
TPM Implementation Strategy
TPM Implementation StrategyTPM Implementation Strategy
TPM Implementation Strategy
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 
Lean Manufacturing - An Overview
Lean Manufacturing - An OverviewLean Manufacturing - An Overview
Lean Manufacturing - An Overview
 
Lean principles
Lean principlesLean principles
Lean principles
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing Tools
 
Lean six sigma green belt project improvement
Lean six sigma  green belt project improvementLean six sigma  green belt project improvement
Lean six sigma green belt project improvement
 
Line Crew Optimisation Methodology
Line Crew Optimisation MethodologyLine Crew Optimisation Methodology
Line Crew Optimisation Methodology
 

Similar to Lean Production Capacity Report

Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternIRJET Journal
 
Project study report c&amp;b
Project  study report c&amp;bProject  study report c&amp;b
Project study report c&amp;bParam Saxena
 
Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3IAEME Publication
 
EE driving the cost out of your design
EE driving the cost out of your designEE driving the cost out of your design
EE driving the cost out of your designbmacforever
 
IRJET- Thermal Load Effect on Exhaust Valve by using Conventional and Mix...
IRJET-  	  Thermal Load Effect on Exhaust Valve by using Conventional and Mix...IRJET-  	  Thermal Load Effect on Exhaust Valve by using Conventional and Mix...
IRJET- Thermal Load Effect on Exhaust Valve by using Conventional and Mix...IRJET Journal
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...IRJET Journal
 
Vice Cum Bender Machine
Vice Cum Bender MachineVice Cum Bender Machine
Vice Cum Bender MachineIRJET Journal
 
Design and Fabrication of Inbuilt Hydraulic Jack for Four Wheelers
Design and Fabrication of Inbuilt Hydraulic Jack for Four WheelersDesign and Fabrication of Inbuilt Hydraulic Jack for Four Wheelers
Design and Fabrication of Inbuilt Hydraulic Jack for Four WheelersIRJET Journal
 
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET Journal
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technologyShubham Arora
 
Study of Manufacturing of Multi-Saddle Clamp
Study of Manufacturing of Multi-Saddle ClampStudy of Manufacturing of Multi-Saddle Clamp
Study of Manufacturing of Multi-Saddle ClampIRJET Journal
 
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...IRJET Journal
 
Nidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec Corporation
 
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEDESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEIRJET Journal
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationAmeya Margaj
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET Journal
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 

Similar to Lean Production Capacity Report (20)

Dlw report
Dlw  report Dlw  report
Dlw report
 
Improvement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and PatternImprovement in the Design of the Fixture and Pattern
Improvement in the Design of the Fixture and Pattern
 
Project study report c&amp;b
Project  study report c&amp;bProject  study report c&amp;b
Project study report c&amp;b
 
Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3Design out maintenance on frequent failure of motor ball bearings-2-3
Design out maintenance on frequent failure of motor ball bearings-2-3
 
EE driving the cost out of your design
EE driving the cost out of your designEE driving the cost out of your design
EE driving the cost out of your design
 
IRJET- Thermal Load Effect on Exhaust Valve by using Conventional and Mix...
IRJET-  	  Thermal Load Effect on Exhaust Valve by using Conventional and Mix...IRJET-  	  Thermal Load Effect on Exhaust Valve by using Conventional and Mix...
IRJET- Thermal Load Effect on Exhaust Valve by using Conventional and Mix...
 
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
Various approaches to Eliminate MIG Welding and Defects occurring in DT cap F...
 
Vice Cum Bender Machine
Vice Cum Bender MachineVice Cum Bender Machine
Vice Cum Bender Machine
 
Design and Fabrication of Inbuilt Hydraulic Jack for Four Wheelers
Design and Fabrication of Inbuilt Hydraulic Jack for Four WheelersDesign and Fabrication of Inbuilt Hydraulic Jack for Four Wheelers
Design and Fabrication of Inbuilt Hydraulic Jack for Four Wheelers
 
Bhel report block 4
Bhel report block 4Bhel report block 4
Bhel report block 4
 
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...IRJET-  	  Productivity Improvement of Assembly Workstation in a Small Scale ...
IRJET- Productivity Improvement of Assembly Workstation in a Small Scale ...
 
Construction using Precast technology
Construction using Precast technologyConstruction using Precast technology
Construction using Precast technology
 
Study of Manufacturing of Multi-Saddle Clamp
Study of Manufacturing of Multi-Saddle ClampStudy of Manufacturing of Multi-Saddle Clamp
Study of Manufacturing of Multi-Saddle Clamp
 
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...
EXPERIMENTAL INVESTIGATION AND PERFORMANCE AND EMISSION ANALYSIS OF DIESEL EN...
 
Nidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applicationsNidec asi capability overview for oil&gas applications
Nidec asi capability overview for oil&gas applications
 
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIEDESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
DESIGN AND ANALYSIS OF MULTIFACE HYDRAULIC BENDING MACHINE DIE
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
IRJET- Deburring Methods for Elimination of Chips in the Internal Tubes of Fr...
 
2 power one
2 power one2 power one
2 power one
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 

More from Julian Kalac P.Eng

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.EngJulian Kalac P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowJulian Kalac P.Eng
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Julian Kalac P.Eng
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment Julian Kalac P.Eng
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS Julian Kalac P.Eng
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVERJulian Kalac P.Eng
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureJulian Kalac P.Eng
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutJulian Kalac P.Eng
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverJulian Kalac P.Eng
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHJulian Kalac P.Eng
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over timeJulian Kalac P.Eng
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACJulian Kalac P.Eng
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian KalacJulian Kalac P.Eng
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACJulian Kalac P.Eng
 

More from Julian Kalac P.Eng (20)

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment
 
Lean logistics
Lean logisticsLean logistics
Lean logistics
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedure
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag Out
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeover
 
MWV CONTROL VS SPEC
MWV CONTROL VS SPECMWV CONTROL VS SPEC
MWV CONTROL VS SPEC
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
 
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE
 
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over time
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian Kalac
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALAC
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

