Standard Costing &
Variance Analysis!
Definitions
• Standard Cost: (CIMA) “Standard cost is the pre-
determined cost based on the technical estimates for
materials, labour and overhead for a selected period
of time for a prescribed set of working conditions.”
• Standard Costing: (CIMA) “the preparation of
standard costs and applying them to measure the
variations from the actual costs and analyzing the
causes of variations with a view to maintain
maximum efficiency of the operations so that any
remedial action may be taken immediately.
Variance Analysis
• Cost Variance: is the difference between
the standard cost and the actual costs.
• Variance Analysis: is the resolution into
constituent parts and the explanation of the
variances.
 Favorable & Unfavorable Variances.
Controllable & Uncontrollable Variances
What all could be
the reasons for the
actual
manufacturing cost
or the sales/profit
to vary from their
standard costs and
price/profit?
Types of
Variances
1. Material
Variance
Material Cost
variance
Material Price
Variance
Material Usage
Variance
Material Mix
Variance
Material Yield
Variance
2. Labour
Variance
Labour Cost
Variance
Labour Rate
Variance
Labour
Efficiency
Variance
Labour Mix
Variance
Idle Time
Variance
3. Overhead
Variance
Overhead Cost
Variance
Variable
overheads Var.
Variable o/h
efficiency var.
Variable o/h
expenditure var.
Fixed overhead
variance
4. Other
Variances
Calendar
Variance
Sales Value
variance
Sales price
variance
Sales volume
variance
Profit Variance
Favorable & Unfavorable Variances
• Favorable variances(F) arise when actual costs
are less than budgeted costs or actual sales/profit
exceed budgeted.
• Un favorable variances(U) arise when actual
costs exceed budgeted or actual sales/profit are
less than budgeted.
Profit Revenue Costs
Actual > Expected F F U
Actual < Expected U U F
Standard Costs
Benchmarks for
measuring performance.
The expected level
of performance.
Based on carefully
predetermined amounts.
Used for planning labor, material
and overhead requirements.
Standard
Costs are
Setting Standard Costs
Accountants, engineers, personnel administrators,
and production managers combine efforts to set
standards based on experience and expectations.
Standards vs. Budgets
Are standards the same
as budgets?
A standard is the expected
cost for one unit.
A budget is the expected
cost for all units.
The price variance is computed
on the entire quantity
purchased.
The quantity variance is
computed only on the quantity
used
How will the material price
variance and material
usage be computed if the
quantity purchased is
different from the quantity
used?
Material Cost Variance
• Material cost variance arises due to variance in the price of material
or its usage.
• This can be calculated by using the following formula,
• Material Cost Variance = (SQ x SP) – (AQ x AP) ,
• Where,
SQ = Standard quantity for the actual output
SP = Standard price per unit of material
AQ = Actual quantity
AP = Actual price per unit of material
• A positive result implies favorable variance and a negative result
implies unfavorable variance (adverse variance).
Material Price Variance
• Material price variance may arise due to number of reasons like
fluctuations in market prices, error in buying due to wrong
purchasing policy etc,
• This can be calculated by using the following formula,
• Material Price Variance = (SP – AP) x AQ
• Where,
SP = Standard price per unit of material
AQ = Actual quantity
AP = Actual price per unit of material
• A positive result implies favorable variance and a negative result
implies unfavorable variance (adverse variance).
Material usage Variance
