Topic 12 - Project Cost Management.pdf

Project Cost Management
Dr. Huy Nguyen
Project Management Framework
2
Process Groups & Knowledge Areas Mapping
Knowledge
Areas
Process Groups
Initiating Planning Executing Monitoring & Controlling Closing
Integration
Develop Project
Charter
Develop Project Management Plan
Direct and Manage Project Work
Manage Project Knowledge
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope
Schedule
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule
Control Schedule
Cost
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Management Manage Quality Control Quality
Resource
Plan Resource Management
Estimate Activity Resources
Acquire Resources
Develop Team
Manage Team
Control Resources
Communications Plan Communications Management Manage Communications Monitor Communications
Risk
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Implement Risk Responses Monitor Risks
Procurement Plan Procurement Management Conduct Procurements Control Procurements
Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
3
Project Cost Management
Knowledge
Area
Process Groups
Initiating Planning Executing
Monitoring &
Controlling
Closing
Cost
• Plan Cost
Management
• Estimate Costs
• Determine Budget
• Control Costs
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
4
Project Cost Management
• The process involved in planning, estimating, budgeting, financing, funding,
managing and controlling cost so that the project can be completed within
approved budget.
• Life cycle costing:
– Looking at the cost of whole life of the product (include maintenance).
• Value analysis (value engineering):
– Looking at less costly way to do the same work within the same scope.
• Law of Diminishing Returns:
– E.g. adding twice resource to task may not get the task done in half cost /
time.
• Time value of money (depreciation);
• Cost will also affect the schedule;
• Cost risk vs. Type of contract.
5
1 - Plan Cost Management
• Process of establishing the policies, procedures, and documentation for
planning, managing, expending, and controlling project costs:
– Cost trade-offs & risk must be considered;
– Cost estimates should be refined.
Inputs
1. Project management
plan
2. Project charter
3. Enterprise
environmental factors
4. Organizational
process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Cost management
plan
6
1 - Plan Cost Management
7
Cost Management Plan (Outputs)
• Units of measure;
• Level of precision;
• Level of accuracy;
• Organizational procedures links;
• Control thresholds;
• Rules of performance measurement (EVM);
• Reporting formats;
• Process descriptions;
• Additional details:
– Description of strategic funding choices;
– Procedure to account for fluctuations in currency exchange rates;
– Procedure for project cost recording.
8
2 - Estimate Costs
• Process of developing an approximation of the monetary resources needed to
complete project activities.
Inputs
1. Cost management
plan
2. Human resource
management plan
3. Scope baseline
4. Project schedule
5. Risk register
6. Enterprise
environmental factors
7. Organizational
process assets
Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimates
6. Reserve analysis
7. Cost of quality
8. Project management
software
9. Vendor bid analysis
10.Group decision-making
techniques
Outputs
1. Activity cost
estimates
2. Basis of estimates
3. Project documents
updates
9
2 - Estimate Costs
10
Types of Cost
• Variable Costs:
– Change with the amount of production / work;
– E.g. material, supplies, wages.
• Fixed Costs:
– Do not change as production change;
– E.g. set-up, rental.
• Direct Costs:
– Directly attributable to the work of project;
– E.g. team travel, recognition, team wages.
• Indirect Costs:
– Overhead or cost incurred for benefit of more than one project;
– E.g. taxes, fringe benefit, janitorial services.
11
• Most difficult to estimate as very little project info is
available, made during initiating process.
Estimate Accuracy
Rough Order of
Magnitude
(ROM)
+/- 50%
Budget
Estimate
- 10%
+ 25%
Definitive
