1. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 1 of 8
CURRICULUM VITAE – Principal Geotechnical Engineer – Jorge Cabaco
PROFESSIONAL EXPERIENCE
2015 - Pres SOILSROCK ENGINEERING – Geo & Enviro Consultants Principal Geotechnical Engineer - Director
2013 - 2015 SFL PILETECH – Piling, Retaining Walls & Anchoring NSW Branch & Engineering Manager
2012 - 2013 GEOVERT – Slope Stabilization, Anchoring, Shotcrete
& Grouting
Business & Engineering Manager
2010 - 2012 GEOVERT – Slope Stabilization, Anchoring, Shotcrete
& Grouting
Operations & Technical Engineer Manager
2008 – 2010 MENARD BACHY – Ground Improvement, Anchoring
& Piling
Senior Project Geotechnical Manager
2006 – 2008 OPWAY ENGINEERING – Piling, Retaining Walls
Anchoring, Shotcrete & Ground Improvement
Senior Project Geotechnical Manager
2001 - 2006 KELLER GROUP – Ground Improvement, Retaining
Walls, Piling, Anchoring, Shotcrete & Grouting
Project Geotechnical Engineer then Manager
1998 - 2001 COBA – Engineering & Environmental Consultants Design Geotechnical Engineer
1998 - 1998 PETERSEN ASSOCIATES – Engineering & Architecture Quantity Surveyor
PROFESSIONAL QUALIFICATIONS
CPEng & NPER, Chartered Professional Engineer No. EA3789414 and National Professional Engineer Register,
Civil, Management and Geotechnics
MIEAust, Registered Member of Engineers Australia, Professional Engineer (Civil College)
MEngSc, Master Degree Geotechnical Engineering, New University of Lisbon
BEng (Hons) Bachelor Degree Geological Engineering, New University of Lisbon
Advanced Rock Mechanics Course – Master Degree Mining Engineering – University of New South Wales
Contract Management Course – EEA, Engineering Education Australia
Certificate of Contract Management - AECOPS (Association of Building Industry & Public Works Companies),
Lisbon
Diploma of Quantity Surveyor in the Building Industry (Institute for Accelerated Technical Skills), Lisbon
CIVIL/GEOTECHNICAL AREAS OF EXPERTISE
GEOTECHNICAL & ENVIRONMENTAL INVESTIGATIONS
Soils and rock investigations – (SPT’s, CPT’s, diamond coring, laboratory testing)
Geotechnical Reports Interpretation & Analyses (design geotechnical parameters; foundations and shoring walls
recommendations, ground bearing capacity assessment for shallow foundations and deep foundations, etc.)
Environmental Assessment & Analyses (Soils identification, waste classification, site contamination assessment,
acid sulfate soil assessments)
GEOTECHNICAL CONSTRUCTION TECHNIQUES
Piling for Foundations & Shoring Systems – CFA Piles “Contiguous Flight Auger”, Bored Piles by Casings and
without casings, Screw Piles, Driven Piles; Sheet Piling; Micro-Piles (Self Drilling and Open Hole) – Design &
Construction
Retaining Walls & Deep Excavations - Temporary and Permanent Ground Anchors; Soil Nails, Shotcrete;
Dewatering Systems by Well Points or Water Wells
Ground Improvement – Stone Columns; Vibro Compaction; Dynamic Compaction; Vertical Drains – Design &
Construction
2. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 2 of 8
Grouting – Jet Grouting (single, double and triple fluid); Curtain Grouting (GIN Method, Upstage and Downstage
Methods); Mine Filling Grouting; TAM “Tube A Manchete”; Compaction Grouting – Design & Construction
Slope Stabilization and Rock Fall Protection - Rock bolts, soil nailing and shotcreting, netting systems such as
Geobrugg and Macaferri meshing; Rock Fall Barriers
Monitoring Instrumentation - geotechnical instruments such as inclinometers, tilt meters, extensometers,
piezometers, pressure cells, load cells, joint meters and survey marks in situ;
RELEVANT PROFESSIONAL AND TECHNICAL EXPERIENCE
Approximately 18 years’ experience on Civil and Geotechnical Engineering Design and Construction projects.
Piling and screw piling expert, capable to design and project management any type of screw piling and piling
methods with extensive experience managing past national and international projects for contractors such as
Keller, Menard Bachy, Opway and SFL Piletech
Jet Grouting and grouting expert, capable to design jet grouting design parameters and extensive experience on
construction management grouting special projects in Europe and Australia for different worldwide international
expert’s contractors such as Keller Group, Menard Bachy, Geovert, Opway and SFL Piletech.