• Material Usage variance is the difference between the actual
quantities of raw materials used in production and the standard
quantities that should have been used to produce the product,
• MUV may arise due to number of reasons like Pilferage of
materials , Wastage , Sub-standard or defective materials etc,
• This can be calculated by using the following formula,
• Material Usage Variance = (SQ – AQ) x SP
Material Mix Variance
• MMV is calculated when a product uses mixture of different raw
materials,
• MMV is that portion of the materials quantity variance, which is
due to the difference between the standard and actual
composition of a mixture.
• It can be represented by the following formula:
Material mix variance = (Standard cost of actual
quantity of the standard mixture – Standard cost of actual quantity
of the actual mixture) or (Revised SQ – AQ) x SP
Practical Problems
1. A furniture company uses sunmica tops for tables.
It provides the following data:
St. Quantity for sunmica per table 4 sq. ft
St. price per sq. ft of sunmica ₱ 5
Actual prod. Of tables 1000
Sunmica actually used 4,300 sq.ft
Actual purchase price per sq. ft ₱ 5.50
Calculate Material variances.
St. price x St. Quantity 5 x 4000 = 20,000.00
St. price x Actual Quanity 5 x 4300 = 21,500.00
Actual Price x Actual Quanity 5.5 x 4300 = 23,650.00
Material Cost Variance (3,650.00)
Material Usage Variance (1,500.00)
Material Price Variance (2,150.00)
Solution:
2. From the following information calculate (i) material cost
variance (ii) material price variance (iii) Material Usage
variance
Standard output 100 units
Standard Material per unit 3 Ibs
Standard price per Ib. ₱ 2
Actual output 80 units
Actual price ₱ 5.50
Actual materials used 250 Ibs
Material Cost Variance 65
Material Usage Variance -60
Material Price Variance 125
3. From the following information calculate (i) material cost
variance (ii) material price variance (iii) Material Usage variance
Quantity of material purchased 3000 units
Value of material purchased ₱ 9000
St. quantity of raw material req. p.u. 25 units
Standard rate of material unit ₱ 2
Opening stock of material Nil
Closing stock of material 500 units
Finished production during the period 80 units
St. price x St. Quantity 2 x 2,000 = 4,000
St. price x Actual Quanity 2 x 2,500 = 5,000
Actual Price x Actual Quanity 3 x 2,500 = 7,500
Material Cost Variance (3,500)
Material Usage Variance (1,000)
Material Price Variance (2,500)
Solution:
4. The standard output of the production house has been set at
1000 pieces per month. However actually 1020 pieces were
produced. Following is the data for actual and standard
production.
Standard Actual Results
Usage 1.5 sq. ft per pad 1.3 sq. ft per pad
Price Rs. 0.15 per sq. ft Rs. 0.18 per sq. ft
Calculate all material variances.
St. price x St. Quantity 0.15 x 1,530 = 229.50
St. price x Actual Quanity 0.15 x 1,326 = 198.90
Actual Price x Actual Quanity 0.18 x 1,326 = 238.68
Material Cost Variance (9.18)
Material Usage Variance 30.60
Material Price Variance (39.78)
Solution:
5. A mfg. concern, which has adopted standard costing, furnishes
the following information:
Standard:
Material for 70 kg. Of finished products 100 kgs.
Price of materials ₱ 1 per kg.
Actual:
Output 210,000 kgs
Material used 280,000 kgs.
Cost of materials ₱ 2,520,000
Calculate all material variances.
St. price x St. Quantity 1 x 300,000 = 300,000
St. price x Actual Quanity 1 x 280,000 = 280,000
Actual Price x Actual Quanity 0.9 x 280,000 = 252,000
Material Cost Variance 48,000
Material Usage Variance 20,000
Material Price Variance 28,000
Solution:
Material Mix Variance
