1. Introduction
1.1 Purpose
The purpose of this report is to compare the different options of tendering method and
procurement system, and select the best for the project.
1.2 Background
Taylor’s University is a member of the Taylor’s Education Group; it has become one of
Malaysia’s most successful and reputable private higher education institution. The
number of student intake increases as Taylor’s reputation has reached to a certain
recognizable level. The most significant problem which is the shortage of car park arises
as the population of student increases.
1.3 Consideration of this project when making decision
This is a case where a multi-storey car park is needed and Taylor’s University is an
education institution so it needs it to be solved in short period of time. This is so that no
disturbance will be caused and affects the student’s schedule. In the perspective of
consultant firm, it is believed that Taylor’s University has a good financial background
which means the employer can afford to pay for t price of the project. A good pay master
shall provide good financial support and results in faster completion of the project.
2. Procurement System
2.1Procurement
Procurement in construction term has been defined as the activities undertaken by a
client or employer who is seeking to bring about the construction or refurbishment of
a building. These are the main factors that affect which type of procurement method
to be used in this case:
1. Cost of the project
2. Completion of the project
3. Single point responsibility
4. Complexity of the project
5. Quality of work
2.1.1 Traditional Method
The traditional procurement remains the most commonly used method.
The employer will engage with consultants to plan and design the project in detail,
and prepare tender documentation, including drawings, work schedules and bills of
quantities. Contractors are then invited and submit tenders for the construction of the
project. Typically, the employer retains the design consultants during the
construction phase to prepare any additional design information that may be required,
to review any designs that might be prepared by the contractor, and to inspect the
works. Normally, one consultant will be appointed to administer the contract. This
Procurement Method
Traditional Method Design & Build Method
form of procurement is suitable for both experienced and inexperienced employers.
Design is completed before tender gives the employer certainty about design
quality and cost, but it can be slower than other forms of contracting, and as
the contractor is appointed only once the design has been produced, they are not
able to help improve the build-ability and packaging of proposals as they develop. It
is considered to be a low risk method of contracting for the employer, as
the contractor takes the financial risk for construction due to underpriced. On the
other hand, if design information is incomplete at tender, or if
significant variations are required after the contractor has been appointed, the cost to
the employer can be significant. Because of this, and because of the separation
of construction, traditional can be seen as adversarial.
2.1.2 Advantages & Disadvantages
Advantages Disadvantages
- Competitive price can be
obtained
- Takes long time before the
project can start
- Everyone is familiar with this
method
- Slow line of communication
- Price certainty at the award of
the contract
- Employer takes risk if the
contractor underpriced for the
project
- No favoritism is allowed - Lack of single control and
responsibility point
- Flexibility of change before the
letter of award is issued
- Employer’s involvement limited
2.2.1 Design & Build Method
Design and Build procurement works on the basis that the main contractor is responsible
for undertaking both the design and construction work on a project, for an agreed lump-
sum price. Design and build projects can vary depending on the extent of the
contractor’s design responsibility and how much initial design is included in the
employer’s requirements. However, the level of design responsibility and input from the
contractor is much greater on design and build projects than a traditional contract with a
contractor’s designed portion. Sufficient time must be allowed to prepare the employer’s
requirements where the employer usually appoints consultants to facilitate this, as well
as time for the contractor to prepare their proposal and tender price. It is vital that the
proposal matches all of the employer’s requirements before any contract is entered into.
The employer has control over any design elements of the project that are included in
their requirements, but once the contract is let responsibility over design passes to the
contractor, so the employer has no direct control over the contractor’s detailed design.
The contractor can carry out the design in a number of ways. Often they will appoint their
own consultants or use their own in-house team. It is also common practice for the
contractor to take on the employer's consultants and continue to use them to complete
the detailed design under what is known as a ‘novation’ agreement.
2.2.2 Advantages & Disadvantages
Advantages Disadvantages
- High quality of work - High initial price
- Faster completion of the project - The owner does not benefit
from independent advice and
input from the
architect/engineer and
contractor
- Single-point responsibility - The project price is determined
after the whole construction has
been done
- Employer is not liable for any
error the design team made
- Uncertainty in commencement
of work as design approval is
pending
- Reduce administrative burden
for employer
- Loss of control and reduce
employer involvement in design
2.2Recommendation
Aspects Traditional Method Design & Build Method
Completion of
project
- Takes longer time to
construct due to the time
for design to complete
- Design and construction
can be carried out
concurrently
Cost of entire
project
- Cheaper compared to
Design & Build method
- Higher price because there
is different design with
different price
Responsibility
point
- Multiple-point of
responsibility
- Single-point responsibility
Suitability for
inexperienced
employer
- Yes - Yes
Control of
design
- Design is flexible since
employer has control
over design team
- Design is decided by
contractor on behalf of
employer as long it meets
the Employer’s
Requirement
Reasoning:
The construction of this project is more likely to solve the problem of Taylor’s users have
encountered, it is strongly recommended to have fast completion of project. By
comparing the cost that these 2 different methods may incurred on employer, the Design
& Build method is definitely higher since the contractors will produce different designs
based on Employer’s Requirement, whereas the traditional method is the employer has
to engage with all consultants and produce the complete design before tendering
process. The tenderer with lowest price usually gets selected for the job but it also
carries the risk of underpriced. Under the circumstances, the design will not matter much
as long as it serves the purpose to reduce the problem of shortage of car park. Taylor’s
organization is also known as the inexperienced employer, it is good to have single-point
responsibility so that it is obvious the responsibility lies on the main contractor if any
issue arises. The reasons provided above enable to determine that design and build
method is more preferable to use in this case.
3. Tendering Method
3.1.1 Open tender method
Open tender method
Tendering Methods
Open Tender Method Selective Method
Direct Negotiation
Method