Lean Production Capacity Report

  • 1. Noble Fire Production Capacity Report Prepared by Julian Kalac, P.Eng 10/9/2012
  • 2. Page 2 of 11 Noble Fire Capacity Report 9 October 2012 To: Eric St-Amant, Kevin Paterson C.C.: Kirk Daize From: Julian Kalac, P.Eng License #90505462 Date: October 6, 2012 Re: Noble Fire Production Capacity OBJECTIVE: The objective of this report is to provide an initial assessment of the current Production Capacity at Noble Fire, identify process bottlenecks, and develop a proposed plan to increase Production Capacity. This report contains detailed process descriptions, machine limitations, pictures, current capacity and detailed recommendations for increased capacity. REFRENCED STANDARDS:  Ontario Building Code  National Fire Protection Association (NFPA)  National Standard for Sprinkler System Design (FC 403 ) The preliminary capacity assessment is based on observations from a 1 ½ day visit on October 4th & 5th . For clarification purposes, NO COSTS were provided nor used in this report on: Material & Labour Costs/unit, Production/Sales Gross Margins, Machine Parts & Downtime costs Since no Production KPI was available, and current capacity is not known, the capacity assessment is based on WELDED “OUTLETS/Hr” & % Machine Utilization. Overview: Noble Fire, known as Don Park Fire, is a division of Noble that produces Fire Sprinkler Systems for both residential and commercial industries as per the NFPA and Ontario Building Code standards Noble Fire has a VERY UNIQUE production process. Initially looking from the outside the operation may appear to be simple and straight forward, but the actual production complexity is hidden deep inside the machines & processes. The plant has approximately 35,000 ft², which includes production, offices, warehouse and pipe racks/storage (see Layout in Appendix).
  • 3. Page 3 of 11 Noble Fire Capacity Report 9 October 2012 There are 8 skilled fabricator/welders & 1 foreman. There are no dedicated Maintenance staff on site. The fabricators do their own maintenance and repairs. The foreman Kirk is very experienced, knowledgeable and mechanically skilled. He “wears many different hats”, i.e. reviews customer drawings, provides quotes on labour costs, coordinates workloads, deals with customer calls/complaints/inquiries, orders material. One thing that would make his job a little easier is for him to have a computer with a hard-drive, printer and photocopier on the production floor instead in the front office. Production Processes There are 4 processes involved in completing a finished pipe: 1. Pipe cutting 2. Plasma Profile Burning 3. Circular welding (outlet onto pipe) 4. Pipe Threading THERE ARE 3 BURN/WELD MACHINES:  WB#1--Whirly-Bird style circular welder (—WITHOUT CUTTER)  WB#2 --Whirly-Bird style circular welders (–WITH A DEDICATED CUTTER)  Nogeo machine (1 1/4” to 3”) Machine Design issues: All 3 Machines are outdated in design and require a great deal of maintenance and operator involvement to make them run. They are very much operator dependent, and not everyone can operate each machine. For example the Nogeo Machine can only be operated by either Sergey or Lead Hand Anthony. Each Machine is unique in it’s limitations and capacity. WB#1 WB#2 NOGEO M/C
  • 4. Page 4 of 11 Noble Fire Capacity Report 9 October 2012 The major Machine and Process issues are: 1. Whirlybird M/C #1 (6 years old) has a Production Capacity of 14-16 outlets/hr and is only 60% Utilized in Run Time and 40% with various downtime issues a) Does NOT HAVE a CUTTER AT THE END, therefore requires Non-Value Add activity of loading pipes onto manual cart, pushing the cart to the Threader/Cutter machine ( up to 130ft distance) and back and unload pipes. Estimated= 1-2 Hrs. downtime/shift. b) By adding 2 additional pipe cutters to the plant, would improve machine utilization by min. 15% c) Material handling (loading/unloading) of pipes is done manually with carts and is very labour intensive and time consuming. d) Welding wire feed issues, causing misfeeds/jams and machine downtime. (1hr/shift) e) Both WHIRLY-BIRD machine(s) DO NOT have programming capability therefore require the operator to manually to measure each pipe length, outlet location/spacing, which are done with a tape measurer while the machine is down (2 hr/day). Note: The tolerances on sprinkler head outlets are designed within 1/32” in total variation per system (500+ pipe lines) WB#1 WB#1 NO CUTTER WB#2
  • 5. Page 5 of 11 Noble Fire Capacity Report 9 October 2012 2. Whirlybird M/C #2 has a Machine Capacity of 16 Outlet/hr a. Has the same issues as WB# 1 listed above, except for the wire feed issue b. On top of that WB# 2 has machine alignment issues between the Burning & Welding cycles and therefore has to work backwards and use welding as the main reference and work backwards to set the burning position. c. This is currently being compensated with the skill and experience of the main operator, Dimitri, who is a very skilled MIG/TIG/GAS welder originally from Romania, where the experience level is much higher than here 3. Nogeo Automated Machine has a Machine Capacity of 16 outlets/hr. a) I personally timed the machine cycle time without interruption to be 3.49 min b) The Machine Cycle time is directly related to the lack of process capability and reliability. This machine needs major maintenance & repair to keep running c) This machine is run only by 1 operator, (Sergey) who is the most experienced welder. He has modified, repaired & kept this machine running with no spare parts. d) Sergey has to manually center the welding adapter every single cycle prior to the weld cycle. This is due to the lack of machine capability to adjust for different outlets sizes and causes over 30% of the machine downtime. e) This could easily be rectified by using a STANDARDIZED AISI 1020 UN-ILET (see picture below) f) Frequent Machine breakdowns are a major cause of the machine downtime. g) There are no spare parts and the manufacturer does not carry any of the parts from this outdated model. This causes over 50% of major downtime and lost of productivity (see pictures below and in appendix). WB# 1 FRONT VIEW Pipe Handling cartPlasma Burner