• Material Mix Variance
= [Revised St. Qty – Actual Qty] x St. Price
Rev. St. Qty = St. Qty of 1 Mat. x Actual Total
Standard Total
From the following information regarding a standard product,
compute 1. Mix 2. Price 3. Usage Variance:
Raw Material Standard Actual
X 40 units @ Rs. 50 p.u. 50 units @ Rs. 50 p.u.
Y 60 units @ Rs. 40 p.u. 60 units @ Rs. 45 p.u.
Total 100 units 110 units
Rev.ST. Qty St. Price St. Qty Act.Price Act. Qty
Revised St. Qty X 40/100 x 110 = units 44 50 40 50 50
Revised St. Qty Y 60/100 x 110 = units 66 40 60 45 60
Material Mix Variance
For X -300
For Y 240 -60 MMV
Material Usage Variance
For X -500
For Y 0 -500 MUV
Material Price Variance
For X 0
From the following information regarding a standard product,
compute 1. Mix 2. Price 3. Usage Variance:
Material
Standard Actual
Qty. Rs. p.u. Total Qty
Unit
Price Total
A 4 1.00 4.00 2 3.50 7.00
B 2 2.00 4.00 1 2.00 2.00
C 2 4.00 8.00 3 3.00 9.00
Total 8 7.00 16.00 6.00 8.50 18.00
St. Price St. Qty Act.Price Act. Qty
Revised St. Qty A 4/8*6= units 3.00 1.00 4 3.50 2
Revised St. Qty B 2/8*6= units 1.50 2.00 2 2.00 1
Revised St. Qty C 2/8*6= units 1.50 4.00 2 3.00 3
Material Mix Variance
For A 1
For B 1 -4 MMV
For C -6
Material Usage Variance
For A 2
For B 2 0 MUV
For C -4
Material Price Variance
For A -5
For B 0 -2 MPV
For C 3
Material variances
• Labour Cost Variance SH*SR – AH*AR
• Labour Usage/Efficie. Var (SH-AHactual)*SR
• Labour Rate Variance (SR-AR)* AH
• Idle time Variance SR*Idle time
Labour Variances
Practice Problem
A firm gives you the following data:
Standard time per unit 2.5 hours
Actual hours worked 2,000 hours
Standard rate of pay Rs. 2 per hour
25 % of the actual hours has been lost as idle time.
Actual output 1,000 units
Actual wages Rs. 4,500
Calculate all labour variances.
St. Rate 2 LUV 2000F
St. Hrs 2500 LPV -500U
Actual Rate 2.25 ITV 1000F
Actual Hrs 2000 LCV 500F
Idle time 500
Practice Problems
Compute the Labour variances from the
information given below:
Standard time 3 hours per unit
Standard rate of wages Rs. 6 per hour
Actual production 700 units
Actual time taken 2000 hours
Actual Wages Rs. 14000
Idle time 50 hours
St. Rate 6 LUV 900F
St. Hrs 2100 LPV -2000U
Actual Rate 7 LCV -1400U
Actual Hrs 2000 IDV 300
Idle time 50
Labor Efficiency Variance- Causes
Unfavorable
Efficiency
Variance
Poorly
trained
workers
Poor
quality
materials
Poorly
maintained
equipment
Poor
supervision
of workers
Responsibility for Labor Variances
I am not responsible for
the unfavorable labor
efficiency variance!
You purchased cheap
material, so it took more
time to process it.
You used too much
time because of
poorly trained
workers and poor
supervision.
Overhead Variances
• Overhead variances arise due to the difference
between actual overheads and absorbed overheads.
The estimate of budget of the overheads is to be
divided into fixed and variable elements. i.e.
1. Variable overhead variances.
– Variable overhead budget or expenditure variance, and
– Variable overhead efficiency variance.
2. Fixed overhead variances.
Formulas
1. Variable overhead variances.
(Standard variable o/hfor actual prodn. – Actual variable o/h)
2. Variable overhead budget or expenditure variance,
(Budgeted variable overhead for actual hours – Actual
variable overhead) i.e. AH*BR – Actual Cost
3. Variable overhead efficiency variance.
Standard variable overhead rate per hour [Std. hours for
actual output – Actual hours] i.e. (SH-AH) *SR
4. Fixed Overhead Variance
Budgeted FO- AFO
Sales Variances
• Sales Margin Price Margin = (AP-BP)*AQ
• Sales Margin Volume variance = (AQ-BQ)*BC
• Total Sales Margin variance = AQ*AC – BQ*BC