Previously responsible for managing design and construction projects at SFL Piletech NSW branch on piling
techniques such as: screw Piles, sheet piling, CFA and Bored Piles for foundations and shoring systems (secant,
contiguous and soldier piles walls). Deep knowledge of Sydney piling market.
Analysing and checking geotechnical parameters and geotechnical models for design assumptions on piling
(including bored, CFA, sheet and screw piles)
Extensive experience on geotechnical reports analyses for design and construct piling projects such as:
Micropiling, Bored Piles, CFA (Contiguous Flight Auger) Piles, Sheet piling, Driven Piles and screw Piles
Experience on design and construction of different retaining structures techniques such as contiguous, secant,
soldier and sheet piles walls combine with anchoring, cantilever pile walls, shotcrete and soil nailing.
Checking and taking account design loadings, earth and water pressures for design and construction projects
related with piling foundations and shoring systems
Experience and supervision of torque ground testing in situ for screw piles design and construction projects
Responsible for many geotechnical projects at level of Project and Technical Manager roles, for design and
construction projects on slope stabilization, rock fall protection, anchoring, soil nailing, shotcrete and ground
improvement
Capable and experience to design, setup on site and managing ground improvement and grouting projects on
stone columns, vibrocompaction, dynamic compaction, wick drains, TAM, curtain grout’s, mine filling grouting
and jet-grouting.
Capable and experience to design, setup on site (using mini drill rigs on slope and/or drill masts attached to
excavator) and managing slope stabilization projects by rock bolts, anchoring, meshing systems (TECCO, Spider or
Macaferri) and shotcrete.
Capable and experience to design, setup on site and managing projects on piling (CFA, Bored, Sheet and Screw
Piles).
Experience in design and construction of different ground improvement construction techniques such as: stone
columns, vibro compaction, dynamic compaction, jet-grouting, compaction grouting, high and low mobility grout,
TAM and GIN for curtain grout.
Experience and responsible to planning and undertaking geotechnical investigations including tests pits, SPT’s,
CPT’s, rock coring for roads and tunnelling.
Experience on site investigations such as SPT’s and CPT’s including planning and testing programs, test results
interpretation and design parameters to design concept ground improvement, slope stabilization and piling
solutions for residential and commercial buildings.
Extensive experience in geotechnical investigations report analyses for design and construct slope stabilization
and rock fall protection projects such as: anchoring, soil nails, anchors, rock bolts, shotcrete and mesh
installation.
Experience in design and construction on different slope stabilization techniques such as: anchoring, soil nails,
self-drilling anchors/nails, rock bolts combine or not with shotcrete or meshing systems TECCO, Spider, Deltax,
Maccaferri, high tensile netting barriers.
3. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 3 of 8
Competent and experience on monitoring geotechnical instrumentation devices such as inclinometers, tilt
meters, extensometers, piezometers, load cells, joint meters and survey marks in situ.
SELECTED MAJOR PROJECTS
BULDING INDUSTRY - RESIDENTIAL AND COMMERCIAL
Design and Estimation Assessment on Secant Pile Wall for Wollongong Road and Martin Avenue, Arncliffe / 2015
Design and Estimation Assessment on Retaining Walls for Townhouse Development Dunning Avenue, Rosebery /
2015
Design and Estimation Assessment on Foundations Piles a Lodge Aged Care, Prestons / 2015
Design and Estimation Assessment on Foundations Piles at Pedestrian Bridge Over Beecroft Road, Beecroft /
2015
Design and Estimation Assessment on Foundations Piles at Inman Road Cromer / 2015
Harold Park, Shopping Centre Glebe – Preliminary Design Options Assessment and Estimation for Ground
Stabilization for Installation of Trade Waste and Sewer Pipes / 2015
Shopping Centre Glebe - Design and Construct Screw Piles Glebe Tram Sheds (168-219mm diameter) Shopping
Centre / Client: Quasar / Duration: 1 month / Sydney / 2015 / Approx. Value $400k
College - Design and Construct Deep Screw Piles (219mm diameter) at Brookvale St. Augustine College / Client:
