Planning
Process Group
Project Management
Processes PMBOK 5th edition
Hossam Maghrabi,PMP
Planning Process Group
Project Boundaries
Project Quality Management,
1. Includes the processes and activities of the performing organization that determine
quality policies, objectives, and responsibilities.
2. Implement the organization’s quality management system Using policies and
procedures, within the project’s context,.
3. Supports continuous process improvement activities as undertaken on behalf of the
performing organization.
4. Works to ensure that the project requirements, including product requirements, are met
and validated.
The basic approach to project quality management as described in this section is intended to be
compatible with International Organization for Standardization (ISO) quality standards.
Planning Process Group
& Project Quality Management
Planning Process Group
& Project Quality Management
Failure to meet the quality requirements can have serious, negative consequences for
any or all of the project’s stakeholders.
Ex. Meeting customer requirements by overworking the project team may result in decreased profits and
increased project risks, employee attrition, errors, or rework.
Meeting project schedule objectives by rushing planned quality inspections may result in undetected
errors, decreased profits, and increased post-implementation risks
Planning Process Group
& Project Quality Management
Quality Measures & Techniques
are specific to the type of deliverables being produced by the project.
Ex. The project quality management of software deliverables may use different approaches and measures
from those used when building a nuclear power plant.
Modern Quality Management Approaches
&
Achieving ISO Compatibility
By seek to minimize variation and to deliver results that meet defined
requirements.
Modern Quality Management focuses on,
1. Customer Satisfaction.
2. Prevention Over Inspection.
3. Continuous Improvement.
4. Management Responsibility.
5. Cost Of Quality (COQ).
Planning Process Group
& Project Quality Management
Plan Quality Management
Data Flow Diagram
The process of identifying quality
requirements and/or standards for the
project and its deliverables, and
documenting how the project will
demonstrate compliance with relevant
quality requirements.
It provides guidance and direction on how
quality will be managed and validated
throughout the project.
Plan Quality Management:
Inputs
1. Project Management Plan
1. Scope baseline - Project Scope Statement, Work Breakdown Structure(WBS), WBS dictionary -.
2. Schedule baseline.
3. Cost baseline.
4. Other management plans (Contribute to the overall project quality).
2. Stakeholder Register
3. Risk Register
4. Requirements Documentation
5. Enterprise Environmental Factors (EEF).
6. Organizational Process Assets (OPA).
Plan Quality Management:
Tools & Techniques (T&T)
1. Cost-Benefit Analysis, Compares the cost of the quality step to the expected
benefit (Less Rework, Higher Productivity, Lower Costs, Increased Stakeholder
Satisfaction, & Increased Profitability).
2.
Plan Quality Management:
Tools & Techniques (T&T)
3. Seven Basic Quality Tools - 7QC Tools ,
1. Cause-and-effect diagrams
2. Flowcharts
3. Check-Sheets
4. Pareto diagrams
5. Histograms
6. Control charts
7. Scatter diagrams
The seven basic quality tools are used within the context of the PDCA Cycle to
solve quality-related problems.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
1. Cause-and-effect diagram - Fishbone or Ishikawa diagrams -
The problem statement is placed at
the head of the Fishbone as a starting
point for describing the problem.
The causes are found by looking at the
problem statement and asking “why”
until the actionable root cause has
been identified or until the reasonable
possibilities on each fishbone have
been exhausted.
The cause and effect diagram is useful
to…
1. Break preconceived notions about
problems.
2. Spur critical thinking.
3. Create ‘aha moments’ by seeing
how causes interact.
4. Encourage the whole team to
participate in continuous
improvement.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
2. Flowchart - Process Maps -
Flowcharts show the activities,
decision points, branching loops,
parallel paths, and the overall order
of processing by mapping the
operational details of procedures that
exist within a horizontal value chain
of a SIPOC model.
Flowcharts may prove useful in
understanding and estimating the cost
of quality in a process, by using the
workflow branching logic and
associated relative frequencies to
estimate expected monetary value for
the conformance and nonconformance
work required to deliver the expected
conforming output.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
3. Check-Sheet - Tally Sheets or Check-List -
Check-Sheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential
quality problem.
Check-Sheets are especially useful for gathering attributes data while performing inspections to identify defects.
Ex. Data about the frequencies or consequences of defects collected in check-sheets are often displayed using Pareto diagrams.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
4. Pareto Diagram - A special form of vertical bar chart used to identify the vital few
sources that are responsible for causing most of a problem’s effects.
A Pareto chart combines
elements of a line chart and bar
graph, where individual values
are shown as bars in descending
numerical order - frequencies -,
and the line represents the
cumulative -consequences- total
of these values.
The Pareto Chart is a simple to
use and powerful graphic to
identify where the majority of
problems in a process are
originating . Using a Pareto
Chart early in problem solving
is an effective strategy to
decrease project complexity.
20% of the people cause 80% of the problems
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
5. Histogram - A special form of bar chart used to describe the central tendency, dispersion, and
shape (frequency distribution) of a statistical distribution (A set of continuous data).
Unlike the control chart, the histogram does not consider the influence of time
on the variation that exists within a distribution.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
6. Control Chart - A graphic display of process data over time and against established
control limits, which has a centerline that assists in detecting a trend of plotted values toward
either control limit.
- Control Limits. The area composed of three standard deviations on either side of the centerline or
mean of a normal distribution of data plotted, which reflects the expected variation in the data.
- Specification Limits. The area, on either side of the centerline, or mean, of data plotted that meets
the customer’s requirements for a product or service. This area may be greater than or less than the area
defined by the control limits.
Plan Quality Management - T&T
3 - Seven Basic Quality Tools - 7QC Tools
7. Scatter Diagram - Correlation Chart - displays the data set as a collection of points in
Cartesian coordinates; each of them is determined by the values of two variables
Scatter Diagrams are used for identifying potential linear and nonlinear relationships between variables and how a change in one
variable affects another.
Scatter Diagrams are used to depict the relationships of price and quality rating, and to show the absence or presence of correlation
between two variables and its degree. The correlation can be positive, negative, or null, its type can be easy defined with only a glance on
the position of points on the Scatter Chart.
- DOE is a statistical method for identifying which factors may
influence specific variables of a product or process under
development or in production. DOF used during the Plan Quality
Management process to determine the number and type of tests and their
impact on cost of quality. DOE also plays a role in optimizing products
or processes.
One important aspect of this technique is that it provides a statistical
framework for systematically changing all of the important factors, rather
than changing the factors one at a time.
For example, automotive designers use this technique to determine which
combination of suspension and tires will produce the most desirable ride
characteristics at a reasonable cost.
Plan Quality Management:
Tools & Techniques (T&T)
4. Benchmarking - involves comparing actual or planned project practices to those of
comparable projects to identify best practices, generate ideas for improvement, and provide a basis
for measuring performance.
- Benchmarked projects may exist within the performing organization or outside of it, or can be within the
same application area.
- Benchmarking allows for analogies from projects in a different application area to be made.
5. Design of Experiments (DOE) -
Plan Quality Management:
Tools & Techniques (T&T)
6. Statistical Sampling - involves choosing part of a population of interest for inspection.
Sample frequency and sizes should be determined during the Plan Quality Management process so
the cost of quality will include the number of tests, expected scrap, etc.
7. Meetings - Project teams may hold planning meetings to develop the quality management plan.
Attendees at these meetings may include the project manager; the project sponsor; selected project
team members; selected stakeholders; anyone with responsibility for Project Quality Management
activities namely Plan Quality Management, Perform Quality Assurance, or Control Quality; and
others as needed.
8. Additional Quality Planning Tools
Plan Quality Management:
Tools & Techniques (T&T)
Brainstorming- is a group creativity
technique by which efforts are made to
find a conclusion for a specific problem by
gathering a list of ideas spontaneously
contributed by its members. For more
information refer to Identify Risks: Tools and
Techniques / Information Gathering Techniques
Force field analysis- These are
diagrams of the forces for and against
change.
.
Nominal group technique- This
technique is used to allow ideas to be
brainstormed in small groups and then
reviewed by a larger group
( Involving problem identification, solution
generation, and decision making.)
Quality management and control tools- Affinity diagrams, Process decision program charts (PDPC),
Interrelationship digraphs, Tree diagrams, Prioritization matrices, Activity network diagrams and Matrix diagrams, for more
information please refer to Perform Quality Assurance: Tools and Techniques)
Plan Quality Management:
Outputs
1. Quality Management Plan - Describes how the organization’s quality policies will
be implemented to meet the quality requirements set for the project.
The quality management plan should be reviewed early in the project to ensure that decisions are based
on accurate information & reductions in costs and in the frequency of schedule overruns that were caused
by rework.
2. Process Improvement Plan - Details the steps for analyzing project management
and product development processes to identify activities that enhance their value through taking in
consideration the following,
- Process boundaries. Describe the purpose of the process, the start and end of the process, its inputs and outputs,
the process owner, and the stakeholders of the process.
- Process configuration. Provides a graphic depiction of processes, with interfaces identified, used to facilitate
analysis.
- Process metrics. Along with control limits, allows analysis of process efficiency.
- Targets for improved performance. Guide the process improvement activities.
3. Project Documents Updates -Stakeholder register, Responsibility assignment matrix,
WBS and WBS Dictionary -
Plan Quality Management:
Outputs
4. Quality Metrics - Specifically describes a project or product attribute and how the control
quality process will measure it.
- A measurement is an actual value.
- The tolerance defines the allowable variations to the metric. For example, if the quality objective
is to stay within the approved budget by ± 10%, the specific quality metric is used to measure the
cost of every deliverable and determine the percent variance from the approved budget for that
deliverable.
Quality metrics are used in the perform quality assurance and control quality processes which include,
on-time performance, cost control, defect frequency, failure rate, availability, reliability, and test coverage….
5. Quality Checklists - Checklist is a structured tool used to verify that a set of required steps
has been performed – Quality checklists should incorporate the acceptance criteria included in the
scope baseline.
Many organizations have standardized checklists also they available from professional associations or
commercial service providers.
As a result of the interactions between Project Human Resource Management processes & the processes in other
Knowledge Areas the additional planning may be required throughout the project. For example:
– After initial team members create a work breakdown structure, additional team members may need to be added to
the team.
– As additional team members are added to the team, their experience levels, or lack thereof, could decrease or
increase project risk, creating the need for additional risk planning.
– When activity durations are estimated, budgeted, scoped, or planned prior to identifying all project team members
and their competency levels, the activity durations may change.
Managing and leading the project team includes, but is not limited to:
1. Influencing the project team. Factors that may impact the project team like team environment, geographical locations
of team members, communications among stakeholders, internal and external politics, cultural issues,…….
2. Professional and ethical behavior.
Planning Process Group
& Project Human Resource Management
Planning Process Group
& Project Human Resource Management
Project Human Resource Management includes the processes that organize, manage, &
lead the project team.
The project team - A comprised of the people with assigned roles and responsibilities for completing
the project.
The project management team - A subset of the project team which responsible for the project
management and leadership activities such as initiating, planning, executing, monitoring, controlling, and
closing the various project phases. This group can also be referred to as the core, executive, or leadership
team.
The project sponsor - A person who works with the project management team, typically assisting
with matters such as project funding, clarifying scope, monitoring progress, and influencing stakeholders in
both the requesting and performing organization for the project benefit.
The project’s staff - Project team members - May have varied skill sets, may be assigned full or
part-time, and may be added or removed from the team as the project progresses.
Although specific roles and responsibilities for the project team members are assigned, Participation
of team members during planning adds their expertise to the process and strengthens their
commitment to the project.
Plan Human Resource Management
Data Flow Diagram
The process of identifying and
documenting Project roles,
responsibilities, required skills,
reporting relationships, and creating a
staffing management plan.
It establishes project organization
charts, and the staffing management
plan including the timetable for staff
acquisition and release.
Also identification of training needs,
team-building strategies, plans for
recognition and rewards programs,
compliance considerations, safety
issues, and the impact of the staffing
management plan on the organization.
Plan Human Resource Management:
Inputs
1. Project Management Plan – Includes,
- The project life cycle and the processes that will be applied to each phase,
- How work will be executed to accomplish the project objectives,
- A change management plan that documents how changes will be monitored and controlled,
- A configuration management plan that documents how configuration management will be
performed,
- How integrity of the project baselines will be maintained, and
- Needs and methods of communication among stakeholders.
2. Activity Resource Requirements to determine the human resource
needs for the project.
Note: The required project team members and their competencies are progressively elaborated as part of the
Plan Human Resource Management process.
3. Enterprise Environmental Factors (EEF).
4. Organizational Process Assets (OPA).
1. Organization Charts and Position Descriptions
- To document team member roles and responsibilities.
- Regardless of the method utilized, the objective is to ensure that each work package has an
unambiguous owner and that all team members have a clear understanding of their roles and
responsibilities.
Note:- Some project assignments are listed in subsidiary plans, such as the risk, quality, or
communications management plans.
Plan Human Resource Management:
Tools & Techniques (T&T)
Plan Human Resource Management:
Tools & Techniques (T&T)
3. Organizational Theory -
provides information regarding the way in which people, teams, &
organizational units behave.
It is important to recognize that different organizational structures
have different individual response, individual performance, and
personal relationship characteristics.
2. Networking -
Is the formal and informal interaction with others in an
organization, industry, or professional environment.
It is a constructive way to understand political and
interpersonal factors that will impact the effectiveness of
various staffing management options.
4. Expert Judgment.
1. List the preliminary requirements for the required skills.
2. Assess the roles required for the project based on standardized role descriptions
within the organization.
3. Determine the preliminary effort level and number of resources needed to meet
project objectives.
4. Determine reporting relationships needed based on the organizational culture.
5. Provide guidelines on lead time required for staffing, based on lessons learned
and market conditions.
6. Identify risks associated with staff acquisition, retention, and release plans.
7. Identify and recommend programs for complying with applicable government
and union contracts.
5. Meetings.
Plan Human Resource Management:
Tools & Techniques (T&T)
1. Human Resource Management Plan - Provides guidance on how project human
resources should be defined, staffed, managed, and eventually released. includes, but is not limited to,
i. Roles and responsibilities,
- Role - A defined function to be performed by a project team member, such as testing, filing, inspecting,
or coding. Role clarity concerning authority, responsibilities, and boundaries should also be documented.
- Authority - The right to apply project resources, expend funds, make decisions, or give approvals,,,,
.Team members operate best when their individual levels of authority match their individual
responsibilities.
- Responsibility - The assigned duties and work that a project team member is expected to perform in
order to complete the project’s activities.
- Competency - The skill and capacity required to complete assigned activities within the project
constraints. If project team members do not possess required competencies, performance can be
jeopardized. When such mismatches are identified, proactive responses such as training, hiring, schedule
changes, or scope changes are initiated.
ii. Project organization charts -
Plan Human Resource Management:
Outputs
A graphic display of project team members
& their reporting relationships.
1. Human Resource Management Plan.
III. Staffing management plan - A component of the human resource management plan that
describes, when and how project team members will be acquired, how long they will be needed
and how human resource requirements will be met.
The plan is updated continually during the project to direct ongoing team member acquisition and
development actions. Items to consider in the plan include,
1. - Staff acquisition - Answer the number of questions that arise when planning the acquisition of project team.
2. Resource calendars - Calendars that identify the working days and shifts on which each specific resource is
available.
3. Staff release plan - Determining the method and timing of releasing team members benefits both the project
and team members.
4. Recognition and rewards - Clear criteria for rewards, promote and reinforce desired behaviors.
5. Training needs - To obtain required competencies & certifications.
6. Compliance - Strategies for complying with human resource policies.
7. Safety - Policies and procedures that protect team members.
Plan Human Resource Management:
Outputs
Includes the processes that are required to ensure timely and appropriate planning, collection,
creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate
disposition of project information.
Effective communication creates a bridge between diverse stakeholders who may have different
cultural and organizational backgrounds, different levels of expertise, and different perspectives and
interests, which impact or have an influence upon the project execution or outcome.
Project managers spend most of their time communicating with team members and other project
stakeholders, whether they are internal (at all organizational levels) or external to the organization.
Planning Process Group
& Plan Communications Management
Planning Process Group
& Plan Communications Management
The process of developing an
appropriate approach and plan
for project communications based
on stakeholder’s information
needs and requirements, and
available organizational assets.
identifies and documents the
approach to communicate most
effectively and efficiently with
stakeholders.
Effective communication means that the information is provided in the right format, at the right
time, to the right audience, and with the right impact.
Efficient communication means providing only the information that is needed.
Plan Communication Management :
Inputs
1. Project Management Plan.
Provides information on how the project will be executed, monitored, controlled,
and closed.
2. Stakeholder Register.
Provides the information needed to plan the communication with project
stakeholders.
3. Enterprise Environmental Factors (EEF).
Since the structure of an organization will have a major effect on the project’s
communication requirements, So The Plan Communications Management is tightly
linked with enterprise environmental factors.
4. Organizational Process Assets (OPA).
Lessons learned and historical information provide insights on both the decisions taken
regarding communications issues and the results of those decisions in previous similar
projects.
1. Communication Requirements Analysis –
To determines the information needs of the project stakeholders by combining the type and format of
information needed with an analysis of the value of that information.
2. Communication Technology,
The methods used to transfer information among project stakeholders may vary significantly.
Factors that can affect the choice of communication technology include,
 Urgency of the need for information.
 Availability of technology.
 Ease of Use .
 Project environment .
 Sensitivity and confidentiality of the information .
- Considering the number of potential communication channels or paths
as an indicator of the complexity of a project’s communications.
- Determine and limit who will communicate with whom and who will
receive what information.
Plan Communication Management :
Tools & Techniques (T&T)
Plan Communication Management :
Tools & Techniques (T&T)
3.Communication Models,
Used to facilitate communications and the exchange of information . It vary
from project to project and also within different stages of the same project
Encode - Thoughts or ideas are translated (encoded) into language by the sender.
Decode - The message is translated by the receiver back into meaningful thoughts
or ideas.
Noise - Message may be influence by various factors (distance, unfamiliar
technology, inadequate infrastructure, cultural difference, and lack of background
information). These factors are collectively termed as noise.
Transmit Message. - This information is then sent by the sender using
communication channel (medium).
Acknowledge - Upon receipt of a message, the receiver may signal -
acknowledge) receipt of the message but this does not necessarily mean agreement
with or comprehension of the message).
Feedback/Response - When the received message has been decoded and
understood, the receiver encodes thoughts and ideas into a message and then
transmits this message to the original sender.
4. Communication Methods, used to share information among project stakeholders.
1. Interactive communication - Includes meetings, phone calls, instant messaging, video conferencing ).
- Most efficient way to ensure a common understanding by all participants
2. Push communication - Include letters, memos, reports, emails, faxes, voice mails, blogs, press releases,,,
- Ensures that the information is distributed but does not ensure that it actually reached or was understood
by the intended audience.
3. Pull communication - Include intranet sites, e-learning, lessons learned databases, knowledge repositories,,,
- Used for very large volumes of information for very large audiences and the recipients requires to access
the communication content.
Note:
The communication methods that are used for a project need to be discussed and agreed upon by the project
stakeholders based on communication requirements; cost and time constraints; and familiarity and availability
of the required tools and resources that may be applicable to the communications process.
5. Meetings - To determine the most appropriate way to update and communicate project
information
– Most project meetings are more formal with a prearranged time, place, and agenda. Typical meetings begin with
a defined list of issues to be discussed, which are circulated in advance with minutes and other information
documented specifically for the meeting. This information is then disseminated to other appropriate stakeholders
on an as-needed basis.
Plan Communication Management :
Tools & Techniques (T&T)
1. Communications Management Plan, Describes how project communications will be
planned, structured, monitored, and controlled.
 The plan contains,
 Stakeholder communication requirements;
 Information to be communicated, including language, format, content, and level of detail;
 Reason for the distribution of that information;
 Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if
applicable;
 Person responsible for communicating the information;
 Person responsible for authorizing release of confidential information;
 Person or groups who will receive the information;
 Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases;
 Resources allocated for communication activities, including time and budget;
 Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved
at a lower staff level;
