Project Plan For a
Training Web-Site
                     Presented By:
               M.Gohar Iqbal (5052)
       Software Project Management
Introduction:
Scope:
   trainings offered by the company (4-5 trainings)
   trainer’s profile (3-4 trainers)
   6-month training calendar


Functional Requirements:
   Home page contains introduction of Training company, its mission etc.
   The website should have the trainings and can add more if required in future.
   Should show upcoming events.
   The website should contains trainer, their profile.
   Through web site anyone (end user) can access the training’s and trainers’ data,
    experience etc. (read only for end users).
   The time management for trainings in form of calendar for 6-months (which is
    given in scope).
   Different Tabs like Clientele, Contact us, About us, Careers etc
Project Plan
Project Team
   Project Manager
   Assistant Project Manager
   Consultant
   2 Web developers and 1 graphics designer
   1 QA tester


Project Schedule:
   2 week project
   Agile method selected particularly SCRUM.
   M.S Project Professional 2010 is used for scheduling.
Gantt Chart
Communication Plan:

Two types of communications are planned:
   Regular/Ongoing meetings:
                  Communications   Purpose        Audience     Author    Communication      Frequency
                                                                         vehicle location
                  Scrum Meeting    Monitor the    Whole team   Project   Emails, Posting    Daily for 15
                                   progress and
                  For two weeks                                Manager   on websites,       min
                                   report.
                                                                         Meetings

   One time event driven communications:
For requirement gathering between vendor and consultant will be done in the
first two days of the first week. And the second last day of the second week with
final product.
Team Skills:
S.NO.   Team Member                 Qualification

01      Project Manager             PMI certified, 20 years implementation experience in ERP
                                    and managing projects.

02      Assistant Project Manager   PMI certified, 10 years implementation experience in
                                    managing ERP projects.

03      Consultant                  Web developing experience for 7 years in php, .net, SAP SD
                                    certified consultant.

04      Web developer               Experience in php, python, and Java and HTML 5 script for 5
                                    years.

05      Web developer               Java, ASP.net and HTML experience for 3 years.

06      Graphic Designer            Adobe Photoshop, Adobe Flash, Adobe Illustrator, Maya, Auto
                                    CAD. Experience of 5 years.



07      QA tester                   CSQA, CSTE, CISA, COBIT, had previous experience for 15
                                    years in testing software.
Risk Assessment:
   RMMM info sheet is used for risk planning.
                                            Risk Information Sheet
        Risk ID: R0003     Date: 25/4/2013            Prob: 80%               Impact: high




        Description: Employee Turnover

        Key personnel leave the project taking critical information with them that
        significantly delays or derails the project.
        Refinement /Context:

        Sub Condition 1: Developer gets another attractive job.

        Sub Condition 2: Any conflict occurs between consultant with developer or manager.
        Mitigation & Monitoring:

        Increased collaboration and information sharing on the team.
        Management/Contingency Plan/Trigger:
        Manage a backup plan inform of extra developers and designers. Developers must have same
        knowledge e.g. of language as were previous had, same with designer.

        Current Status: Planned

        Originator: Project Manager                   Assigned: Asst. Project Manager
THANK YOU!

More Related Content

Viewers also liked

Addie model
Addie modelAddie model
Addie modelSDM1946
 
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressed
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressedDunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressed
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressedRoss Peizer
 
Teacher technology survey and needs assessment school name
Teacher technology survey and needs assessment            school nameTeacher technology survey and needs assessment            school name
Teacher technology survey and needs assessment school namelisawitteman
 
20150212_HAI Health needs assessment lebanon_Final Report
20150212_HAI Health needs assessment lebanon_Final Report20150212_HAI Health needs assessment lebanon_Final Report
20150212_HAI Health needs assessment lebanon_Final ReportBoris Aristin
 
Heat exchanger - Training course material
Heat exchanger - Training course materialHeat exchanger - Training course material
Heat exchanger - Training course materialBassem Eleaba, MEng
 
A project report on training and development
A project report on training and developmentA project report on training and development
A project report on training and developmentProjects Kart
 
