September 2015 Corporate Presentation

TSXV: FPC | WWW.FALCORES.COM | 1TSXV: FPC | WWW.FALCORES.COM
REDISCOVERING THE ROUYN-NORANDA MINING DISTRICT
REBIRTH OF THE HORNE MINE
SEPTEMBER 30, 2015
TSXV: FPC | WWW.FALCORES.COM | 2
Disclaimer
This presentation contains a review of the Company’s properties in Canada. Viewers are cautioned that the projects are at an early stage of exploration and that estimates and
projections contained herein are based on limited and incomplete data. More work is required before the mineralization on the projects and their economic aspects can be
confidentially modeled. Therefore, the work results and estimates herein may be considered to be generally indicative only of the nature and quality of the projects. No representation
or prediction is intended as to the results of future work, nor can there be any promise that the estimates herein will be confirmed by future exploration or analysis, or that the
projects will otherwise prove to be economic.
The TSX Venture Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this presentation, which has been prepared by management. There can
be no assurance that any of the assumptions in the resource estimates will be supported by a Pre-feasibility or Feasibility Study or that any forward looking event will come to pass. The
data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and
investment.
This presentation contains information with respect to adjacent or similar mineral properties in respect of which the Company has no interest or rights to explore or mine. Readers are
cautioned that the Company has no interest in or right to acquire any interest in any such properties, and that mineral deposits on adjacent or similar properties are not indicative of
mineral deposits on the Company’s properties. Past performance is no guarantee of future performance and all investors are urged to consult their investment professionals before
making an investment decision. Investors are further cautioned that past performance is no guarantee of future performance
Forward-Looking Statements
Certain information included in this presentation constitutes forward-looking statements, including any information as to our projects, plans and future performance. All statements,
other than statements of historical fact, are forward-looking statements. The words “expect”, “believe”, “anticipate”, “will”, “intend”, “estimate”, “forecast”, “budget”, “schedule” and
similar expressions identify forward-looking statements. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered
reasonable by management, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual
results to differ materially from those projected in the forward-looking statements.
Such factors include, but are not limited to: changes to current estimates of mineral reserves and resources; labour availability; litigation; availability of and increased costs associated
with contractors and exploration equipment; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits; contests
over title to properties; uncertainty with the Company’s ability to secure capital to execute its business plans; changes in national and local government legislation in Canada; risk of
loss due to sabotage and civil disturbances; risks arising from holding derivative instruments; and business opportunities that may be pursued by the company. Many of these
uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements
made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance.
The company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as
required by applicable law.
Cautionary Note to U.S Investors Concerning Measured, Indicated and Inferred Resources
This presentation uses the terms “measured,” “indicated” and “inferred resources. We advise investors that while those terms are recognized and required by Canadian regulations,
the United States Securities and Exchange commission does not recognize them. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or
other economic studies. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral
reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable.
CAUTIONARY STATEMENT
TSXV: FPC | WWW.FALCORES.COM | 3
2.8 MILLION GOLD EQUIVALENT OUNCES
OF INFERRED RESOURCES (43-101)*
ROUYN-NORANDA, QUEBEC
* SEE APRIL 17, 2014 FALCO PRESS RELEASE
TSXV: FPC | WWW.FALCORES.COM | 4
FALCO – A QUALITY CANADIAN GOLD DEVELOPER
INVESTMENT THESIS
ROBUST INITIAL ASSET
IN HORNE 5
DESIRABLE & STRONG
LAND POSITION IN
THE ABITIBI
EXPLORATION TARGETS
TO DRIVE FURTHER
VALUE
GOOD CONSOLIDATION
PROSPECTS
LOW POLITICAL RISK
FLEXIBLE BALANCE
SHEET
EXPERIENCED
MANAGEMENT WITH
TECHNICAL EXPERTISE
STRONG
SHAREHOLDER
BASE
TSXV: FPC | WWW.FALCORES.COM | 5
Capital Structure
Shareholder Registry
Osisko Gold Royalties 12.0%
Goodman & Company 8.2%
Raymond James 7.0%
Quebec Funds 6.6%
Pate Capital 3.7%
Sentry 2.5%
Tocqueville 2.3%
US Global 2.3%
Insiders (D&O) 3.5%
Shares Outstanding (basic) 99,730,657
Stock Options 7,383,890
Warrants 9,547,583
Shares Outstanding (fully diluted} 116,662,130
Cash (March 31, 2015) C$7,436,098
CORPORATE SUMMARY
A NEW DEVELOPMENT VEHICLE IN THE ABITIBI
Share Price Performance
0
400
800
1,200
1,600
2,000
2,400
2,800
$0.20
$0.30
$0.40
$0.50
$0.60
$0.70
$0.80
9-Sep-14 9-Dec-14 9-Mar-15 9-Jun-15 9-Sep-15
VOLUME(IN000'S)
PRICE(C$)
FT Hold period expiry
Closes Financing
TSXV: FPC | WWW.FALCORES.COM | 6
 2nd LARGEST GOLD PRODUCER IN CANADA
 ONE OF THE LOWEST FISCAL POLICY IN CANADA
 6TH SPOT IN THE 2014 FRASER RANKING FOR INVESTMENT ATTRACTIVNESS
 HEALTHY & EXISTING MINING CULTURE
 STRONG & EXPERIENCED LABOUR POOL
 GOVERNMENT SUPPORT AND ESTABLISHED PERMITTING PROCESS
LOW POLITICAL RISK
QUEBEC’S COMPETITIVE ADVANTAGE
TSXV: FPC | WWW.FALCORES.COM | 7
Larder Lake
13 Moz Au
Kirkland Lake
24 Moz Au
Timmins
71 Moz Au
Rouyn-Noranda
19 Moz Au
Malartic
14 Moz Au
Bousquet
21 Moz Au
Lennox Creek Fault Zone
Porcupine Destor Fault Zone
Cadillac
Fault Zone
ONTARIO
QUEBEC
Rouyn-Noranda
Timiskaming Sediments
Cobalt Plate
Felsic Intrusive
Kap High
Mafic/Ultramafic Volcanics
Geology
Val d’Or
14 Moz Au
Major gold mining camp
 50 current and former gold and base metal mines in the Rouyn-Noranda camp
 Rouyn-Noranda camp has produced 19 Moz of gold and 2.9 Blbs of copper, but
underexplored for gold
0 25 50 75 100
Kilometres
SOUTHERN ABITIBI GREENSTONE BELT