 Method for updating and refining the communications management plan as the project progresses and develops;
 Glossary of common terminology;
 Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and
meeting plans, etc.; and
 Communication constraints.
2. Project Documents Updates ( Project schedule, Stakeholder register ,,)
Plan Communication Management:
Outputs
Planning Process Group
& Project Procurement Management
Includes the processes necessary to purchase or acquire products, services, or results needed from
outside the project team. The organization can be either the buyer or seller of the products, services,
or results of a project.
Include the contract management and change control processes required to develop and administer
contracts or purchase orders issued by authorized project team members.
Include controlling any contract issued by an outside organization (the buyer) that is acquiring
deliverables from the project in the performing organization (the seller), and administering
contractual obligations placed on the project team by the contract.
Planning Process Group
& Project Procurement Management
Contract - Also called an agreement, an understanding, a subcontract, or a purchase order -
o A contract represents a mutually binding agreement that, obligates the seller to provide something of
value (e.g., specified products, services, or results) and obligates the buyer to provide monetary or other
valuable compensation.
o A procurement contract includes terms and conditions, and may incorporate other items that the
buyer specifies as to what the seller is to perform or provide.
o The legally binding nature of a contract or agreement usually means it will be subjected to a
more extensive approval process to ensure that the contract language describes the products, services, or
results that will satisfy the identified project need.
Project management team & Contract
It is the project management team’s responsibility to make certain that all procurements meet the specific
needs of the project while adhering to organizational procurement policies. They may seek support in early
phases from specialists in contracting, purchasing, law, and technical disciplines. Such involvement can be
mandated by an organization’s policies.
Project risks & Contract.
By actively managing the agreement life cycle and carefully wording the terms and conditions of a
procurement, some identifiable project risks may be shared or transferred to a seller. Contract /Agreement
is one method of allocating the responsibility for managing or sharing potential risks.
In this contest we assume that the buyer of an item for the project is assigned to the project team and the seller is
organizationally external to the project team & a formal contractual relationship will be developed and exists
between the buyer and the seller.
Project Procurement Management is discussed within the perspective of the buyer-seller relationship.
Planning Process Group
& Project Procurement Management
The buyer-seller relationship may exist at many levels on same project &
between organizations internal and external to the acquiring organization.
Depending on the buyer’s position in the
project acquisition cycle, the buyer may be
called a client, customer, prime contractor,
contractor, acquiring
The seller can be viewed during the
contract life cycle first as a bidder, then as
the selected source, and then as the
contracted supplier or vendor.
The seller will typically manage the work as a project if the acquisition is not just for shelf material,
goods, or common products. In such cases,
Terms and conditions of the contract become
key inputs to many of the seller’s
management processes.
The contract can actually contain the inputs -Major
Deliverables, Key Milestones, Cost Objectives- or it can limit the
project team’s options-Buyer approval of staffing decisions is
often required on design projects-.
Planning Process Group
& Project Procurement Management
This process,
• Determines whether to acquire
outside support, and if so, what
to acquire, how to acquire it,
how much is needed, and when
to acquire it.
• Evaluating potential sellers
• Evaluating the risks involved
with each make-or-buy analysis
• Reviewing the type of contract
planned to be used with respect
to avoiding or mitigating risks.
Decisions made in this process can
influence the project schedule and
are integrated with Develop
Schedule, Estimate Activity
Resources, and make-or-buy
analysis.
Plan Procurement Management :
Inputs
1. Project Management Plan - Project scope statement, WBS, WBS dictionary .
2. Requirements Documentation.
3. Risk Register.
4. Activity Resource Requirements- Contain information on specific needs such as people, equipment, or
location .
5. Project Schedule - Contains information on required timelines or mandated deliverable dates .
6. Activity Cost Estimates - To evaluate the reasonableness of the bids or proposals received from potential
sellers .
7. Stakeholder Register.
8. Enterprise Environmental Factors - Marketplace conditions and their available Products, services ,
Suppliers, including past performance or reputation …….
9. Organization Process Assets- Formal procurement policies, procedures, and guidelines ,
Procurement Management systems, An established multi-tier supplier system of
prequalified sellers …..
Plan Procurement Management:
Inputs
1. Make-or-Buy Analysis, Determine whether particular work can best be accomplished by
the project team or should be purchased from outside sources.
- Budget constraints may influence make-or-buy decisions.
- A make-or-buy analysis should consider all related costs—both direct costs as well as indirect support
costs.
- Available contract types are also considered during the buy analysis.
The risk sharing between the buyer and seller determines the suitable contract types, while the specific
contract terms and conditions formalize the degree of risk being assumed by the buyer and seller.
2. Expert Judgment,
- To assess the inputs to and outputs from this process.
- To develop or modify the criteria that will be used to evaluate seller proposals.
3. Market Research,
- To examination of industry and specific vendor capabilities.
4. Meetings, Research alone may not provide specific information to formulate a procurement strategy. By
collaborating / meeting with potential bidders, the organization purchasing the material or service may benefit
while the supplier can influence a mutually beneficial approach or product.
Plan Procurement Management:
Tools & Techniques (T&T)
1. Procurement Management Plan - It describes how the procurement processes will be
managed from developing procurement documents through contract closure. It can include guidance
for,
- Types of contracts to be used.
- Risk management issues.
- Any constraints and assumptions that could affect planned procurements;
- Procurement metrics to be used to manage contracts and evaluate sellers.
- Identifying prequalified sellers, if any, to be used;
- Establishing the form and format to be used for the procurement/contract statements of work;
- Establishing the direction to be provided to the sellers on developing and maintaining a work
breakdown structure (WBS);
- Identifying requirements for performance bonds or insurance contracts to mitigate some forms of
project risk;
- Setting the scheduled dates in each contract for the contract deliverables and coordinating with the
schedule development and control processes;
- Handling the make-or-buy decisions and linking them into the Estimate Activity Resources and
Develop Schedule processes;
Plan Procurement Management:
Outputs
2. Make-or-Buy Decisions - A make-or-buy analysis results in a decision of whether
particular work can best be accomplished by the project team or needs to be purchased from outside
sources.
If the decision is to make the item, then the procurement plan may define processes and
agreements internal to the organization.
The buy decision drives a similar process of reaching agreement with a supplier for the product
or services.
3. Procurement Statement of Work - describes the procurement item in sufficient
detail to allow prospective sellers to determine if they are capable of providing the products, services,
or results.
- The SOW for procurement is developed from the project scope baseline.
- Each individual procurement item requires a SOW; however, multiple products or services can
be grouped as one procurement item within a single SOW.
- The procurement SOW can be revised and refined as required until incorporated into a signed
agreement.
Plan Procurement Management:
Outputs
4. Procurement documents -
Used to solicit proposals from prospective sellers and facilitate easy evaluation of the responses. It include
a description of the desired form of the response, and should be consistent with the value of, and risks
associated with, the planned procurement.
- Types of procurement documents include,
RFI - Request For Information, IFB - Invitation For Bid, RFP - Request For Proposal ,
RFQ -Request For Quotation ,
Tender Notice, Invitation For Negotiation, and Invitation for seller’s initial response.
- Terms such as Bid, Tender, or Quotation are generally used when the seller selection decision
will be based on price, while a term such as Proposal is generally used when other
considerations, such as technical capability or technical approach are paramount.
5. Change Requests - A decision that involves procuring goods, services, or resources
typically requires a change request. Other decisions during procurement planning can also create the
need for additional change requests.
6. Project Documents Updates - Requirements documentation, Requirements traceability
matrix, and Risk register.
Plan Procurement Management:
Outputs
7. Source Selection Criteria - Such Criteria are developed and used to rate or score seller
proposals, and can be objective or subjective. It is often included as a part of the procurement
documents.
Some possible source selection criteria are,
Plan Procurement Management:
Outputs
Planning Process Group
& Plan Stakeholder Management
Identifies how the project will
affect stakeholders, which then
allows the project manager to
develop various ways to effectively
engage stakeholders in the project,
to manage their expectations, and
to ultimately achieving the project
objectives.
Stakeholder management
Is about creation and maintenance
of relationships between the
project team and stakeholders,
with the aim to satisfy their
respective needs and requirements
within project boundaries.
It’s more than improving
communications and requires
more than managing a team.
within project boundaries.
Plan Stakeholder Management :
Inputs
1. Project Management Plan- All created project plans.
2. Stakeholder Register- Provides the information needed to plan appropriate ways to engage
project stakeholders.
3. Enterprise Environmental Factors (EEF) –
The management of stakeholders should be adapted to the project environment. Of these,
organizational culture, structure, and political climate are of particular importance, because they help
in determining the best options to support a better adaptive process for managing stakeholders.
4. Organizational Process Assets (OPA).
Lessons learned database and historical information are of particular importance, because they
provide insights on previous stakeholder management plans and their effectiveness.
1. Expert Judgment - Can be obtained through individual consultations (one-on-one meetings,
interviews, etc.) or through a panel format (focus groups, surveys, etc.).
The project manager should apply expert judgment to decide upon the level of engagement required
at each stage of the project from each stakeholder. For example, at the beginning of a project, it may be
necessary for senior stakeholders to be highly engaged in order to clear away any obstacles to success. Once these
have been successfully removed, it may be sufficient for senior stakeholders to change their level of engagement
from leading to supportive, and other stakeholders, such as end users, may become more important.
2. Meetings,
To define the required engagement levels of all stakeholder.
3. Analytical Techniques,
Identify gaps between the current and desired stakeholder engagement levels. Then actions and
communications required to close these gaps can be identified by the project team using expert
judgment.
Plan Stakeholder Management :
Tools & Techniques (T&T)
1. Stakeholder Management Plan,
Identifies the management strategies required to effectively engage stakeholders.
– In addition to the data gathered in the stakeholder register, the stakeholder management plan often provides:
• Desired and current engagement levels of key stakeholders;
• Scope and impact of change to stakeholders;
• Identified interrelationships and potential overlap between stakeholders;
• Stakeholder communication requirements for the current project phase;
• Information to be distributed to stakeholders, including language, format, content, and level of detail;
• Reason for the distribution of that information and the expected impact to stakeholder engagement;
• Time frame and frequency for the distribution of required information to stakeholders; and
• Method for updating and refining the stakeholder management plan as the project progresses and
develops.
Project managers should be aware of the sensitive nature of the stakeholder management plan and
take appropriate precautions.
1. Project Documents Updates - Project schedule, Stakeholder register ,,.
Plan Stakeholder Management :
Outputs