Total Constructions / Duration: 1.5 month / Sydney / 2015/ Approx. Value $220k
Residential Building - Contiguous Pile Wall at Rosebery (600mm diameter) / Client: ACE Demolition & Excavation
/ Duration: 1 month / Sydney / 2015 – Approx. Value $600k
Apartments - Secant Pile Wall (600mm diameter) at Meadowbank / Client: Infinity Constructions / Duration: 1.5
month / Sydney / 2015 / Approx. Value $700k
Residential Apartments - Sacrificial Sheet Piling Design and Construct Project at Affordable Housing 130 Portman
Street Zetland / Client: ACE Demolitions & Excavation / Duration: 1.5 months / Sydney / 2014-15 / Approx. Value
$300k
Residential Apartments - CFA contiguous Piling Wall (400mm diameter) at 1-3 Charles Street Canterbury / Client:
Yascorp / Duration: 1 month / Sydney / Approx. Value $550k
Petrol Station - Design and Construct Contiguous CFA Wall (450mm diameter) Caltex Coogee / Client: Perish
Constructions / Duration: 1 month / Sydney 2014 / Approx. Value $300k
College - Contiguous Deep CFA Piling Wall (600mm diameter) at Randwick / Client: Deicorp / Duration: 3 months
/ Sydney / 2014 / Approx. Value $1.4M
Residential Apartments - Soldier Bored Pile Wall (Rock Drilling; 600mm diameter) / Client: Oxford Constructions /
Duration: 2 months / Wollongong / 2014 / Approx. Value $410k
Residential Building - CFA Contiguous Piling Wall (300mm Diameter) at 23 Byron Street Coogee / Client: Smith
Group / Duration: 1 month / Sydney / 2014 / Approx. Value $280k
Residential Building - Secant CFA Piling Wall (450mm diameter) Collaroy /Client: Evolution Property / Duration: 1
month / Sydney / 2014 / Approx. Value $300k
Screw Piles Design and Construct Project (219-273mm diameter 800-1000KN design loads) at 108 Parraweena
Road / Client: Rohrig Constructions / Duration: 1 month / Sydney / 2014 / Approx. Value $230k
Car Park - Screw Piles Design and Construct Project (219-273mm; 600-1000KN design loads) at Multi-Story Car
Park – Bungan Lane, Mona Vale / Client: Parkview / Duration: 3 weeks / Sydney / 2014 / Approx. Value $155k
Design and Construct Deep Screw Piles (30m depth; 219-273mm diameter) at Cooks Hill Eclipse Apartments /
Client: Graph Building / Duration: 3 months / Newcastle / 2013/14 / Approx. Value $1.1M
Stadium - Design and Construct Deep Screw Piles (20m depth; 273mm diameter) at Marrickville Fraser Park
Soccer Club Stadium / Client: Portuguese Marrickville Football Club / Duration: 1 month / Sydney / 2013/14 /
Approx. Value $300k
Residential Houses - Several minor Screw Piles Projects – Design and Construction Projects around Sydney
2013/14 – range from Approx. Value $10-100k
Commercial Building - CFA Foundations Piles (600mm diameter) at Catholic Club Car Park 424-458 Hoxton Park
Rd Liverpool / Client: James Clifford Construction / Duration: 1.5 month / Sydney / 2013 / Approx. Value $400k
4. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 4 of 8
Commercial Building - Sacrificial Sheet Piling Wall Design and Construction at Alexandria Australian Post / Client:
ADCO / Duration: 1 month / Sydney / 2013 / Approx. Value $280k
Sheet Piling Wall Design and Construction / Client: Ford Civil / Duration / Wolli Creek – Sydney / 2013 / Approx.
Value $350k
College - CFA Foundations Piles for St. Ursula’s College Catholic School at 69 Caroline St Kingsgrove / Client:
Grindley Constructions / Duration: 1 month / Sydney / 2013 / Approx. Value $150k
Bored Foundation Piles for Endeavour Energy St Andrews Rd, Leppington / Client: Hansen Yuncken / Duration: 1
month / Sydney / 2013 / Approx. Value $220k
Residential Building - Contiguous CFA Wall (450mm diameter) at 41 Birmingham Street Alexandria / Client:
Gordon Constructions / Duration: 1 month / Sydney / 2013 / Approx. Value $150k
Bondi Hotel - Underpinning Jet Grouting Columns Ø 1500mm single fluid – The Beach House / Bondi Hotel /
Client: Gavellen & Absolut Contracting / Duration: 2 Weeks / Quantities: 300 lm/ Bondi Beach / Sydney / Approx.
Value $150k / 2009
Commercial Warehouse - Mine Subsidence Grouting – Drilling and Grouting Mine Marketown East Steel Street /
Newcastle West / 2008 - Approx. Value $3M / Client: Adco Constructions / Duration: 5 Months / Quantities:
4,377lm Drilled & 7,900m3 grouted
Casino - Underpinning Jet Grouting Columns Ø 600mm single fluid – Conrad Jupiter’s Casino Car Park
Stabilizations Works / Gold Coast / Client: Jupiters Casino / Duration: 7 Months / Quantities: 6,100 lm / Approx.