OVER 100 YEARS OF MINING HISTORY
TSXV: FPC | WWW.FALCORES.COM | 8
Initial production
End of Mining
(2.5 Blbs Cu &
11.5 Moz Au)
Falco acquires
properties
(Sep 2012)
Discovery of
Horne Mine
Digitization & compilation of
Horne historical drill results
(Aug 2013)
NI 43-101 Horne 5
resource estimate
(Mar 2014)
1923 1927 1976 1985 2012 2013 2014
Remnant mining
(102,000 oz Au)
$2.2M Regional
Exploration
(Jun 2014)
HORNE PROJECT
38 YEARS LATER
TSXV: FPC | WWW.FALCORES.COM | 9
City of
Rouyn-Noranda
Glencore
Smelter
Horne Mine
Quemont Mine
Falco Surface
Rights
Horne West
Horne project located in an Industrial Park
HORNE PROJECT
LOCATED NORTH OF THE CITY
TSXV: FPC | WWW.FALCORES.COM | 10
 Inferred resource estimate from
historic drilling
 Open at depth and along
strike
 Discovery costs of <$0.25/oz
Au
 1km strike length; 40-120m thick;
1,700m vertical extent
 En echelon stacked tabular body;
well defined metal zonation
(gold, copper, zinc)
 Extensively developed (1930s to
1960s)
 4,386 drill holes at 15m
spacing (305,000m)
 40 working levels & 55km of
underground development
HORNE PROJECT
MAIDEN RESOURCE ESTIMATE
TSXV: FPC | WWW.FALCORES.COM | 11
ENV_B
ENV_C
ENV_D
NSR Assumptions and Parameters  Maiden resource of 2.8 Moz AuEq at 3.4 g/t
 Opportunity to increase the resource:
 Conservative NSR & base metal payabilities
 Silver content not considered
Commodity Payable
Metal
Metal Price
($US)
Gold 87% $1,300.00
Copper 65% $3.30
Zinc 37% $0.95
Resource
Class
Cut-off
(NSR $C)
Tonnes
(Millions)
AuEq
(g/t)
Au
(g/t)
Cu
(%)
Zn
(%)
Contained
AuEq (Moz)
Contained
Au (Moz)
Contained
Cu (Mlbs)
Contained
Zn (Mlbs)
Inferred
>50 67.6 2.48 1.8 0.17 0.72 5.4 4.0 261 1,073
>60 50.4 2.75 2.1 0.19 0.73 4.5 3.3 214 814
>70 35.9 3.07 2.3 0.21 0.72 3.5 2.7 168 573
>80 25.3 3.41 2.6 0.23 0.70 2.8 2.2 131 393
>90 17.9 3.77 3.0 0.26 0.69 2.2 1.7 102 272
>100 12.8 4.17 3.4 0.28 0.67 1.7 1.4 79 190
>110 9.5 4.57 3.7 0.30 0.66 1.4 1.1 63 138
Exchange Rate: CAD/USD = 1.05
HORNE PROJECT
RESOURCE ESTIMATE – UPSIDE OPPORTUNITIES
TSXV: FPC | WWW.FALCORES.COM | 12
HORNE PROJECT
HORNE 5 PRELIMINARY ECONOMIC ASSESMENT TEAM
 Luc Lessard, Eng.,
 Former COO, Vice-President of Engineering & Construction for Osisko , IAMGOLD and Cambior
 Francois Vezina, Eng., MBA, Mine Development
 Former Mine Manager Osisko and Agnico-Eagle; Technical Services Manager for Agnico-Eagle (LaRonde II, Pinos Altos, Kittilä)
 Director – Mining, Osisko Mining Group
 Christian Laroche, Eng., Processing & Metallurgy
 Metallurgical engineer with 15 years experience in plant design, engineering, feasibility, construction and commissioning
 Director – Metallurgy, Osisko Mining Group
 InnovExplo, Mineral Resource Evaluation, Modelling and Mine Development
 Est. 2003, Independent Canadian mining consulting firm
 SGS Lakefield, Metallurgy
 Est. 1941, recognized world-wide as a premier testing and consulting facility
 BBA, Mill Design
 Est. 1979, Independent Canadian consulting engineering firm
 Golder, Tailings Management
 Est. 1961, Independent Canadian consulting engineering firm
 WSP, Surface infrastructure and Environment
 Est. 1959, Independent Canadian consulting engineering firm
TSXV: FPC | WWW.FALCORES.COM | 13
Goldex
(Agnico-Eagle)
Young-Davidson
(AuRico)
LaRonde
(Agnico-Eagle)
Horne 5 **
(Falco)
Resource Grade
(g/t AuEq) 1.8 2.8 5.1 3.4
Mining Method Long hole Transverse long hole
Longitudinal Retreat /
Transverse Open
Stoping
Transverse long hole **
Depth (m) 800 - 1,500 750 - 1,500 2,000-3,000 600 - 2,300
Stope Size 15-38 x 30 x 50 20-25 x 20 x 30 5-25 x 15 x 30 38 x 15 x 15 **
Mining Rate 5,100 tpd 8,000 tpd * 7,200 tpd >10,000 tpd **
Operating Cost/NSR $41/t * $53.50/t * $95/t Under review
Annual Production (koz) 71,000 * 200,000 * 230,000 * Under review
* Projected life-of-mine (LOM)
** Horne 5 tonnes and grades per 43-101 report; balance is conceptual
Horne 5 $80 NSR Cutoff in Maiden 43-101 Resource Estimate Under Review
Source: Company website and filings
COMPARABLE MINE ANALYSIS
HIGH MARGIN POTENTIAL
TSXV: FPC | WWW.FALCORES.COM | 14
 16,000m surface drill program
 9 holes, 9 wedge holes
 Metallurgical testing
 Updated NI 43-101
 Primary objectives of confirmation drilling:
 Upgrade resource category from Inferred to
Indicated
 Confirm metallurgical parameters (improve
payability)
 Confirm historic silver grades of >15 g/t
 Targeted Results
 Increase tonnes by >30%
 Increase AuEq to >3.5 Moz
 $3.7M cost; Completion by H2 2015
N S
HORNE PROJECT
CONFIRMATORY DRILL PROGRAM – HORNE 5
TSXV: FPC | WWW.FALCORES.COM | 15
HORNE PROJECT
CONFIRMATORY DRILL PROGRAM – INITIAL RESULTS
($0 NSR)
Hole_ID
From
(m)
To
(m)
Length
(m)
Au
(g/t)
Ag
(g/t)
Cu
(%)
Zn
(%)
Au_Eq_
With
Silver
(g/t)
Au_Eq_
Without
Silver
(g/t)
Au
(g/t)
Cu
(%)
Zn
(%)
Au_Eq_
Without
Silver
(g/t)
2015 vs
2014
%
H5-15-01 1,110 1,141 31.2 2.03 10.16 0.46 0.04 3.00 2.85 2.26 0.30 0.10 2.82 0.9%
H5-15-01-Atw 1,105 1,142 36.7 0.88 4.51 0.27 0.06 1.45 1.38 2.18 0.35 0.12 2.85 (51.5%)
H5-15-02 1,001 1,102 100.9 1.32 29.46 0.11 1.94 2.93 2.48 1.14 0.11 1.19 1.92 29.4%
H5-15-02-Atw 1,002 1,089 87.0 1.43 28.61 0.13 1.47 2.82 2.39 1.25 0.12 1.41 2.16 10.6%
H5-15-03B 1,248 1,365 116.7 0.50 15.51 0.06 1.00 1.34 1.11 0.79 0.06 0.67 1.23 (9.7%)
H5-15-03Dtw 1,255 1,390 134.4 0.55 15.44 0.08 1.10 1.46 1.23 0.82 0.06 0.70 1.28 (3.7%)
Total 506.9 0.96 19.39 0.13 1.17 2.05 1.76 1.14 0.12 0.83 1.76 0.4%
Grade % Difference (15.6%) 8.8% 39.8% 0.4%
2015 Diamond Drill Hole Results
Weighted Average of 2014 Raw
Assays within a 15 m radius
cylinder around DDH
New Drill Hole DataNew Drill Hole DataHistorical Raw Assay Data
Hole_ID
Length
(m)
Au_Eq_With Silver
(g/t)
Au_Eq Without
Silver
(g/t)
Au_Eq Without Silver
(g/t)
2015 Results vs
Historical Data
H5-15-01 31.2 3.00 2.85 2.82 0.9%
H5-15-01-Atw 36.7 1.45 1.38 2.85 (51.5%)
H5-15-02 100.9 2.93 2.48 1.92 29.4%
H5-15-02-Atw 87.0 2.82 2.39 2.16 10.6%
H5-15-03B 116.7 1.34 1.11 1.23 (9.7%)
H5-15-03Dtw 134.4 1.46 1.23 1.28 (3.7%)
Total 506.9 2.05 1.76 1.76 0.4%
TSXV: FPC | WWW.FALCORES.COM | 16
600m
HORNE PROJECT
CONFIRMATORY DRILL PROGRAM – HORNE 5
ENV_A
Targets (Zones)
 All within the Main
Envelope (ENV_A)
 At least one in each
High Grade Zones
 Two in the two major
high grade zones
(HG_A and HG_B)
 HG_A targeted a
silver-zinc rich zone
HG_A
HG_B
HG_E
HG_C
HG_D
High Grade Zones Main Envelope
1000 ft
E
305 m