A project report on training and development with reference to hal
A project report on training and development with reference to halA project report on training and development with reference to hal
A project report on training and development with reference to halProjects Kart
 
Example training plans
Example training plansExample training plans
Example training plansSteve Saffhill
 
Study on effectiveness of training and development
Study on effectiveness of training and developmentStudy on effectiveness of training and development
Study on effectiveness of training and developmentAnoop Voyager
 
49368010 project-report-on-training-and-development
49368010 project-report-on-training-and-development49368010 project-report-on-training-and-development
49368010 project-report-on-training-and-developmentsagarkirti
 

Viewers also liked (13)

Addie model
Addie modelAddie model
Addie model
 
Training Module Project Plan
Training Module Project PlanTraining Module Project Plan
Training Module Project Plan
 
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressed
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressedDunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressed
Dunes City Bicycle Pedestrian Needs Assessment Presentation 8_14_14.compressed
 
Teacher technology survey and needs assessment school name
Teacher technology survey and needs assessment            school nameTeacher technology survey and needs assessment            school name
Teacher technology survey and needs assessment school name
 
20150212_HAI Health needs assessment lebanon_Final Report
20150212_HAI Health needs assessment lebanon_Final Report20150212_HAI Health needs assessment lebanon_Final Report
20150212_HAI Health needs assessment lebanon_Final Report
 
Heat exchanger - Training course material
Heat exchanger - Training course materialHeat exchanger - Training course material
Heat exchanger - Training course material
 
A project report on training and development
A project report on training and developmentA project report on training and development
A project report on training and development
 
TRAINING DESIGN
TRAINING DESIGNTRAINING DESIGN
TRAINING DESIGN
 
A project report on training and development with reference to hal
A project report on training and development with reference to halA project report on training and development with reference to hal
A project report on training and development with reference to hal
 
Training Design sample
Training Design sampleTraining Design sample
Training Design sample
 
Example training plans
Example training plansExample training plans
Example training plans
 
Study on effectiveness of training and development
Study on effectiveness of training and developmentStudy on effectiveness of training and development
Study on effectiveness of training and development
 
49368010 project-report-on-training-and-development
49368010 project-report-on-training-and-development49368010 project-report-on-training-and-development
49368010 project-report-on-training-and-development
 

Similar to Project plan for a training web site (20)

Project manager with 10+ years of IT experience.
Project manager with 10+ years of IT experience.Project manager with 10+ years of IT experience.
Project manager with 10+ years of IT experience.
 
Gowsika_Cognos_Business_Intelligence
Gowsika_Cognos_Business_IntelligenceGowsika_Cognos_Business_Intelligence
Gowsika_Cognos_Business_Intelligence
 
Himal_Cv
Himal_CvHimal_Cv
Himal_Cv
 
Resume
ResumeResume
Resume
 
Project governance
Project governanceProject governance
Project governance
 
NeetaBudhani_Resume
NeetaBudhani_ResumeNeetaBudhani_Resume
NeetaBudhani_Resume
 
PB_28042011
PB_28042011PB_28042011
PB_28042011
 
Rohit Resume
Rohit ResumeRohit Resume
Rohit Resume
 
05262016 resume
05262016 resume05262016 resume
05262016 resume
 
ManuNair_PM_Profile
ManuNair_PM_ProfileManuNair_PM_Profile
ManuNair_PM_Profile
 
Cloud Developer Resume Jhon-Arzu-Gil
Cloud Developer Resume Jhon-Arzu-Gil Cloud Developer Resume Jhon-Arzu-Gil
Cloud Developer Resume Jhon-Arzu-Gil
 
Mohab CV e
Mohab CV eMohab CV e
Mohab CV e
 
Project Plan And Estimation
Project Plan And EstimationProject Plan And Estimation
Project Plan And Estimation
 
Resume
ResumeResume
Resume
 
Duryodhan_rout_2+yrs_UI_Developer
Duryodhan_rout_2+yrs_UI_DeveloperDuryodhan_rout_2+yrs_UI_Developer
Duryodhan_rout_2+yrs_UI_Developer
 
Cognizant
CognizantCognizant
Cognizant
 
Consultant/Manager with 15+ Years of experience in IT industry handling multi...
Consultant/Manager with 15+ Years of experience in IT industry handling multi...Consultant/Manager with 15+ Years of experience in IT industry handling multi...
Consultant/Manager with 15+ Years of experience in IT industry handling multi...
 