Value $3.5M / 2009
Car Park - Ground installation of profiles steel beams HEB 140 & Provisional Strand Anchors 350 kN – retaining
wall for car park of Residence Building Quinta das Pedreiras / Lisbon / 2008 / Client: Boanorma Lda / Duration 1
Month / Quantities: 1,100lm Strand Anchors / 400 lm HEB 140 Steel Beams
Residential Building - Micro-piles Ø 200mm reinforced with hollow steel tubes diameter 114,3mm, using double
packers and manchetes for high pressure grouting and Permanent Strand Anchors 500kN; concrete wall
reinforcement using steel beams - reinforcing and concrete wall stabilization for a building residence / Sesimbra /
2008 / Client: Teodoro Gomes Alho e Filho Lda / Duration 4 weeks / Quantities: 200lm Strand Anchors / 100 lm
Micropiles
Car Park - Jet Grouting Columns Ø 1400m & 1800m double fluid reinforced with micro-piles using hollow steel
tubes Ø 127 mm foundations reinforcement; Jet Grouting Columns double fluid Ø 1500mm & 2000mm curtain
grout - Excavation and reinforcement of foundations of the underground car park near by the Lima river at Viana
do Castelo North of Portugal; Approx. Value €1.1M; 2004-05; Client: Mota Engil; Owner: Viana do Castelo Council
– North Coast of Portugal; Duration: 1 year; Quantities: 1,800 lm jet grouting columns; 600 lm micro piles; 4
dewatering using 4 vacuum aggregate pumps; 13 water wells pumping a total of about 660 ltrs per second;
Hotel Historil - Drilling for Ground installation of steel beams profiles HEB 120 and Temporary Strand Anchors
625kN; Drilling and Installation of Micropiles Ø 150mm using hollow tubes section Ø 114,3mm – retaining wall
and foundations reinforcement for car park of Hotel Palace Park / Estoril / 2008 / Client: Hotel Historil / Duration
2 Months / Quantities: 200lm Strand Anchors / 2,200 lm Micropiles
Paper Manufacture - Stone Columns Ø 800mm (using vibrators from PTC and BAUER) – soils improvements for
foundations; self-drilling Micro-Piles Ø 150mm reinforced with hollow tubes diameter 114,3mm – reinforcement
foundations of existing pillars; Bored piles Ø 800mm – deep foundations of central biomass chimney - Paper
Manufacture CELBI / Figueira da Foz / 2007-2008 - Approx. Value €600k / Client: CELBI Paper Manufacture /
Duration 3 Months / Quantities: 11,000lm Stone Columns / 1,000 lm Bored Piles / 500lm Micropiles
Post Warehouse - Jet Grouting Columns Ø 100mm triple fluid – underpinning jet grouting columns, warehouse
Chronopost Póvoa de St. Iria / Client: Construsan / Duration 4 Months / Quantities: 10,500 lm Jet Grouting
Columns / L Approx. Value €3M / Lisbon / 2006
Leca Manufacture - Micro-piles Ø 180mm reinforced with hollow steel tubes diameter 139,7mm – underpinning
of pillar’s foundations in Leca Maxit Manufacture Avelar / Coimbra Central Portugal / 2006
Car Park Deep Excavation - Jet Grouting Columns Ø 1000-1200-1500mm triple fluid reinforced with micro-piles
using hollow tubes Ø 88,9-127-168 mm – excavation, retaining wall and foundations reinforcement for car park
of residence building Viriato Street / Client: Euromobiliaria / Duration 5 months / Quantities: 1,200 lm jet
grouting columns; 1,500 lm micro piles; 40,000 m3 excavation; 2,000 m3 steel concrete reinforced walls and
concrete beams reinforced with 52mm GEWI bars / Approx. Value €800k / Lisbon / 2006
Commercial Arena Building - Micro-piles Ø 150mm reinforced with hollow steel tubes diameter 88,9mm –
reinforcing foundations for Arena building Arade / Portimão / Algarve / 2005
5. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 5 of 8
Commercial Warehouse - Stone Columns Ø 1000mm – soils improvement for foundations of Warehouse
Intermarché / Oporto / 2005
Car Park Underground - Jet Grouting Columns Ø 1400m & 1800m double fluid reinforced with micro-piles using
hollow steel tubes Ø 127 mm foundations reinforcement ; Jet Grouting Columns double fluid Ø 1500mm &
2000mm curtain grout - Excavation and reinforcement foundations on Underground Car Park near of Lima river
at Viana do Castelo / Client: Mota Engil / Owner: Viana do Castelo Council – North Coast of Portugal / Duration: 1
year / Quantities: 1,800 lm jet grouting columns; 600 lm micro piles; 4 dewatering using 4 vacuum aggregate
pumps; 13 water wells pumping a total of about 660 lm per second / Approx. Value €1.1M / 2004-2005
Major Commercial Building Warehouse - Jet Grouting Columns triple fluid Ø 800mm in between bored piles -
retaining wall for excavation support to reduce the affluence water Warehouse of “El Corte Ingles” Vila Nova de
Gaia / Client: Mota Engil / Owner: Porto Council / Duration: 4 Months / Quantities: 7,500 lm jet grouting columns
/ Approx. Value €800K / Porto / North Portugal / 2004-2005
Agriculture Warehouse - Vibrocompaction – soils improvements for foundations of warehouse Agriculture Monliz
Alpiarça / Santarem Central Portugal / 2004
Hotel Curia - Micro-piles Ø 200mm reinforced with hollow steel tubes diameter 168mm – foundations at Hotel
Curia / Anadia / Approx. Value €200k / Central Portugal / 2003
TRANSPORTATION - ROADS, RAILWAYS, BRIDGES AND TUNNELING
Lennox Bridge Portals (open cut pedestrian tunnel at the bridge abutments) CFA Contiguous Pile Wall and Screw
Piles Design and Construct Project at Parramatta / Client: Abergeldie / Duration: 2 months / Sydney / 2014 /
Approx. Value $200k
Sydney Light Rail - Foundations CFA Piles / Client: John Holland / Duration: 2 months / Sydney / 2013 / Approx.