Estimate
- 5%
+ 10%
• Used to finalize the Request for Authorization (RFA), and
establish commitment, made during planning phase.
• During the project and refined.
Quality / Accuracy of Cost Estimation
12
3 - Determine Budget
• Process of aggregating the estimated cost of individual activities or work
packages to establish an authorized cost baseline.
Inputs
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates
5. Project schedule
6. Resource calendars
7. Risk register
8. Agreements
9. Organizational process
assets
Tools & Techniques
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationship
5. Funding limit
reconciliation
Outputs
1. Cost performance
baseline
2. Project funding
requirements
3. Project documents
updates
13
3 - Determine Budget
14
Cost Aggregation
• Reserves & risk management are important while
estimating:
– Contingency reserves: The cost impacts of the
remaining risk;
 Cost baseline
– Management reserves: Extra fund to cover
unforeseen risk or changes to the project;
 Cost budget
Activity estimates
Work package estimates
Control account estimates
Project estimates
Contingency reserves
Management reserves
Cost baseline
Cost budget
15
Determines Budget: Other Considerations
• High level parametric estimate as a rule of thumb:
– E.g. testing cost 50% of development cost;
• Funding limit reconciliation = checking cash flow:
– When the money will be available?
• Reconciliation needed before proposed cost baseline and cost budget become
final:
– Such reconciliation is part of integration management.
16
4 - Control Costs
• Process of monitoring the status of the project to update the project cost and
managing changes to the cost baseline.
Inputs
1. Project management
plan
2. Project funding
requirements
3. Work performance
data
4. Organizational
process assets
Tools & Techniques
1. Earned value
management
2. Forecasting
3. To-complete
performance index
4. Performance reviews
5. Project management
software
6. Reserve analysis
Outputs
1. Work performance
information
2. Cost forecast
3. Change requests
4. Project management
plan updates
5. Project documents
updates
6. Organizational
process updates
17
4 - Control Costs
18
How to Control Cost?
• Follow the cost management plan;
• Look at any organizational process asset that are available;
• Manage change:
– Recording all appropriate change;
– Preventing incorrect change;
– Ensuring requested changes are agreed upon;
– Managing the actual changes when and as they occur.
• Measure and measure and measure (monitoring).
19
Progress Report
• Progress / performance report (output from communication area):
– Where work cannot be measured, estimate could be done by a guess;
• Percent complete:
– 50 / 50 Rule;
– 20 / 80 Rule;
– 0 / 100 Rule;
– Activity is considered X percent complete when it begins and get credit for
the last Y percent only when it is complete.
20
Earned Value Management (Tools & Techniques)
• Method to measure project performance and progress against scope,
schedule and cost baseline (performance measurement baseline).
• Interpretation of basic EVM performance measures:
– Cost Performance Index (CPI);
– Schedule Performance Index (SPI).
21
Earned Value Management (cont.)
EV can be calculated by
(% progress) x (planned man-days)
22
Earned Value Technique
Terms and Formulas Definition Example
Earned Value (EV)
As of today, what is the estimated value of the
work actually accomplished?
$100K
Actual Cost (AC)
As of today, what is the actual cost incurred for
the work accomplished?
$200K
Planned Value (PV)
As of today, what is the estimated value of work
planned to be done?
$300K
Cost Variance (CV)
= EV - AC
Negative is over budget.
Positive is under budget.
$100K - $200K
= ($100K)
Schedule Variance (SV)
= EV - PV
Negative is behind schedule.
Positive is ahead schedule.
$100K - $300K
= ($200K)
Cost Performance Index
(CPI) = EV / AC
We are getting $__ worth of work out of every $1
spent. Are funds being used efficiently?
$100K / $200K
= 0.5 i.e. 50%
Schedule Performance
Index (SPI) = EV / PV