More Related Content

What's hot

Quality management procedures
Quality management proceduresQuality management procedures
Quality management procedures
selinasimpson1201
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 

What's hot (20)

PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARY
 
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
Understanding the Project Management Body of Knowledge (PMBOK®) Guide: Transi...
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Project: Monitoring
Project: Monitoring Project: Monitoring
Project: Monitoring
 
Quality management procedures
Quality management proceduresQuality management procedures
Quality management procedures
 
Stephen bowerman professional curriculum vitae 2016
Stephen bowerman professional curriculum vitae 2016Stephen bowerman professional curriculum vitae 2016
Stephen bowerman professional curriculum vitae 2016
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project management and control
Project management and controlProject management and control
Project management and control
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
PMP_Project Quality Management
PMP_Project Quality ManagementPMP_Project Quality Management
PMP_Project Quality Management
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 

Viewers also liked

Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management
Serdar Temiz
 
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรมเรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
Apichaya Savetvijit
 
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพChapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
Ronnarit Junsiri
 
Chapter 2 ความหมายของการควบคุมคุณภาพ
Chapter 2 ความหมายของการควบคุมคุณภาพChapter 2 ความหมายของการควบคุมคุณภาพ
Chapter 2 ความหมายของการควบคุมคุณภาพ
Ronnarit Junsiri
 

Viewers also liked (18)

Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management
 
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรมเรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
เรื่อง การจัดทำระบบคุณภาพในโรงงานอุตสาหกรรม
 
Project Risk Management PMBOK
Project Risk Management PMBOKProject Risk Management PMBOK
Project Risk Management PMBOK
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3
 
Key Employee Incentive and Retention Plans | Creating a Motivated Management ...
Key Employee Incentive and Retention Plans | Creating a Motivated Management ...Key Employee Incentive and Retention Plans | Creating a Motivated Management ...
Key Employee Incentive and Retention Plans | Creating a Motivated Management ...
 