Value $650k
Roads – Light Poles - Screw Piles – Several RMS Projects same ongoing contract – Sydney 2013/14 – range from
$20k-$50k
Seaford Rail Extension Project - Slope Stabilization - Soil Nailing and Shotcreting – Adelaide SA / 2012 - Approx.
Value $6.4M / Client: Theiss & MacDow Joint Venture / Duration: 8 Months / Quantities: 45,000 lm Nails; 22,000
m2 Shotcrete
Warrego Highway Toowoomba Range - Slope Stabilization - Soil Nailing and Shotcrete / Brisbane QLS / 2011 -
Approx. Value $3M / Client: Fulton Hogan Construction Pty Ltd / Duration: 5 Months / Quantities: 3,500 lm Soil
Nails & 700 m2 Shotcrete
Cunningham’s Gap Road - Slope Stabilization – Rock Bolts, Blasting and Shotcreting Emergency works using rope
technical access / Client: Fulton Hogan / Duration: 3 months / Brisbane QLS / 2010-2011
Western Escarpment - Antias Jacksons - Slope Stabilization – Rock Bolts and Mesh Installation / Client: Lend Lease
/ Duration: 3 weeks / Pyrmont / Sydney NSW / 2010
Paddington Gold Rail Underpinning - Slope Stabilization – Soil Nails & Shotcreting / Client: Paddington Gold /
Kalgoorlie WA / Approx. Value $400K / 2010
Kiwi Rail North South Junction Slope Stabilisation – Deltax Mesh Installation and Rock Bolts / Client: Downer EDI /
Duration: 7 month / Wellington / New Zealand / Approx. Value NZD2.5M / 2011
Fairy Meadow Rail Way Station - Ground Anchors / Client: Rail Corp / Duration: 1 week / Wollongong / 2010
Nerang Tunnel - Low Pressure Grouting / Client: Theiss / Duration: 2 month / Nerang / Gold Coast / Approx.
Value $150k / 2010
Bridge Repair Figueira e Barros - Micro-piles ø 150mm reinforced with hollow steel tubes diameter 88,9mm using
double packers and manchetes for high pressure grouting – reinforcing foundations Old Bridge Figueira e Barros
Avis / Client: Pontave / Duration: 1 Month / Quantities: 800lm / South Portugal / 2008
Bridge Foundations - Bored Piles Ø 600mm – deep foundations for rehabilitation of 4 Bridges Alberge, Agualva,
Bem-Gordo and Cotovia villages in Setubal / Client: Tecnovia / Duration 2 Months / Quantities: 2,200lm Bored
Piles / Lisbon / 2007
Bridges Foundations - Bored Piles Ø 600 & 800mm – deep foundations for new 3 Bridges for connections
between two national roads EN109 to EN334 / Client: Pontave SA / Duration 1.5 Month / Quantities: 1,100lm
Bored Piles / Figueira da Foz / Centre of Portugal / 2007
Bridge Foundations - Bored Piles Ø 600mm – deep foundations for rehabilitations of Bridge Comenda village
Setubal / Lisbon / Client: Tecnovia / Duration 1 Month / Quantities: 600lm Bored Piles / Lisbon / 2007
6. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 6 of 8
Tunnel of Terreiro do Paco Subway - Design and Construction Jet Grouting Columns Ø 2000mm with triple fluid &
bored piles using bentonite Ø 1200mm and 1500mm – piles and jet-grouting columns were constructed to treat
the sand layers surrounding the underground tunnel of Terreiro do Paco Subway Station to prevent liquefaction.