We are (only) progressing at __ percent of the
rate originally planed.
$100K / $300K
= 0.33 i.e. 33%
Revised Total Duration Baseline Duration / Schedule Performance Index
4 / 0.33
= 12 months
Example:
Project Budget: $400K
Project Schedule: 4 months
At the 3 month checkpoint:
Spent: $200K
Work completed: $100K
23
Earned Value Technique (cont.)
Terms and Formulas Definition
Budget at completion (BAC) How much did we BUDGET for the TOTAL project effort?
Estimate at Completion (EAC)
= BAC / CPI
What do we currently expect the TOTAL project cost (a
forecast)?
Estimate to Complete (ETC)
= EAC - AC
From this point on, how much MORE do we expect it to cost to
finish the project (a forecast)?
Variance at Completion (VAC)
= BAC - EAC
As of today, how much over or under budget do we expect to
be at the end of the project?
• EAC is an important forecasting value.
24
Earned Value: Graphical Representation
TIME
COST
Schedule
Variance
(SV)
Cost
Variance
(CV)
ACTUAL
PLAN
EARN VALUE
Estimate at
Completion
(EAC)
Budget at
Completion
(BAC)
Projection of
schedule delay
at completion
Projection of cost
variance at
completion (VAC)
TODAY
(Reporting day)
BAC
EAC
AC
EV
PV
• Project is over budget & behind schedule:
25
Exercise
Task Progress Cost spent
Side 1 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100% $1,200
Side 2 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100% $1,000
Side 3 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||75% $750
Side 4 |||||||||||||||||||||||||||||||||||||||50% $500
Side 5 |0% $0
Side 6 |0% $0
• You have a project to build a box. The box is six sided. Each side is to take
one day to build and is budgeted for $1000 per side. The sides are planned to
be completed one after the other. Today is the end of day three.
• Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI,
SV, SPI, EAC, ETC, VAC.
• Describe your interpretation based on the calculation.
26
Exercise Solution
Parameter Calculation Result
PV
EV
AC
BAC
CV
CPI
SV
SPI
EAC
ETC
VAC
• Project is below / over budget?
• Project is late / ahead schedule?
• How much more money we need?
27
Exercise Solution
Parameter Calculation Result
PV 1000 + 1000 + 1000 3000
EV (100% x 1000) + (100% x 1000) + (75% x 1000) + (50% x 1000) 3250
AC 1200 + 1000 + 750 + 500 3450
BAC 6 x 1000 6000
CV 3250 - 3450 -200
CPI 3250 / 3450 0.94
SV 3250 - 3000 250
SPI 3250 / 3000 1.08
EAC 6000 / 0.94 6383
ETC 6383 - 3450 2933
VAC 6000 - 6383 -383
• Over budget, getting 0.94 dollar for every dollar we spent;
• Ahead schedule, progressing 108% of the rate planned;
• Probably will spend $6383 at the end (estimation), need $2933 to complete,
over budget at the end for about $383 (estimation)
28
Forecasting EAC
• There are many ways to calculate EAC, depending on the assumption made.
• Simple EAC calculation (EAC = BAC / CPI) assume that the cumulative CPI
adequately reflects past performance that will continue to the end of the project.
• EAC = AC + BAC - EV:
– Used when current variances are thought to be atypical of the future.
• EAC = AC + [(BAC - EV) / (Cumulative CPI x Cumulative SPI)]:
– It assumes poor cost performance and need to hit a firm completion date.
29
Forecasting EAC (cont.)
• Common alternative ways to calculate EAC:
Assumption Example Formula
Future cost performance will be the same as all
past cost performance
EAC = AC + [(BAC - EV) / CPI] = BAC / CPI
Future cost performance will be the same as the
last three measurement periods (i, j, k)
EAC = AC + [(BAC - EV) / ((EVi + EVj + EVk) / (ACi
+ ACj + ACk))]
Future cost performance will be influenced
additionally by past schedule performance
EAC = AC + [(BAC - EV) / (CPI x SPI)]
Future cost performance will be influenced jointly
in some proportion by both indices
EAC = AC + [(BAC - EV) / (0.8 CPI + 0.2 SPI)]
30
To-Complete Performance Index (TCPI)
• Helps the team determine the efficiency that must be achieved on the
remaining work for a project to meet a specified endpoint, such as BAC or the
team’s revised EAC.
• TCPI
AC)
-
(EAC
or
AC)
-
(BAC
Remaining
Funds
EV)
-
(BAC
Remaining
Work