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพChapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
Chapter 5 เครื่องมือเพื่อการควบคุมคุณภาพ
 
Project Management-Project procurement Management
Project Management-Project procurement ManagementProject Management-Project procurement Management
Project Management-Project procurement Management
 
Chapter 2 ความหมายของการควบคุมคุณภาพ
Chapter 2 ความหมายของการควบคุมคุณภาพChapter 2 ความหมายของการควบคุมคุณภาพ
Chapter 2 ความหมายของการควบคุมคุณภาพ
 
PMP Chap 12 - Project Procurement Management Details - Part 1
PMP   Chap 12 - Project Procurement Management Details - Part 1PMP   Chap 12 - Project Procurement Management Details - Part 1
PMP Chap 12 - Project Procurement Management Details - Part 1
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management Overview
 
บทที่ 4 การวางแผนกำลังการผลิต
บทที่ 4 การวางแผนกำลังการผลิตบทที่ 4 การวางแผนกำลังการผลิต
บทที่ 4 การวางแผนกำลังการผลิต
 
การจัดการคุณภาพ(Quality management)
การจัดการคุณภาพ(Quality management)การจัดการคุณภาพ(Quality management)
การจัดการคุณภาพ(Quality management)
 
PMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPRPMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPR
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
APQP: Advanced Product/Project Quality Planning
APQP: Advanced Product/Project Quality PlanningAPQP: Advanced Product/Project Quality Planning
APQP: Advanced Product/Project Quality Planning
 
การควบคุมคุณภาพ
การควบคุมคุณภาพการควบคุมคุณภาพ
การควบคุมคุณภาพ
 
บทที 6 การจัดการคุณภาพ
บทที 6 การจัดการคุณภาพบทที 6 การจัดการคุณภาพ
บทที 6 การจัดการคุณภาพ
 

Similar to Pmbok 5th planning process group part three

Project on quality management
Project on quality managementProject on quality management
Project on quality management
selinasimpson2901
 
Quality management in project management
Quality management in project managementQuality management in project management
Quality management in project management
selinasimpson0501
 
Quality management in projects
Quality management in projectsQuality management in projects
Quality management in projects
selinasimpson311
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy template
selinasimpson2701
 
L07 quality management
L07 quality managementL07 quality management
L07 quality management
Asa Chan
 
Quality management organizations
Quality management organizationsQuality management organizations
Quality management organizations
selinasimpson0801
 
It project quality management
It project quality managementIt project quality management
It project quality management
selinasimpson2701
 
Quality management strategy prince2
Quality management strategy prince2Quality management strategy prince2
Quality management strategy prince2
selinasimpson2601
 

Similar to Pmbok 5th planning process group part three (20)

Project on quality management
Project on quality managementProject on quality management
Project on quality management
 
Quality management in project management
Quality management in project managementQuality management in project management
Quality management in project management
 
PROJECT QUALITY MANAGEMENT.pptx
PROJECT QUALITY MANAGEMENT.pptxPROJECT QUALITY MANAGEMENT.pptx
PROJECT QUALITY MANAGEMENT.pptx
 
Presentation on Quality Management
Presentation on Quality ManagementPresentation on Quality Management
Presentation on Quality Management
 
Quality management in projects
Quality management in projectsQuality management in projects
Quality management in projects
 
Quality management strategy template
Quality management strategy templateQuality management strategy template
Quality management strategy template
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.ppt
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
A lean model based outlook on cost & quality optimization in software projects
A lean model based outlook on cost & quality optimization in software projectsA lean model based outlook on cost & quality optimization in software projects
A lean model based outlook on cost & quality optimization in software projects
 
L07 quality management
L07 quality managementL07 quality management
L07 quality management
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Quality management organizations
Quality management organizationsQuality management organizations
Quality management organizations
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Profolio
ProfolioProfolio
Profolio
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Prince2 quality management
Prince2 quality managementPrince2 quality management
Prince2 quality management
 
It project quality management
It project quality managementIt project quality management
It project quality management
 
Review on Quality Management using 7 QC Tools
Review on Quality Management using 7 QC ToolsReview on Quality Management using 7 QC Tools
Review on Quality Management using 7 QC Tools
 
Quality management strategy prince2
Quality management strategy prince2Quality management strategy prince2
Quality management strategy prince2
 

Recently uploaded

Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 

Recently uploaded (17)

Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 

Pmbok 5th planning process group part three

  • 1. Planning Process Group Project Management Processes PMBOK 5th edition Hossam Maghrabi,PMP
  • 3. Project Quality Management, 1. Includes the processes and activities of the performing organization that determine quality policies, objectives, and responsibilities. 2. Implement the organization’s quality management system Using policies and procedures, within the project’s context,. 3. Supports continuous process improvement activities as undertaken on behalf of the performing organization. 4. Works to ensure that the project requirements, including product requirements, are met and validated. The basic approach to project quality management as described in this section is intended to be compatible with International Organization for Standardization (ISO) quality standards. Planning Process Group & Project Quality Management
  • 4. Planning Process Group & Project Quality Management Failure to meet the quality requirements can have serious, negative consequences for any or all of the project’s stakeholders. Ex. Meeting customer requirements by overworking the project team may result in decreased profits and increased project risks, employee attrition, errors, or rework. Meeting project schedule objectives by rushing planned quality inspections may result in undetected errors, decreased profits, and increased post-implementation risks
  • 5. Planning Process Group & Project Quality Management Quality Measures & Techniques are specific to the type of deliverables being produced by the project. Ex. The project quality management of software deliverables may use different approaches and measures from those used when building a nuclear power plant.
  • 6. Modern Quality Management Approaches & Achieving ISO Compatibility By seek to minimize variation and to deliver results that meet defined requirements. Modern Quality Management focuses on, 1. Customer Satisfaction. 2. Prevention Over Inspection. 3. Continuous Improvement. 4. Management Responsibility. 5. Cost Of Quality (COQ). Planning Process Group & Project Quality Management
  • 7. Plan Quality Management Data Flow Diagram The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with relevant quality requirements. It provides guidance and direction on how quality will be managed and validated throughout the project.
  • 8. Plan Quality Management: Inputs 1. Project Management Plan 1. Scope baseline - Project Scope Statement, Work Breakdown Structure(WBS), WBS dictionary -. 2. Schedule baseline. 3. Cost baseline. 4. Other management plans (Contribute to the overall project quality). 2. Stakeholder Register 3. Risk Register 4. Requirements Documentation 5. Enterprise Environmental Factors (EEF). 6. Organizational Process Assets (OPA).
  • 9. Plan Quality Management: Tools & Techniques (T&T) 1. Cost-Benefit Analysis, Compares the cost of the quality step to the expected benefit (Less Rework, Higher Productivity, Lower Costs, Increased Stakeholder Satisfaction, & Increased Profitability). 2.
  • 10. Plan Quality Management: Tools & Techniques (T&T) 3. Seven Basic Quality Tools - 7QC Tools , 1. Cause-and-effect diagrams 2. Flowcharts 3. Check-Sheets 4. Pareto diagrams 5. Histograms 6. Control charts 7. Scatter diagrams The seven basic quality tools are used within the context of the PDCA Cycle to solve quality-related problems.
  • 11. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 1. Cause-and-effect diagram - Fishbone or Ishikawa diagrams - The problem statement is placed at the head of the Fishbone as a starting point for describing the problem. The causes are found by looking at the problem statement and asking “why” until the actionable root cause has been identified or until the reasonable possibilities on each fishbone have been exhausted. The cause and effect diagram is useful to… 1. Break preconceived notions about problems. 2. Spur critical thinking. 3. Create ‘aha moments’ by seeing how causes interact. 4. Encourage the whole team to participate in continuous improvement.
  • 12. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 2. Flowchart - Process Maps - Flowcharts show the activities, decision points, branching loops, parallel paths, and the overall order of processing by mapping the operational details of procedures that exist within a horizontal value chain of a SIPOC model. Flowcharts may prove useful in understanding and estimating the cost of quality in a process, by using the workflow branching logic and associated relative frequencies to estimate expected monetary value for the conformance and nonconformance work required to deliver the expected conforming output.
  • 13. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 3. Check-Sheet - Tally Sheets or Check-List - Check-Sheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem. Check-Sheets are especially useful for gathering attributes data while performing inspections to identify defects. Ex. Data about the frequencies or consequences of defects collected in check-sheets are often displayed using Pareto diagrams.
  • 14. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 4. Pareto Diagram - A special form of vertical bar chart used to identify the vital few sources that are responsible for causing most of a problem’s effects. A Pareto chart combines elements of a line chart and bar graph, where individual values are shown as bars in descending numerical order - frequencies -, and the line represents the cumulative -consequences- total of these values. The Pareto Chart is a simple to use and powerful graphic to identify where the majority of problems in a process are originating . Using a Pareto Chart early in problem solving is an effective strategy to decrease project complexity. 20% of the people cause 80% of the problems
  • 15. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 5. Histogram - A special form of bar chart used to describe the central tendency, dispersion, and shape (frequency distribution) of a statistical distribution (A set of continuous data). Unlike the control chart, the histogram does not consider the influence of time on the variation that exists within a distribution.
  • 16. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 6. Control Chart - A graphic display of process data over time and against established control limits, which has a centerline that assists in detecting a trend of plotted values toward either control limit. - Control Limits. The area composed of three standard deviations on either side of the centerline or mean of a normal distribution of data plotted, which reflects the expected variation in the data. - Specification Limits. The area, on either side of the centerline, or mean, of data plotted that meets the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits.
  • 17. Plan Quality Management - T&T 3 - Seven Basic Quality Tools - 7QC Tools 7. Scatter Diagram - Correlation Chart - displays the data set as a collection of points in Cartesian coordinates; each of them is determined by the values of two variables Scatter Diagrams are used for identifying potential linear and nonlinear relationships between variables and how a change in one variable affects another. Scatter Diagrams are used to depict the relationships of price and quality rating, and to show the absence or presence of correlation between two variables and its degree. The correlation can be positive, negative, or null, its type can be easy defined with only a glance on the position of points on the Scatter Chart.
  • 18. - DOE is a statistical method for identifying which factors may influence specific variables of a product or process under development or in production. DOF used during the Plan Quality Management process to determine the number and type of tests and their impact on cost of quality. DOE also plays a role in optimizing products or processes. One important aspect of this technique is that it provides a statistical framework for systematically changing all of the important factors, rather than changing the factors one at a time. For example, automotive designers use this technique to determine which combination of suspension and tires will produce the most desirable ride characteristics at a reasonable cost. Plan Quality Management: Tools & Techniques (T&T) 4. Benchmarking - involves comparing actual or planned project practices to those of comparable projects to identify best practices, generate ideas for improvement, and provide a basis for measuring performance. - Benchmarked projects may exist within the performing organization or outside of it, or can be within the same application area. - Benchmarking allows for analogies from projects in a different application area to be made. 5. Design of Experiments (DOE) -
  • 19. Plan Quality Management: Tools & Techniques (T&T) 6. Statistical Sampling - involves choosing part of a population of interest for inspection. Sample frequency and sizes should be determined during the Plan Quality Management process so the cost of quality will include the number of tests, expected scrap, etc. 7. Meetings - Project teams may hold planning meetings to develop the quality management plan. Attendees at these meetings may include the project manager; the project sponsor; selected project team members; selected stakeholders; anyone with responsibility for Project Quality Management activities namely Plan Quality Management, Perform Quality Assurance, or Control Quality; and others as needed.
  • 20. 8. Additional Quality Planning Tools Plan Quality Management: Tools & Techniques (T&T) Brainstorming- is a group creativity technique by which efforts are made to find a conclusion for a specific problem by gathering a list of ideas spontaneously contributed by its members. For more information refer to Identify Risks: Tools and Techniques / Information Gathering Techniques Force field analysis- These are diagrams of the forces for and against change. . Nominal group technique- This technique is used to allow ideas to be brainstormed in small groups and then reviewed by a larger group ( Involving problem identification, solution generation, and decision making.) Quality management and control tools- Affinity diagrams, Process decision program charts (PDPC), Interrelationship digraphs, Tree diagrams, Prioritization matrices, Activity network diagrams and Matrix diagrams, for more information please refer to Perform Quality Assurance: Tools and Techniques)
  • 21. Plan Quality Management: Outputs 1. Quality Management Plan - Describes how the organization’s quality policies will be implemented to meet the quality requirements set for the project. The quality management plan should be reviewed early in the project to ensure that decisions are based on accurate information & reductions in costs and in the frequency of schedule overruns that were caused by rework. 2. Process Improvement Plan - Details the steps for analyzing project management and product development processes to identify activities that enhance their value through taking in consideration the following, - Process boundaries. Describe the purpose of the process, the start and end of the process, its inputs and outputs, the process owner, and the stakeholders of the process. - Process configuration. Provides a graphic depiction of processes, with interfaces identified, used to facilitate analysis. - Process metrics. Along with control limits, allows analysis of process efficiency. - Targets for improved performance. Guide the process improvement activities. 3. Project Documents Updates -Stakeholder register, Responsibility assignment matrix, WBS and WBS Dictionary -
  • 22. Plan Quality Management: Outputs 4. Quality Metrics - Specifically describes a project or product attribute and how the control quality process will measure it. - A measurement is an actual value. - The tolerance defines the allowable variations to the metric. For example, if the quality objective is to stay within the approved budget by ± 10%, the specific quality metric is used to measure the cost of every deliverable and determine the percent variance from the approved budget for that deliverable. Quality metrics are used in the perform quality assurance and control quality processes which include, on-time performance, cost control, defect frequency, failure rate, availability, reliability, and test coverage…. 5. Quality Checklists - Checklist is a structured tool used to verify that a set of required steps has been performed – Quality checklists should incorporate the acceptance criteria included in the scope baseline. Many organizations have standardized checklists also they available from professional associations or commercial service providers.
  • 23. As a result of the interactions between Project Human Resource Management processes & the processes in other Knowledge Areas the additional planning may be required throughout the project. For example: – After initial team members create a work breakdown structure, additional team members may need to be added to the team. – As additional team members are added to the team, their experience levels, or lack thereof, could decrease or increase project risk, creating the need for additional risk planning. – When activity durations are estimated, budgeted, scoped, or planned prior to identifying all project team members and their competency levels, the activity durations may change. Managing and leading the project team includes, but is not limited to: 1. Influencing the project team. Factors that may impact the project team like team environment, geographical locations of team members, communications among stakeholders, internal and external politics, cultural issues,……. 2. Professional and ethical behavior. Planning Process Group & Project Human Resource Management