W
1000 ft
E
305 m
W
H5-15-01
H5-15-02
H5-15-03
TSXV: FPC | WWW.FALCORES.COM | 17
1110.4m
Mineralized Zones Hole H5-15-01
HORNE PROJECT
2015 DRILL PROGRAM – HORNE 5
TSXV: FPC | WWW.FALCORES.COM | 18
Highly Prospective Land in a Top Jurisdiction
 13 former mines on 740 km2 of Falco properties
 Over 80 years of data archives
 Great land package with several high potential green and
brown field prospects
LAND PACKAGE
DOMINANT POSITION IN ESTABLISHED CAMP
Balmoral 700 km
Lake Shore Gold 182 km
Niogold 125 km
Eastmain Resources 125 km
Eagle Hill 124 km
St. Andrews Goldfields 120 km
Integra Gold 30 km
Falco Resources 740+ km
TSXV: FPC | WWW.FALCORES.COM | 19
Background
Previously Untested
 Cu-Zn-Au property, located 25km northwest of
Rouyn-Noranda
 One of the most significant VMS properties in the
Camp
Lithogeochemically similar to Horne Complex
rocks
 Falco identified near-surface conductors related to
stratigraphy with the chemical characteristics of
Horne Complex
 Over 2km of laterally extensive exhalative sequence,
akin to VMS systems
 Several Zn-rich anomalies
Consistent with lateral placement to VMS
mineralization
Distribution Map of High Probability
“Horne Type” Samples
Rimo
Horne Complex
RIVIERE MOUILLEUSE (RIMO)
SIMILAR SIGNATURE TO HORNE
TSXV: FPC | WWW.FALCORES.COM | 20
RIVIERE MOUILLEUSE (RIMO)
SIMILAR SIGNATURE TO HORNE
 5,000 meter drilling program
has commenced
 2 drills
 ~10 holes
TSXV: FPC | WWW.FALCORES.COM | 21
Potential to increase Mineral Resources in the Horne Complex
 11 gold targets within the shadow of the old mines
 Identified potential Horne West extension at depth
 Targeting 3 zones initially
HORNE 5 PLUS PROGRAM
ADDITIONAL TARGETS IN THE HORNE COMPLEX
TSXV: FPC | WWW.FALCORES.COM | 22
Horne West
Au g/t
 Several near-surface
mineralized zones
close to Horne
 Drilled by Noranda but
smelter sought higher
copper values
 Would provide early
cash flow during
production ramp-up
 Testing extensions
Horne 5
Deposit
Horne
Mine
Possible
Extension
HORNE 5 PLUS PROGRAM
NEAR SURFACE TARGETS
TSXV: FPC | WWW.FALCORES.COM | 23
 Glencore will retain its back-in right to acquire a 65% interest on any base metal deposit containing
more than 350,000 tonnes copper metal equivalent after presentation of a NI 43-101 compliant
resource, under the following conditions:
 paying Falco three times the project-specific exploration and development expenditures;
 paying Falco three times the Rouyn regional base metal exploration expenditures up to a maximum of $20
million;
 Glencore must complete a compliant feasibility study, within a specified period and at no cost to Falco;
 Falco will retain a 35% interest; receive a 6-month financing period subsequent to a production decision; and
will participate in a JV management committee where unanimous agreement is required on critical mining
decision
 The back-in right does not apply to any gold deposit, defined as a deposit where the value of gold and
silver are three times greater than the value of base metals, using 6-month average metal prices at
closing as defined at the date of the agreement. As such, gold deposits are solely to the Falco
account.
 Glencore retains a 1-2% NSR on all metals on mineral claims transferred to Falco. Where historic
royalties exist, the combined royalty is capped at 3 to 4%. In areas with no prior royalties, the NSR is
capped at 2%.
 Glencore has the right to explore for and exploit smelter materials (e.g. flux) in all areas. Should
smelter materials be mined from the Falco properties, Falco will receive a royalty of $0.50 per tonne
plus 50% of any gold which may be recovered
 Glencore retains their rights of first refusal for custom milling and smelting of base metal production
GLENCORE AGREEMENT
TERMS OF THE AGREEMENT
TSXV: FPC | WWW.FALCORES.COM | 24
FALCO RESOURCES
VALUE PROPOSITION – EV / RESOURCES
$7 $8
$14
$28
$3 $9
$13 $13
$16
$22 $24
$5 $6
$12
$31
$8
$23
$32
$64 $65 $67
$90
$139
PureGold
Falco
Niogold
Eastmain
PilotGold
Almaden
Corvus
Integra
Kaminak
Dalradian
Continental
Lydian
Midas
WestKirkland
Pretium
TrueGold
Asanko
TMAC
GuyanaGF
Aureus
Torex
Rubicon
Roxgold
Resources
PEA
PFS / Feasibility Study - Not Yet Funded
Fully Financed and In Construction / Ramp up
PEA Average: $14
Fully Funded and in
Construction / Ramp-Up
Average: $61
Resource Average: $14 PFS / Feasibility - Not Yet
Funded Average: $13
SOURCE: BMO, FACTSET AND COMPANY FILINGS
TSXV: FPC | WWW.FALCORES.COM | 25
CORPORATE TIMELINE
First Half
of 2017
•Full
Feasibility
Study
•Construction
Decision
2016
•Significant
Infill Drilling
Program
from surface
•Initiate
dewatering
program
2nd
Quarter
2016
•Initial
Preliminary
Economic
Assessment
November
-December
2015
•New 43-101
Resource
Estimate
Summer &
Fall 2015
•5,000 meter
program on
RIMO
•7,800 meter
program on
Horne 5 plus
•Metallurgy
•Hydrology
•Geotechnical
•Environment
•Engage with
community
and all
stakeholders
January to
August
2015
•16,000
meters
Confirmatory
Drilling
Program
TSXV: FPC | WWW.FALCORES.COM | 26
Sean Roosen, Chairman
 Chairman & CEO of Osisko Royalties
Luc Lessard, President & CEO, Director
 Former COO of Canadian Malartic Partnership
 Former COO and Senior Vice-President of Engineering
& Construction for Osisko Mining
 Former Vice-President of Engineering & Construction
for Iamgold
 Former Executive Director of Engineering &
Construction for Cambior
Jim Davidson, Director
 Co-Founder of Falco Resources
 Former CFO of Western Minerals Group
Claude Ferron, Director
 Former COO of Xstrata Copper Canada
Paul Henri-Girard, Director
 Former Vice-President of Canadian Operations at
Agnico Eagle Mines
Luc Lessard, President & CEO, Director
Vincent Metcalfe, CFO
 Former mining investment banker
Claude Bernier, Exploration Manager
 Over 40 years of experience on various exploration projects
Claude Léveillée, Vice-President Community Relations &
Human Resources
 Former Corporate Director, Human Resources/Organizational
Development at Agnico Eagle Mines
SENIOR LEADERSHIP TEAM
Board of Directors Officers
TSXV: FPC | WWW.FALCORES.COM | 27
Head Office
Falco Resources Ltd.
1100, avenue des
Canadiens-de-Montréal
Bureau 300
Montréal, QC H3B 2S2
Tél. : +1.514.905.3162
Toll Free : +1.888.915.2009
Courriel : info@falcores.com
Investor Inquiries
Vincent Metcalfe, CFO
Tel: +1.514.905.3162
Email: vmetcalfe@falcores.com
CONTACT US
1 von 27