More Related Content

What's hot

Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
tfkc1212
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
Pang Khai Shuen
 

What's hot (20)

Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Pp report
Pp reportPp report
Pp report
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpm
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Final pp1
Final pp1Final pp1
Final pp1
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Procurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remediesProcurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remedies
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public owner
 

Similar to p1p

Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
Lilian Nwachukwu
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
ashleyyeap
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
마 이환
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
ahmong4
 

Similar to p1p (20)

Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
[Report] Who's protecting your blindside? Construction Management: Protectin...
[Report] Who's protecting your blindside?  Construction Management: Protectin...[Report] Who's protecting your blindside?  Construction Management: Protectin...
[Report] Who's protecting your blindside? Construction Management: Protectin...
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Contracts 2
Contracts 2Contracts 2
Contracts 2
 
Pick the Best Engagement Model for Software Startup development
Pick the Best Engagement Model for Software Startup developmentPick the Best Engagement Model for Software Startup development
Pick the Best Engagement Model for Software Startup development
 
QA interview at Peakglobal Central kalimantan .pptx
QA interview at Peakglobal Central kalimantan .pptxQA interview at Peakglobal Central kalimantan .pptx
QA interview at Peakglobal Central kalimantan .pptx
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery models
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 

Recently uploaded

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Recently uploaded (20)

Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 

p1p

  • 1. 1. Introduction 1.1 Purpose The purpose of this report is to compare the different options of tendering method and procurement system, and select the best for the project. 1.2 Background Taylor’s University is a member of the Taylor’s Education Group; it has become one of Malaysia’s most successful and reputable private higher education institution. The number of student intake increases as Taylor’s reputation has reached to a certain recognizable level. The most significant problem which is the shortage of car park arises as the population of student increases. 1.3 Consideration of this project when making decision This is a case where a multi-storey car park is needed and Taylor’s University is an education institution so it needs it to be solved in short period of time. This is so that no disturbance will be caused and affects the student’s schedule. In the perspective of consultant firm, it is believed that Taylor’s University has a good financial background which means the employer can afford to pay for t price of the project. A good pay master shall provide good financial support and results in faster completion of the project.
  • 2. 2. Procurement System 2.1Procurement Procurement in construction term has been defined as the activities undertaken by a client or employer who is seeking to bring about the construction or refurbishment of a building. These are the main factors that affect which type of procurement method to be used in this case: 1. Cost of the project 2. Completion of the project 3. Single point responsibility 4. Complexity of the project 5. Quality of work 2.1.1 Traditional Method The traditional procurement remains the most commonly used method. The employer will engage with consultants to plan and design the project in detail, and prepare tender documentation, including drawings, work schedules and bills of quantities. Contractors are then invited and submit tenders for the construction of the project. Typically, the employer retains the design consultants during the construction phase to prepare any additional design information that may be required, to review any designs that might be prepared by the contractor, and to inspect the works. Normally, one consultant will be appointed to administer the contract. This Procurement Method Traditional Method Design & Build Method
  • 3. form of procurement is suitable for both experienced and inexperienced employers. Design is completed before tender gives the employer certainty about design quality and cost, but it can be slower than other forms of contracting, and as the contractor is appointed only once the design has been produced, they are not able to help improve the build-ability and packaging of proposals as they develop. It is considered to be a low risk method of contracting for the employer, as the contractor takes the financial risk for construction due to underpriced. On the other hand, if design information is incomplete at tender, or if significant variations are required after the contractor has been appointed, the cost to the employer can be significant. Because of this, and because of the separation of construction, traditional can be seen as adversarial. 2.1.2 Advantages & Disadvantages Advantages Disadvantages - Competitive price can be obtained - Takes long time before the project can start - Everyone is familiar with this method - Slow line of communication - Price certainty at the award of the contract - Employer takes risk if the contractor underpriced for the project - No favoritism is allowed - Lack of single control and responsibility point - Flexibility of change before the letter of award is issued - Employer’s involvement limited
  • 4. 2.2.1 Design & Build Method Design and Build procurement works on the basis that the main contractor is responsible for undertaking both the design and construction work on a project, for an agreed lump- sum price. Design and build projects can vary depending on the extent of the contractor’s design responsibility and how much initial design is included in the employer’s requirements. However, the level of design responsibility and input from the contractor is much greater on design and build projects than a traditional contract with a contractor’s designed portion. Sufficient time must be allowed to prepare the employer’s requirements where the employer usually appoints consultants to facilitate this, as well as time for the contractor to prepare their proposal and tender price. It is vital that the proposal matches all of the employer’s requirements before any contract is entered into. The employer has control over any design elements of the project that are included in their requirements, but once the contract is let responsibility over design passes to the contractor, so the employer has no direct control over the contractor’s detailed design. The contractor can carry out the design in a number of ways. Often they will appoint their own consultants or use their own in-house team. It is also common practice for the contractor to take on the employer's consultants and continue to use them to complete the detailed design under what is known as a ‘novation’ agreement. 2.2.2 Advantages & Disadvantages Advantages Disadvantages - High quality of work - High initial price - Faster completion of the project - The owner does not benefit from independent advice and input from the architect/engineer and contractor - Single-point responsibility - The project price is determined after the whole construction has been done - Employer is not liable for any error the design team made - Uncertainty in commencement of work as design approval is pending - Reduce administrative burden for employer - Loss of control and reduce employer involvement in design
  • 5. 2.2Recommendation Aspects Traditional Method Design & Build Method Completion of project - Takes longer time to construct due to the time for design to complete - Design and construction can be carried out concurrently Cost of entire project - Cheaper compared to Design & Build method - Higher price because there is different design with different price Responsibility point - Multiple-point of responsibility - Single-point responsibility Suitability for inexperienced employer - Yes - Yes Control of design - Design is flexible since employer has control over design team - Design is decided by contractor on behalf of employer as long it meets the Employer’s Requirement Reasoning: The construction of this project is more likely to solve the problem of Taylor’s users have encountered, it is strongly recommended to have fast completion of project. By comparing the cost that these 2 different methods may incurred on employer, the Design & Build method is definitely higher since the contractors will produce different designs based on Employer’s Requirement, whereas the traditional method is the employer has to engage with all consultants and produce the complete design before tendering process. The tenderer with lowest price usually gets selected for the job but it also carries the risk of underpriced. Under the circumstances, the design will not matter much as long as it serves the purpose to reduce the problem of shortage of car park. Taylor’s organization is also known as the inexperienced employer, it is good to have single-point responsibility so that it is obvious the responsibility lies on the main contractor if any issue arises. The reasons provided above enable to determine that design and build method is more preferable to use in this case.
  • 7. 3.1.1 Open tender method Open tender method Tendering Methods Open Tender Method Selective Method Direct Negotiation Method