More Related Content

What's hot

Chapter 07 Marginal Costing
Chapter 07   Marginal CostingChapter 07   Marginal Costing
Chapter 07 Marginal Costingayanthimadhumali
 
Time period - Short Run & Long Run
Time period - Short Run & Long RunTime period - Short Run & Long Run
Time period - Short Run & Long RunJerrin Mathews
 
Standrad costing
Standrad costingStandrad costing
Standrad costingFaltu Focat
 
Effects ppt
Effects pptEffects ppt
Effects pptgnitu
 
Equilibrium price determination
Equilibrium price determinationEquilibrium price determination
Equilibrium price determinationDebanshu Ghosh
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysisNaveen Sharma
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysisSumit Malhotra
 
Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)tutor2u
 
Long run production and cost theory
Long run production and cost theoryLong run production and cost theory
Long run production and cost theoryboxonomics
 
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES.
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES. INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES.
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES. PRABHJOT KAUR
 

What's hot (20)

Chapter 07 Marginal Costing
Chapter 07   Marginal CostingChapter 07   Marginal Costing
Chapter 07 Marginal Costing
 
Time period - Short Run & Long Run
Time period - Short Run & Long RunTime period - Short Run & Long Run
Time period - Short Run & Long Run
 
Standrad costing
Standrad costingStandrad costing
Standrad costing
 
Elasticity of demand
Elasticity of demandElasticity of demand
Elasticity of demand
 
Demand analysis
Demand analysis Demand analysis
Demand analysis
 
Business cycle
Business cycleBusiness cycle
Business cycle
 
Effects ppt
Effects pptEffects ppt
Effects ppt
 
Standard costing technique 1
Standard costing technique 1Standard costing technique 1
Standard costing technique 1
 
Process costing (1)
Process costing (1)Process costing (1)
Process costing (1)
 
Equilibrium price determination
Equilibrium price determinationEquilibrium price determination
Equilibrium price determination
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysis
 
Standard costs and variance analysis
Standard costs and variance analysisStandard costs and variance analysis
Standard costs and variance analysis
 
Variance Analysis
Variance AnalysisVariance Analysis
Variance Analysis
 
Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)
 
Material accounting part 1
Material accounting part 1Material accounting part 1
Material accounting part 1
 
Inflation measuring
Inflation measuringInflation measuring
Inflation measuring
 
Lec 14 Market Equilibrium
Lec 14 Market EquilibriumLec 14 Market Equilibrium
Lec 14 Market Equilibrium
 
Standard costing PPT
Standard costing PPTStandard costing PPT
Standard costing PPT
 
Long run production and cost theory
Long run production and cost theoryLong run production and cost theory
Long run production and cost theory
 
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES.
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES. INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES.
INFLATION ITS TYPES, CAUSES, CONSEQUENCES AND MEASURES.
 

Similar to Standard-Costing-Variance-Analysis.ppt

Amresh management accounting
Amresh management accountingAmresh management accounting
Amresh management accountingAMRESH VELGEKAR
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variancespankajmaini
 
Akaun Chapter 11
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11WanBK Leo
 
Standard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial AccountingStandard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial AccountingGhous2
 
Standard costing presentation
Standard costing presentationStandard costing presentation
Standard costing presentationJay Singh
 
Acc mgt noreen08 standard costs
Acc mgt noreen08 standard costsAcc mgt noreen08 standard costs
Acc mgt noreen08 standard costsJudianto Nugroho
 
Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02Anqur Rauth
 
Material Ledger Product costing
Material Ledger Product costingMaterial Ledger Product costing
Material Ledger Product costingotchmarz
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures Andafiali
 
Standard Costing
Standard CostingStandard Costing
Standard Costingnarman1402
 
Chapter 08 Standard Costing
Chapter 08   Standard CostingChapter 08   Standard Costing
Chapter 08 Standard Costingayanthimadhumali
 
Budgetory Control System and Cost Control
Budgetory Control System and Cost ControlBudgetory Control System and Cost Control
Budgetory Control System and Cost ControlKishore Raveendran
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptxTeeshaGehaniJagdesh
 

Similar to Standard-Costing-Variance-Analysis.ppt (20)

Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard cost akuntansi biaya
Standard cost akuntansi biayaStandard cost akuntansi biaya
Standard cost akuntansi biaya
 
Amresh management accounting
Amresh management accountingAmresh management accounting
Amresh management accounting
 
management accounting
 management accounting management accounting
management accounting
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variances
 
Akaun Chapter 11
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11
 
Standard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial AccountingStandard Costs Variance Analysis and its impact on Managerial Accounting
Standard Costs Variance Analysis and its impact on Managerial Accounting
 
