PPROJECTROJECT RRISKISK MMANAGEMENTANAGEMENT
Hisham Haridy, PMP, PMI-RMP
February 2016
Plan Risk
Management
Identify
Risks
Perform
Qualitative
Risk
Perform
Quantitative
Risk
Plan Risk
Responses
Control
Risks
Project Risk Management includes the processes of conducting risk management
planning, identification, analysis, response planning, and controlling risk on a
project.
Risk Management
Management Risks Risk
Analysis
Risk
Analysis
Responses Risks
Determining
which risks might
affect the project
and documenting
their
characteristics
(Risk
Register). At
least 300 risk
should be
identified.
Prioritizing risks
for subsequent
further analysis
or action by
assessing and
combining their
probability of
occurrence and
impact (Risk
Register
Update),
Ranking,
Watchlist.
Numerically
analyzing the
effect on overall
project
objectives of
identified risks
(Risk Register
Update),
Watchlist.
Implementing risk
response plans,
tracking identified
risks, monitoring
residual risks,
identifying new
risks, and
evaluating risk
process
effectiveness
throughout the
project.
Deciding how to
approach, plan,
and execute the
risk management
activities for a
project (Risk
management
Plan). Who?
When? What?
How? How much?
P, I, PI matrix,
RBS. Risk
tolerance.
Developing
options and
actions to
enhance
opportunities,
and to reduce
threats to
project
objectives.
PROJECT RISK MANAGEMENT February 2016
DEFINATIONSDEFINATIONS
Project Risk
Project risk in an uncertain event or condition that, if it occurs, has a positive or
negative effect on at least one of the project objectives (scope, schedule, budget,
quality)
Opportunity Threat
A project risk that has a positive
effect is referred to as an
A project risk that has a negative
effect is referred to as a threat.effect is referred to as an
opportunity.
A project manager will proactively
manage opportunities to the project
and look for ways to exploit,
enhance, or share the opportunity.
effect is referred to as a threat.
A project manager will proactively
manage threats to the project and
look for ways to reduce the
probability or impact of the threat
(Mitigate) or eliminate the threat
all together (avoid) or transfer to
another party.
PROJECT RISK MANAGEMENT February 2016
DEFINATIONSDEFINATIONS
Uncertainty
Uncertainty is a lack of knowledge about an event that reduces confidence in conclusions drawn
from the data.
The investigation of uncertainties may help identify risks.
Under certainty, the outcome can be predicted with a high degree of confidence.
In reality, most decisions are taken without complete information, and therefore give rise to some
degree of uncertainty in the outcome.
Known Risks Unknown Risks Issue
That have been identified and
analyzed, making it possible to
plan responses for those risks.
That cannot be managed
proactively, should be assigned a
contingency reserve.
Unknown risks cannot be
managed proactively and
therefore may be assigned
a management reserve
A negative project risk
that has occurred is
considered an issue.
PROJECT RISK MANAGEMENT February 2016
DEFINATIONSDEFINATIONS
Risk Attitude
Risk Factors
When looking at risk, one should determine:
The probability that it will occur (what)
The range of possible outcomes (impact or amount at stake)
Expected timing (when) in the project life cycle
The anticipated frequency of risk events from that source (how often).
Organizations perceive risk as the effect of uncertainty on projects and organizational objectives.
Organizations and stakeholders are willing to accept varying degrees of risk depending on their risk
attitude.
The risk attitudes of both the organization and the stakeholders may be influenced by a number
of factors, which are broadly classified into three themes:
1. Risk appetite
2. Risk tolerance
3. Risk threshold
PROJECT RISK MANAGEMENT February 2016
DEFINATIONSDEFINATIONS
Risk Tolerance
Tolerances are the areas of risk that are acceptable or unacceptable OR which is the degree,
amount, or volume of risk that an organization or individual will withstand.
For example, "a risk that affects our reputation will not be tolerated”.
Tolerance areas can include any project constraints (such as scope, time, cost, quality, etc.), as
well as reputation and other intangibles that may affect the customer.well as reputation and other intangibles that may affect the customer.
Three common classifications used for describing risk tolerance or risk profile are the risk averse
(or avoider), risk neutral, or risk seeker (or taker).
Averse/Avoider Neutral Seeker/Taker
PROJECT RISK MANAGEMENT February 2016
DEFINATIONSDEFINATIONS
Risk Threshold
which refers to measures along the level of uncertainty or the level of impact at
which a stakeholder may have a specific interest.
A threshold is the point at which a risk becomes unacceptable.
Below that risk threshold, the organization will accept the risk.
Above that risk threshold, the organization will not tolerate the risk
For example, "If there is a delay, it can be no longer than two weeks.“For example, "If there is a delay, it can be no longer than two weeks.“
PROJECT RISK MANAGEMENT February 2016
ProjectProject Life Cycle and RiskLife Cycle and Risk
PROJECT RISK MANAGEMENT February 2016
Plan Risk Management
“The process of defining how to conduct risk management activities for a project”
Inputs Tools and Techniques Outputs
1. Project management plan.
2. Project Charter
1. Analytical techniques
2. Expert judgment
1. Risk management plan
3. Stakeholder register
4. Enterprise environmental
factors
5. Organizational process
assets
3. Meetings
The risk management plan is vital to communicate with and obtain
agreement and support from all stakeholders to ensure the risk
management process is supported and performed effectively over the
project life cycle.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Project management plan
All approved subsidiary management plans and baselines should be taken into
consideration in order to make the risk management plan consistent with them.
The project management plan provides baseline or current state of risk-affected
areas including scope, schedule, and cost.
2. Project charter
The project charter can provide various inputs such as high-level risks, high-level
project descriptions, and high-level requirements
3. Stakeholder register
The stakeholder register, which contains all details related to the project’s
stakeholders, provides an overview of their roles.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
4. Enterprise environmental factors
Risk attitudes, thresholds, and tolerances that describe the degree of risk that
an organization will withstand.
5. Organizational process assets
Risk categories,
Common definitions of concepts and terms,
Risk statement formats,
Standard templates,
Roles and responsibilities,
Authority levels for decision making, and
Lessons learned.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Analytical Techniques
Analytical techniques are used to understand and define the overall risk management
context of the project.
Risk management context is a combination of stakeholder risk attitudes and the
strategic risk exposure of a given project based on the overall project context.
A stakeholder risk profile analysis may be
performed to grade and qualify the project
stakeholder risk appetite and tolerance.
the use of strategic risk scoring sheets, are used
to provide a high-level assessment of the risk
exposure of the project based on the overall
project context.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Expert Judgment
To ensure a comprehensive establishment of the risk management plan, judgment,
and expertise should be considered from groups or individuals with specialized
training or knowledge on the subject area, such as:
Senior management,
Project stakeholders,
Project managers who have worked on projects in the same area (directly or
through lessons learned),
Subject matter experts (SMEs) in business or project area,
Industry groups and consultants, and
Professional and technical associations.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
3. Meetings
Project teams hold planning meetings to develop the risk management plan.
Attendees at these meetings may include the project manager, selected project
team members and stakeholders, anyone in the organization with responsibility to
manage the risk planning and execution activities, and others, as needed.
High-level plans for conducting the risk management activities are defined in these
meetings.
Risk management cost elements and schedule activities will be developed for
inclusion in the project budget and schedule, respectively.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Risk contingency reserve application approaches may be established or reviewed.
Risk management responsibilities will be assigned.
General organizational templates for risk categories and definitions of terms such as
levels of risk, probability by type of risk, impact by type of objectives, and the
probability and impact matrix will be tailored to the specific project.probability and impact matrix will be tailored to the specific project.
If templates for other steps in the process do not exist they may be generated in
these meetings.
The outputs of these activities will be
summarized in the risk management
plan.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Risk management plan
Methodology
Roles and responsibilities
Budgeting
Timing
Risk categories: Provides a structure that ensures a comprehensive process of
systematically identifying risks to a consistent level of detail and contributes to thesystematically identifying risks to a consistent level of detail and contributes to the
effectiveness and quality of the Identify Risks process.
An organization can use a previously prepared categorization framework which might
take the form of a simple list of categories or might be structured into a Risk
Breakdown Structure (RBS).
The RBS is a hierarchically organized depiction of the identified project risks
arranged by risk category and subcategory that identifies the various areas and
causes of potential risks.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Example of Risk Breakdown Structure (RBS)
A risk breakdown structure (RBS) helps the project team to look at many sources from which
project risk may arise in a risk identification exercise.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Definitions of probability and impact: General definitions of probability levels
and impact levels are tailored to the individual project during the Plan Risk
Management process for use in subsequent processes.
Probability and impact matrix: A probability and impact matrix is a grid for
mapping the probability of each risk occurrence and its impact on project objectives if
that risk occurs.
Risks are prioritized according to their potential implications for having an effect onRisks are prioritized according to their potential implications for having an effect on
the project’s objectives. A typical approach to prioritizing risks is to use a look-up
table or a probability and impact matrix.
Revised stakeholder tolerances
Reporting formats
Tracking: Documents how risk activities will be recorded for the benefit of the
current project, as well as for future needs and lessons learned, as well as whether
and how risk management processes will be audited.
PROJECT RISK MANAGEMENT February 2016
Example (Risk Management Plan)Example (Risk Management Plan)
Who What When How How much ($)
Hisham Identify 4 W Brain Storming, Delphi 4000
Ahmed Qualitative 6 W Risk Ranking 6000
Aly Response plan 2 W Strategies 2000
Project Duration: 36 M
Project Budget: 175 M$
1 2
3 4
5
6
Scale Probability
Scale Rang
VL < 20
L 20-40
M 40-60
H 60-80
VH >80
Scale Impact (for an
objective)
Scale Rang
VL < 10
L 10-20
M 20-30
H 30-60
VH >60
Risk Tolerance : Risk Averse
Risk Matrix
6
7
8
9
PROJECT RISK MANAGEMENT February 2016
Inputs Tools and Techniques Outputs
1. Risk management plan
2. Cost management plan
3. Schedule management plan
1. Documentation reviews
2. Information gathering techniques
3. Checklist analysis
1. Risk register
Identify Risks
“The process of determining which risks may affect the project and documenting their
characteristics”
3. Schedule management plan
4. Quality management plan
5. Human resource management plan
6. Scope baseline
7. Activity cost estimates
8. Activity duration estimates
9. Stakeholder register
10. Project documents
11. Procurement documents
12. Enterprise environmental Factors
13. Organizational process assets.
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgment
The key benefit of this process is the documentation of existing risks and the knowledge and
ability it provides to the project team to anticipate events.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Risk Management Plan
The assignments of roles and responsibilities, provision for risk management
activities in the budget and schedule, and categories of risk (RBS).
2. Cost Management Plan
The cost management plan provides processes and controls that can be used to help
identify risks across the project.identify risks across the project.
3. Schedule Management Plan
The schedule management plan provides insight to project time/schedule objectives
and expectations which may be impacted by risks (known and unknown).
4. Quality Management Plan
The quality management plan provides a baseline of quality measures and metrics
for use in identifying risks.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
5. Human Resource Management Plan
The human resource management plan provides guidance on how project human
resources should be defined, staffed, managed, and eventually released.
It can also contain roles and responsibilities, project organization charts, and the
staffing management plan, which form a key input to identify risk process.
6. Scope baseline
Uncertainty in project assumptions should be evaluated as potential causes of
project risk.
The WBS is a critical input to identifying risks.
7. Activity cost estimates
It provides a quantitative assessment of the likely cost to complete scheduled
activities and ideally are expressed as a range, with the width of the range indicating
the degree(s) of risk.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
8. Activity duration estimates
The time allowances for the activities or project as a whole, again with the width of
the range of such estimates indicating the relative degree(s) of risk .
9. Stakeholder register
Information about the stakeholders will be useful in soliciting inputs for identifying
risks as this will ensure that key stakeholders, especially the customer, are
interviewed or otherwise participate during the “Identify Risks” process
10.Project documents
Assumptions log,
Work performance reports,
Earned value reports,
Network diagrams,
Baselines, and
Other project information proven to be valuable in identifying risks.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
11.Procurement Documents
If the project requires external procurement of resources, procurement documents
become a key input to the Identify Risks process.
The complexity and the level of detail of the procurement documents should be
consistent with the value of, and risks associated with, planned procurement.
12.Enterprise Environmental Factors
Published information, including commercial databases,
Academic studies,
Published checklists,
Benchmarking,
Industry studies, and
Risk attitudes.
13. Organizational Process Assets.
Project files, including actual data,
Organizational and project process controls,
Risk statement templates, and
Lessons learned.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Documentation reviews
A structured review may be performed of project documentation, including plans,
assumptions, previous project files, contracts and other information.
The quality of the plans, as well as consistency between those plans and the project
requirements and assumptions, can be indicators of risk in the project.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Information Gathering Techniques
Brainstorming
The goal of brainstorming is to obtain a
comprehensible list of project risks.
This is a common technique for risk information
gathering.
A meeting where one idea helps generate another.A meeting where one idea helps generate another.
It can generate a large number of risks quickly.
One idea will bounce off another.
Pre-Mortem
Like brainstorming session (meeting to come up ideas).
The assembled group is asked to imagine that the project is
completed or has been terminated.
The group is then asked to describe why the project
failed/success.
Post-Mortem
A discussion of
an event after it
has happened,
especially of what
was wrong with it or
why it failed
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Affinity Diagram
This technique allows large numbers of ideas to be sorted into
groups for review and analysis.
It is a way to reach a consensus of experts on a subject.
It helps to expose crucial relationships and patterns in data
that may not be initially apparent.that may not be initially apparent.
Nominal group technique
Used when you need a technique to gain a group’s opinion
(group thinking), rather than individual opinions.
This technique enhances brainstorming with a voting process
used to rank the most useful ideas for further brainstorming
or for prioritization.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Delphi Technique
A selected group of experts answers
questionnaires and provides feedback.
Expert Judgment approach.
It is a way to reach a consensus of experts on
a subject.
It involves the following:It involves the following:
– Questionnaire to solicit ideas from the experts.
– Responses are submitted anonymously,
compiled, and then circulated to the experts
for review.
A consensus may be reached in a few rounds.
The Delphi technique helps reduce bias in the data and keeps any one person
from having undue influence on the outcome
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Interviewing:
Interviewing experienced project team members, stakeholders, and subject matter
experts (SMEs) can identify risks.
Interviews are another common source of risk identification data gathering.
They are NOT informal discussion.
They need to be planned, organized, and
controlled during delivery in order to be
most effective.
Gain the expert’s support for the project.
Expert interviews take time.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Root Cause Analysis:
Root-cause analysis is a specific technique used to identify a problem, discover the
underlying causes that lead to it, and develop preventive action.
This is a method used to further define the risk event.
Risks should be a specific, but often
the risks that are identified are
general and need more analysis to
determine what the real problem is.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
3. Checklist Analysis
Risk identification checklists can be developed based on historical information
and knowledge that has been accumulated from previous similar projects and from
other sources of information.
The lowest level of the RBS can also be used as a risk checklist.
It is a list of risk categories (prompt list)
The team should make sure to explore items that do not
appear on the checklist.
The checklist should be reviewed during project closure to
incorporate new lessons learned and improve it for use on
future projects.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
4. Assumptions Analysis
Every project is developed based on a set of hypotheses, scenarios, or assumptions.
Analyzing and exploring the validity of the assumptions can help identify risks due to
inaccuracy, inconsistency, or incompleteness.
5. Diagramming Techniques
Risk diagramming methods can be used to help in risk identification and risk trigger
identification such as;
Cause and effect diagrams:
These are also known as Ishikawa or fishbone diagrams and are useful for
identifying causes of risks.
Hypotheses: “an idea or explanation for something that is based on known facts but has not yet been proved”,
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
System or process flow charts:
These show how various elements of a system interrelate and the mechanism of
causation.
Influence diagrams:
These are graphical representations of situations showing causal influences,