Geotechnical monitoring instrumentation were installed inside and outside of the tunnel to control and monitor
potential movements within the tunnel (settlement survey marks, inclinometers, crack measurements and survey
prisms; core drilling samples were removed from the jet-grouting columns to carry UCS tests to check and
confirm jet-grouting columns strength – Lisbon / 2007 – Approx. Value €5,5M (involvement in the tender
estimation, project award and project delivery as a Project Manager); Client: Metropolitano de Lisboa (Lisbon
Metro); Duration: 8 Months; Quantities: 1,500lm Jet Grouting Columns; 5,500 lm Piles.
Rail Way Lares Bridge - Repair and Rehabilitation of the foundations pillars – marine works repairing of
foundations of the bridge pillars; installation of micro concrete piles and application of sacrificial steel formwork
reinforced with steel mesh SL81 trough the foundation of the pillars; core drilling boreholes vertical and inclined
(SPT’s, Vane tests, lab tests, Atterberg Limits, triaxial testing) for geotechnical analysing and interpretation for
further rectification works & low pressure grout injections reinforced with steel bars, monitoring instrumentation
using surveying marks on the pillars; location: Figueira da Foz Central Coast Portugal; Approx. Value €1M; 2006-
07; Client: REFER (Portuguese Rail Way Public Company); Duration: 4 Months; Quantities: repairing of 3 pillars,
300 lm drill coring through the pillars, 250 lm drilling of soils investigations.
Curtain Grout - Jet Grouting Columns Ø 600mm single fluid – curtain grout for reduce the affluence water to the
village / Coruche Central Portugal / 2006 Client: RCC – Ramalho Rosa Cobetar / Duration 3 Months / Quantities:
6,000 lm Jet Grouting Columns / Centre Portugal / 2006
Bridge Foundations - Bored Piles Ø 1200mm (drive vibrator hammer, casing with lost steel pipes, bentonite fluid
stabilization) including sonic tests and cross hole; Micro-piles Ø 200mm reinforced with hollow steel tubes
diameter 114,3mm, using double packers and manchetes for high pressure injection for build the bond lenght
including tensile load pull out testing - reinforcing and rehabilitation of old Steel Bridge / Alcacer do Sal / 2008 -
Approx. Value €500k / Client: IEP - Instituto de Estradas de Portugal (Roads Authority of Portugal) / Duration 2
Months / Quantities: 800lm Bored Piles / 1,000 lm Micropiles
Rail Way Station - Bored Piles Ø 800mm for Bridges/ Client: Espinho Council / Duration 1 Month / Quantities:
400lm Bored Piles / Espinho Portugal / 2008
Rail Way Line North between Azambuja and Santarém - Stone Columns Injected and no Injected Ø 1000m – soils
improvement for reinforcement foundations / Client: Mota-Engil / Duration: 1 month / Portugal / 2005
Modernization of Rail Way North Line between Alhandra and Azambuja, Vila Franca de Xira, Portugal - Stone
Columns Ø 1000mm, Vertical Wick Drains & CPT’s & Vane Tests / Client: Somague Engenharia SA; Owner: REFER
Public Rail Way Portuguese Company; Lisbon; Duration: 4 Months; Quantities: 1,500,000 lm Vertical Wick Drains;
24,400 lm stone columns / Approx. Value €3.6M / 2004;
High Way A10 - Ground Permanent Strand Anchors - 500 & 600 kN – retaining wall / Bucelas / Carregado / Lisbon
/ Portugal / 2002
Rail Way North Line - Areeiro - Ground Permanent Strand Anchors from 4 to 7 strands 450, 500, 600, 750 kN –
structure containment wall / Client: Ferrovial / Owner: REFER – Rail Way Public Portuguese Company / Duration:
8 Months / Quantities: 8,600 lm anchors; 1,500 lm geodrains / Approx. Value €800k / Lisbon / 2002
High Way A10 - Ground Permanent Strand Anchors - 500 & 600 kN – retaining wall near of the High Way A10 -
Bucelas / Carregado / Lisbon / Portugal / 2002
Metro Station Terreiro do Paco / Underground Works / Tunnelling – Geotechnical & Building Geotechnical
Instrumentation and Monitoring - Geotechnical Instrumentation and Monitoring of the surrounding buildings and
Deep Excavation / Client: Metropaco / Owner: Metropolitan of Lisbon - Metro Public Portuguese Company /
Duration: 3 months / 2001
HEAVY CIVIL - PORTS, AIRPORTS, DAMS AND WATER TREATMENT STATIONS
Design and construct Sheet Piling for Interceptor Trench Excavation at North Maroubra Beach / Client: Enviro