31
Earned Schedule - An emerging EVM practice
• SPI ($):
– At project start SPI is reliable;
– At some point SPI accuracy diminishes;
– Toward the project end it is useless (SPI = 1 at project end);
– Does not show weeks / months of schedule variance.
• SPI (t):
– Time based schedule measures;
– Create a SPI that is accurate to the of the project:
• SV (t) = ES - AT;
• SPI (t) = ES / AT.
• ES = Earned Schedule (Planned time);
• AT = Actual time.
32
EVM - Hints to remember
• EV comes first in every formula;
• If it’s variance, the formula is EV - something;
• If it’s index, the formula is EV / something;
• If it relates to cost, use AC;
• If it relates to schedule, use PV;
• Negative number is bad, positive is good;
• If it’s index, smaller than 1 is bad, bigger than 1 is good.
33
Thank You
Next topic:
Project Resource Management
34
1 von 34

Recomendados

cost Management V4 von
cost Management V4cost Management V4
cost Management V4Qussay Karam
52 views100 Folien
PMP-Cost Management area von
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management areaZaur Ahmadov, PMP
120 views34 Folien
07 project cost management von
07 project cost management07 project cost management
07 project cost managementOmer Alsayed PhD,MBA, PMP®
10.1K views50 Folien
07 projectcostmanagement von
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
504 views27 Folien
Session 22 4th edition PMP von
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMPمحمد عصمت عبد الرازق
1.1K views26 Folien
Project managment 6 von
Project managment 6Project managment 6
Project managment 6Абдулазіз Мухаммед
883 views16 Folien

Más contenido relacionado

Similar a Topic 12 - Project Cost Management.pdf

Pmp – pmbok 5th edition chapter7 project cost management von
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
28.5K views25 Folien
Session 21 4th edition PMP von
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMPمحمد عصمت عبد الرازق
855 views22 Folien
Project Cost Management - PMBOK6 von
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
12.3K views39 Folien
Managing the Consulting Engagement von
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
46.7K views33 Folien
Projectmanagement 130721095616-phpapp01 von
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
376 views43 Folien
7 cost managmenet von
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
131 views49 Folien

Similar a Topic 12 - Project Cost Management.pdf(20)

Pmp – pmbok 5th edition chapter7 project cost management von Yudha Pratama, PMP
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
Yudha Pratama, PMP28.5K views
Project Cost Management - PMBOK6 von Agus Suhanto
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto12.3K views
Managing the Consulting Engagement von Saumya Ganguly
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
Saumya Ganguly46.7K views
Projectmanagement 130721095616-phpapp01 von samansari22
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22376 views
04 projectintegrationmanagement von Dhamo daran
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
Dhamo daran218 views
7.0 Project Cost Management Overview von DavidMcLachlan1
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
DavidMcLachlan1114 views
Project Execution and Project management (GT IV batch) 2.pptx von bhanu852126
Project Execution and Project management (GT IV batch) 2.pptxProject Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptx
bhanu8521269 views
A brief on project cost management von Imran Jamil
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil2.2K views
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area von GlobalSkillup
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
GlobalSkillup1K views
Monitor and control process group part two von Hossam Maghrabi
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
Hossam Maghrabi2.3K views
Project life cycle_management by Subbu von TechGigDotCom
Project life cycle_management by SubbuProject life cycle_management by Subbu
Project life cycle_management by Subbu
TechGigDotCom2K views
Melbourne streamlining earned value with hd published von InSync Conference
Melbourne streamlining earned value with hd publishedMelbourne streamlining earned value with hd published
Melbourne streamlining earned value with hd published
InSync Conference275 views
ادارة تكلفة المشروع von Mohamed Dahi
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
Mohamed Dahi7.1K views

Más de HuyNguyen657394

Topic 15 - Leadership in Project Management.pdf von
Topic 15 - Leadership in Project Management.pdfTopic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdfHuyNguyen657394
26 views35 Folien
Topic 14 - Project Team Management.pdf von
Topic 14 - Project Team Management.pdfTopic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdfHuyNguyen657394
101 views35 Folien
Tips - IT Project Management.pdf von
Tips - IT Project Management.pdfTips - IT Project Management.pdf
Tips - IT Project Management.pdfHuyNguyen657394
4 views16 Folien
Topic 13 - Project Resource Management.pdf von
Topic 13 - Project Resource Management.pdfTopic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdfHuyNguyen657394
18 views40 Folien
Topic 11 - Project Schedule Management.pdf von
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
8 views41 Folien
Topic 10 - Project Performance Management.pdf von
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
4 views23 Folien

Más de HuyNguyen657394(18)