time ordering of events, and other relationships among variables andtime ordering of events, and other relationships among variables and
outcomes.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Cause and Effect Diagram Example
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Process Flow Chart Example
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Influence Diagram Example
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
6. SWOT analysis
Strengths, weaknesses, opportunities, and threats
(SWOT) technique ensures examination of the project
from each of the SWOT perspectives.
This increases the breadth of considered risks.
7. Expert judgment
Risks can be identified directly by experts with relevant experience of similar projects
or business areas.
Such experts should be identified by the project manager and invited to consider all
aspects of the project and suggest possible risks based on their previous experience
and areas of expertise.
The experts’ bias should be taken into account in this process.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Risk Register
The outputs from risk identification are typically contained as initial entries into a
document called a risk register.
A template of the risk register can be downloaded from the Project Management
On-Line Guide.
The risk identification part of the template identifies:
Status: Whether a risk is an active risk, a dormant risk, or a retired risk.
ID#: The identification for the risk.
Date Identified & Project Phase: When a risk was identified and what project
phase (preconstruction or construction) the risk was identified in.
Dormant: Something that is dormant is not active or growing but has the ability to be active at a later time:
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Functional Assignment: The capital delivery functions (planning, design,
environmental, construction, etc.) which are impacted by the risk.
Risk Event: What the risk event is to the project with detailed description using
the SMART technique (Specific, Measurable, Achievable, Realistic, and Time
sensitive)
Risk Trigger: warning signs that indicate the risk is likely to occur or imminent
that used to determine when response strategies will be implemented.
Once the risk has been identified, the project team can conduct further analysis
(qualitative and quantitative) on the risk event.
Imminent; Coming or likely to happen very soon
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Example of Risk Register
PROJECT RISK MANAGEMENT February 2016
Inputs
Tools and
Techniques
Outputs
Perform Qualitative Risk Analysis
“The process of prioritizing risks for further analysis or action by assessing and
combining their probability of occurrence and impact”
1. Risk management plan
2. Scope baseline
3. Risk register
4. Enterprise environmental
factors
5. Organizational process
assets
1. Risk probability and impact
assessment
2. Probability and impact
matrix
3. Risk data quality assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert judgment
1. Project documents updates
The key benefit of this process is that it enables project managers to reduce the level of uncertainty
and to focus on high-priority risks
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Risk Management Plan
Key elements used; roles and responsibilities for conducting risk management,
budgets, schedule activities for risk management, risk categories, definitions of
probability and impact, the probability and impact matrix, and revised stakeholders’ risk
tolerances.
2. Scope Baseline
Projects of a common or recurrent type tend to have more well-understood risks.
Projects using state-of-the-art or first-of-its-kind technology, and highly complex
projects, tend to have more uncertainty.
This can be evaluated by examining the scope baseline.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
3. Risk Register
The risk register contains the information that will be used to assess and prioritize
risks.
4. Enterprise Environmental Factors
Industry studies of similar projects by risk specialists, and
Risk databases that may be available from industry or proprietary sources.
5. Organizational Process Assets
The organizational process assets that can influence the Perform Qualitative Risk
Analysis process include information on prior, similar completed projects.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Risk Probability and Impact Assessment
Risk probability assessment investigates the likelihood that each specific risk will
occur.
The probability of an event is defined, for risk management purposes, as the
probability of that event occurring in the absence of any actions to forestall it.
Risk impact (consequence) assessment investigates the potential effect on a
project objective such as schedule, cost, quality, or performance, including bothproject objective such as schedule, cost, quality, or performance, including both
negative effects for threats and positive effects for opportunities.
It is important that all those who are evaluating the risks use a standard
interpretation for risk assessment of probability and impact, in order to achieve
consistent evaluation of risk across multiple projects.
If risk scales are NOT already standardized in your organization, you must decided
which scales to use to determine probability and impact qualitatively.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Probability and Impact Matrix (PIM)
Risks can be prioritized for further quantitative analysis and response, based on their
risk rating/ranking.
Rankings are assigned to risks based on their assessed probability and impact
ratings
Risk score helps put the risk into a category that will guide risk response actions.Risk score helps put the risk into a category that will guide risk response actions.
Evaluation of each risk’s importance and, hence, priority for attention is typically
conducted using a look-up table or a probability and impact matrix.
P-I matrix can be based on ordinal (very low, low, medium, high, and very high ) or
cardinal (.1/ .3/ .5/ .7/ .9 or 1/ 2/ 3/ 4/ 5) scales.
Risk score helps put the risk into a category that will guide risk response actions.
Risk score = Probability X Impact
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
The organization should determine which combinations of probability and impact
result in a classification of high risk “red condition”, moderate risk “yellow condition”,
and low risk “green condition”.
For consistency with other risk assessment terms, a 1-5 scale for probability is used.
Project Risk Threshold is the
total amount of risk acceptable on the
Project Risk Score = ∑ risks score/ no. of risks.
project and usually takes the form of
maximum project risk score on
predetermined scale (e.g., a risk
score of no more than 50 on a scale
of 1 to 80).
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
3. Risk Data Quality Assessment
A qualitative risk analysis requires accurate and unbiased data if it is to be credible.
Analysis of the quality of risk data is a technique to evaluate the degree to which the
data about risks is useful for risk management.
It involves examining the degree to which the risk is understood and the accuracy,
quality, reliability, and integrity of the data about the risk.
The use of low-quality risk data may lead to a qualitative risk analysis of little use to
the project.
If data quality is unacceptable, it may be necessary to gather better data.
Often, collection of information about risks is difficult, and consumes time and resources
beyond that originally planned.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Sometimes it is difficult for people who are evaluating risks to be objective due to
BIAS.
Motivational Bias Cognitive Bias
People may attempt to bias the
results in one direction or
another.
People evaluation may be biased
due to difference in perception.
Having a description for 1 to 10 for example in the matrix will help eliminate some of
theses biases.
another.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
4. Risk Categorization
Risks to the project can be categorized by:
Sources of risk (using RBS).
The area of the project affected (using WBS).
Other useful category (project phase).
To determine areas of the project most exposed to the effects of uncertainty.
Grouping risks by common root causes can lead to developing effective riskGrouping risks by common root causes can lead to developing effective risk
responses.
5. Risk Urgency Assessment
Risks requiring near-term responses may be considered more urgent to address.
Indicators of priority can include time to affect a risk response, symptoms and
warning signs, and the risk rating.
6. Expert Judgment
Assess the probability and impact of each risk to determine its location in the matrix.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Project Documents Updates
Risk register updates
Relative ranking or priority list of project risks.
Risks grouped by categories.
Causes of risk or project areas requiring particular attention.
List of risks requiring response in the near-term: Those risks that require an
urgent response and those that can be handled at a later date may be put intourgent response and those that can be handled at a later date may be put into
different groups.
List of risks for additional analysis and response: Some risks might warrant more
analysis, including Quantitative Risk Analysis, as well as response action.
Watchlists of low-priority risks;
Risks that are NOT assessed as important in the Perform Qualitative Risk
Analysis process can be placed on a watchlist for continued monitoring.
Trends in qualitative risk analysis results.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Assumption log updates
Relative ranking or priority list of project risks.
The assumptions log needs to be revisited to accommodate this new information.
Assumptions may be incorporated into the project scope statement or in a separate
assumptions log.
The specific objectives of perform Qualitative Risk Analysis are to:
1. Subjectively evaluate the probability and impact of each risk.
2. Create a short list of risks by determining the top or critical risks that you
will quantify further and/or address in Plan Risk Responses process.
3. Assess the quality and reliability of the information you are working with.
4. Make a go/no-go decision.
PROJECT RISK MANAGEMENT February 2016
Inputs
Tools and
Techniques
Outputs
Perform Quantitative Risk Analysis
“The process of numerically analyzing the effect of identified risks on overall
project objectives”
1. Risk management plan
2. Cost management plan
3. Schedule management plan
4. Risk register
5. Enterprise environmental
factors
6. Organizational process
assets
1. Data gathering and
representation techniques
2. Quantitative risk analysis
and modeling techniques
3. Expert judgment
1. Project documents updates
The key benefit of this process is that it produces quantitative risk information to support
decision making in order to reduce project uncertainty.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Risk Management Plan
Provides guidelines, methods, and tools to be used in quantitative risk analysis.
2. Cost Management Plan
Provides guidelines on establishing and managing risk reserves.
3. Schedule Management Plan
Provides guidelines on establishing and managing risk reserves.
4. Risk Register
Used as a reference point for performing quantitative risk analysis.
5. Enterprise Environmental Factors
Industry studies of similar projects by risk specialists, and
Risk databases that may be available from industry or proprietary sources.
6. Organizational Process Assets
Information on prior, similar completed projects.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Data Gathering and Representation Techniques
Interviewing:
Draw on experience and historical data to quantify the probability and impact of
risks on project objectives.
The information needed depends upon the type of probability distributions that
will be used.will be used.
For instance, information would be gathered on the optimistic (low), pessimistic
(high), and most likely scenarios for some commonly used distributions.
Documenting the rationale of the risk ranges and the assumptions behind them
are important components of the risk interview because they can provide insight
on the reliability and credibility of the analysis.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Probability: The likelihood that a risk, or an event, will occur.
Probability = 0-1
Probability distributions:
Continuous probability distributions, used extensively in modeling and
simulation represent the uncertainty in values such as durations of schedule
activities and costs of project components.
Probability distribution are used to plot range of cost and schedule associated with
a risk.
This data can also be built from the three-point technique you use while
interviewing people, and try to get a range of cost and schedule that is possible if
a risk is materialized.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Once this data is collected you can draw one of the shape distribution graphs.
Commonly used ones are beta distribution that uses two value parameters
(alpha and beta), and triangular distribution which uses three parameters
(most-likely, best-case, worst-case).
Cost and time values are represented on x-axis and probability values on y-axis.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Continuous Distribution Discrete Distribution
Includes the probabilities of a full range of possible
outcomes.
Typically used for cost, time and quality metrics.
Show uncertainty in values.
Values are infinitely divisible (time, mass, distance).
May have a probability of ZERO.
Frequently use for modeling and simulation.
Includes the probabilities of a fixed number
of outcomes (based on a whole number).
Used to show uncertain events where the
probability of occurrence can be calculated.
May NOT have a probability of ZERO.
Used to represent possible scenarios in a
decision tree, result of a prototype, and
Usually represented as a curve.
There are five different types of Continuous
Distribution:
1. Normal Distribution (standard deviations)
2. Uniform Distribution (values equally probable,
scenarios where no obvious)
3. Beta Distribution
4. Triangular Distribution (three-point estimates)
5. Lognormal distribution (standard deviations,
random values)
decision tree, result of a prototype, and
result of tests.
For example, represented in a bar chart e.g.
assessing the probability of a task - like the
installation of plumbing - taking from four to
nine days to complete.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Quantitative Risk Analysis and Modeling Techniques
Sensitivity analysis:
Sensitivity analysis helps to determine which risks have the most potential impact
on the project.
It examines the extent to which the uncertainty of each project element affects
the objective being examined when all other uncertain elements are held at their
baseline values.baseline values.
Tornado diagram is the most useful way to represent the results of a Sensitivity
Analysis.
A tornado diagram in which a bar represents
each risk and the range of the impact it could
have, from negative to positive impact.
The length of each bar represents the relative
impact of each risk - the bars are ordered in
sequence from greatest impact to least.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Expected monetary value analysis:
Expected monetary value (EMV) analysis is a statistical concept that calculates the
average outcome when the future includes scenarios that may or may not
happen.
The EMV of opportunities will generally be expressed as positive values, while
those of threats will be negative.
EMV is calculated by multiplying the value of each possible outcome by its
probability of occurrence, and adding them together.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Decision tree analysis
Decision tree analysis is usually structured using a decision tree diagram that
describes a situation under consideration, and the implications of each of the
available choices and possible scenarios.
Solving the decision tree
provides the Expected Monetary
Value for each alternative, whenValue for each alternative, when
all the rewards and subsequent
decisions are quantified.
The decision tree analysis
technique for making decisions in
the presence of uncertainty can
be applied to many different
project management situations
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Modeling and simulation
A project simulation uses a model that translates the uncertainties specified at a
detailed level of the project into their potential impact on project objectives.
Simulations are typically performed using the Monte Carlo technique.
The Monte Carlo process, as applied to risk management,
• Create a series of
probability distributions for
Date: 7/11/2004 2:24:06 PM
Samples: 1000
Completion Std Deviation: 8.36 d
95% Confidence Interval: 0.52 d
probability distributions for
potential risk items.
• Randomly sample these
distributions.
• Transform these numbers
into useful information that
reflects quantification of
the potential risks of a real-
world situation.
Unique ID: 1
Name: Project
Each bar represents 3 d
Completion Date
Frequency
CumulativeProbability
3/11/31 4/5
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16 Completion Probability Table
Prob ProbDate Date
0.05 2/10
0.10 2/15
0.15 2/17
0.20 2/18
0.25 2/22
0.30 2/23
0.35 2/24
0.40 2/25
0.45 2/28
0.50 3/1
0.55 3/2
0.60 3/3
0.65 3/4
0.70 3/7
0.75 3/9
0.80 3/11
0.85 3/14
0.90 3/17
0.95 3/21
1.00 4/5
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Monte Carlo technique
1. It usually done with a computer-based program.
2. Evaluates the overall risk in the project.
3. Determines the probability of completing the project on any specific day, or for any specific
cost.
4. Determines the probability of any activity actually being on the critical path.
5. Takes into account path convergence.5. Takes into account path convergence.
6. Translates uncertainties into impacts to the total project.
7. Can be used to assess cost and schedule impacts.
8. Results in a probability distribution.
3. Expert Judgment
This is used to analyze and prepare input data to be used for the tools that does
modeling and simulation.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Quantitative Risk Analysis and Modeling Techniques:
1. Sensitivity Analysis: Determines which risks have the most potential impact on
the project.
2. Expected Monetary Value Analysis (EMV): multiplying the value of each
outcome by the probability of its occurrence.
3. Decision Tree Analysis: Incorporates probabilities of risks and costs or rewards
of each logical path.
4. Modeling & Simulation: Translates how uncertainties specified in a detailed level
of the project may affect its objectives.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Project Documents updates
The risk register updates from Perform Quantitative Risk Analysis include:
Probabilistic analysis of the project.
Probability of achieving cost and time objectives.
Prioritized list of quantified risks.
• Those that pose greater threats come at the top.
• Risks with big buffers most likely influences the critical path.
Trends in quantitative risk analysis results: showing conclusions that make affect
risk response.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Example of Risk Register
PROJECT RISK MANAGEMENT February 2016
Inputs
Tools and
Techniques
Outputs
1. Risk management plan 1. Strategies for negative risks 1. Project management plan
Plan Risk Responses
“The process of developing options and actions to enhance opportunities
and to reduce threats to project objectives.
1. Risk management plan
2. Risk register
1. Strategies for negative risks
or threats
2. Strategies for positive risks
or opportunities
3. Contingent response
strategies
4. Expert judgment
1. Project management plan
updates
2. Project document updates
The key benefit of this process is that it addresses the risks by their priority, inserting resources
and activities into the budget, schedule and project management plan as needed.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Risk Management Plan
Important components of the risk management plan include roles and
responsibilities, risk analysis definitions, timing for reviews (and for eliminating risks
from review) and risk thresholds for low, moderate, and high risks.