Recomendados

2015 investor presentation june von
2015 investor presentation   june2015 investor presentation   june
2015 investor presentation juneFalcoCorporate
642 views28 Folien
2015 Investor Presentation - Vancouver von
2015 Investor Presentation - Vancouver2015 Investor Presentation - Vancouver
2015 Investor Presentation - VancouverFalcoCorporate
470 views25 Folien
Ami kemess lunch june 22 2017 final website von
Ami kemess lunch   june 22 2017 final websiteAmi kemess lunch   june 22 2017 final website
Ami kemess lunch june 22 2017 final websiteAuricoCorporate
1.2K views50 Folien
Ami corporate update november 2016 (nov 18) von
Ami corporate update   november 2016 (nov 18)Ami corporate update   november 2016 (nov 18)
Ami corporate update november 2016 (nov 18)AuricoCorporate
1K views25 Folien
Maverix Metals Corporate Presentation von
Maverix Metals Corporate PresentationMaverix Metals Corporate Presentation
Maverix Metals Corporate PresentationDanielle Connor
1.3K views19 Folien
Impact Silver Corporate Presentation - December 2021 von
Impact Silver Corporate Presentation - December 2021Impact Silver Corporate Presentation - December 2021
Impact Silver Corporate Presentation - December 2021Adnet Communications
292 views31 Folien

Más contenido relacionado

Was ist angesagt?

Ami corporate update june 2017 von
Ami corporate update   june 2017Ami corporate update   june 2017
Ami corporate update june 2017AuricoCorporate
1K views26 Folien
Ami corporate update september 2016 von
Ami corporate update   september 2016Ami corporate update   september 2016
Ami corporate update september 2016AuricoCorporate
241 views25 Folien
Lion One Metals Presentation Oct 2021 von
Lion One Metals Presentation Oct 2021Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021Joe Gray
390 views17 Folien
Probe Metals Corporate Presentation von
 Probe Metals Corporate Presentation  Probe Metals Corporate Presentation
Probe Metals Corporate Presentation Karen Willoughby
8.5K views15 Folien
Ami corporate update may 2016 von
Ami corporate update   may 2016Ami corporate update   may 2016
Ami corporate update may 2016AuricoCorporate
368 views27 Folien
Corporate Presentation September von
Corporate Presentation SeptemberCorporate Presentation September
Corporate Presentation SeptemberCarolynGraham14
11.8K views24 Folien

Was ist angesagt?(20)