Brocoders general presentation
Brocoders general presentationBrocoders general presentation
Brocoders general presentation
 
Resume-Natasha P Divecha
Resume-Natasha P Divecha Resume-Natasha P Divecha
Resume-Natasha P Divecha
 
Mahesh_J_Resume.docx
Mahesh_J_Resume.docxMahesh_J_Resume.docx
Mahesh_J_Resume.docx
 

More from gohar Iqbal

Key performance indicatiors
Key performance indicatiorsKey performance indicatiors
Key performance indicatiorsgohar Iqbal
 
Psychological contract
Psychological contractPsychological contract
Psychological contractgohar Iqbal
 
Hr for non hr managers recruitment
Hr for non hr managers   recruitmentHr for non hr managers   recruitment
Hr for non hr managers recruitmentgohar Iqbal
 
Virtual workplace ethics
Virtual workplace ethicsVirtual workplace ethics
Virtual workplace ethicsgohar Iqbal
 
Compensation and Benefit - Security Papers Limited Pakistan
Compensation and Benefit - Security Papers Limited PakistanCompensation and Benefit - Security Papers Limited Pakistan
Compensation and Benefit - Security Papers Limited Pakistangohar Iqbal
 
Industrial strategy & the future of skills policy
Industrial strategy & the future of skills policyIndustrial strategy & the future of skills policy
Industrial strategy & the future of skills policygohar Iqbal
 
Industrial relations at pak suzuki
Industrial relations at pak suzukiIndustrial relations at pak suzuki
Industrial relations at pak suzukigohar Iqbal
 
Know your strenghts
Know your strenghtsKnow your strenghts
Know your strenghtsgohar Iqbal
 
Bank co Utilizing Reward Strategy
Bank co Utilizing Reward StrategyBank co Utilizing Reward Strategy
Bank co Utilizing Reward Strategygohar Iqbal
 
Dynamo reruitment and selection
Dynamo reruitment and selectionDynamo reruitment and selection
Dynamo reruitment and selectiongohar Iqbal
 
Assessment centers
Assessment centersAssessment centers
Assessment centersgohar Iqbal
 
Managerial Policy hypothetical project
Managerial Policy hypothetical projectManagerial Policy hypothetical project
Managerial Policy hypothetical projectgohar Iqbal
 
Training design processof Indus Pharma
Training design processof  Indus PharmaTraining design processof  Indus Pharma
Training design processof Indus Pharmagohar Iqbal
 
Recruitment article ppt gohar 5052
Recruitment article ppt gohar 5052Recruitment article ppt gohar 5052
Recruitment article ppt gohar 5052gohar Iqbal
 
Economic policy analysis
Economic policy analysisEconomic policy analysis
Economic policy analysisgohar Iqbal
 

More from gohar Iqbal (20)

Key performance indicatiors
Key performance indicatiorsKey performance indicatiors
Key performance indicatiors
 
Psychological contract
Psychological contractPsychological contract
Psychological contract
 
Hr for non hr managers recruitment
Hr for non hr managers   recruitmentHr for non hr managers   recruitment
Hr for non hr managers recruitment
 
Virtual workplace ethics
Virtual workplace ethicsVirtual workplace ethics
Virtual workplace ethics
 
Compensation and Benefit - Security Papers Limited Pakistan
Compensation and Benefit - Security Papers Limited PakistanCompensation and Benefit - Security Papers Limited Pakistan
Compensation and Benefit - Security Papers Limited Pakistan
 
Industrial strategy & the future of skills policy
Industrial strategy & the future of skills policyIndustrial strategy & the future of skills policy
Industrial strategy & the future of skills policy
 
Industrial relations at pak suzuki
Industrial relations at pak suzukiIndustrial relations at pak suzuki
Industrial relations at pak suzuki
 