Risk thresholds help identify those risks for which specific responses are needed.
2. Risk Register
The risk register refers to identified risks, root causes of risks, lists of potential
responses, risk owners, symptoms and warning signs, the relative rating or priority
list of project risks, a list of risks requiring response in the near term, a list of risks
for additional analysis and response, trends in qualitative analysis results, and a
watchlist of low-priority risks.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Strategies for negative risks or threats
Avoidance or Eliminate
Risk avoidance involves changing a project objective to eliminate the threat
posed by the risk event.
It usually involves changing the project management plan to eliminate the
threat entirely.
The project manager may also isolate the project objectives from the risk’sThe project manager may also isolate the project objectives from the risk’s
impact or change the objective that is in jeopardy.
Examples of this include extending the schedule, changing the strategy, or
reducing scope.
The most radical avoidance strategy is to shut down the project entirely.
Some risks that arise early in the project can be avoided by clarifying
requirements, obtaining information, improving communication, or acquiring
expertise.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Transference or Deflect
Risk transference requires shifting the negative impact of a threat, along with
the ownership of the response, to a third party.
Transferring the risk DOES NOT eliminate the risk.
Transferring liability for a risk is most effective in dealing with financial risk
exposure.
Risk transference nearly always involves payment of a risk premium to the party
taking on the risk.
Some examples of risk transference are insurance, performance bonds,
warranties, guarantees, etc.
The best response strategy for fire or theft.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Mitigation
Risk mitigation implies a reduction in the probability and/or impact of a threat
posed by the risk event to an acceptable threshold.
Taking early action to reduce the probability and/or impact of a risk event
occurring on a project is often more effective than trying to repair the damage
after the risk has occurred.
Adopting less complex processes, conducting more tests, or choosing a
more stable supplier are examples of mitigation actions.
Mitigation may require prototype development to reduce the risk of scaling up
from a bench-scale model of a process or product
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Acceptance
This strategy is adopted because it is seldom possible to eliminate all risk from a
project.
This strategy is used when the project team has decided not to change the
project management plan to address or deal with the identified risk event, or the
project team is unable to identify any other suitable response strategy.
Acceptance is a risk response strategy used for both threats and opportunities.Acceptance is a risk response strategy used for both threats and opportunities.
This strategy can be either passive or active.
Passive Acceptance Active Acceptance
Requires no action except to document the strategy.
Leaving the project team to deal with the risks as they
occur.
To periodically review the threat to ensure that it
does not change significantly.
To establish a contingency reserve,
including amounts of time, money, or
resources to handle the risks.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Strategies for positive risks or opportunities
Exploit
This strategy may be selected for risks with positive impacts where the
organization wishes to ensure that the opportunity is realized.
This strategy seeks to eliminate the uncertainty associated with an opportunity
by making sure it happens.
Examples of directly exploiting responses includeExamples of directly exploiting responses include
assigning an organization’s most talented
resources to the project to reduce the time to
completion or using new technologies or
technology upgrades to reduce cost and duration
required to realize project objectives.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Share
Sharing a positive risk involves allocating ownership
to a third party who is best able to capture the
opportunity for the project.
One example of a share risk strategy is forming of
partnerships or joint ventures.
EnhanceEnhance
This strategy, similar to mitigation, increased the
probability and/or positive impacts of an opportunity.
Identifying and maximizing key drivers of these
positive-impact risks may increase the probability of
their occurrence.
Examples of enhancing opportunities include adding
more resources / crashing to an activity to finish early.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
Accept
Accepting an opportunity is being willing to take advantage of the opportunity if
it arises, but not actively pursuing it.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
3. Contingent response strategies
Contingency reserve is not a risk response strategy; it is an output of risk planning.
When a project team chooses to actively accept a project risk event, a
contingency reserve is established.
This is the amount of funds or budget needed above the estimate to reduce the risk
of overruns of project objectives to a level acceptable to the organization (within/of overruns of project objectives to a level acceptable to the organization (within/
below threshold limit).
4. Expert judgment
Expert judgment is input from knowledgeable parties pertaining to the actions to be
taken on a specific and defined risk.
Expertise may be provided by any group or person with specialized education,
knowledge, skill, experience, or training in establishing risk responses.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Project Management Plan Updates
Schedule management plan: This may include changes in tolerance or behavior related to
resource loading and leveling, as well as updates to the schedule strategy.
Cost management plan: This may include changes in tolerance or behavior related to cost
accounting, tracking, and reports, as well as updates to the budget strategy and how
contingency reserves are consumed.
Quality management plan: This may include changes in tolerance or behavior related to
requirements, quality assurance, or quality control, as well as updates to the requirements
documentation.
Procurement management plan: The procurement management plan may be updated to
reflect changes in strategy, such as alterations in the make-or-buy decision or contract type(s)
driven by the risk responses.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Human resource management plan: The staffing management plan, part of the human
resource management plan, is updated to reflect changes in project organizational structure and
resource applications driven by the risk responses. This may include changes in tolerance or
behavior related to staff allocation, as well as updates to the resource loading.
Scope baseline: Because of new, modified or omitted work generated by the risk responses,
the scope baseline may be updated to reflect those changes.
Schedule baseline: Because of new work (or omitted work) generated by the risk responses,Schedule baseline: Because of new work (or omitted work) generated by the risk responses,
the schedule baseline may be updated to reflect those changes.
Cost baseline: Because of new work (or omitted work) generated by the risk responses, the
cost baseline may be updated to reflect those changes.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
2. Project Document Updates
Updates to the risk register
Risk owners and assigned responsibilities;
Agreed-upon response strategies;
Specific actions to implement the chosen response strategy;
Trigger conditions, symptoms, and warning signs of a risk occurrence;
Budget and schedule activities required to implement the chosen responses;
Contingency plans and triggers that call for their execution;Contingency plans and triggers that call for their execution;
Fallback plans for use as a reaction to a risk that has occurred and the primary response
proves to be inadequate;
Residual risks that are expected to remain after planned responses have been taken, as
well as those that have been deliberately accepted;
Secondary risks that arise as a direct outcome of implementing a risk response; and
Contingency reserves that are calculated based on the quantitative risk analysis of the
project and the organization’s risk thresholds.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Risk triggers;
Trigger conditions, symptoms, and warning signs of a risk occurrence;
These are events that trigger the contingency response.
A project manager should identify the early warning signs (indirect
manifestations of actual risk events) for each risk on a project so that he or she
will know when to take action.
A risk may have one or more causes, and if the event occurs, one or moreA risk may have one or more causes, and if the event occurs, one or more
impacts.
Identifying the causes of risk events help define the risk trigger.
A risk trigger indicates that a risk event in imminent.
Occurs, one or more impacts.
Risk response owners;
Each risk must be assigned to someone who may help develop the risk
response and who will be assigned to carry out the risk response or “own” the
risk and MUST keep the project manager informed of any changes.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Contingency plans
Contingency plans are plans describing the specific actions that will be taken if
the opportunity or threat occurs.
Fallback plans;
These are specific actions that will be taken if the contingency plan is NOT
effective.
Residual risk; “ a leftover risk”
After implemented a risk response strategy, minor risk might still remain.After implemented a risk response strategy, minor risk might still remain.
The contingency reserve is set up to handle situations like this.
Secondary risks;
Risks that come about as a result of implementing a risk response.
When planning for risk, identify and plan responses for secondary risks that
could occur.
Reserves (contingency)
Having reserves for time and cost is a required part of project management.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Other project documents updated could include:
Assumptions log updates: The assumptions log needs to be revisited to accommodate
this new information.
Technical documentation updates: As new information becomes available through the
application of risk responses, technical approaches and physical deliverables may change.
Any supporting documentation needs to be revisited to accommodate this new information.
Change requests: Planning for possible risk responses can often result in
recommendations for changes to the resources, activities, cost estimates, and other itemsrecommendations for changes to the resources, activities, cost estimates, and other items
identified during other planning processes.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
Example of Risk Register
PROJECT RISK MANAGEMENT February 2016
Inputs
Tools and
Techniques
Outputs
Control Risks
“The process of implementing risk response plans, tracking identified risks, monitoring
residual risks, identifying new risks, and evaluating risk process effectiveness throughout the
project”
1. Project management plan
2. Risk register
3. Work performance data
4. Work performance reports
1. Risk reassessment
2. Risk audits
3. Variance and trend analysis
4. Technical performance
measurement
5. Reserve analysis
6. Meetings
1. Work performance
information
2. Change requests
3. Project management plan
updates
4. Project document updates
5. Organizational process
assets updates
The key benefit of this process is that it improves efficiency of the risk approach throughout the
project life cycle to continuously optimize risk responses
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
1. Project Management Plan
The project management plan described contains the risk management plan which
include;
Risk tolerances
Protocols and the assignment of people (including the risk owners),
Time, and other resources to project risk management.
2. Risk Register
The risk register has key inputs that includeThe risk register has key inputs that include
Identified risks
Risk owners
Agreed-upon risk responses
Specific implementation actions
Symptoms and warning signs of risk,
Residual and secondary risks
A watchlist of low-priority risks
The time and cost contingency reserves.
PROJECT RISK MANAGEMENT February 2016
INPUTSINPUTS
3. Work Performance Data
Work performance information related to various performance results includes:
Deliverable status.
Schedule progress.
Costs incurred.
4. Performance Reports
Performance reports take information from performance measurements and analyze
it to provide project work performance information including variance analysis,
earned value data, and forecasting data.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
1. Risk Reassessment
Control Risks often results in identification of new risks, reassessment of current
risks, and the closing of risks that are outdated.
Project risk reassessments should be regularly scheduled.
The results of such reassessments may include newly identifications, additional
qualitative or quantitative risk analysis, and further risk response planning.
Closing of Risks That Are NO Longer Applicable
The time when each identified risk can logically occur will eventually pass.
Closing of risks allows the team to focus on managing those risks that are still open.
The closing of a risk will likely result in the risk reserve being returned to the company.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
2. Risk Audits
Risk audits examine and document the effectiveness of risk responses in
dealing with identified risks and their root causes, as well as the effectiveness of
the risk management process.
It is arranged by project manager and results in identification of lessons learned
for the project and for other project in the organization.
Risk audits are evidence of how seriously risk should be taken on a project.
3. Variance and Trend Analysis
Compare the planned results to the actual results.
Trends in the project’s execution should be reviewed using performance data.
Earned value analysis and other methods of project variance and trend analysis may
be used for monitoring overall project performance.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
4. Technical performance measurement
Technical performance measurement compares technical accomplishments during
project execution to the project management plan’s schedule of technical
achievement.
Technical performance measures may include weight, transaction times, number of
delivered defects, storage capacity, etc.
Deviation, such as demonstrating more or less functionality than planned at aDeviation, such as demonstrating more or less functionality than planned at a
milestone, can help to forecast the degree of success in achieving the project’s
scope.
5. Reserve analysis
Reserve analysis compares the amount of the contingency reserves remaining to
the amount of risk remaining at any time in the project, in order to determine if the
remaining reserve is adequate.
Throughout execution of the project, some risks may occur, with positive or negative
impacts on budget or schedule contingency reserves.
PROJECT RISK MANAGEMENT February 2016
TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES
6. Meetings
Project risk management should be an agenda item at periodic status meetings.
The amount of time required for that item will vary, depending upon the risks that
have been identified, their priority, and difficulty of response.
Risk management becomes easier the more often it is practiced.
Frequent discussions about risk make it more likely that people will identify risks and
opportunities.
Risk should be a major topic at status
meetings to keep focus on risks, to continue
to identify new risks, and to make sure plans
remain appropriate.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
1. Work Performance Information
Work performance information, as a Control Risks output, provides a mechanism to
communicate and support project decision making.
Risk s can be identified anytime during the project lifecycle.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
2. Change requests
Implementing contingency plans or workarounds frequently results in a requirement
to change the project management plan to respond to risks.
Recommended corrective actions: These are activities that realign the performance
of the project work with the project management plan. They include contingency
plans and workarounds. The latter are responses that were not initially planned, but
are required to deal with emerging risks that were previously unidentified or
accepted passively.
Recommended preventive actions: These are activities that ensure that future
performance of the project work is aligned with the project management plan.
Workaround;
Workarounds are unplanned responses developed to deal with the
occurrence of unanticipated risk event.
Project managers who do not perform risk management spend most of their
time creating workarounds.
PROJECT RISK MANAGEMENT February 2016
OUTPUTSOUTPUTS
3. Project management plan updates
If the approved change requests have an effect on the risk management processes,
then the corresponding component documents of the project management plan are
revised and reissued to reflect the approved changes.
4. Project document updates
Actual outcomes of risk reassessments, risk audits, and periodic risk reviews.
Actual outcomes of the project’s risks and of the risk responses.
5. Organizational process assets updates
Templates for the risk management plan, including the probability and impact
matrix, and risk register.
Risk breakdown structure.
Lessons learned from the project risk management activities.
PROJECT RISK MANAGEMENT February 2016
Refreshments
Q1: All of the following are factors in the assessment of project risk EXCEPT:
A. Risk event.
B. Risk probability.
C. Amount at stake.
D. Insurance premiums.
Q2: If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a
US $100,000 loss, the expected monetary value for the project is:
A. $100,000 profit.
B. $60,000 loss.
C. $20,000 profit.
D. $40,000 loss.
PROJECT RISK MANAGEMENT February 2016
Refreshments
Q3:You have been appointed as the manager of a new, large, and complex project. Because
this project is business-critical and very visible, senior management has told you to analyze
the project's risks and prepare response strategies for them as soon as possible. The
organization has risk management procedures that are seldom used or followed, and has had
a history of handling risks badly. The project's first milestone is in two weeks. In preparing the
risk response plan, input from which of the following is generally LEAST important?
A. Project team membersA. Project team members
B. Project sponsor
C. Individuals responsible for risk management policies and templates
D. Key stakeholders
PROJECT RISK MANAGEMENT February 2016
Refreshments
Q4: A project team is creating a project management plan when management asks
them to identify project risks and provide some form of qualitative output as soon as
possible, What should the project team provide?
A. Prioritized list of project risks
B. Risk triggers
C. Contingency reservesC. Contingency reserves
D. Probability of achieving the time and cost objectives
PROJECT RISK MANAGEMENT February 2016
Refreshments
Q5: During the Identify Risks process, a project manager made a long list of risks
identified by all the stakeholders using various methods. He then made sure that all the
risks were understood and that triggers had been identified. Later, in the Plan Risk
Responses process, he took all the risks identified by the stakeholders and determined
ways to mitigate them. What has he done wrong?
A. The project manager should have waited until the Perform Qualitative Risk Analysis
process to get the stakeholders involved.
B. More people should be involved in the Plan Risk Responses process.
C. The project manager should have created workarounds.
D. Triggers are not identified until the Identify Risks process.
PROJECT RISK MANAGEMENT February 2016
THANK YOU
PROJECT RISK MANAGEMENT February 2016