Ami corporate update september 2016 von AuricoCorporate
Ami corporate update   september 2016Ami corporate update   september 2016
Ami corporate update september 2016
AuricoCorporate241 views
Lion One Metals Presentation Oct 2021 von Joe Gray
Lion One Metals Presentation Oct 2021Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021
Joe Gray390 views
Probe Metals Corporate Presentation von Karen Willoughby
 Probe Metals Corporate Presentation  Probe Metals Corporate Presentation
Probe Metals Corporate Presentation
Karen Willoughby8.5K views
Corporate Presentation September von CarolynGraham14
Corporate Presentation SeptemberCorporate Presentation September
Corporate Presentation September
CarolynGraham1411.8K views
NYSSA’s 17th Annual Mining Conference von NOVAGOLD
NYSSA’s 17th Annual Mining ConferenceNYSSA’s 17th Annual Mining Conference
NYSSA’s 17th Annual Mining Conference
NOVAGOLD2.6K views
Primero corporate presentation november final von primero_mining
Primero corporate presentation november finalPrimero corporate presentation november final
Primero corporate presentation november final
primero_mining387 views
Lion One Metals Presentation Nov 2021 von Lion One Metals
Lion One Metals Presentation Nov 2021Lion One Metals Presentation Nov 2021
Lion One Metals Presentation Nov 2021
Lion One Metals815 views
TriStar Gold Corporate Presentation - February 2022 von Adnet Communications
TriStar Gold Corporate Presentation - February 2022TriStar Gold Corporate Presentation - February 2022
TriStar Gold Corporate Presentation - February 2022
Adnet Communications50.4K views
Primero Corporate Presentation December 2014 von primero_mining
Primero Corporate Presentation December 2014Primero Corporate Presentation December 2014
Primero Corporate Presentation December 2014
primero_mining925 views
Ami corporate update march 31 2016 von AuricoCorporate
Ami corporate update   march 31 2016Ami corporate update   march 31 2016
Ami corporate update march 31 2016
AuricoCorporate761 views
2022.03.08 prb presentation final von Probe Gold
2022.03.08 prb presentation final2022.03.08 prb presentation final
2022.03.08 prb presentation final
Probe Gold269 views
2016 04-07 - ProbeMetals/Adventure Gold Presentation von Karen Willoughby
2016 04-07 - ProbeMetals/Adventure Gold Presentation2016 04-07 - ProbeMetals/Adventure Gold Presentation
2016 04-07 - ProbeMetals/Adventure Gold Presentation
Karen Willoughby353 views
WRN Corporate Presentation (September 2015) von Chris Donaldson
WRN Corporate Presentation (September 2015)WRN Corporate Presentation (September 2015)
WRN Corporate Presentation (September 2015)
Chris Donaldson1.9K views
Klondike Silver Corporate Brochure von MomentumPR
Klondike Silver Corporate BrochureKlondike Silver Corporate Brochure
Klondike Silver Corporate Brochure
MomentumPR2.8K views
Denver Gold Forum 2014 von AuRico Gold
Denver Gold Forum 2014Denver Gold Forum 2014
Denver Gold Forum 2014
AuRico Gold 3.7K views

Destacado

Factsheet Nobles Crus - Italian von
Factsheet Nobles Crus - ItalianFactsheet Nobles Crus - Italian
Factsheet Nobles Crus - ItalianElite Advisers
954 views2 Folien
Murtaza A Merchant CV von
Murtaza A Merchant CVMurtaza A Merchant CV
Murtaza A Merchant CVMurtaza Ali Merchant
164 views2 Folien
February 2016 Corporate Presentation von
February 2016 Corporate PresentationFebruary 2016 Corporate Presentation
February 2016 Corporate PresentationFalcoCorporate
889 views35 Folien
Telecommunications systemsand networking von
Telecommunications systemsand networkingTelecommunications systemsand networking
Telecommunications systemsand networkingOnline
747 views47 Folien
Clasificación de las empresas von
Clasificación de las empresasClasificación de las empresas
Clasificación de las empresasDanielSotoTobar
262 views39 Folien
SMEC Communication Products Overviews von
SMEC Communication Products OverviewsSMEC Communication Products Overviews
SMEC Communication Products OverviewsHarry Sohn
671 views34 Folien

Destacado(19)

Factsheet Nobles Crus - Italian von Elite Advisers
Factsheet Nobles Crus - ItalianFactsheet Nobles Crus - Italian
Factsheet Nobles Crus - Italian
Elite Advisers954 views
February 2016 Corporate Presentation von FalcoCorporate
February 2016 Corporate PresentationFebruary 2016 Corporate Presentation
February 2016 Corporate Presentation
FalcoCorporate889 views
Telecommunications systemsand networking von Online
Telecommunications systemsand networkingTelecommunications systemsand networking
Telecommunications systemsand networking
Online 747 views
SMEC Communication Products Overviews von Harry Sohn
SMEC Communication Products OverviewsSMEC Communication Products Overviews
SMEC Communication Products Overviews
Harry Sohn671 views
德貞女子中學(中五級) - 中國的改革開放 von KBTNHKU
德貞女子中學(中五級) - 中國的改革開放德貞女子中學(中五級) - 中國的改革開放
德貞女子中學(中五級) - 中國的改革開放
KBTNHKU5.5K views
5 класигра von ayxan12
5 класигра5 класигра
5 класигра
ayxan12472 views
Data center von gssmedia
Data centerData center
Data center
gssmedia1.8K views
ATK (Teacher workshop) (5-3-2011) von KBTNHKU
ATK (Teacher workshop) (5-3-2011)ATK (Teacher workshop) (5-3-2011)
ATK (Teacher workshop) (5-3-2011)
KBTNHKU1.3K views
Wi-Fi 802.11n Based Access Network for IPTV Service Delivery in Pakistan von IEEEP Karachi
Wi-Fi 802.11n Based Access Network for IPTV Service Delivery in PakistanWi-Fi 802.11n Based Access Network for IPTV Service Delivery in Pakistan
Wi-Fi 802.11n Based Access Network for IPTV Service Delivery in Pakistan
IEEEP Karachi3.1K views
20120218 Dissemination - Tim sharing von KBTNHKU
20120218 Dissemination - Tim sharing20120218 Dissemination - Tim sharing
20120218 Dissemination - Tim sharing
KBTNHKU2.6K views
Basics of Currency Trading von flame2011
Basics of Currency TradingBasics of Currency Trading
Basics of Currency Trading
flame20112.7K views
2016 zonal intervention projects and nass von statisense
2016 zonal intervention projects and nass2016 zonal intervention projects and nass
2016 zonal intervention projects and nass
statisense6.1K views
AWS Enterprise Summit London | Transforming Your IT with AWS von Amazon Web Services
AWS Enterprise Summit London | Transforming Your IT with AWSAWS Enterprise Summit London | Transforming Your IT with AWS
AWS Enterprise Summit London | Transforming Your IT with AWS
Amazon Web Services2.4K views
Damos la bienvenida al verano! von rafamainf
Damos la bienvenida al verano!Damos la bienvenida al verano!
Damos la bienvenida al verano!
rafamainf2.2K views
Policía nacional von rafamainf
Policía nacionalPolicía nacional
Policía nacional
rafamainf3.4K views
what is War? Reasons and types of War von Tallat Satti
what is War? Reasons and types of Warwhat is War? Reasons and types of War
what is War? Reasons and types of War
Tallat Satti28.4K views