Pacific Services / Duration: 1.5 months / Design and Construction Sheet Piling / Sydney / 2013 / Approx. Value
$500k
Sacrificial Sheet Piling Design and Construct at Hanger 96 Qantas Sydney Airport / client: Civilcraft Pty / Duration:
2 weeks / Sydney / 2013 / Approx. Value $100k
CFA and Screw Foundations Piles Design and Construct at Qantas Domestic Airport Terminal 1 Bay 8 / Client:
Midas Construct / Sydney / 2013 / Approx. Value $150k
7. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 7 of 8
Airport Link Bowen Hills - DCP Rock Bolts Using Drill Mast assemble in Excavator drilling up to 10m high / Client:
Airport Link Theiss/Duration: 2 weeks / Brisbane QLD / 2010
Port Botany Expansion Project, Sydney - Ground Compaction Works – Dynamic Compaction & Vibro Compaction
onshore/offshore works – planning and undertaken a large campaign of SPT’s tests and CPT’s tests to confirm
design specifications of sand densification > 65% and qc > 10 MPa post treatment and prior treatment to check
the in situ parameters / Client: Baulderstone Hornibrook & Jean De Null / Duration: 12 Months / Quantities:
8,000,000m3 / Approx. Value $18M / 2008/09.
Blowering Dam ACT - Ground Anchors – Permanent 19xStrand Anchors 35m deep – Further site investigations
were undertaken in order to confirm the weak rock conditions to install the bond anchor length, and determine
adequate process procedure to improve the rock prior the installation of the anchors which comprised to drill
and grouting and redrill and re-grout till the holes were sustained and not collapsing / Client: MacMahon;
Duration: 6 Months / Location: Canberra ACT / Approx. Value $500k / 2010-11.
Slope Stabilization – Soil Nails and Mesh Installation using rope access gear and mini drill rig – Watersedge
Terrace – Geelong VIC / 2010
Cotter Dam – Main Dam - Curtain Grout –– Drilling and Grouting Package – Canberra ACT / 2012 - Approx. Value
$3.2M – This project comprised around 7,500 lm of drilling and pressure grout by upstage grouting GIN method
by using a full automated computerised grout control system; a campaign of rock coring drilling using NQ size
were carried to check rock treatment/ Client: Bulk Water Alliance Joint Venture John Holland & Abbi Group/
Duration: 5 Months/ Quantities: 4,500 lm percussion drilling and 1,000 lm of rock core drilling quality holes
checks including logging and 6,876 lm drainage holes open by percussion drilling.
Water Treatment Residual Station - Vibrocompaction, Dewatering with “well Points” and deep water well for
water supply – soils improvements and excavation for foundations of Water Treatment Residual Station in
Coimbrão / Client: Soares da Costa / Owner: SIMLIS – Hidric Public Company / Duration 3 months / Quantities:
405.000 m
3
vibrocompaction treatment of sands Soils; 6 Vacuum agregates pumps for water wells; water well
220m depth / Leiria Central of Portugal / 2005
Obidos Dam - Stone Columns Ø 1000mm (soils improvements) Soil Nailing & Shotcreting – soils improvements of
Dam foundations and slope stabilization at Óbidos Dam Land Project / Client: RRC - Ramalho Rosa Cobetar /
Owner: IHERA – Hidric Portuguese Resources Company / Duration: 5 Months / Quantities: 45,000 lm stone
columns; 2,000 lm soil nailing; 2,000 m2 shotcreting / Approx. Value €1M / Óbidos – Central Portugal / 2003
Land Dam for Bridge Abutment - Stone Columns Ø 1000mm – reinforcement of soil foundations for a dam land
Sacavém / Lisbon / 2002
MINING & RESOURCES
Site Mine - West Angeles CENP - Rockfall Protection Site Mine - Rock Bolts & Mesh Installation using rope
technical access and mini drill rigs / Client: Pilbara Iron Company Pty Ltd - Rio Tinto / Duration: 2,5 Months /
Quantities: 6,000 m2 Mesh Newman WA / Approx. Value $2.5M / 2011
Site Mine - Rubicon Site Mine - Rockfall Protection - Drape Maccaferi Mesh Installation / Client: Barrick Kanowna
Limited / Duration: 1,5 Months / Quantities: 6,000 m2 Mesh / Kalgoorlie WA / Value Approx. $1.5M / 2011
Site Mine at Sino Ore Karratha - Testing Rock Bolts / Client: Cimeco / Duration: 1 month / Quantities: 120 Bolts /
Approx. Value $250k / Karratha WA / 2010
Site Mine – Sino Ore - Pressure Grouting & Rock Bolts - Remedial Works at Crusher Pockets 1 & 2 / Client: Citic
Pacific Mining / Duration: 1 Month / Karratha WA / 2 Approx. Value $1M / 2010