More Related Content

What's hot

PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentationscottdreynolds
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementSaket Bansal
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesSlideTeam
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMarkos Mulat G
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
project risk management
project risk managementproject risk management
project risk managementAshima Thakur
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management OverviewJIGNESH PADIA
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Managementcgautam
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Project management
Project managementProject management
Project managementJay Raval
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
Introduction To Risk Management PowerPoint Presentation Slides
Introduction To Risk Management PowerPoint Presentation SlidesIntroduction To Risk Management PowerPoint Presentation Slides
Introduction To Risk Management PowerPoint Presentation SlidesSlideTeam
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 

What's hot (20)

PMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep PresentationPMI-RMP Exam Prep Presentation
PMI-RMP Exam Prep Presentation
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
Introduction to Risk Management
Introduction to Risk ManagementIntroduction to Risk Management
Introduction to Risk Management
 
Risk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation SlidesRisk Management Process And Procedures PowerPoint Presentation Slides
Risk Management Process And Procedures PowerPoint Presentation Slides
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Risk management
Risk managementRisk management
Risk management
 
project risk management
project risk managementproject risk management
project risk management
 
Risk Management Overview
Risk Management OverviewRisk Management Overview
Risk Management Overview
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project management
Project managementProject management
Project management
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Introduction To Risk Management PowerPoint Presentation Slides
Introduction To Risk Management PowerPoint Presentation SlidesIntroduction To Risk Management PowerPoint Presentation Slides
Introduction To Risk Management PowerPoint Presentation Slides
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 

Viewers also liked

What Is Project Risk Management?
What Is Project Risk Management?What Is Project Risk Management?
What Is Project Risk Management?Igor Kokcharov
 
Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained  Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained Igor Kokcharov
 
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...polenumerique33
 
PRA et PCA : plans de reprise et de continuité d'activité
 PRA et PCA : plans de reprise et de continuité d'activité PRA et PCA : plans de reprise et de continuité d'activité
PRA et PCA : plans de reprise et de continuité d'activitéChristophe Casalegno
 
Plan de Reprise d'Activité
Plan de Reprise d'ActivitéPlan de Reprise d'Activité
Plan de Reprise d'ActivitéitSMF France
 
Plan de continuité des activités: le vrai enjeu stratégique
Plan de continuité des activités: le vrai enjeu stratégiquePlan de continuité des activités: le vrai enjeu stratégique
Plan de continuité des activités: le vrai enjeu stratégiqueDigicomp Academy Suisse Romande SA
 
Plan de continuité d'activité - PCA
Plan de continuité d'activité - PCAPlan de continuité d'activité - PCA
Plan de continuité d'activité - PCAWissem CHEROUANA
 
Comment construire un plan de continuité d'activité ?
Comment construire un plan de continuité d'activité ?Comment construire un plan de continuité d'activité ?
Comment construire un plan de continuité d'activité ?BRIVA
 
Plan de reprise d’activité
Plan de reprise d’activitéPlan de reprise d’activité
Plan de reprise d’activitéExam PM
 

Viewers also liked (20)

What Is Project Risk Management?
What Is Project Risk Management?What Is Project Risk Management?
What Is Project Risk Management?
 
Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained  Responsibility Assignment Matrix - RACI Chart Explained
Responsibility Assignment Matrix - RACI Chart Explained
 
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...
Guide AFNOR Mettre en place un Plan de Continuité d’Activité (PCA) dans les P...
 
PRA et PCA : plans de reprise et de continuité d'activité
 PRA et PCA : plans de reprise et de continuité d'activité PRA et PCA : plans de reprise et de continuité d'activité
PRA et PCA : plans de reprise et de continuité d'activité
 
Plan de Reprise d'Activité
Plan de Reprise d'ActivitéPlan de Reprise d'Activité
Plan de Reprise d'Activité
 
Plan de continuité des activités: le vrai enjeu stratégique
Plan de continuité des activités: le vrai enjeu stratégiquePlan de continuité des activités: le vrai enjeu stratégique
Plan de continuité des activités: le vrai enjeu stratégique
 
Plan de continuité d'activité - PCA
Plan de continuité d'activité - PCAPlan de continuité d'activité - PCA
Plan de continuité d'activité - PCA
 
Comment construire un plan de continuité d'activité ?
Comment construire un plan de continuité d'activité ?Comment construire un plan de continuité d'activité ?
Comment construire un plan de continuité d'activité ?
 