Similar a September 2015 Corporate Presentation

2015 investor-presentation-vancouver-april v001-s68iw2 von
2015 investor-presentation-vancouver-april v001-s68iw22015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw2FalcoCorporate
618 views25 Folien
12.3 2016 investor presentation von
12.3 2016 investor presentation12.3 2016 investor presentation
12.3 2016 investor presentationFalcoCorporate
313 views37 Folien
Montreal Marketing von
Montreal MarketingMontreal Marketing
Montreal MarketingAuRico Gold
1.2K views29 Folien
August Investor presentation von
August Investor presentationAugust Investor presentation
August Investor presentationFalcoCorporate
309 views38 Folien
2015 TD Securities Mining Conference Presentation von
2015 TD Securities Mining Conference Presentation2015 TD Securities Mining Conference Presentation
2015 TD Securities Mining Conference PresentationAuRico Gold
625 views29 Folien
2015 08-17 AuRico Metals Inc. Corporate Update von
2015 08-17 AuRico Metals Inc. Corporate Update2015 08-17 AuRico Metals Inc. Corporate Update
2015 08-17 AuRico Metals Inc. Corporate Updateauricometals
538 views22 Folien

Similar a September 2015 Corporate Presentation(20)

2015 investor-presentation-vancouver-april v001-s68iw2 von FalcoCorporate
2015 investor-presentation-vancouver-april v001-s68iw22015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw2
FalcoCorporate618 views
12.3 2016 investor presentation von FalcoCorporate
12.3 2016 investor presentation12.3 2016 investor presentation
12.3 2016 investor presentation
FalcoCorporate313 views
2015 TD Securities Mining Conference Presentation von AuRico Gold
2015 TD Securities Mining Conference Presentation2015 TD Securities Mining Conference Presentation
2015 TD Securities Mining Conference Presentation
AuRico Gold 625 views
2015 08-17 AuRico Metals Inc. Corporate Update von auricometals
2015 08-17 AuRico Metals Inc. Corporate Update2015 08-17 AuRico Metals Inc. Corporate Update
2015 08-17 AuRico Metals Inc. Corporate Update
auricometals538 views
20.1 falco presentation may 2017 von FalcoCorporate
20.1 falco presentation   may 201720.1 falco presentation   may 2017
20.1 falco presentation may 2017
FalcoCorporate755 views
Sales Desk Presentation - February 2-6, 2015 von AuRico Gold
Sales Desk Presentation - February 2-6, 2015Sales Desk Presentation - February 2-6, 2015
Sales Desk Presentation - February 2-6, 2015
AuRico Gold 542 views
Scotiabank Latin American Mining Conference 2013 von AuRico Gold
Scotiabank Latin American Mining Conference 2013Scotiabank Latin American Mining Conference 2013
Scotiabank Latin American Mining Conference 2013
AuRico Gold 505 views
AuRico Metals - Corporate Presentation von auricometals
AuRico Metals - Corporate PresentationAuRico Metals - Corporate Presentation
AuRico Metals - Corporate Presentation
auricometals250 views
21.1 falco presentation august 2017 100dpi von FalcoCorporate
21.1 falco presentation   august 2017 100dpi21.1 falco presentation   august 2017 100dpi
21.1 falco presentation august 2017 100dpi
FalcoCorporate229 views
2015 09-09 Corporate Update von auricometals
2015 09-09 Corporate Update2015 09-09 Corporate Update
2015 09-09 Corporate Update
auricometals406 views
Bank of America Merrill Lynch 20th Annual Canada Mining Conference von AuRico Gold
Bank of America Merrill Lynch 20th Annual Canada Mining ConferenceBank of America Merrill Lynch 20th Annual Canada Mining Conference
Bank of America Merrill Lynch 20th Annual Canada Mining Conference
AuRico Gold 432 views
AuRico Metals August 2016 Investor Presentation von AuricoCorporate
AuRico Metals August 2016 Investor PresentationAuRico Metals August 2016 Investor Presentation
AuRico Metals August 2016 Investor Presentation
AuricoCorporate598 views
Credit Suisse Global Precious Metals Conference 2013 von AuRico Gold
Credit Suisse Global Precious Metals Conference 2013 Credit Suisse Global Precious Metals Conference 2013
Credit Suisse Global Precious Metals Conference 2013
AuRico Gold 399 views
Canaccord Conference presentation von AuRico Gold
Canaccord Conference presentationCanaccord Conference presentation
Canaccord Conference presentation
AuRico Gold 462 views
Denver Gold Forum 2013 von AuRico Gold
Denver Gold Forum 2013Denver Gold Forum 2013
Denver Gold Forum 2013
AuRico Gold 930 views
Falco Resources - March 2016 investor presentation von Vincent Metcalfe
Falco Resources - March 2016 investor presentationFalco Resources - March 2016 investor presentation
Falco Resources - March 2016 investor presentation
Vincent Metcalfe299 views

Más de FalcoCorporate

Falco jan2018 von
Falco jan2018Falco jan2018
Falco jan2018FalcoCorporate
1.5K views41 Folien
50.1 falco presentation feasibility - final - v2 von
50.1 falco presentation   feasibility - final - v250.1 falco presentation   feasibility - final - v2
50.1 falco presentation feasibility - final - v2FalcoCorporate
844 views46 Folien
50.1 falco presentation feasibility - final(1) von
50.1 falco presentation   feasibility - final(1)50.1 falco presentation   feasibility - final(1)
50.1 falco presentation feasibility - final(1)FalcoCorporate
133 views46 Folien
30.3 falco presentation osisko days - sept 2017 125dpi von
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpiFalcoCorporate
546 views41 Folien
30.2 falco presentation rbc august 2017 100dpi von
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpiFalcoCorporate
260 views41 Folien
17.7 falco presentation bmo von
17.7 falco presentation   bmo17.7 falco presentation   bmo
17.7 falco presentation bmoFalcoCorporate
901 views41 Folien