Topic 15 - Leadership in Project Management.pdf von HuyNguyen657394
Topic 15 - Leadership in Project Management.pdfTopic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdf
HuyNguyen65739426 views
Topic 14 - Project Team Management.pdf von HuyNguyen657394
Topic 14 - Project Team Management.pdfTopic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdf
HuyNguyen657394101 views
Topic 13 - Project Resource Management.pdf von HuyNguyen657394
Topic 13 - Project Resource Management.pdfTopic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdf
HuyNguyen65739418 views
Topic 11 - Project Schedule Management.pdf von HuyNguyen657394
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
HuyNguyen6573948 views
Topic 10 - Project Performance Management.pdf von HuyNguyen657394
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
HuyNguyen6573944 views
Topic 9 - Project Stakeholder Management.pdf von HuyNguyen657394
Topic 9 - Project Stakeholder Management.pdfTopic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdf
HuyNguyen65739418 views
Topic 8 - Project Quality Management.pdf von HuyNguyen657394
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
HuyNguyen6573945 views
Topic 7 - Project Scope Management.pdf von HuyNguyen657394
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
HuyNguyen65739451 views
Topic 6 - Project Integration Management.pdf von HuyNguyen657394
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
HuyNguyen65739433 views
Topic 4 - Project Management Process.pdf von HuyNguyen657394
Topic 4 - Project Management Process.pdfTopic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdf
HuyNguyen65739413 views
Topic 3 - Project Selection & Portfolio Management.pdf von HuyNguyen657394
Topic 3 - Project Selection & Portfolio Management.pdfTopic 3 - Project Selection & Portfolio Management.pdf
Topic 3 - Project Selection & Portfolio Management.pdf
HuyNguyen65739427 views
Topic 2 - Project Life Cycle and Project Management Organization.pdf von HuyNguyen657394
Topic 2 - Project Life Cycle and Project Management Organization.pdfTopic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdf
HuyNguyen6573948 views
Topic 1 - Introduction of Project Management.pdf von HuyNguyen657394
Topic 1 - Introduction of Project Management.pdfTopic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdf
HuyNguyen65739418 views

Último

SWM L1-L14_drhasan (Part 1).pdf von
SWM L1-L14_drhasan (Part 1).pdfSWM L1-L14_drhasan (Part 1).pdf
SWM L1-L14_drhasan (Part 1).pdfMahmudHasan747870
48 views150 Folien
Dynamics of Hard-Magnetic Soft Materials von
Dynamics of Hard-Magnetic Soft MaterialsDynamics of Hard-Magnetic Soft Materials
Dynamics of Hard-Magnetic Soft MaterialsShivendra Nandan
14 views32 Folien
NEW SUPPLIERS SUPPLIES (copie).pdf von
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdfgeorgesradjou
14 views30 Folien
Update 42 models(Diode/General ) in SPICE PARK(DEC2023) von
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Tsuyoshi Horigome
23 views16 Folien
fakenews_DBDA_Mar23.pptx von
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptxdeepmitra8
12 views34 Folien
What is Unit Testing von
What is Unit TestingWhat is Unit Testing
What is Unit TestingSadaaki Emura
23 views25 Folien

Último(20)

NEW SUPPLIERS SUPPLIES (copie).pdf von georgesradjou
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdf
georgesradjou14 views
Update 42 models(Diode/General ) in SPICE PARK(DEC2023) von Tsuyoshi Horigome
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
Update 42 models(Diode/General ) in SPICE PARK(DEC2023)
fakenews_DBDA_Mar23.pptx von deepmitra8
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptx
deepmitra812 views
Design of machine elements-UNIT 3.pptx von gopinathcreddy
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptx
gopinathcreddy29 views
MSA Website Slideshow (16).pdf von msaucla
MSA Website Slideshow (16).pdfMSA Website Slideshow (16).pdf
MSA Website Slideshow (16).pdf
msaucla58 views
Machine Element II Course outline.pdf von odatadese1
Machine Element II Course outline.pdfMachine Element II Course outline.pdf
Machine Element II Course outline.pdf
odatadese18 views
STUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptx von AnnieRachelJohn
STUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptxSTUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptx
STUDY OF SMART MATERIALS USED IN CONSTRUCTION-1.pptx
AnnieRachelJohn33 views
An approach of ontology and knowledge base for railway maintenance von IJECEIAES
An approach of ontology and knowledge base for railway maintenanceAn approach of ontology and knowledge base for railway maintenance
An approach of ontology and knowledge base for railway maintenance
IJECEIAES12 views