Plan de reprise d’activité
Plan de reprise d’activitéPlan de reprise d’activité
Plan de reprise d’activité
 
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
CCP_SEC6_Economic Analysis Statistics and Probability and Risk
CCP_SEC6_Economic Analysis Statistics and Probability and RiskCCP_SEC6_Economic Analysis Statistics and Probability and Risk
CCP_SEC6_Economic Analysis Statistics and Probability and Risk
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
PMP_Professional and Social Responsibility
PMP_Professional and Social ResponsibilityPMP_Professional and Social Responsibility
PMP_Professional and Social Responsibility
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 

Similar to PMP_Project Risk Management

Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementHossam Maghrabi
 
Plan risk management
Plan risk management Plan risk management
Plan risk management Shereef Sabri
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship AliAbbas390458
 
Project Management by Mostafa Ewees
Project Management  by Mostafa EweesProject Management  by Mostafa Ewees
Project Management by Mostafa EweesMostafa Ewees
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxGeorgeKabongah2
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and applicationMarco De Santis, PMP, CFPP
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
 
Ihor Pavlenko: PMO Risk Management (UA )
Ihor Pavlenko: PMO Risk Management (UA )Ihor Pavlenko: PMO Risk Management (UA )
Ihor Pavlenko: PMO Risk Management (UA )Lviv Startup Club
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enVyacheslav Guzovsky
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)rafeeqameen
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxjoellemurphey
 
An introduction to finance
An introduction to financeAn introduction to finance
An introduction to financeRobert Reed
 
Pm0016 set-1
Pm0016 set-1Pm0016 set-1
Pm0016 set-1Paul Hunt
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaGlobalSkillup
 

Similar to PMP_Project Risk Management (20)

Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk Management
 
Plan risk management
Plan risk management Plan risk management
Plan risk management
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Project Management by Mostafa Ewees
Project Management  by Mostafa EweesProject Management  by Mostafa Ewees
Project Management by Mostafa Ewees
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and application
 
Risk management
Risk managementRisk management
Risk management
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 
11 risk management
11 risk management11 risk management
11 risk management
 
The Project Risk Management Process
The Project Risk Management ProcessThe Project Risk Management Process
The Project Risk Management Process
 
Li Rmp Prep
Li Rmp PrepLi Rmp Prep
Li Rmp Prep
 
Ihor Pavlenko: PMO Risk Management (UA )
Ihor Pavlenko: PMO Risk Management (UA )Ihor Pavlenko: PMO Risk Management (UA )
Ihor Pavlenko: PMO Risk Management (UA )
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Risk Management Assignment
Risk Management AssignmentRisk Management Assignment
Risk Management Assignment
 
Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
 
An introduction to finance
An introduction to financeAn introduction to finance
An introduction to finance
 
Pm0016 set-1
Pm0016 set-1Pm0016 set-1
Pm0016 set-1
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 

More from Hisham Haridy MBA, PMP®, RMP®, SP®

Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Hisham Haridy MBA, PMP®, RMP®, SP®
 
Practical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaPractical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaHisham Haridy MBA, PMP®, RMP®, SP®
 

More from Hisham Haridy MBA, PMP®, RMP®, SP® (14)

Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...
 
Implication of economic conditions in changing project objectives
Implication of economic conditions in changing project objectivesImplication of economic conditions in changing project objectives
Implication of economic conditions in changing project objectives
 
Practical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaPractical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabia
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
1_Project Management Foundation
1_Project Management Foundation1_Project Management Foundation
1_Project Management Foundation
 
ERM overview
ERM overviewERM overview
ERM overview
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
CCP_SEC1_Cost
CCP_SEC1_CostCCP_SEC1_Cost
CCP_SEC1_Cost
 
CCP_introduction
CCP_introductionCCP_introduction
CCP_introduction
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
PMP_Project Quality Management
PMP_Project Quality ManagementPMP_Project Quality Management
PMP_Project Quality Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 

Recently uploaded

Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 

Recently uploaded (16)

Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 

PMP_Project Risk Management

  • 1. PPROJECTROJECT RRISKISK MMANAGEMENTANAGEMENT Hisham Haridy, PMP, PMI-RMP February 2016
  • 2. Plan Risk Management Identify Risks Perform Qualitative Risk Perform Quantitative Risk Plan Risk Responses Control Risks Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning, and controlling risk on a project. Risk Management Management Risks Risk Analysis Risk Analysis Responses Risks Determining which risks might affect the project and documenting their characteristics (Risk Register). At least 300 risk should be identified. Prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact (Risk Register Update), Ranking, Watchlist. Numerically analyzing the effect on overall project objectives of identified risks (Risk Register Update), Watchlist. Implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. Deciding how to approach, plan, and execute the risk management activities for a project (Risk management Plan). Who? When? What? How? How much? P, I, PI matrix, RBS. Risk tolerance. Developing options and actions to enhance opportunities, and to reduce threats to project objectives. PROJECT RISK MANAGEMENT February 2016
  • 3. DEFINATIONSDEFINATIONS Project Risk Project risk in an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one of the project objectives (scope, schedule, budget, quality) Opportunity Threat A project risk that has a positive effect is referred to as an A project risk that has a negative effect is referred to as a threat.effect is referred to as an opportunity. A project manager will proactively manage opportunities to the project and look for ways to exploit, enhance, or share the opportunity. effect is referred to as a threat. A project manager will proactively manage threats to the project and look for ways to reduce the probability or impact of the threat (Mitigate) or eliminate the threat all together (avoid) or transfer to another party. PROJECT RISK MANAGEMENT February 2016
  • 4. DEFINATIONSDEFINATIONS Uncertainty Uncertainty is a lack of knowledge about an event that reduces confidence in conclusions drawn from the data. The investigation of uncertainties may help identify risks. Under certainty, the outcome can be predicted with a high degree of confidence. In reality, most decisions are taken without complete information, and therefore give rise to some degree of uncertainty in the outcome. Known Risks Unknown Risks Issue That have been identified and analyzed, making it possible to plan responses for those risks. That cannot be managed proactively, should be assigned a contingency reserve. Unknown risks cannot be managed proactively and therefore may be assigned a management reserve A negative project risk that has occurred is considered an issue. PROJECT RISK MANAGEMENT February 2016
  • 5. DEFINATIONSDEFINATIONS Risk Attitude Risk Factors When looking at risk, one should determine: The probability that it will occur (what) The range of possible outcomes (impact or amount at stake) Expected timing (when) in the project life cycle The anticipated frequency of risk events from that source (how often). Organizations perceive risk as the effect of uncertainty on projects and organizational objectives. Organizations and stakeholders are willing to accept varying degrees of risk depending on their risk attitude. The risk attitudes of both the organization and the stakeholders may be influenced by a number of factors, which are broadly classified into three themes: 1. Risk appetite 2. Risk tolerance 3. Risk threshold PROJECT RISK MANAGEMENT February 2016
  • 6. DEFINATIONSDEFINATIONS Risk Tolerance Tolerances are the areas of risk that are acceptable or unacceptable OR which is the degree, amount, or volume of risk that an organization or individual will withstand. For example, "a risk that affects our reputation will not be tolerated”. Tolerance areas can include any project constraints (such as scope, time, cost, quality, etc.), as well as reputation and other intangibles that may affect the customer.well as reputation and other intangibles that may affect the customer. Three common classifications used for describing risk tolerance or risk profile are the risk averse (or avoider), risk neutral, or risk seeker (or taker). Averse/Avoider Neutral Seeker/Taker PROJECT RISK MANAGEMENT February 2016
  • 7. DEFINATIONSDEFINATIONS Risk Threshold which refers to measures along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. A threshold is the point at which a risk becomes unacceptable. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk For example, "If there is a delay, it can be no longer than two weeks.“For example, "If there is a delay, it can be no longer than two weeks.“ PROJECT RISK MANAGEMENT February 2016
  • 8. ProjectProject Life Cycle and RiskLife Cycle and Risk PROJECT RISK MANAGEMENT February 2016
  • 9. Plan Risk Management “The process of defining how to conduct risk management activities for a project” Inputs Tools and Techniques Outputs 1. Project management plan. 2. Project Charter 1. Analytical techniques 2. Expert judgment 1. Risk management plan 3. Stakeholder register 4. Enterprise environmental factors 5. Organizational process assets 3. Meetings The risk management plan is vital to communicate with and obtain agreement and support from all stakeholders to ensure the risk management process is supported and performed effectively over the project life cycle. PROJECT RISK MANAGEMENT February 2016
  • 10. INPUTSINPUTS 1. Project management plan All approved subsidiary management plans and baselines should be taken into consideration in order to make the risk management plan consistent with them. The project management plan provides baseline or current state of risk-affected areas including scope, schedule, and cost. 2. Project charter The project charter can provide various inputs such as high-level risks, high-level project descriptions, and high-level requirements 3. Stakeholder register The stakeholder register, which contains all details related to the project’s stakeholders, provides an overview of their roles. PROJECT RISK MANAGEMENT February 2016
  • 11. INPUTSINPUTS 4. Enterprise environmental factors Risk attitudes, thresholds, and tolerances that describe the degree of risk that an organization will withstand. 5. Organizational process assets Risk categories, Common definitions of concepts and terms, Risk statement formats, Standard templates, Roles and responsibilities, Authority levels for decision making, and Lessons learned. PROJECT RISK MANAGEMENT February 2016
  • 12. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Analytical Techniques Analytical techniques are used to understand and define the overall risk management context of the project. Risk management context is a combination of stakeholder risk attitudes and the strategic risk exposure of a given project based on the overall project context. A stakeholder risk profile analysis may be performed to grade and qualify the project stakeholder risk appetite and tolerance. the use of strategic risk scoring sheets, are used to provide a high-level assessment of the risk exposure of the project based on the overall project context. PROJECT RISK MANAGEMENT February 2016
  • 13. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Expert Judgment To ensure a comprehensive establishment of the risk management plan, judgment, and expertise should be considered from groups or individuals with specialized training or knowledge on the subject area, such as: Senior management, Project stakeholders, Project managers who have worked on projects in the same area (directly or through lessons learned), Subject matter experts (SMEs) in business or project area, Industry groups and consultants, and Professional and technical associations. PROJECT RISK MANAGEMENT February 2016
  • 14. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 3. Meetings Project teams hold planning meetings to develop the risk management plan. Attendees at these meetings may include the project manager, selected project team members and stakeholders, anyone in the organization with responsibility to manage the risk planning and execution activities, and others, as needed. High-level plans for conducting the risk management activities are defined in these meetings. Risk management cost elements and schedule activities will be developed for inclusion in the project budget and schedule, respectively. PROJECT RISK MANAGEMENT February 2016
  • 15. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Risk contingency reserve application approaches may be established or reviewed. Risk management responsibilities will be assigned. General organizational templates for risk categories and definitions of terms such as levels of risk, probability by type of risk, impact by type of objectives, and the probability and impact matrix will be tailored to the specific project.probability and impact matrix will be tailored to the specific project. If templates for other steps in the process do not exist they may be generated in these meetings. The outputs of these activities will be summarized in the risk management plan. PROJECT RISK MANAGEMENT February 2016
  • 16. OUTPUTSOUTPUTS 1. Risk management plan Methodology Roles and responsibilities Budgeting Timing Risk categories: Provides a structure that ensures a comprehensive process of systematically identifying risks to a consistent level of detail and contributes to thesystematically identifying risks to a consistent level of detail and contributes to the effectiveness and quality of the Identify Risks process. An organization can use a previously prepared categorization framework which might take the form of a simple list of categories or might be structured into a Risk Breakdown Structure (RBS). The RBS is a hierarchically organized depiction of the identified project risks arranged by risk category and subcategory that identifies the various areas and causes of potential risks. PROJECT RISK MANAGEMENT February 2016
  • 17. OUTPUTSOUTPUTS Example of Risk Breakdown Structure (RBS) A risk breakdown structure (RBS) helps the project team to look at many sources from which project risk may arise in a risk identification exercise. PROJECT RISK MANAGEMENT February 2016
  • 18. OUTPUTSOUTPUTS Definitions of probability and impact: General definitions of probability levels and impact levels are tailored to the individual project during the Plan Risk Management process for use in subsequent processes. Probability and impact matrix: A probability and impact matrix is a grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs. Risks are prioritized according to their potential implications for having an effect onRisks are prioritized according to their potential implications for having an effect on the project’s objectives. A typical approach to prioritizing risks is to use a look-up table or a probability and impact matrix. Revised stakeholder tolerances Reporting formats Tracking: Documents how risk activities will be recorded for the benefit of the current project, as well as for future needs and lessons learned, as well as whether and how risk management processes will be audited. PROJECT RISK MANAGEMENT February 2016
  • 19. Example (Risk Management Plan)Example (Risk Management Plan) Who What When How How much ($) Hisham Identify 4 W Brain Storming, Delphi 4000 Ahmed Qualitative 6 W Risk Ranking 6000 Aly Response plan 2 W Strategies 2000 Project Duration: 36 M Project Budget: 175 M$ 1 2 3 4 5 6 Scale Probability Scale Rang VL < 20 L 20-40 M 40-60 H 60-80 VH >80 Scale Impact (for an objective) Scale Rang VL < 10 L 10-20 M 20-30 H 30-60 VH >60 Risk Tolerance : Risk Averse Risk Matrix 6 7 8 9 PROJECT RISK MANAGEMENT February 2016
  • 20. Inputs Tools and Techniques Outputs 1. Risk management plan 2. Cost management plan 3. Schedule management plan 1. Documentation reviews 2. Information gathering techniques 3. Checklist analysis 1. Risk register Identify Risks “The process of determining which risks may affect the project and documenting their characteristics” 3. Schedule management plan 4. Quality management plan 5. Human resource management plan 6. Scope baseline 7. Activity cost estimates 8. Activity duration estimates 9. Stakeholder register 10. Project documents 11. Procurement documents 12. Enterprise environmental Factors 13. Organizational process assets. 3. Checklist analysis 4. Assumptions analysis 5. Diagramming techniques 6. SWOT analysis 7. Expert judgment The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events. PROJECT RISK MANAGEMENT February 2016
  • 21. INPUTSINPUTS 1. Risk Management Plan The assignments of roles and responsibilities, provision for risk management activities in the budget and schedule, and categories of risk (RBS). 2. Cost Management Plan The cost management plan provides processes and controls that can be used to help identify risks across the project.identify risks across the project. 3. Schedule Management Plan The schedule management plan provides insight to project time/schedule objectives and expectations which may be impacted by risks (known and unknown). 4. Quality Management Plan The quality management plan provides a baseline of quality measures and metrics for use in identifying risks. PROJECT RISK MANAGEMENT February 2016
  • 22. INPUTSINPUTS 5. Human Resource Management Plan The human resource management plan provides guidance on how project human resources should be defined, staffed, managed, and eventually released. It can also contain roles and responsibilities, project organization charts, and the staffing management plan, which form a key input to identify risk process. 6. Scope baseline Uncertainty in project assumptions should be evaluated as potential causes of project risk. The WBS is a critical input to identifying risks. 7. Activity cost estimates It provides a quantitative assessment of the likely cost to complete scheduled activities and ideally are expressed as a range, with the width of the range indicating the degree(s) of risk. PROJECT RISK MANAGEMENT February 2016
  • 23. INPUTSINPUTS 8. Activity duration estimates The time allowances for the activities or project as a whole, again with the width of the range of such estimates indicating the relative degree(s) of risk . 9. Stakeholder register Information about the stakeholders will be useful in soliciting inputs for identifying risks as this will ensure that key stakeholders, especially the customer, are interviewed or otherwise participate during the “Identify Risks” process 10.Project documents Assumptions log, Work performance reports, Earned value reports, Network diagrams, Baselines, and Other project information proven to be valuable in identifying risks. PROJECT RISK MANAGEMENT February 2016
  • 24. INPUTSINPUTS 11.Procurement Documents If the project requires external procurement of resources, procurement documents become a key input to the Identify Risks process. The complexity and the level of detail of the procurement documents should be consistent with the value of, and risks associated with, planned procurement. 12.Enterprise Environmental Factors Published information, including commercial databases, Academic studies, Published checklists, Benchmarking, Industry studies, and Risk attitudes. 13. Organizational Process Assets. Project files, including actual data, Organizational and project process controls, Risk statement templates, and Lessons learned. PROJECT RISK MANAGEMENT February 2016
  • 25. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Documentation reviews A structured review may be performed of project documentation, including plans, assumptions, previous project files, contracts and other information. The quality of the plans, as well as consistency between those plans and the project requirements and assumptions, can be indicators of risk in the project. PROJECT RISK MANAGEMENT February 2016
  • 26. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Information Gathering Techniques Brainstorming The goal of brainstorming is to obtain a comprehensible list of project risks. This is a common technique for risk information gathering. A meeting where one idea helps generate another.A meeting where one idea helps generate another. It can generate a large number of risks quickly. One idea will bounce off another. Pre-Mortem Like brainstorming session (meeting to come up ideas). The assembled group is asked to imagine that the project is completed or has been terminated. The group is then asked to describe why the project failed/success. Post-Mortem A discussion of an event after it has happened, especially of what was wrong with it or why it failed PROJECT RISK MANAGEMENT February 2016
  • 27. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Affinity Diagram This technique allows large numbers of ideas to be sorted into groups for review and analysis. It is a way to reach a consensus of experts on a subject. It helps to expose crucial relationships and patterns in data that may not be initially apparent.that may not be initially apparent. Nominal group technique Used when you need a technique to gain a group’s opinion (group thinking), rather than individual opinions. This technique enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization. PROJECT RISK MANAGEMENT February 2016
  • 28. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Delphi Technique A selected group of experts answers questionnaires and provides feedback. Expert Judgment approach. It is a way to reach a consensus of experts on a subject. It involves the following:It involves the following: – Questionnaire to solicit ideas from the experts. – Responses are submitted anonymously, compiled, and then circulated to the experts for review. A consensus may be reached in a few rounds. The Delphi technique helps reduce bias in the data and keeps any one person from having undue influence on the outcome PROJECT RISK MANAGEMENT February 2016
  • 29. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Interviewing: Interviewing experienced project team members, stakeholders, and subject matter experts (SMEs) can identify risks. Interviews are another common source of risk identification data gathering. They are NOT informal discussion. They need to be planned, organized, and controlled during delivery in order to be most effective. Gain the expert’s support for the project. Expert interviews take time. PROJECT RISK MANAGEMENT February 2016
  • 30. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Root Cause Analysis: Root-cause analysis is a specific technique used to identify a problem, discover the underlying causes that lead to it, and develop preventive action. This is a method used to further define the risk event. Risks should be a specific, but often the risks that are identified are general and need more analysis to determine what the real problem is. PROJECT RISK MANAGEMENT February 2016
  • 31. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 3. Checklist Analysis Risk identification checklists can be developed based on historical information and knowledge that has been accumulated from previous similar projects and from other sources of information. The lowest level of the RBS can also be used as a risk checklist. It is a list of risk categories (prompt list) The team should make sure to explore items that do not appear on the checklist. The checklist should be reviewed during project closure to incorporate new lessons learned and improve it for use on future projects. PROJECT RISK MANAGEMENT February 2016
  • 32. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 4. Assumptions Analysis Every project is developed based on a set of hypotheses, scenarios, or assumptions. Analyzing and exploring the validity of the assumptions can help identify risks due to inaccuracy, inconsistency, or incompleteness. 5. Diagramming Techniques Risk diagramming methods can be used to help in risk identification and risk trigger identification such as; Cause and effect diagrams: These are also known as Ishikawa or fishbone diagrams and are useful for identifying causes of risks. Hypotheses: “an idea or explanation for something that is based on known facts but has not yet been proved”, PROJECT RISK MANAGEMENT February 2016
  • 33. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES System or process flow charts: These show how various elements of a system interrelate and the mechanism of causation. Influence diagrams: These are graphical representations of situations showing causal influences, time ordering of events, and other relationships among variables andtime ordering of events, and other relationships among variables and outcomes. PROJECT RISK MANAGEMENT February 2016