Quarry Stabilization Butik Batok at Singapore Federal Defence - Slope Stabilization – Tecco Mesh Installation and
rock Bolts using rope access gear and mini drill rigs / Client: Sembcorp / Duration: 1 Year / Approx. Value
SGD$5M / 2010-2011
GEOTECHNICAL INVESTIGATIONS & ENVIRONMENTAL ASSESSMENT
Geotechnical Investigation at Vine Street, Fairfield / 2015
Geotechnical Investigations at Pacific Highway, Chatswood / 2015
Geotechnical Investigations at Eurobion Avenue, Manly / 2015
Geotechnical Investigations at Marple Avenue, Villawood / 2015
Soils Classification on VENM, ENM and GSW validation assessment at French Forest Road, Seaforth / 2015
8. CV – Principal Geotechnical Engineer - Jorge Cabaco Page 8 of 8
Apartments Building Development – Soils Classification on VENM, ENM and GSW validation assessment at
Ramsgate Avenue, Bondi Beach / 2015
Apartments Building Development – Soils contamination on asbestos validation assessment at Ramsgate Avenue,
Bondi Beach / 2015
Residential Building – Pit tests at Heyde Avenue, Strathfield / Environmental Soils Assessment Contamination /
2015
Residential Building – Pit Tests at Mount Vernon Rd, Mount Vernon / Environmental Soils Assessment
Contamination for Penrith Council / 2015
Car Park – Pit tests at Narellan for soils assessment contamination and waste classification / South Sydney / 2015
Geotechnical Investigation – torque testing to check ground conditions for screw piles installation – multiple sites
around Sydney and central coast / 2013-2015
Geotechnical Investigations – Boreholes and SPT’s to verify ground conditions at Beechmont Road Slope
Stabilization works / Gold Coast / 2013
Geotechnical Investigation and reporting – NQ boreholes through rock coring 60m deep at Cotter Dam Grouting
works to check rock strength and fractures / Cotter Dam / ACT / 2012
Geotechnical Investigations and reporting – boreholes core drill through jet-grouting columns for quality check
program at Jupiters Casino works / Gold Coast / 2009
Geotechnical Investigation and reporting – boreholes and SPT’s and CPT’s to check soils improvement quality
work at Port Botany – multiple tests / Sydney / 2008-2009
Geotechnical Investigations and reporting – boreholes core drills at Market Street mine fill works / Newcastle /
2008
Geotechnical Investigations and reporting – boreholes and SPT’s to confirm ground conditions at Terreiro do
Paco tunnel 60m deep; rock coring through jet-grouting columns to check quality columns strength / Lisbon /
2007
Geotechnical Investigation – boreholes with SPT’s to check ground conditions of Bridge pillars of Lares Bridge,
and coring through the concrete pillars to check pillars integrity / Lares Bridge / Centre of Portugal / 2006
Geotechnical Investigations and water testing – CPT’s to check soils improvement work by vibrocompaction and
water pressure testing for dewatering at Water treatment station Coimbrao / Centre of Portugal / 2005
Geotechnical investigations – boreholes and CPT for foundations of water treatment station at Coimbrao /
Central Coast of Portugal / 2005
Geotechnical Investigation – Boreholes and SPT for foundations warehouse Póvoa de St. Iria / Lisbon / 2005
Geotechnical Investigations - Boreholes and SPT – retaining wall for construction of car park residence building -
São Pedro Sul / Centre of Portugal / 2002
Geotechnical Investigations - Boreholes and SPT’s at National Theatre of Faro / Client: Faro Council / Duration: 1
Month / Algarve / South Portugal / 2003-2004;
Geotechnical Investigations - Boreholes and SPT’s, soil samples and lab testing – Soils Investigation for
Geotechnical investigation report for foundations of residence building - Parque das Nações / Lisbon / 2002
Geotechnical investigations, report and design and Construction of Ramela Tunnel / Tras-os-Montes / North
Portugal / 2001
Geotechnical investigations, report and design for Highway IC24 & IC29 / Oporto / North Portugal / 2001
Geotechnical investigations, report and design for construction of Highway IP2 / Interior of Portugal / 2001
Geotechnical investigations, report and design for slope stabilization of National Road EN115 / Bucelas / Lisbon /
2001
Geotechnical investigations, report and design for Motorway A2 / Algarve / South Portugal / 2001