PERT Analysis. Program evaluation and review technique. Optimistic Time, Realistic Time, Pessimistic Time. A presentation from students of RNB Global University.
3. Overview
• Program (Project) Evaluation and
Review Technique (PERT) It is basically a
method to analyse the tasks involved in
completing a given project, especially the
time needed to complete each task, and
to identify the minimum time needed to
complete the total project.
4. Terminology
• OPTIMISTIC TIME (O): Best time if
everything goes perfectly
• REALISTIC TIME(M): Most likely time
• PESSIMISTIC TIME(P): A worst-case
situation
5.
6. Steps of PERT
• With the help of above formula we will find “Expected
Time” for each activity.
• Draw a network.
• From the PERT network diagram take the various ratio
diagram and find the overall expected duration as sum of
duration activities on the route.
• The route path which shows maximum duration is critical
path
• The variance of expected time for each activity
• Tp – To
6
• Then we have to find out Standard Deviation which is
S.D = √Sum of variance of activities on critical Path
{ }
2
______________________________
9. • 1-2-3-5-8 = 7+14+11+4 =36
• 1-2-4-5-8 = 7+5+7+4 =23
• 1-6-7-8 = 6+11+18 = 35
Activity 1-2-3-5-8 is having longer duration so it is lying on
the critical path.
Consider talking about:
Events and activities
Management tools
Consider talking about:
Example
Next step, creating network diagram by hand or by using diagram software
Next step, determination of critical path and possible slack