  • 34. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Cause and Effect Diagram Example PROJECT RISK MANAGEMENT February 2016
  • 35. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Process Flow Chart Example PROJECT RISK MANAGEMENT February 2016
  • 36. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Influence Diagram Example PROJECT RISK MANAGEMENT February 2016
  • 37. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 6. SWOT analysis Strengths, weaknesses, opportunities, and threats (SWOT) technique ensures examination of the project from each of the SWOT perspectives. This increases the breadth of considered risks. 7. Expert judgment Risks can be identified directly by experts with relevant experience of similar projects or business areas. Such experts should be identified by the project manager and invited to consider all aspects of the project and suggest possible risks based on their previous experience and areas of expertise. The experts’ bias should be taken into account in this process. PROJECT RISK MANAGEMENT February 2016
  • 38. OUTPUTSOUTPUTS 1. Risk Register The outputs from risk identification are typically contained as initial entries into a document called a risk register. A template of the risk register can be downloaded from the Project Management On-Line Guide. The risk identification part of the template identifies: Status: Whether a risk is an active risk, a dormant risk, or a retired risk. ID#: The identification for the risk. Date Identified & Project Phase: When a risk was identified and what project phase (preconstruction or construction) the risk was identified in. Dormant: Something that is dormant is not active or growing but has the ability to be active at a later time: PROJECT RISK MANAGEMENT February 2016
  • 39. OUTPUTSOUTPUTS Functional Assignment: The capital delivery functions (planning, design, environmental, construction, etc.) which are impacted by the risk. Risk Event: What the risk event is to the project with detailed description using the SMART technique (Specific, Measurable, Achievable, Realistic, and Time sensitive) Risk Trigger: warning signs that indicate the risk is likely to occur or imminent that used to determine when response strategies will be implemented. Once the risk has been identified, the project team can conduct further analysis (qualitative and quantitative) on the risk event. Imminent; Coming or likely to happen very soon PROJECT RISK MANAGEMENT February 2016
  • 40. OUTPUTSOUTPUTS Example of Risk Register PROJECT RISK MANAGEMENT February 2016
  • 41. Inputs Tools and Techniques Outputs Perform Qualitative Risk Analysis “The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact” 1. Risk management plan 2. Scope baseline 3. Risk register 4. Enterprise environmental factors 5. Organizational process assets 1. Risk probability and impact assessment 2. Probability and impact matrix 3. Risk data quality assessment 4. Risk categorization 5. Risk urgency assessment 6. Expert judgment 1. Project documents updates The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks PROJECT RISK MANAGEMENT February 2016
  • 42. INPUTSINPUTS 1. Risk Management Plan Key elements used; roles and responsibilities for conducting risk management, budgets, schedule activities for risk management, risk categories, definitions of probability and impact, the probability and impact matrix, and revised stakeholders’ risk tolerances. 2. Scope Baseline Projects of a common or recurrent type tend to have more well-understood risks. Projects using state-of-the-art or first-of-its-kind technology, and highly complex projects, tend to have more uncertainty. This can be evaluated by examining the scope baseline. PROJECT RISK MANAGEMENT February 2016
  • 43. INPUTSINPUTS 3. Risk Register The risk register contains the information that will be used to assess and prioritize risks. 4. Enterprise Environmental Factors Industry studies of similar projects by risk specialists, and Risk databases that may be available from industry or proprietary sources. 5. Organizational Process Assets The organizational process assets that can influence the Perform Qualitative Risk Analysis process include information on prior, similar completed projects. PROJECT RISK MANAGEMENT February 2016
  • 44. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Risk Probability and Impact Assessment Risk probability assessment investigates the likelihood that each specific risk will occur. The probability of an event is defined, for risk management purposes, as the probability of that event occurring in the absence of any actions to forestall it. Risk impact (consequence) assessment investigates the potential effect on a project objective such as schedule, cost, quality, or performance, including bothproject objective such as schedule, cost, quality, or performance, including both negative effects for threats and positive effects for opportunities. It is important that all those who are evaluating the risks use a standard interpretation for risk assessment of probability and impact, in order to achieve consistent evaluation of risk across multiple projects. If risk scales are NOT already standardized in your organization, you must decided which scales to use to determine probability and impact qualitatively. PROJECT RISK MANAGEMENT February 2016
  • 45. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Probability and Impact Matrix (PIM) Risks can be prioritized for further quantitative analysis and response, based on their risk rating/ranking. Rankings are assigned to risks based on their assessed probability and impact ratings Risk score helps put the risk into a category that will guide risk response actions.Risk score helps put the risk into a category that will guide risk response actions. Evaluation of each risk’s importance and, hence, priority for attention is typically conducted using a look-up table or a probability and impact matrix. P-I matrix can be based on ordinal (very low, low, medium, high, and very high ) or cardinal (.1/ .3/ .5/ .7/ .9 or 1/ 2/ 3/ 4/ 5) scales. Risk score helps put the risk into a category that will guide risk response actions. Risk score = Probability X Impact PROJECT RISK MANAGEMENT February 2016
  • 46. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES The organization should determine which combinations of probability and impact result in a classification of high risk “red condition”, moderate risk “yellow condition”, and low risk “green condition”. For consistency with other risk assessment terms, a 1-5 scale for probability is used. Project Risk Threshold is the total amount of risk acceptable on the Project Risk Score = ∑ risks score/ no. of risks. project and usually takes the form of maximum project risk score on predetermined scale (e.g., a risk score of no more than 50 on a scale of 1 to 80). PROJECT RISK MANAGEMENT February 2016
  • 47. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 3. Risk Data Quality Assessment A qualitative risk analysis requires accurate and unbiased data if it is to be credible. Analysis of the quality of risk data is a technique to evaluate the degree to which the data about risks is useful for risk management. It involves examining the degree to which the risk is understood and the accuracy, quality, reliability, and integrity of the data about the risk. The use of low-quality risk data may lead to a qualitative risk analysis of little use to the project. If data quality is unacceptable, it may be necessary to gather better data. Often, collection of information about risks is difficult, and consumes time and resources beyond that originally planned. PROJECT RISK MANAGEMENT February 2016
  • 48. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Sometimes it is difficult for people who are evaluating risks to be objective due to BIAS. Motivational Bias Cognitive Bias People may attempt to bias the results in one direction or another. People evaluation may be biased due to difference in perception. Having a description for 1 to 10 for example in the matrix will help eliminate some of theses biases. another. PROJECT RISK MANAGEMENT February 2016
  • 49. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 4. Risk Categorization Risks to the project can be categorized by: Sources of risk (using RBS). The area of the project affected (using WBS). Other useful category (project phase). To determine areas of the project most exposed to the effects of uncertainty. Grouping risks by common root causes can lead to developing effective riskGrouping risks by common root causes can lead to developing effective risk responses. 5. Risk Urgency Assessment Risks requiring near-term responses may be considered more urgent to address. Indicators of priority can include time to affect a risk response, symptoms and warning signs, and the risk rating. 6. Expert Judgment Assess the probability and impact of each risk to determine its location in the matrix. PROJECT RISK MANAGEMENT February 2016
  • 50. OUTPUTSOUTPUTS 1. Project Documents Updates Risk register updates Relative ranking or priority list of project risks. Risks grouped by categories. Causes of risk or project areas requiring particular attention. List of risks requiring response in the near-term: Those risks that require an urgent response and those that can be handled at a later date may be put intourgent response and those that can be handled at a later date may be put into different groups. List of risks for additional analysis and response: Some risks might warrant more analysis, including Quantitative Risk Analysis, as well as response action. Watchlists of low-priority risks; Risks that are NOT assessed as important in the Perform Qualitative Risk Analysis process can be placed on a watchlist for continued monitoring. Trends in qualitative risk analysis results. PROJECT RISK MANAGEMENT February 2016
  • 51. OUTPUTSOUTPUTS Assumption log updates Relative ranking or priority list of project risks. The assumptions log needs to be revisited to accommodate this new information. Assumptions may be incorporated into the project scope statement or in a separate assumptions log. The specific objectives of perform Qualitative Risk Analysis are to: 1. Subjectively evaluate the probability and impact of each risk. 2. Create a short list of risks by determining the top or critical risks that you will quantify further and/or address in Plan Risk Responses process. 3. Assess the quality and reliability of the information you are working with. 4. Make a go/no-go decision. PROJECT RISK MANAGEMENT February 2016
  • 52. Inputs Tools and Techniques Outputs Perform Quantitative Risk Analysis “The process of numerically analyzing the effect of identified risks on overall project objectives” 1. Risk management plan 2. Cost management plan 3. Schedule management plan 4. Risk register 5. Enterprise environmental factors 6. Organizational process assets 1. Data gathering and representation techniques 2. Quantitative risk analysis and modeling techniques 3. Expert judgment 1. Project documents updates The key benefit of this process is that it produces quantitative risk information to support decision making in order to reduce project uncertainty. PROJECT RISK MANAGEMENT February 2016
  • 53. INPUTSINPUTS 1. Risk Management Plan Provides guidelines, methods, and tools to be used in quantitative risk analysis. 2. Cost Management Plan Provides guidelines on establishing and managing risk reserves. 3. Schedule Management Plan Provides guidelines on establishing and managing risk reserves. 4. Risk Register Used as a reference point for performing quantitative risk analysis. 5. Enterprise Environmental Factors Industry studies of similar projects by risk specialists, and Risk databases that may be available from industry or proprietary sources. 6. Organizational Process Assets Information on prior, similar completed projects. PROJECT RISK MANAGEMENT February 2016
  • 54. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Data Gathering and Representation Techniques Interviewing: Draw on experience and historical data to quantify the probability and impact of risks on project objectives. The information needed depends upon the type of probability distributions that will be used.will be used. For instance, information would be gathered on the optimistic (low), pessimistic (high), and most likely scenarios for some commonly used distributions. Documenting the rationale of the risk ranges and the assumptions behind them are important components of the risk interview because they can provide insight on the reliability and credibility of the analysis. PROJECT RISK MANAGEMENT February 2016
  • 55. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Probability: The likelihood that a risk, or an event, will occur. Probability = 0-1 Probability distributions: Continuous probability distributions, used extensively in modeling and simulation represent the uncertainty in values such as durations of schedule activities and costs of project components. Probability distribution are used to plot range of cost and schedule associated with a risk. This data can also be built from the three-point technique you use while interviewing people, and try to get a range of cost and schedule that is possible if a risk is materialized. PROJECT RISK MANAGEMENT February 2016
  • 56. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Once this data is collected you can draw one of the shape distribution graphs. Commonly used ones are beta distribution that uses two value parameters (alpha and beta), and triangular distribution which uses three parameters (most-likely, best-case, worst-case). Cost and time values are represented on x-axis and probability values on y-axis. PROJECT RISK MANAGEMENT February 2016
  • 57. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Continuous Distribution Discrete Distribution Includes the probabilities of a full range of possible outcomes. Typically used for cost, time and quality metrics. Show uncertainty in values. Values are infinitely divisible (time, mass, distance). May have a probability of ZERO. Frequently use for modeling and simulation. Includes the probabilities of a fixed number of outcomes (based on a whole number). Used to show uncertain events where the probability of occurrence can be calculated. May NOT have a probability of ZERO. Used to represent possible scenarios in a decision tree, result of a prototype, and Usually represented as a curve. There are five different types of Continuous Distribution: 1. Normal Distribution (standard deviations) 2. Uniform Distribution (values equally probable, scenarios where no obvious) 3. Beta Distribution 4. Triangular Distribution (three-point estimates) 5. Lognormal distribution (standard deviations, random values) decision tree, result of a prototype, and result of tests. For example, represented in a bar chart e.g. assessing the probability of a task - like the installation of plumbing - taking from four to nine days to complete. PROJECT RISK MANAGEMENT February 2016
  • 58. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Quantitative Risk Analysis and Modeling Techniques Sensitivity analysis: Sensitivity analysis helps to determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values.baseline values. Tornado diagram is the most useful way to represent the results of a Sensitivity Analysis. A tornado diagram in which a bar represents each risk and the range of the impact it could have, from negative to positive impact. The length of each bar represents the relative impact of each risk - the bars are ordered in sequence from greatest impact to least. PROJECT RISK MANAGEMENT February 2016
  • 59. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Expected monetary value analysis: Expected monetary value (EMV) analysis is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen. The EMV of opportunities will generally be expressed as positive values, while those of threats will be negative. EMV is calculated by multiplying the value of each possible outcome by its probability of occurrence, and adding them together. PROJECT RISK MANAGEMENT February 2016
  • 60. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Decision tree analysis Decision tree analysis is usually structured using a decision tree diagram that describes a situation under consideration, and the implications of each of the available choices and possible scenarios. Solving the decision tree provides the Expected Monetary Value for each alternative, whenValue for each alternative, when all the rewards and subsequent decisions are quantified. The decision tree analysis technique for making decisions in the presence of uncertainty can be applied to many different project management situations PROJECT RISK MANAGEMENT February 2016
  • 61. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES PROJECT RISK MANAGEMENT February 2016
  • 62. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Modeling and simulation A project simulation uses a model that translates the uncertainties specified at a detailed level of the project into their potential impact on project objectives. Simulations are typically performed using the Monte Carlo technique. The Monte Carlo process, as applied to risk management, • Create a series of probability distributions for Date: 7/11/2004 2:24:06 PM Samples: 1000 Completion Std Deviation: 8.36 d 95% Confidence Interval: 0.52 d probability distributions for potential risk items. • Randomly sample these distributions. • Transform these numbers into useful information that reflects quantification of the potential risks of a real- world situation. Unique ID: 1 Name: Project Each bar represents 3 d Completion Date Frequency CumulativeProbability 3/11/31 4/5 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.02 0.04 0.06 0.08 0.10 0.12 0.14 0.16 Completion Probability Table Prob ProbDate Date 0.05 2/10 0.10 2/15 0.15 2/17 0.20 2/18 0.25 2/22 0.30 2/23 0.35 2/24 0.40 2/25 0.45 2/28 0.50 3/1 0.55 3/2 0.60 3/3 0.65 3/4 0.70 3/7 0.75 3/9 0.80 3/11 0.85 3/14 0.90 3/17 0.95 3/21 1.00 4/5 PROJECT RISK MANAGEMENT February 2016
  • 63. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Monte Carlo technique 1. It usually done with a computer-based program. 2. Evaluates the overall risk in the project. 3. Determines the probability of completing the project on any specific day, or for any specific cost. 4. Determines the probability of any activity actually being on the critical path. 5. Takes into account path convergence.5. Takes into account path convergence. 6. Translates uncertainties into impacts to the total project. 7. Can be used to assess cost and schedule impacts. 8. Results in a probability distribution. 3. Expert Judgment This is used to analyze and prepare input data to be used for the tools that does modeling and simulation. PROJECT RISK MANAGEMENT February 2016
  • 64. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Quantitative Risk Analysis and Modeling Techniques: 1. Sensitivity Analysis: Determines which risks have the most potential impact on the project. 2. Expected Monetary Value Analysis (EMV): multiplying the value of each outcome by the probability of its occurrence. 3. Decision Tree Analysis: Incorporates probabilities of risks and costs or rewards of each logical path. 4. Modeling & Simulation: Translates how uncertainties specified in a detailed level of the project may affect its objectives. PROJECT RISK MANAGEMENT February 2016
  • 65. OUTPUTSOUTPUTS 1. Project Documents updates The risk register updates from Perform Quantitative Risk Analysis include: Probabilistic analysis of the project. Probability of achieving cost and time objectives. Prioritized list of quantified risks. • Those that pose greater threats come at the top. • Risks with big buffers most likely influences the critical path. Trends in quantitative risk analysis results: showing conclusions that make affect risk response. PROJECT RISK MANAGEMENT February 2016
  • 66. OUTPUTSOUTPUTS Example of Risk Register PROJECT RISK MANAGEMENT February 2016
  • 67. Inputs Tools and Techniques Outputs 1. Risk management plan 1. Strategies for negative risks 1. Project management plan Plan Risk Responses “The process of developing options and actions to enhance opportunities and to reduce threats to project objectives. 1. Risk management plan 2. Risk register 1. Strategies for negative risks or threats 2. Strategies for positive risks or opportunities 3. Contingent response strategies 4. Expert judgment 1. Project management plan updates 2. Project document updates The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed. PROJECT RISK MANAGEMENT February 2016