Topic 12 - Project Cost Management.pdf

  • 3. Process Groups & Knowledge Areas Mapping Knowledge Areas Process Groups Initiating Planning Executing Monitoring & Controlling Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase Scope Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope Schedule Plan Schedule Management Define Activities Sequence Activities Estimate Activity Durations Develop Schedule Control Schedule Cost Plan Cost Management Estimate Costs Determine Budget Control Costs Quality Plan Quality Management Manage Quality Control Quality Resource Plan Resource Management Estimate Activity Resources Acquire Resources Develop Team Manage Team Control Resources Communications Plan Communications Management Manage Communications Monitor Communications Risk Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Implement Risk Responses Monitor Risks Procurement Plan Procurement Management Conduct Procurements Control Procurements Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement 3
  • 4. Project Cost Management Knowledge Area Process Groups Initiating Planning Executing Monitoring & Controlling Closing Cost • Plan Cost Management • Estimate Costs • Determine Budget • Control Costs Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes 4
  • 5. Project Cost Management • The process involved in planning, estimating, budgeting, financing, funding, managing and controlling cost so that the project can be completed within approved budget. • Life cycle costing: – Looking at the cost of whole life of the product (include maintenance). • Value analysis (value engineering): – Looking at less costly way to do the same work within the same scope. • Law of Diminishing Returns: – E.g. adding twice resource to task may not get the task done in half cost / time. • Time value of money (depreciation); • Cost will also affect the schedule; • Cost risk vs. Type of contract. 5
  • 6. 1 - Plan Cost Management • Process of establishing the policies, procedures, and documentation for planning, managing, expending, and controlling project costs: – Cost trade-offs & risk must be considered; – Cost estimates should be refined. Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs 1. Cost management plan 6
  • 7. 1 - Plan Cost Management 7
  • 8. Cost Management Plan (Outputs) • Units of measure; • Level of precision; • Level of accuracy; • Organizational procedures links; • Control thresholds; • Rules of performance measurement (EVM); • Reporting formats; • Process descriptions; • Additional details: – Description of strategic funding choices; – Procedure to account for fluctuations in currency exchange rates; – Procedure for project cost recording. 8
  • 9. 2 - Estimate Costs • Process of developing an approximation of the monetary resources needed to complete project activities. Inputs 1. Cost management plan 2. Human resource management plan 3. Scope baseline 4. Project schedule 5. Risk register 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analogous estimating 3. Parametric estimating 4. Bottom-up estimating 5. Three-point estimates 6. Reserve analysis 7. Cost of quality 8. Project management software 9. Vendor bid analysis 10.Group decision-making techniques Outputs 1. Activity cost estimates 2. Basis of estimates 3. Project documents updates 9
  • 10. 2 - Estimate Costs 10
  • 11. Types of Cost • Variable Costs: – Change with the amount of production / work; – E.g. material, supplies, wages. • Fixed Costs: – Do not change as production change; – E.g. set-up, rental. • Direct Costs: – Directly attributable to the work of project; – E.g. team travel, recognition, team wages. • Indirect Costs: – Overhead or cost incurred for benefit of more than one project; – E.g. taxes, fringe benefit, janitorial services. 11
  • 12. • Most difficult to estimate as very little project info is available, made during initiating process. Estimate Accuracy Rough Order of Magnitude (ROM) +/- 50% Budget Estimate - 10% + 25% Definitive Estimate - 5% + 10% • Used to finalize the Request for Authorization (RFA), and establish commitment, made during planning phase. • During the project and refined. Quality / Accuracy of Cost Estimation 12