  • 6. Page 6 of 11 Noble Fire Capacity Report 9 October 2012 THREADER PROBLEMS: 1. Oster threader (>30 years) only threads up to 2” pipes 2. Dies keep breaking causing downtime (40% downtime) YTD replaced over 10 sets 3. The material used to make the dies are only case hardened and not made out of HSS—High Speed Steel (M-2) which is the proper tool steel for this application 4. Set-Up time on 1” – 2” Threader takes min 15min/set-up. (3-4 set-ups/day= 1hr M/C downtime) Manually centering the weld adapter prior to welding AISI 1020 STD OUTLET One of the repairs Sergey was showing me he used rope to hold the weld unit together! Problems due to lack of standardized outlets SOLUTION
  • 7. Page 7 of 11 Noble Fire Capacity Report 9 October 2012 CURRENT PRODUCTION CAPABILITY AND SUGGESTED IMPROVEMENTS Current Fire Capacity on the 3 burn/weld machines M/C Pcs/Hr Daily Capacity Weekly Capacity Monthly capacity Annual Capacity WB #1 15 112.5 562.5 2250 27000 WB #2 16 120 600 2400 28800 NOGEO M/C 17 128 638 2550 30600 TOTAL CAPACITY 48 360 1800 7200 86400 AFTER IMPROVMENETS 1-ADDING 2 CUTTERS + 2 THREADER + IMPROVING WB #1 WIRE FEED (estimated cost < $15,000) 2-Replace all outlets with 1 STANDARD AISI 1020 UNI-LET 3/4" OUTLET M/C Pcs/Hr Daily Capacity Weekly Capacity Monthly capacity Annual Capacity WB #1 20 150 750 3000 36000 WB #2 21 157.5 788 3150 37800 NOGEO M/C 23 172.5 863 3450 41400 TOTAL CAPACITY 64 480 2400 9600 115200 Productivity Improvement= 25.0% SUGGESTED IMMEDIATE IMPROVEMENTS: 1. Add 2 PIPE CUTTERS (2”), for WB#1 and Main area. Estimated Cost=$ 2,000 2. Add 1 ROTHENBERGER 4” THREADER with automatic die heads (Max. $10,000) 3. IMPLEMENT AISI 1020 STANDARD UNI-LET outlet which will standardize all welded outlets and significantly reduce machine downtime, especially on the complex NOGEO. 4. Repair WB#1 WIRE FEED ISSUE. I have provided a wire feed troubleshooting guide/checklist to Fernando, WB#1 operator. 5. Implement a PREVENTATIVE MAINTENANCE PLAN for the NOGEO machine with a recommended SPARE PARTS list from the manufacturer in order to reduce downtime TOTAL NEW EQUIPMENT COST = $15,000 Note: These are only estimated improvements which need to be validated
  • 8. Page 8 of 11 Noble Fire Capacity Report 9 October 2012 FURTHER OPTIONS DEPENDING ON THE CONFIDENCE LEVEL OF FUTURE SALES 1. HIRE 2ND SHIFT Because of the equipment issues & limitations, I do not believe adding a 2nd shift would be a feasible option due to the frequent machine breakdowns, design limitations, lack of process/machine capability & unique operator dependency. Hiring & training new people on equipment which are NOT capable, have many limitations, breakdowns and unreliable will only cause more issues and lost of productivity. These machines are not capable of mass production, and would need to retrofitted to make them suitable for mass production. 2. PURCHASE NEW MACHINE(S): This option would only be feasible if there were sufficient sales for the next 5-6 years in order to amortize the capital costs. The question then becomes the confidence level in the projected future sales. I strongly suggest to look into improving the current Whirly-Bird machine issues listed above before purchasing another new machine with the same issues. 3. REPLACE NOGEO WELD UNIT WITH CYPRESS WHIRLYBIRD CW-5 If the Production Capacity after the IMMEDIATE IMPROVEMENTS listed above is still not sufficient, then this would be the most feasible and most effective option. Reason: in order to maximize the utilization of the NOGEO machine The CW-5 model comes with programming capability to allow for individual and combined operations. By investing in this replacement weld unit, the production capacity can increase by over 800% and allow capability for mass production. The cost of 1 of these units needs to be verified, but I have found a used on for $29,000 plus $3000 for carriage and set-up adapter. See the specifications and pictures in the APPENDIX. TOTAL COST USED UNIT = $33,000
  • 9. Page 9 of 11 Noble Fire Capacity Report 9 October 2012 CYPRESS CW-5 CIRCULAR WELDERS CAPACITY ANALYSIS COMPARISON (CW-5 vs NOGEO) CURRENT NOGEO M/C Individual Operation Combined Operations Combined Operations Cycle Time (Seconds) Cycle Time (Seconds) Cycle Time (Seconds) Burn Cut 10 5 30 Weld Time 20 10 150 Loading/Unloading 20 10 10 Chuck Travel Time 10 5 39 Total M/C Cycle Time (Seconds) 60 30 229 Pipes/Min 1 2 0.26 Pipes/Hr 60 120 15.7 Total Available Time/Shift 8.5 8.5 8.5 Breaks & Lunches 1 1 1 RUN TIME 7.5 7.5 7.5 Max Pipes/Shift (8.5 Hrs) 510 1020 117.9 Maintenance Time/Downtime 1.0 1.0 2.0 RUN TIME 7.5 7.5 6.5 EXPECTED PIPES/SHIFT 450 900 102.2 Note: The approximate time for a cut is 6-10 seconds, depending upon diameter and thickness. The approximate time for a weld is 15-20 seconds CYPRESS CIRCULAR WELDER CW-5 New Machine Utilization requires relieving for break and lunches
  • 10. Page 10 of 11 Noble Fire Capacity Report 9 October 2012
  • 11. Page 11 of 11 Noble Fire Capacity Report 9 October 2012 CONCLUSION Based on the overall situation and current production capacity I recommend the immediate suggestions be implemented right away. An estimated 24% increased productivity is well worth the $15,000 cost. I also strongly suggest a Preventative Maintenance Plan for the NOGEO machine with SPARE PARTS ON HAND to reduce machine downtime. I also suggest the manufacturer, NOGEO, come in and do an overall assessment of the machine capability and to evaluate the proposed option of replacing the welding unit with a more sophisticated as listed above or similar. I have reviewed this report with Kirk, the plant foreman and he is in agreement with the recommendations and suggested improvements. If needed I can be of assistance to discuss the proposal with NOGEO I also suggest Production to begin tracking & reporting machine downtime and causes in order to accurately determine the machine efficiency. I would like to thank Kirk and his group for their assistance during the visit. Sincerely, Julian Kalac, P.Eng.