  • 68. INPUTSINPUTS 1. Risk Management Plan Important components of the risk management plan include roles and responsibilities, risk analysis definitions, timing for reviews (and for eliminating risks from review) and risk thresholds for low, moderate, and high risks. Risk thresholds help identify those risks for which specific responses are needed. 2. Risk Register The risk register refers to identified risks, root causes of risks, lists of potential responses, risk owners, symptoms and warning signs, the relative rating or priority list of project risks, a list of risks requiring response in the near term, a list of risks for additional analysis and response, trends in qualitative analysis results, and a watchlist of low-priority risks. PROJECT RISK MANAGEMENT February 2016
  • 69. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Strategies for negative risks or threats Avoidance or Eliminate Risk avoidance involves changing a project objective to eliminate the threat posed by the risk event. It usually involves changing the project management plan to eliminate the threat entirely. The project manager may also isolate the project objectives from the risk’sThe project manager may also isolate the project objectives from the risk’s impact or change the objective that is in jeopardy. Examples of this include extending the schedule, changing the strategy, or reducing scope. The most radical avoidance strategy is to shut down the project entirely. Some risks that arise early in the project can be avoided by clarifying requirements, obtaining information, improving communication, or acquiring expertise. PROJECT RISK MANAGEMENT February 2016
  • 70. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Transference or Deflect Risk transference requires shifting the negative impact of a threat, along with the ownership of the response, to a third party. Transferring the risk DOES NOT eliminate the risk. Transferring liability for a risk is most effective in dealing with financial risk exposure. Risk transference nearly always involves payment of a risk premium to the party taking on the risk. Some examples of risk transference are insurance, performance bonds, warranties, guarantees, etc. The best response strategy for fire or theft. PROJECT RISK MANAGEMENT February 2016
  • 71. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Mitigation Risk mitigation implies a reduction in the probability and/or impact of a threat posed by the risk event to an acceptable threshold. Taking early action to reduce the probability and/or impact of a risk event occurring on a project is often more effective than trying to repair the damage after the risk has occurred. Adopting less complex processes, conducting more tests, or choosing a more stable supplier are examples of mitigation actions. Mitigation may require prototype development to reduce the risk of scaling up from a bench-scale model of a process or product PROJECT RISK MANAGEMENT February 2016
  • 72. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Acceptance This strategy is adopted because it is seldom possible to eliminate all risk from a project. This strategy is used when the project team has decided not to change the project management plan to address or deal with the identified risk event, or the project team is unable to identify any other suitable response strategy. Acceptance is a risk response strategy used for both threats and opportunities.Acceptance is a risk response strategy used for both threats and opportunities. This strategy can be either passive or active. Passive Acceptance Active Acceptance Requires no action except to document the strategy. Leaving the project team to deal with the risks as they occur. To periodically review the threat to ensure that it does not change significantly. To establish a contingency reserve, including amounts of time, money, or resources to handle the risks. PROJECT RISK MANAGEMENT February 2016
  • 73. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES PROJECT RISK MANAGEMENT February 2016
  • 74. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Strategies for positive risks or opportunities Exploit This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with an opportunity by making sure it happens. Examples of directly exploiting responses includeExamples of directly exploiting responses include assigning an organization’s most talented resources to the project to reduce the time to completion or using new technologies or technology upgrades to reduce cost and duration required to realize project objectives. PROJECT RISK MANAGEMENT February 2016
  • 75. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Share Sharing a positive risk involves allocating ownership to a third party who is best able to capture the opportunity for the project. One example of a share risk strategy is forming of partnerships or joint ventures. EnhanceEnhance This strategy, similar to mitigation, increased the probability and/or positive impacts of an opportunity. Identifying and maximizing key drivers of these positive-impact risks may increase the probability of their occurrence. Examples of enhancing opportunities include adding more resources / crashing to an activity to finish early. PROJECT RISK MANAGEMENT February 2016
  • 76. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES Accept Accepting an opportunity is being willing to take advantage of the opportunity if it arises, but not actively pursuing it. PROJECT RISK MANAGEMENT February 2016
  • 77. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 3. Contingent response strategies Contingency reserve is not a risk response strategy; it is an output of risk planning. When a project team chooses to actively accept a project risk event, a contingency reserve is established. This is the amount of funds or budget needed above the estimate to reduce the risk of overruns of project objectives to a level acceptable to the organization (within/of overruns of project objectives to a level acceptable to the organization (within/ below threshold limit). 4. Expert judgment Expert judgment is input from knowledgeable parties pertaining to the actions to be taken on a specific and defined risk. Expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training in establishing risk responses. PROJECT RISK MANAGEMENT February 2016
  • 78. OUTPUTSOUTPUTS 1. Project Management Plan Updates Schedule management plan: This may include changes in tolerance or behavior related to resource loading and leveling, as well as updates to the schedule strategy. Cost management plan: This may include changes in tolerance or behavior related to cost accounting, tracking, and reports, as well as updates to the budget strategy and how contingency reserves are consumed. Quality management plan: This may include changes in tolerance or behavior related to requirements, quality assurance, or quality control, as well as updates to the requirements documentation. Procurement management plan: The procurement management plan may be updated to reflect changes in strategy, such as alterations in the make-or-buy decision or contract type(s) driven by the risk responses. PROJECT RISK MANAGEMENT February 2016
  • 79. OUTPUTSOUTPUTS Human resource management plan: The staffing management plan, part of the human resource management plan, is updated to reflect changes in project organizational structure and resource applications driven by the risk responses. This may include changes in tolerance or behavior related to staff allocation, as well as updates to the resource loading. Scope baseline: Because of new, modified or omitted work generated by the risk responses, the scope baseline may be updated to reflect those changes. Schedule baseline: Because of new work (or omitted work) generated by the risk responses,Schedule baseline: Because of new work (or omitted work) generated by the risk responses, the schedule baseline may be updated to reflect those changes. Cost baseline: Because of new work (or omitted work) generated by the risk responses, the cost baseline may be updated to reflect those changes. PROJECT RISK MANAGEMENT February 2016
  • 80. OUTPUTSOUTPUTS 2. Project Document Updates Updates to the risk register Risk owners and assigned responsibilities; Agreed-upon response strategies; Specific actions to implement the chosen response strategy; Trigger conditions, symptoms, and warning signs of a risk occurrence; Budget and schedule activities required to implement the chosen responses; Contingency plans and triggers that call for their execution;Contingency plans and triggers that call for their execution; Fallback plans for use as a reaction to a risk that has occurred and the primary response proves to be inadequate; Residual risks that are expected to remain after planned responses have been taken, as well as those that have been deliberately accepted; Secondary risks that arise as a direct outcome of implementing a risk response; and Contingency reserves that are calculated based on the quantitative risk analysis of the project and the organization’s risk thresholds. PROJECT RISK MANAGEMENT February 2016
  • 81. OUTPUTSOUTPUTS Risk triggers; Trigger conditions, symptoms, and warning signs of a risk occurrence; These are events that trigger the contingency response. A project manager should identify the early warning signs (indirect manifestations of actual risk events) for each risk on a project so that he or she will know when to take action. A risk may have one or more causes, and if the event occurs, one or moreA risk may have one or more causes, and if the event occurs, one or more impacts. Identifying the causes of risk events help define the risk trigger. A risk trigger indicates that a risk event in imminent. Occurs, one or more impacts. Risk response owners; Each risk must be assigned to someone who may help develop the risk response and who will be assigned to carry out the risk response or “own” the risk and MUST keep the project manager informed of any changes. PROJECT RISK MANAGEMENT February 2016
  • 82. OUTPUTSOUTPUTS Contingency plans Contingency plans are plans describing the specific actions that will be taken if the opportunity or threat occurs. Fallback plans; These are specific actions that will be taken if the contingency plan is NOT effective. Residual risk; “ a leftover risk” After implemented a risk response strategy, minor risk might still remain.After implemented a risk response strategy, minor risk might still remain. The contingency reserve is set up to handle situations like this. Secondary risks; Risks that come about as a result of implementing a risk response. When planning for risk, identify and plan responses for secondary risks that could occur. Reserves (contingency) Having reserves for time and cost is a required part of project management. PROJECT RISK MANAGEMENT February 2016
  • 83. OUTPUTSOUTPUTS Other project documents updated could include: Assumptions log updates: The assumptions log needs to be revisited to accommodate this new information. Technical documentation updates: As new information becomes available through the application of risk responses, technical approaches and physical deliverables may change. Any supporting documentation needs to be revisited to accommodate this new information. Change requests: Planning for possible risk responses can often result in recommendations for changes to the resources, activities, cost estimates, and other itemsrecommendations for changes to the resources, activities, cost estimates, and other items identified during other planning processes. PROJECT RISK MANAGEMENT February 2016
  • 84. OUTPUTSOUTPUTS Example of Risk Register PROJECT RISK MANAGEMENT February 2016
  • 85. Inputs Tools and Techniques Outputs Control Risks “The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project” 1. Project management plan 2. Risk register 3. Work performance data 4. Work performance reports 1. Risk reassessment 2. Risk audits 3. Variance and trend analysis 4. Technical performance measurement 5. Reserve analysis 6. Meetings 1. Work performance information 2. Change requests 3. Project management plan updates 4. Project document updates 5. Organizational process assets updates The key benefit of this process is that it improves efficiency of the risk approach throughout the project life cycle to continuously optimize risk responses PROJECT RISK MANAGEMENT February 2016
  • 86. INPUTSINPUTS 1. Project Management Plan The project management plan described contains the risk management plan which include; Risk tolerances Protocols and the assignment of people (including the risk owners), Time, and other resources to project risk management. 2. Risk Register The risk register has key inputs that includeThe risk register has key inputs that include Identified risks Risk owners Agreed-upon risk responses Specific implementation actions Symptoms and warning signs of risk, Residual and secondary risks A watchlist of low-priority risks The time and cost contingency reserves. PROJECT RISK MANAGEMENT February 2016
  • 87. INPUTSINPUTS 3. Work Performance Data Work performance information related to various performance results includes: Deliverable status. Schedule progress. Costs incurred. 4. Performance Reports Performance reports take information from performance measurements and analyze it to provide project work performance information including variance analysis, earned value data, and forecasting data. PROJECT RISK MANAGEMENT February 2016
  • 88. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 1. Risk Reassessment Control Risks often results in identification of new risks, reassessment of current risks, and the closing of risks that are outdated. Project risk reassessments should be regularly scheduled. The results of such reassessments may include newly identifications, additional qualitative or quantitative risk analysis, and further risk response planning. Closing of Risks That Are NO Longer Applicable The time when each identified risk can logically occur will eventually pass. Closing of risks allows the team to focus on managing those risks that are still open. The closing of a risk will likely result in the risk reserve being returned to the company. PROJECT RISK MANAGEMENT February 2016
  • 89. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 2. Risk Audits Risk audits examine and document the effectiveness of risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process. It is arranged by project manager and results in identification of lessons learned for the project and for other project in the organization. Risk audits are evidence of how seriously risk should be taken on a project. 3. Variance and Trend Analysis Compare the planned results to the actual results. Trends in the project’s execution should be reviewed using performance data. Earned value analysis and other methods of project variance and trend analysis may be used for monitoring overall project performance. PROJECT RISK MANAGEMENT February 2016
  • 90. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 4. Technical performance measurement Technical performance measurement compares technical accomplishments during project execution to the project management plan’s schedule of technical achievement. Technical performance measures may include weight, transaction times, number of delivered defects, storage capacity, etc. Deviation, such as demonstrating more or less functionality than planned at aDeviation, such as demonstrating more or less functionality than planned at a milestone, can help to forecast the degree of success in achieving the project’s scope. 5. Reserve analysis Reserve analysis compares the amount of the contingency reserves remaining to the amount of risk remaining at any time in the project, in order to determine if the remaining reserve is adequate. Throughout execution of the project, some risks may occur, with positive or negative impacts on budget or schedule contingency reserves. PROJECT RISK MANAGEMENT February 2016
  • 91. TOOLS AND TECHNIQUESTOOLS AND TECHNIQUES 6. Meetings Project risk management should be an agenda item at periodic status meetings. The amount of time required for that item will vary, depending upon the risks that have been identified, their priority, and difficulty of response. Risk management becomes easier the more often it is practiced. Frequent discussions about risk make it more likely that people will identify risks and opportunities. Risk should be a major topic at status meetings to keep focus on risks, to continue to identify new risks, and to make sure plans remain appropriate. PROJECT RISK MANAGEMENT February 2016
  • 92. OUTPUTSOUTPUTS 1. Work Performance Information Work performance information, as a Control Risks output, provides a mechanism to communicate and support project decision making. Risk s can be identified anytime during the project lifecycle. PROJECT RISK MANAGEMENT February 2016
  • 93. OUTPUTSOUTPUTS 2. Change requests Implementing contingency plans or workarounds frequently results in a requirement to change the project management plan to respond to risks. Recommended corrective actions: These are activities that realign the performance of the project work with the project management plan. They include contingency plans and workarounds. The latter are responses that were not initially planned, but are required to deal with emerging risks that were previously unidentified or accepted passively. Recommended preventive actions: These are activities that ensure that future performance of the project work is aligned with the project management plan. Workaround; Workarounds are unplanned responses developed to deal with the occurrence of unanticipated risk event. Project managers who do not perform risk management spend most of their time creating workarounds. PROJECT RISK MANAGEMENT February 2016
  • 94. OUTPUTSOUTPUTS 3. Project management plan updates If the approved change requests have an effect on the risk management processes, then the corresponding component documents of the project management plan are revised and reissued to reflect the approved changes. 4. Project document updates Actual outcomes of risk reassessments, risk audits, and periodic risk reviews. Actual outcomes of the project’s risks and of the risk responses. 5. Organizational process assets updates Templates for the risk management plan, including the probability and impact matrix, and risk register. Risk breakdown structure. Lessons learned from the project risk management activities. PROJECT RISK MANAGEMENT February 2016
  • 95. Refreshments Q1: All of the following are factors in the assessment of project risk EXCEPT: A. Risk event. B. Risk probability. C. Amount at stake. D. Insurance premiums. Q2: If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value for the project is: A. $100,000 profit. B. $60,000 loss. C. $20,000 profit. D. $40,000 loss. PROJECT RISK MANAGEMENT February 2016
  • 96. Refreshments Q3:You have been appointed as the manager of a new, large, and complex project. Because this project is business-critical and very visible, senior management has told you to analyze the project's risks and prepare response strategies for them as soon as possible. The organization has risk management procedures that are seldom used or followed, and has had a history of handling risks badly. The project's first milestone is in two weeks. In preparing the risk response plan, input from which of the following is generally LEAST important? A. Project team membersA. Project team members B. Project sponsor C. Individuals responsible for risk management policies and templates D. Key stakeholders PROJECT RISK MANAGEMENT February 2016
  • 97. Refreshments Q4: A project team is creating a project management plan when management asks them to identify project risks and provide some form of qualitative output as soon as possible, What should the project team provide? A. Prioritized list of project risks B. Risk triggers C. Contingency reservesC. Contingency reserves D. Probability of achieving the time and cost objectives PROJECT RISK MANAGEMENT February 2016
  • 98. Refreshments Q5: During the Identify Risks process, a project manager made a long list of risks identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers had been identified. Later, in the Plan Risk Responses process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong? A. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholders involved. B. More people should be involved in the Plan Risk Responses process. C. The project manager should have created workarounds. D. Triggers are not identified until the Identify Risks process. PROJECT RISK MANAGEMENT February 2016
  • 99. THANK YOU PROJECT RISK MANAGEMENT February 2016