  • 13. 3 - Determine Budget • Process of aggregating the estimated cost of individual activities or work packages to establish an authorized cost baseline. Inputs 1. Cost management plan 2. Scope baseline 3. Activity cost estimates 4. Basis of estimates 5. Project schedule 6. Resource calendars 7. Risk register 8. Agreements 9. Organizational process assets Tools & Techniques 1. Cost aggregation 2. Reserve analysis 3. Expert judgment 4. Historical relationship 5. Funding limit reconciliation Outputs 1. Cost performance baseline 2. Project funding requirements 3. Project documents updates 13
  • 14. 3 - Determine Budget 14
  • 15. Cost Aggregation • Reserves & risk management are important while estimating: – Contingency reserves: The cost impacts of the remaining risk;  Cost baseline – Management reserves: Extra fund to cover unforeseen risk or changes to the project;  Cost budget Activity estimates Work package estimates Control account estimates Project estimates Contingency reserves Management reserves Cost baseline Cost budget 15
  • 16. Determines Budget: Other Considerations • High level parametric estimate as a rule of thumb: – E.g. testing cost 50% of development cost; • Funding limit reconciliation = checking cash flow: – When the money will be available? • Reconciliation needed before proposed cost baseline and cost budget become final: – Such reconciliation is part of integration management. 16
  • 17. 4 - Control Costs • Process of monitoring the status of the project to update the project cost and managing changes to the cost baseline. Inputs 1. Project management plan 2. Project funding requirements 3. Work performance data 4. Organizational process assets Tools & Techniques 1. Earned value management 2. Forecasting 3. To-complete performance index 4. Performance reviews 5. Project management software 6. Reserve analysis Outputs 1. Work performance information 2. Cost forecast 3. Change requests 4. Project management plan updates 5. Project documents updates 6. Organizational process updates 17
  • 18. 4 - Control Costs 18
  • 19. How to Control Cost? • Follow the cost management plan; • Look at any organizational process asset that are available; • Manage change: – Recording all appropriate change; – Preventing incorrect change; – Ensuring requested changes are agreed upon; – Managing the actual changes when and as they occur. • Measure and measure and measure (monitoring). 19
  • 20. Progress Report • Progress / performance report (output from communication area): – Where work cannot be measured, estimate could be done by a guess; • Percent complete: – 50 / 50 Rule; – 20 / 80 Rule; – 0 / 100 Rule; – Activity is considered X percent complete when it begins and get credit for the last Y percent only when it is complete. 20
  • 21. Earned Value Management (Tools & Techniques) • Method to measure project performance and progress against scope, schedule and cost baseline (performance measurement baseline). • Interpretation of basic EVM performance measures: – Cost Performance Index (CPI); – Schedule Performance Index (SPI). 21
  • 22. Earned Value Management (cont.) EV can be calculated by (% progress) x (planned man-days) 22
  • 23. Earned Value Technique Terms and Formulas Definition Example Earned Value (EV) As of today, what is the estimated value of the work actually accomplished? $100K Actual Cost (AC) As of today, what is the actual cost incurred for the work accomplished? $200K Planned Value (PV) As of today, what is the estimated value of work planned to be done? $300K Cost Variance (CV) = EV - AC Negative is over budget. Positive is under budget. $100K - $200K = ($100K) Schedule Variance (SV) = EV - PV Negative is behind schedule. Positive is ahead schedule. $100K - $300K = ($200K) Cost Performance Index (CPI) = EV / AC We are getting $__ worth of work out of every $1 spent. Are funds being used efficiently? $100K / $200K = 0.5 i.e. 50% Schedule Performance Index (SPI) = EV / PV We are (only) progressing at __ percent of the rate originally planed. $100K / $300K = 0.33 i.e. 33% Revised Total Duration Baseline Duration / Schedule Performance Index 4 / 0.33 = 12 months Example: Project Budget: $400K Project Schedule: 4 months At the 3 month checkpoint: Spent: $200K Work completed: $100K 23