Standard costing presentation
Standard costing presentationStandard costing presentation
Standard costing presentation
 
Projecto variance
Projecto varianceProjecto variance
Projecto variance
 
Acc mgt noreen08 standard costs
Acc mgt noreen08 standard costsAcc mgt noreen08 standard costs
Acc mgt noreen08 standard costs
 
Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02Advancedcostaccounting 140417192903-phpapp02
Advancedcostaccounting 140417192903-phpapp02
 
3901853 standard-costing
3901853 standard-costing3901853 standard-costing
3901853 standard-costing
 
Material Ledger Product costing
Material Ledger Product costingMaterial Ledger Product costing
Material Ledger Product costing
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Chapter 08 Standard Costing
Chapter 08   Standard CostingChapter 08   Standard Costing
Chapter 08 Standard Costing
 
Budgetory Control System and Cost Control
Budgetory Control System and Cost ControlBudgetory Control System and Cost Control
Budgetory Control System and Cost Control
 
Standard costing
Standard costingStandard costing
Standard costing
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptx
 

Recently uploaded

M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 

Recently uploaded (20)

Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 

Standard-Costing-Variance-Analysis.ppt

  • 2. Definitions • Standard Cost: (CIMA) “Standard cost is the pre- determined cost based on the technical estimates for materials, labour and overhead for a selected period of time for a prescribed set of working conditions.” • Standard Costing: (CIMA) “the preparation of standard costs and applying them to measure the variations from the actual costs and analyzing the causes of variations with a view to maintain maximum efficiency of the operations so that any remedial action may be taken immediately.
  • 3. Variance Analysis • Cost Variance: is the difference between the standard cost and the actual costs. • Variance Analysis: is the resolution into constituent parts and the explanation of the variances.  Favorable & Unfavorable Variances. Controllable & Uncontrollable Variances
  • 4. What all could be the reasons for the actual manufacturing cost or the sales/profit to vary from their standard costs and price/profit?
  • 5. Types of Variances 1. Material Variance Material Cost variance Material Price Variance Material Usage Variance Material Mix Variance Material Yield Variance 2. Labour Variance Labour Cost Variance Labour Rate Variance Labour Efficiency Variance Labour Mix Variance Idle Time Variance 3. Overhead Variance Overhead Cost Variance Variable overheads Var. Variable o/h efficiency var. Variable o/h expenditure var. Fixed overhead variance 4. Other Variances Calendar Variance Sales Value variance Sales price variance Sales volume variance Profit Variance
  • 6. Favorable & Unfavorable Variances • Favorable variances(F) arise when actual costs are less than budgeted costs or actual sales/profit exceed budgeted. • Un favorable variances(U) arise when actual costs exceed budgeted or actual sales/profit are less than budgeted. Profit Revenue Costs Actual > Expected F F U Actual < Expected U U F
  • 7. Standard Costs Benchmarks for measuring performance. The expected level of performance. Based on carefully predetermined amounts. Used for planning labor, material and overhead requirements. Standard Costs are
  • 8. Setting Standard Costs Accountants, engineers, personnel administrators, and production managers combine efforts to set standards based on experience and expectations.
  • 9. Standards vs. Budgets Are standards the same as budgets? A standard is the expected cost for one unit. A budget is the expected cost for all units.
  • 10. The price variance is computed on the entire quantity purchased. The quantity variance is computed only on the quantity used How will the material price variance and material usage be computed if the quantity purchased is different from the quantity used?