Más de FalcoCorporate(20)

50.1 falco presentation feasibility - final - v2 von FalcoCorporate
50.1 falco presentation   feasibility - final - v250.1 falco presentation   feasibility - final - v2
50.1 falco presentation feasibility - final - v2
FalcoCorporate844 views
50.1 falco presentation feasibility - final(1) von FalcoCorporate
50.1 falco presentation   feasibility - final(1)50.1 falco presentation   feasibility - final(1)
50.1 falco presentation feasibility - final(1)
FalcoCorporate133 views
30.3 falco presentation osisko days - sept 2017 125dpi von FalcoCorporate
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpi
FalcoCorporate546 views
30.2 falco presentation rbc august 2017 100dpi von FalcoCorporate
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpi
FalcoCorporate260 views
10.3 2016 investor presentation pea von FalcoCorporate
10.3 2016 investor presentation   pea10.3 2016 investor presentation   pea
10.3 2016 investor presentation pea
FalcoCorporate1.9K views
9.2 2016 investor presentation von FalcoCorporate
9.2 2016 investor presentation9.2 2016 investor presentation
9.2 2016 investor presentation
FalcoCorporate522 views
9.1 2016 investor presentation von FalcoCorporate
9.1 2016 investor presentation9.1 2016 investor presentation
9.1 2016 investor presentation
FalcoCorporate460 views
Rebirth of the Horne Mine - A Company Maker von FalcoCorporate
Rebirth of the Horne Mine - A Company MakerRebirth of the Horne Mine - A Company Maker
Rebirth of the Horne Mine - A Company Maker
FalcoCorporate612 views
2015 presentation-investisseurs-juin von FalcoCorporate
2015 presentation-investisseurs-juin2015 presentation-investisseurs-juin
2015 presentation-investisseurs-juin
FalcoCorporate443 views
March 2015 Corporate Presentation von FalcoCorporate
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation
FalcoCorporate267 views
March 2015 investor presentation revised cover von FalcoCorporate
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
FalcoCorporate892 views
March 2015 investor presentation fr von FalcoCorporate
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation fr
FalcoCorporate616 views
March 2015 investor presentation revised cover von FalcoCorporate
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
FalcoCorporate1.1K views
March 2015 investor presentation revised cover von FalcoCorporate
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
FalcoCorporate1K views
March 2015 investor presentation fr von FalcoCorporate
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation fr
FalcoCorporate707 views
March 2015 Corporate Presentation von FalcoCorporate
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation
FalcoCorporate327 views
March 2015 investor presentation fr von FalcoCorporate
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation fr
FalcoCorporate693 views

Último

WRN_Corporate_Presentation_Dec_2023.pdf von
WRN_Corporate_Presentation_Dec_2023.pdfWRN_Corporate_Presentation_Dec_2023.pdf
WRN_Corporate_Presentation_Dec_2023.pdfSandyNoyes
135 views57 Folien
Results Summary for the 3rd quarter of 2023 von
Results Summary for the 3rd quarter of 2023Results Summary for the 3rd quarter of 2023
Results Summary for the 3rd quarter of 2023TIM SA
5 views17 Folien
December 2023 MND IR PPT_final.pdf von
December 2023 MND IR PPT_final.pdfDecember 2023 MND IR PPT_final.pdf
December 2023 MND IR PPT_final.pdfMandalayResources
39 views20 Folien
morgan-stanley-global-consumer-and-retail-conference.pdf von
morgan-stanley-global-consumer-and-retail-conference.pdfmorgan-stanley-global-consumer-and-retail-conference.pdf
morgan-stanley-global-consumer-and-retail-conference.pdfAmanKaurKahlon
1.3K views35 Folien
2311_presentation materials_en_slideshare.pdf von
2311_presentation materials_en_slideshare.pdf2311_presentation materials_en_slideshare.pdf
2311_presentation materials_en_slideshare.pdfsansanir
22 views56 Folien
Ucas Application.pptx von
Ucas Application.pptxUcas Application.pptx
Ucas Application.pptxHenrydanielb
5 views3 Folien

Último(7)

WRN_Corporate_Presentation_Dec_2023.pdf von SandyNoyes
WRN_Corporate_Presentation_Dec_2023.pdfWRN_Corporate_Presentation_Dec_2023.pdf
WRN_Corporate_Presentation_Dec_2023.pdf
SandyNoyes135 views
Results Summary for the 3rd quarter of 2023 von TIM SA
Results Summary for the 3rd quarter of 2023Results Summary for the 3rd quarter of 2023
Results Summary for the 3rd quarter of 2023
TIM SA5 views
morgan-stanley-global-consumer-and-retail-conference.pdf von AmanKaurKahlon
morgan-stanley-global-consumer-and-retail-conference.pdfmorgan-stanley-global-consumer-and-retail-conference.pdf
morgan-stanley-global-consumer-and-retail-conference.pdf
AmanKaurKahlon1.3K views
2311_presentation materials_en_slideshare.pdf von sansanir
2311_presentation materials_en_slideshare.pdf2311_presentation materials_en_slideshare.pdf
2311_presentation materials_en_slideshare.pdf
sansanir22 views
Corporate Presentation Probe Gold Dec 2023.pdf von Probe Gold
Corporate Presentation Probe Gold Dec 2023.pdfCorporate Presentation Probe Gold Dec 2023.pdf
Corporate Presentation Probe Gold Dec 2023.pdf
Probe Gold99 views