  • 24. Planning Process Group & Project Human Resource Management Project Human Resource Management includes the processes that organize, manage, & lead the project team. The project team - A comprised of the people with assigned roles and responsibilities for completing the project. The project management team - A subset of the project team which responsible for the project management and leadership activities such as initiating, planning, executing, monitoring, controlling, and closing the various project phases. This group can also be referred to as the core, executive, or leadership team. The project sponsor - A person who works with the project management team, typically assisting with matters such as project funding, clarifying scope, monitoring progress, and influencing stakeholders in both the requesting and performing organization for the project benefit. The project’s staff - Project team members - May have varied skill sets, may be assigned full or part-time, and may be added or removed from the team as the project progresses. Although specific roles and responsibilities for the project team members are assigned, Participation of team members during planning adds their expertise to the process and strengthens their commitment to the project.
  • 25. Plan Human Resource Management Data Flow Diagram The process of identifying and documenting Project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan. It establishes project organization charts, and the staffing management plan including the timetable for staff acquisition and release. Also identification of training needs, team-building strategies, plans for recognition and rewards programs, compliance considerations, safety issues, and the impact of the staffing management plan on the organization.
  • 26. Plan Human Resource Management: Inputs 1. Project Management Plan – Includes, - The project life cycle and the processes that will be applied to each phase, - How work will be executed to accomplish the project objectives, - A change management plan that documents how changes will be monitored and controlled, - A configuration management plan that documents how configuration management will be performed, - How integrity of the project baselines will be maintained, and - Needs and methods of communication among stakeholders. 2. Activity Resource Requirements to determine the human resource needs for the project. Note: The required project team members and their competencies are progressively elaborated as part of the Plan Human Resource Management process. 3. Enterprise Environmental Factors (EEF). 4. Organizational Process Assets (OPA).
  • 27. 1. Organization Charts and Position Descriptions - To document team member roles and responsibilities. - Regardless of the method utilized, the objective is to ensure that each work package has an unambiguous owner and that all team members have a clear understanding of their roles and responsibilities. Note:- Some project assignments are listed in subsidiary plans, such as the risk, quality, or communications management plans. Plan Human Resource Management: Tools & Techniques (T&T)
  • 28. Plan Human Resource Management: Tools & Techniques (T&T) 3. Organizational Theory - provides information regarding the way in which people, teams, & organizational units behave. It is important to recognize that different organizational structures have different individual response, individual performance, and personal relationship characteristics. 2. Networking - Is the formal and informal interaction with others in an organization, industry, or professional environment. It is a constructive way to understand political and interpersonal factors that will impact the effectiveness of various staffing management options.
  • 29. 4. Expert Judgment. 1. List the preliminary requirements for the required skills. 2. Assess the roles required for the project based on standardized role descriptions within the organization. 3. Determine the preliminary effort level and number of resources needed to meet project objectives. 4. Determine reporting relationships needed based on the organizational culture. 5. Provide guidelines on lead time required for staffing, based on lessons learned and market conditions. 6. Identify risks associated with staff acquisition, retention, and release plans. 7. Identify and recommend programs for complying with applicable government and union contracts. 5. Meetings. Plan Human Resource Management: Tools & Techniques (T&T)
  • 30. 1. Human Resource Management Plan - Provides guidance on how project human resources should be defined, staffed, managed, and eventually released. includes, but is not limited to, i. Roles and responsibilities, - Role - A defined function to be performed by a project team member, such as testing, filing, inspecting, or coding. Role clarity concerning authority, responsibilities, and boundaries should also be documented. - Authority - The right to apply project resources, expend funds, make decisions, or give approvals,,,, .Team members operate best when their individual levels of authority match their individual responsibilities. - Responsibility - The assigned duties and work that a project team member is expected to perform in order to complete the project’s activities. - Competency - The skill and capacity required to complete assigned activities within the project constraints. If project team members do not possess required competencies, performance can be jeopardized. When such mismatches are identified, proactive responses such as training, hiring, schedule changes, or scope changes are initiated. ii. Project organization charts - Plan Human Resource Management: Outputs A graphic display of project team members & their reporting relationships.
  • 31. 1. Human Resource Management Plan. III. Staffing management plan - A component of the human resource management plan that describes, when and how project team members will be acquired, how long they will be needed and how human resource requirements will be met. The plan is updated continually during the project to direct ongoing team member acquisition and development actions. Items to consider in the plan include, 1. - Staff acquisition - Answer the number of questions that arise when planning the acquisition of project team. 2. Resource calendars - Calendars that identify the working days and shifts on which each specific resource is available. 3. Staff release plan - Determining the method and timing of releasing team members benefits both the project and team members. 4. Recognition and rewards - Clear criteria for rewards, promote and reinforce desired behaviors. 5. Training needs - To obtain required competencies & certifications. 6. Compliance - Strategies for complying with human resource policies. 7. Safety - Policies and procedures that protect team members. Plan Human Resource Management: Outputs
  • 32. Includes the processes that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project information. Effective communication creates a bridge between diverse stakeholders who may have different cultural and organizational backgrounds, different levels of expertise, and different perspectives and interests, which impact or have an influence upon the project execution or outcome. Project managers spend most of their time communicating with team members and other project stakeholders, whether they are internal (at all organizational levels) or external to the organization. Planning Process Group & Plan Communications Management
  • 33. Planning Process Group & Plan Communications Management The process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements, and available organizational assets. identifies and documents the approach to communicate most effectively and efficiently with stakeholders. Effective communication means that the information is provided in the right format, at the right time, to the right audience, and with the right impact. Efficient communication means providing only the information that is needed.
  • 34. Plan Communication Management : Inputs 1. Project Management Plan. Provides information on how the project will be executed, monitored, controlled, and closed. 2. Stakeholder Register. Provides the information needed to plan the communication with project stakeholders. 3. Enterprise Environmental Factors (EEF). Since the structure of an organization will have a major effect on the project’s communication requirements, So The Plan Communications Management is tightly linked with enterprise environmental factors. 4. Organizational Process Assets (OPA). Lessons learned and historical information provide insights on both the decisions taken regarding communications issues and the results of those decisions in previous similar projects.
  • 35. 1. Communication Requirements Analysis – To determines the information needs of the project stakeholders by combining the type and format of information needed with an analysis of the value of that information. 2. Communication Technology, The methods used to transfer information among project stakeholders may vary significantly. Factors that can affect the choice of communication technology include,  Urgency of the need for information.  Availability of technology.  Ease of Use .  Project environment .  Sensitivity and confidentiality of the information . - Considering the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. - Determine and limit who will communicate with whom and who will receive what information. Plan Communication Management : Tools & Techniques (T&T)
  • 36. Plan Communication Management : Tools & Techniques (T&T) 3.Communication Models, Used to facilitate communications and the exchange of information . It vary from project to project and also within different stages of the same project Encode - Thoughts or ideas are translated (encoded) into language by the sender. Decode - The message is translated by the receiver back into meaningful thoughts or ideas. Noise - Message may be influence by various factors (distance, unfamiliar technology, inadequate infrastructure, cultural difference, and lack of background information). These factors are collectively termed as noise. Transmit Message. - This information is then sent by the sender using communication channel (medium). Acknowledge - Upon receipt of a message, the receiver may signal - acknowledge) receipt of the message but this does not necessarily mean agreement with or comprehension of the message). Feedback/Response - When the received message has been decoded and understood, the receiver encodes thoughts and ideas into a message and then transmits this message to the original sender.
  • 37. 4. Communication Methods, used to share information among project stakeholders. 1. Interactive communication - Includes meetings, phone calls, instant messaging, video conferencing ). - Most efficient way to ensure a common understanding by all participants 2. Push communication - Include letters, memos, reports, emails, faxes, voice mails, blogs, press releases,,, - Ensures that the information is distributed but does not ensure that it actually reached or was understood by the intended audience. 3. Pull communication - Include intranet sites, e-learning, lessons learned databases, knowledge repositories,,, - Used for very large volumes of information for very large audiences and the recipients requires to access the communication content. Note: The communication methods that are used for a project need to be discussed and agreed upon by the project stakeholders based on communication requirements; cost and time constraints; and familiarity and availability of the required tools and resources that may be applicable to the communications process. 5. Meetings - To determine the most appropriate way to update and communicate project information – Most project meetings are more formal with a prearranged time, place, and agenda. Typical meetings begin with a defined list of issues to be discussed, which are circulated in advance with minutes and other information documented specifically for the meeting. This information is then disseminated to other appropriate stakeholders on an as-needed basis. Plan Communication Management : Tools & Techniques (T&T)
  • 38. 1. Communications Management Plan, Describes how project communications will be planned, structured, monitored, and controlled.  The plan contains,  Stakeholder communication requirements;  Information to be communicated, including language, format, content, and level of detail;  Reason for the distribution of that information;  Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable;  Person responsible for communicating the information;  Person responsible for authorizing release of confidential information;  Person or groups who will receive the information;  Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases;  Resources allocated for communication activities, including time and budget;  Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level;  Method for updating and refining the communications management plan as the project progresses and develops;  Glossary of common terminology;  Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; and  Communication constraints. 2. Project Documents Updates ( Project schedule, Stakeholder register ,,) Plan Communication Management: Outputs