  • 11. Material Cost Variance • Material cost variance arises due to variance in the price of material or its usage. • This can be calculated by using the following formula, • Material Cost Variance = (SQ x SP) – (AQ x AP) , • Where, SQ = Standard quantity for the actual output SP = Standard price per unit of material AQ = Actual quantity AP = Actual price per unit of material • A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).
  • 12. Material Price Variance • Material price variance may arise due to number of reasons like fluctuations in market prices, error in buying due to wrong purchasing policy etc, • This can be calculated by using the following formula, • Material Price Variance = (SP – AP) x AQ • Where, SP = Standard price per unit of material AQ = Actual quantity AP = Actual price per unit of material • A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).
  • 13. Material usage Variance • Material Usage variance is the difference between the actual quantities of raw materials used in production and the standard quantities that should have been used to produce the product, • MUV may arise due to number of reasons like Pilferage of materials , Wastage , Sub-standard or defective materials etc, • This can be calculated by using the following formula, • Material Usage Variance = (SQ – AQ) x SP
  • 14. Material Mix Variance • MMV is calculated when a product uses mixture of different raw materials, • MMV is that portion of the materials quantity variance, which is due to the difference between the standard and actual composition of a mixture. • It can be represented by the following formula: Material mix variance = (Standard cost of actual quantity of the standard mixture – Standard cost of actual quantity of the actual mixture) or (Revised SQ – AQ) x SP
  • 15. Practical Problems 1. A furniture company uses sunmica tops for tables. It provides the following data: St. Quantity for sunmica per table 4 sq. ft St. price per sq. ft of sunmica ₱ 5 Actual prod. Of tables 1000 Sunmica actually used 4,300 sq.ft Actual purchase price per sq. ft ₱ 5.50 Calculate Material variances.
  • 16. St. price x St. Quantity 5 x 4000 = 20,000.00 St. price x Actual Quanity 5 x 4300 = 21,500.00 Actual Price x Actual Quanity 5.5 x 4300 = 23,650.00 Material Cost Variance (3,650.00) Material Usage Variance (1,500.00) Material Price Variance (2,150.00) Solution:
  • 17. 2. From the following information calculate (i) material cost variance (ii) material price variance (iii) Material Usage variance Standard output 100 units Standard Material per unit 3 Ibs Standard price per Ib. ₱ 2 Actual output 80 units Actual price ₱ 5.50 Actual materials used 250 Ibs Material Cost Variance 65 Material Usage Variance -60 Material Price Variance 125
  • 18. 3. From the following information calculate (i) material cost variance (ii) material price variance (iii) Material Usage variance Quantity of material purchased 3000 units Value of material purchased ₱ 9000 St. quantity of raw material req. p.u. 25 units Standard rate of material unit ₱ 2 Opening stock of material Nil Closing stock of material 500 units Finished production during the period 80 units
  • 19. St. price x St. Quantity 2 x 2,000 = 4,000 St. price x Actual Quanity 2 x 2,500 = 5,000 Actual Price x Actual Quanity 3 x 2,500 = 7,500 Material Cost Variance (3,500) Material Usage Variance (1,000) Material Price Variance (2,500) Solution:
  • 20. 4. The standard output of the production house has been set at 1000 pieces per month. However actually 1020 pieces were produced. Following is the data for actual and standard production. Standard Actual Results Usage 1.5 sq. ft per pad 1.3 sq. ft per pad Price Rs. 0.15 per sq. ft Rs. 0.18 per sq. ft Calculate all material variances.
  • 21. St. price x St. Quantity 0.15 x 1,530 = 229.50 St. price x Actual Quanity 0.15 x 1,326 = 198.90 Actual Price x Actual Quanity 0.18 x 1,326 = 238.68 Material Cost Variance (9.18) Material Usage Variance 30.60 Material Price Variance (39.78) Solution:
  • 22. 5. A mfg. concern, which has adopted standard costing, furnishes the following information: Standard: Material for 70 kg. Of finished products 100 kgs. Price of materials ₱ 1 per kg. Actual: Output 210,000 kgs Material used 280,000 kgs. Cost of materials ₱ 2,520,000 Calculate all material variances.