  • 24. Earned Value Technique (cont.) Terms and Formulas Definition Budget at completion (BAC) How much did we BUDGET for the TOTAL project effort? Estimate at Completion (EAC) = BAC / CPI What do we currently expect the TOTAL project cost (a forecast)? Estimate to Complete (ETC) = EAC - AC From this point on, how much MORE do we expect it to cost to finish the project (a forecast)? Variance at Completion (VAC) = BAC - EAC As of today, how much over or under budget do we expect to be at the end of the project? • EAC is an important forecasting value. 24
  • 25. Earned Value: Graphical Representation TIME COST Schedule Variance (SV) Cost Variance (CV) ACTUAL PLAN EARN VALUE Estimate at Completion (EAC) Budget at Completion (BAC) Projection of schedule delay at completion Projection of cost variance at completion (VAC) TODAY (Reporting day) BAC EAC AC EV PV • Project is over budget & behind schedule: 25
  • 26. Exercise Task Progress Cost spent Side 1 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100% $1,200 Side 2 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100% $1,000 Side 3 |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||75% $750 Side 4 |||||||||||||||||||||||||||||||||||||||50% $500 Side 5 |0% $0 Side 6 |0% $0 • You have a project to build a box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three. • Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC. • Describe your interpretation based on the calculation. 26
  • 27. Exercise Solution Parameter Calculation Result PV EV AC BAC CV CPI SV SPI EAC ETC VAC • Project is below / over budget? • Project is late / ahead schedule? • How much more money we need? 27
  • 28. Exercise Solution Parameter Calculation Result PV 1000 + 1000 + 1000 3000 EV (100% x 1000) + (100% x 1000) + (75% x 1000) + (50% x 1000) 3250 AC 1200 + 1000 + 750 + 500 3450 BAC 6 x 1000 6000 CV 3250 - 3450 -200 CPI 3250 / 3450 0.94 SV 3250 - 3000 250 SPI 3250 / 3000 1.08 EAC 6000 / 0.94 6383 ETC 6383 - 3450 2933 VAC 6000 - 6383 -383 • Over budget, getting 0.94 dollar for every dollar we spent; • Ahead schedule, progressing 108% of the rate planned; • Probably will spend $6383 at the end (estimation), need $2933 to complete, over budget at the end for about $383 (estimation) 28
  • 29. Forecasting EAC • There are many ways to calculate EAC, depending on the assumption made. • Simple EAC calculation (EAC = BAC / CPI) assume that the cumulative CPI adequately reflects past performance that will continue to the end of the project. • EAC = AC + BAC - EV: – Used when current variances are thought to be atypical of the future. • EAC = AC + [(BAC - EV) / (Cumulative CPI x Cumulative SPI)]: – It assumes poor cost performance and need to hit a firm completion date. 29
  • 30. Forecasting EAC (cont.) • Common alternative ways to calculate EAC: Assumption Example Formula Future cost performance will be the same as all past cost performance EAC = AC + [(BAC - EV) / CPI] = BAC / CPI Future cost performance will be the same as the last three measurement periods (i, j, k) EAC = AC + [(BAC - EV) / ((EVi + EVj + EVk) / (ACi + ACj + ACk))] Future cost performance will be influenced additionally by past schedule performance EAC = AC + [(BAC - EV) / (CPI x SPI)] Future cost performance will be influenced jointly in some proportion by both indices EAC = AC + [(BAC - EV) / (0.8 CPI + 0.2 SPI)] 30
  • 31. To-Complete Performance Index (TCPI) • Helps the team determine the efficiency that must be achieved on the remaining work for a project to meet a specified endpoint, such as BAC or the team’s revised EAC. • TCPI AC) - (EAC or AC) - (BAC Remaining Funds EV) - (BAC Remaining Work  31
  • 32. Earned Schedule - An emerging EVM practice • SPI ($): – At project start SPI is reliable; – At some point SPI accuracy diminishes; – Toward the project end it is useless (SPI = 1 at project end); – Does not show weeks / months of schedule variance. • SPI (t): – Time based schedule measures; – Create a SPI that is accurate to the of the project: • SV (t) = ES - AT; • SPI (t) = ES / AT. • ES = Earned Schedule (Planned time); • AT = Actual time. 32
  • 33. EVM - Hints to remember • EV comes first in every formula; • If it’s variance, the formula is EV - something; • If it’s index, the formula is EV / something; • If it relates to cost, use AC; • If it relates to schedule, use PV; • Negative number is bad, positive is good; • If it’s index, smaller than 1 is bad, bigger than 1 is good. 33
  • 34. Thank You Next topic: Project Resource Management 34