  • 39. Planning Process Group & Project Procurement Management Includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team. The organization can be either the buyer or seller of the products, services, or results of a project. Include the contract management and change control processes required to develop and administer contracts or purchase orders issued by authorized project team members. Include controlling any contract issued by an outside organization (the buyer) that is acquiring deliverables from the project in the performing organization (the seller), and administering contractual obligations placed on the project team by the contract.
  • 40. Planning Process Group & Project Procurement Management Contract - Also called an agreement, an understanding, a subcontract, or a purchase order - o A contract represents a mutually binding agreement that, obligates the seller to provide something of value (e.g., specified products, services, or results) and obligates the buyer to provide monetary or other valuable compensation. o A procurement contract includes terms and conditions, and may incorporate other items that the buyer specifies as to what the seller is to perform or provide. o The legally binding nature of a contract or agreement usually means it will be subjected to a more extensive approval process to ensure that the contract language describes the products, services, or results that will satisfy the identified project need. Project management team & Contract It is the project management team’s responsibility to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies. They may seek support in early phases from specialists in contracting, purchasing, law, and technical disciplines. Such involvement can be mandated by an organization’s policies. Project risks & Contract. By actively managing the agreement life cycle and carefully wording the terms and conditions of a procurement, some identifiable project risks may be shared or transferred to a seller. Contract /Agreement is one method of allocating the responsibility for managing or sharing potential risks.
  • 41. In this contest we assume that the buyer of an item for the project is assigned to the project team and the seller is organizationally external to the project team & a formal contractual relationship will be developed and exists between the buyer and the seller. Project Procurement Management is discussed within the perspective of the buyer-seller relationship. Planning Process Group & Project Procurement Management The buyer-seller relationship may exist at many levels on same project & between organizations internal and external to the acquiring organization. Depending on the buyer’s position in the project acquisition cycle, the buyer may be called a client, customer, prime contractor, contractor, acquiring The seller can be viewed during the contract life cycle first as a bidder, then as the selected source, and then as the contracted supplier or vendor. The seller will typically manage the work as a project if the acquisition is not just for shelf material, goods, or common products. In such cases, Terms and conditions of the contract become key inputs to many of the seller’s management processes. The contract can actually contain the inputs -Major Deliverables, Key Milestones, Cost Objectives- or it can limit the project team’s options-Buyer approval of staffing decisions is often required on design projects-.
  • 42. Planning Process Group & Project Procurement Management This process, • Determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it. • Evaluating potential sellers • Evaluating the risks involved with each make-or-buy analysis • Reviewing the type of contract planned to be used with respect to avoiding or mitigating risks. Decisions made in this process can influence the project schedule and are integrated with Develop Schedule, Estimate Activity Resources, and make-or-buy analysis.
  • 43. Plan Procurement Management : Inputs 1. Project Management Plan - Project scope statement, WBS, WBS dictionary . 2. Requirements Documentation. 3. Risk Register. 4. Activity Resource Requirements- Contain information on specific needs such as people, equipment, or location . 5. Project Schedule - Contains information on required timelines or mandated deliverable dates . 6. Activity Cost Estimates - To evaluate the reasonableness of the bids or proposals received from potential sellers . 7. Stakeholder Register. 8. Enterprise Environmental Factors - Marketplace conditions and their available Products, services , Suppliers, including past performance or reputation ……. 9. Organization Process Assets- Formal procurement policies, procedures, and guidelines , Procurement Management systems, An established multi-tier supplier system of prequalified sellers …..
  • 45. 1. Make-or-Buy Analysis, Determine whether particular work can best be accomplished by the project team or should be purchased from outside sources. - Budget constraints may influence make-or-buy decisions. - A make-or-buy analysis should consider all related costs—both direct costs as well as indirect support costs. - Available contract types are also considered during the buy analysis. The risk sharing between the buyer and seller determines the suitable contract types, while the specific contract terms and conditions formalize the degree of risk being assumed by the buyer and seller. 2. Expert Judgment, - To assess the inputs to and outputs from this process. - To develop or modify the criteria that will be used to evaluate seller proposals. 3. Market Research, - To examination of industry and specific vendor capabilities. 4. Meetings, Research alone may not provide specific information to formulate a procurement strategy. By collaborating / meeting with potential bidders, the organization purchasing the material or service may benefit while the supplier can influence a mutually beneficial approach or product. Plan Procurement Management: Tools & Techniques (T&T)
  • 46. 1. Procurement Management Plan - It describes how the procurement processes will be managed from developing procurement documents through contract closure. It can include guidance for, - Types of contracts to be used. - Risk management issues. - Any constraints and assumptions that could affect planned procurements; - Procurement metrics to be used to manage contracts and evaluate sellers. - Identifying prequalified sellers, if any, to be used; - Establishing the form and format to be used for the procurement/contract statements of work; - Establishing the direction to be provided to the sellers on developing and maintaining a work breakdown structure (WBS); - Identifying requirements for performance bonds or insurance contracts to mitigate some forms of project risk; - Setting the scheduled dates in each contract for the contract deliverables and coordinating with the schedule development and control processes; - Handling the make-or-buy decisions and linking them into the Estimate Activity Resources and Develop Schedule processes; Plan Procurement Management: Outputs
  • 47. 2. Make-or-Buy Decisions - A make-or-buy analysis results in a decision of whether particular work can best be accomplished by the project team or needs to be purchased from outside sources. If the decision is to make the item, then the procurement plan may define processes and agreements internal to the organization. The buy decision drives a similar process of reaching agreement with a supplier for the product or services. 3. Procurement Statement of Work - describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results. - The SOW for procurement is developed from the project scope baseline. - Each individual procurement item requires a SOW; however, multiple products or services can be grouped as one procurement item within a single SOW. - The procurement SOW can be revised and refined as required until incorporated into a signed agreement. Plan Procurement Management: Outputs
  • 48. 4. Procurement documents - Used to solicit proposals from prospective sellers and facilitate easy evaluation of the responses. It include a description of the desired form of the response, and should be consistent with the value of, and risks associated with, the planned procurement. - Types of procurement documents include, RFI - Request For Information, IFB - Invitation For Bid, RFP - Request For Proposal , RFQ -Request For Quotation , Tender Notice, Invitation For Negotiation, and Invitation for seller’s initial response. - Terms such as Bid, Tender, or Quotation are generally used when the seller selection decision will be based on price, while a term such as Proposal is generally used when other considerations, such as technical capability or technical approach are paramount. 5. Change Requests - A decision that involves procuring goods, services, or resources typically requires a change request. Other decisions during procurement planning can also create the need for additional change requests. 6. Project Documents Updates - Requirements documentation, Requirements traceability matrix, and Risk register. Plan Procurement Management: Outputs
  • 49. 7. Source Selection Criteria - Such Criteria are developed and used to rate or score seller proposals, and can be objective or subjective. It is often included as a part of the procurement documents. Some possible source selection criteria are, Plan Procurement Management: Outputs
  • 50. Planning Process Group & Plan Stakeholder Management Identifies how the project will affect stakeholders, which then allows the project manager to develop various ways to effectively engage stakeholders in the project, to manage their expectations, and to ultimately achieving the project objectives. Stakeholder management Is about creation and maintenance of relationships between the project team and stakeholders, with the aim to satisfy their respective needs and requirements within project boundaries. It’s more than improving communications and requires more than managing a team. within project boundaries.
  • 51. Plan Stakeholder Management : Inputs 1. Project Management Plan- All created project plans. 2. Stakeholder Register- Provides the information needed to plan appropriate ways to engage project stakeholders. 3. Enterprise Environmental Factors (EEF) – The management of stakeholders should be adapted to the project environment. Of these, organizational culture, structure, and political climate are of particular importance, because they help in determining the best options to support a better adaptive process for managing stakeholders. 4. Organizational Process Assets (OPA). Lessons learned database and historical information are of particular importance, because they provide insights on previous stakeholder management plans and their effectiveness.
  • 52. 1. Expert Judgment - Can be obtained through individual consultations (one-on-one meetings, interviews, etc.) or through a panel format (focus groups, surveys, etc.). The project manager should apply expert judgment to decide upon the level of engagement required at each stage of the project from each stakeholder. For example, at the beginning of a project, it may be necessary for senior stakeholders to be highly engaged in order to clear away any obstacles to success. Once these have been successfully removed, it may be sufficient for senior stakeholders to change their level of engagement from leading to supportive, and other stakeholders, such as end users, may become more important. 2. Meetings, To define the required engagement levels of all stakeholder. 3. Analytical Techniques, Identify gaps between the current and desired stakeholder engagement levels. Then actions and communications required to close these gaps can be identified by the project team using expert judgment. Plan Stakeholder Management : Tools & Techniques (T&T)
  • 53. 1. Stakeholder Management Plan, Identifies the management strategies required to effectively engage stakeholders. – In addition to the data gathered in the stakeholder register, the stakeholder management plan often provides: • Desired and current engagement levels of key stakeholders; • Scope and impact of change to stakeholders; • Identified interrelationships and potential overlap between stakeholders; • Stakeholder communication requirements for the current project phase; • Information to be distributed to stakeholders, including language, format, content, and level of detail; • Reason for the distribution of that information and the expected impact to stakeholder engagement; • Time frame and frequency for the distribution of required information to stakeholders; and • Method for updating and refining the stakeholder management plan as the project progresses and develops. Project managers should be aware of the sensitive nature of the stakeholder management plan and take appropriate precautions. 1. Project Documents Updates - Project schedule, Stakeholder register ,,. Plan Stakeholder Management : Outputs