  • 23. St. price x St. Quantity 1 x 300,000 = 300,000 St. price x Actual Quanity 1 x 280,000 = 280,000 Actual Price x Actual Quanity 0.9 x 280,000 = 252,000 Material Cost Variance 48,000 Material Usage Variance 20,000 Material Price Variance 28,000 Solution:
  • 24. Material Mix Variance • Material Mix Variance = [Revised St. Qty – Actual Qty] x St. Price Rev. St. Qty = St. Qty of 1 Mat. x Actual Total Standard Total
  • 25. From the following information regarding a standard product, compute 1. Mix 2. Price 3. Usage Variance: Raw Material Standard Actual X 40 units @ Rs. 50 p.u. 50 units @ Rs. 50 p.u. Y 60 units @ Rs. 40 p.u. 60 units @ Rs. 45 p.u. Total 100 units 110 units Rev.ST. Qty St. Price St. Qty Act.Price Act. Qty Revised St. Qty X 40/100 x 110 = units 44 50 40 50 50 Revised St. Qty Y 60/100 x 110 = units 66 40 60 45 60 Material Mix Variance For X -300 For Y 240 -60 MMV Material Usage Variance For X -500 For Y 0 -500 MUV Material Price Variance For X 0
  • 26. From the following information regarding a standard product, compute 1. Mix 2. Price 3. Usage Variance: Material Standard Actual Qty. Rs. p.u. Total Qty Unit Price Total A 4 1.00 4.00 2 3.50 7.00 B 2 2.00 4.00 1 2.00 2.00 C 2 4.00 8.00 3 3.00 9.00 Total 8 7.00 16.00 6.00 8.50 18.00 St. Price St. Qty Act.Price Act. Qty Revised St. Qty A 4/8*6= units 3.00 1.00 4 3.50 2 Revised St. Qty B 2/8*6= units 1.50 2.00 2 2.00 1 Revised St. Qty C 2/8*6= units 1.50 4.00 2 3.00 3 Material Mix Variance For A 1 For B 1 -4 MMV For C -6 Material Usage Variance For A 2 For B 2 0 MUV For C -4 Material Price Variance For A -5 For B 0 -2 MPV For C 3
  • 27. Material variances • Labour Cost Variance SH*SR – AH*AR • Labour Usage/Efficie. Var (SH-AHactual)*SR • Labour Rate Variance (SR-AR)* AH • Idle time Variance SR*Idle time Labour Variances
  • 28. Practice Problem A firm gives you the following data: Standard time per unit 2.5 hours Actual hours worked 2,000 hours Standard rate of pay Rs. 2 per hour 25 % of the actual hours has been lost as idle time. Actual output 1,000 units Actual wages Rs. 4,500 Calculate all labour variances. St. Rate 2 LUV 2000F St. Hrs 2500 LPV -500U Actual Rate 2.25 ITV 1000F Actual Hrs 2000 LCV 500F Idle time 500
  • 29. Practice Problems Compute the Labour variances from the information given below: Standard time 3 hours per unit Standard rate of wages Rs. 6 per hour Actual production 700 units Actual time taken 2000 hours Actual Wages Rs. 14000 Idle time 50 hours St. Rate 6 LUV 900F St. Hrs 2100 LPV -2000U Actual Rate 7 LCV -1400U Actual Hrs 2000 IDV 300 Idle time 50
  • 30. Labor Efficiency Variance- Causes Unfavorable Efficiency Variance Poorly trained workers Poor quality materials Poorly maintained equipment Poor supervision of workers
  • 31. Responsibility for Labor Variances I am not responsible for the unfavorable labor efficiency variance! You purchased cheap material, so it took more time to process it. You used too much time because of poorly trained workers and poor supervision.
  • 32. Overhead Variances • Overhead variances arise due to the difference between actual overheads and absorbed overheads. The estimate of budget of the overheads is to be divided into fixed and variable elements. i.e. 1. Variable overhead variances. – Variable overhead budget or expenditure variance, and – Variable overhead efficiency variance. 2. Fixed overhead variances.
  • 33. Formulas 1. Variable overhead variances. (Standard variable o/hfor actual prodn. – Actual variable o/h) 2. Variable overhead budget or expenditure variance, (Budgeted variable overhead for actual hours – Actual variable overhead) i.e. AH*BR – Actual Cost 3. Variable overhead efficiency variance. Standard variable overhead rate per hour [Std. hours for actual output – Actual hours] i.e. (SH-AH) *SR 4. Fixed Overhead Variance Budgeted FO- AFO
  • 34. Sales Variances • Sales Margin Price Margin = (AP-BP)*AQ • Sales Margin Volume variance = (AQ-BQ)*BC • Total Sales Margin variance = AQ*AC – BQ*BC