Know your strenghts
Know your strenghtsKnow your strenghts
Know your strenghts
 
Bank co Utilizing Reward Strategy
Bank co Utilizing Reward StrategyBank co Utilizing Reward Strategy
Bank co Utilizing Reward Strategy
 
Dynamo reruitment and selection
Dynamo reruitment and selectionDynamo reruitment and selection
Dynamo reruitment and selection
 
Assessment centers
Assessment centersAssessment centers
Assessment centers
 
Managerial Policy hypothetical project
Managerial Policy hypothetical projectManagerial Policy hypothetical project
Managerial Policy hypothetical project
 
Training design processof Indus Pharma
Training design processof  Indus PharmaTraining design processof  Indus Pharma
Training design processof Indus Pharma
 
Elearning
ElearningElearning
Elearning
 
Recruitment article ppt gohar 5052
Recruitment article ppt gohar 5052Recruitment article ppt gohar 5052
Recruitment article ppt gohar 5052
 
Rashanlelo
RashanleloRashanlelo
Rashanlelo
 
Lily
LilyLily
Lily
 
HRM suzuki
HRM suzukiHRM suzuki
HRM suzuki
 
Economic policy analysis
Economic policy analysisEconomic policy analysis
Economic policy analysis
 
Eatoye
EatoyeEatoye
Eatoye
 

Recently uploaded

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Victor Rentea
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Zilliz
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 

Recently uploaded (20)

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 

Project plan for a training web site

  • 1. Project Plan For a Training Web-Site Presented By: M.Gohar Iqbal (5052) Software Project Management
  • 2. Introduction: Scope:  trainings offered by the company (4-5 trainings)  trainer’s profile (3-4 trainers)  6-month training calendar Functional Requirements:  Home page contains introduction of Training company, its mission etc.  The website should have the trainings and can add more if required in future.  Should show upcoming events.  The website should contains trainer, their profile.  Through web site anyone (end user) can access the training’s and trainers’ data, experience etc. (read only for end users).  The time management for trainings in form of calendar for 6-months (which is given in scope).  Different Tabs like Clientele, Contact us, About us, Careers etc
  • 3. Project Plan Project Team  Project Manager  Assistant Project Manager  Consultant  2 Web developers and 1 graphics designer  1 QA tester Project Schedule:  2 week project  Agile method selected particularly SCRUM.  M.S Project Professional 2010 is used for scheduling.
  • 5. Communication Plan: Two types of communications are planned:  Regular/Ongoing meetings: Communications Purpose Audience Author Communication Frequency vehicle location Scrum Meeting Monitor the Whole team Project Emails, Posting Daily for 15 progress and For two weeks Manager on websites, min report. Meetings  One time event driven communications: For requirement gathering between vendor and consultant will be done in the first two days of the first week. And the second last day of the second week with final product.
  • 6. Team Skills: S.NO. Team Member Qualification 01 Project Manager PMI certified, 20 years implementation experience in ERP and managing projects. 02 Assistant Project Manager PMI certified, 10 years implementation experience in managing ERP projects. 03 Consultant Web developing experience for 7 years in php, .net, SAP SD certified consultant. 04 Web developer Experience in php, python, and Java and HTML 5 script for 5 years. 05 Web developer Java, ASP.net and HTML experience for 3 years. 06 Graphic Designer Adobe Photoshop, Adobe Flash, Adobe Illustrator, Maya, Auto CAD. Experience of 5 years. 07 QA tester CSQA, CSTE, CISA, COBIT, had previous experience for 15 years in testing software.
  • 7. Risk Assessment:  RMMM info sheet is used for risk planning. Risk Information Sheet Risk ID: R0003 Date: 25/4/2013 Prob: 80% Impact: high Description: Employee Turnover Key personnel leave the project taking critical information with them that significantly delays or derails the project. Refinement /Context: Sub Condition 1: Developer gets another attractive job. Sub Condition 2: Any conflict occurs between consultant with developer or manager. Mitigation & Monitoring: Increased collaboration and information sharing on the team. Management/Contingency Plan/Trigger: Manage a backup plan inform of extra developers and designers. Developers must have same knowledge e.g. of language as were previous had, same with designer. Current Status: Planned Originator: Project Manager Assigned: Asst. Project Manager