September 2015 Corporate Presentation

  • 1. TSXV: FPC | WWW.FALCORES.COM | 1TSXV: FPC | WWW.FALCORES.COM REDISCOVERING THE ROUYN-NORANDA MINING DISTRICT REBIRTH OF THE HORNE MINE SEPTEMBER 30, 2015
  • 2. TSXV: FPC | WWW.FALCORES.COM | 2 Disclaimer This presentation contains a review of the Company’s properties in Canada. Viewers are cautioned that the projects are at an early stage of exploration and that estimates and projections contained herein are based on limited and incomplete data. More work is required before the mineralization on the projects and their economic aspects can be confidentially modeled. Therefore, the work results and estimates herein may be considered to be generally indicative only of the nature and quality of the projects. No representation or prediction is intended as to the results of future work, nor can there be any promise that the estimates herein will be confirmed by future exploration or analysis, or that the projects will otherwise prove to be economic. The TSX Venture Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this presentation, which has been prepared by management. There can be no assurance that any of the assumptions in the resource estimates will be supported by a Pre-feasibility or Feasibility Study or that any forward looking event will come to pass. The data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and investment. This presentation contains information with respect to adjacent or similar mineral properties in respect of which the Company has no interest or rights to explore or mine. Readers are cautioned that the Company has no interest in or right to acquire any interest in any such properties, and that mineral deposits on adjacent or similar properties are not indicative of mineral deposits on the Company’s properties. Past performance is no guarantee of future performance and all investors are urged to consult their investment professionals before making an investment decision. Investors are further cautioned that past performance is no guarantee of future performance Forward-Looking Statements Certain information included in this presentation constitutes forward-looking statements, including any information as to our projects, plans and future performance. All statements, other than statements of historical fact, are forward-looking statements. The words “expect”, “believe”, “anticipate”, “will”, “intend”, “estimate”, “forecast”, “budget”, “schedule” and similar expressions identify forward-looking statements. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements. Such factors include, but are not limited to: changes to current estimates of mineral reserves and resources; labour availability; litigation; availability of and increased costs associated with contractors and exploration equipment; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits; contests over title to properties; uncertainty with the Company’s ability to secure capital to execute its business plans; changes in national and local government legislation in Canada; risk of loss due to sabotage and civil disturbances; risks arising from holding derivative instruments; and business opportunities that may be pursued by the company. Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. The company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law. Cautionary Note to U.S Investors Concerning Measured, Indicated and Inferred Resources This presentation uses the terms “measured,” “indicated” and “inferred resources. We advise investors that while those terms are recognized and required by Canadian regulations, the United States Securities and Exchange commission does not recognize them. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable. CAUTIONARY STATEMENT
  • 3. TSXV: FPC | WWW.FALCORES.COM | 3 2.8 MILLION GOLD EQUIVALENT OUNCES OF INFERRED RESOURCES (43-101)* ROUYN-NORANDA, QUEBEC * SEE APRIL 17, 2014 FALCO PRESS RELEASE
  • 4. TSXV: FPC | WWW.FALCORES.COM | 4 FALCO – A QUALITY CANADIAN GOLD DEVELOPER INVESTMENT THESIS ROBUST INITIAL ASSET IN HORNE 5 DESIRABLE & STRONG LAND POSITION IN THE ABITIBI EXPLORATION TARGETS TO DRIVE FURTHER VALUE GOOD CONSOLIDATION PROSPECTS LOW POLITICAL RISK FLEXIBLE BALANCE SHEET EXPERIENCED MANAGEMENT WITH TECHNICAL EXPERTISE STRONG SHAREHOLDER BASE
  • 5. TSXV: FPC | WWW.FALCORES.COM | 5 Capital Structure Shareholder Registry Osisko Gold Royalties 12.0% Goodman & Company 8.2% Raymond James 7.0% Quebec Funds 6.6% Pate Capital 3.7% Sentry 2.5% Tocqueville 2.3% US Global 2.3% Insiders (D&O) 3.5% Shares Outstanding (basic) 99,730,657 Stock Options 7,383,890 Warrants 9,547,583 Shares Outstanding (fully diluted} 116,662,130 Cash (March 31, 2015) C$7,436,098 CORPORATE SUMMARY A NEW DEVELOPMENT VEHICLE IN THE ABITIBI Share Price Performance 0 400 800 1,200 1,600 2,000 2,400 2,800 $0.20 $0.30 $0.40 $0.50 $0.60 $0.70 $0.80 9-Sep-14 9-Dec-14 9-Mar-15 9-Jun-15 9-Sep-15 VOLUME(IN000'S) PRICE(C$) FT Hold period expiry Closes Financing
  • 6. TSXV: FPC | WWW.FALCORES.COM | 6  2nd LARGEST GOLD PRODUCER IN CANADA  ONE OF THE LOWEST FISCAL POLICY IN CANADA  6TH SPOT IN THE 2014 FRASER RANKING FOR INVESTMENT ATTRACTIVNESS  HEALTHY & EXISTING MINING CULTURE  STRONG & EXPERIENCED LABOUR POOL  GOVERNMENT SUPPORT AND ESTABLISHED PERMITTING PROCESS LOW POLITICAL RISK QUEBEC’S COMPETITIVE ADVANTAGE
  • 7. TSXV: FPC | WWW.FALCORES.COM | 7 Larder Lake 13 Moz Au Kirkland Lake 24 Moz Au Timmins 71 Moz Au Rouyn-Noranda 19 Moz Au Malartic 14 Moz Au Bousquet 21 Moz Au Lennox Creek Fault Zone Porcupine Destor Fault Zone Cadillac Fault Zone ONTARIO QUEBEC Rouyn-Noranda Timiskaming Sediments Cobalt Plate Felsic Intrusive Kap High Mafic/Ultramafic Volcanics Geology Val d’Or 14 Moz Au Major gold mining camp  50 current and former gold and base metal mines in the Rouyn-Noranda camp  Rouyn-Noranda camp has produced 19 Moz of gold and 2.9 Blbs of copper, but underexplored for gold 0 25 50 75 100 Kilometres SOUTHERN ABITIBI GREENSTONE BELT OVER 100 YEARS OF MINING HISTORY
  • 8. TSXV: FPC | WWW.FALCORES.COM | 8 Initial production End of Mining (2.5 Blbs Cu & 11.5 Moz Au) Falco acquires properties (Sep 2012) Discovery of Horne Mine Digitization & compilation of Horne historical drill results (Aug 2013) NI 43-101 Horne 5 resource estimate (Mar 2014) 1923 1927 1976 1985 2012 2013 2014 Remnant mining (102,000 oz Au) $2.2M Regional Exploration (Jun 2014) HORNE PROJECT 38 YEARS LATER
  • 9. TSXV: FPC | WWW.FALCORES.COM | 9 City of Rouyn-Noranda Glencore Smelter Horne Mine Quemont Mine Falco Surface Rights Horne West Horne project located in an Industrial Park HORNE PROJECT LOCATED NORTH OF THE CITY
  • 10. TSXV: FPC | WWW.FALCORES.COM | 10  Inferred resource estimate from historic drilling  Open at depth and along strike  Discovery costs of <$0.25/oz Au  1km strike length; 40-120m thick; 1,700m vertical extent  En echelon stacked tabular body; well defined metal zonation (gold, copper, zinc)  Extensively developed (1930s to 1960s)  4,386 drill holes at 15m spacing (305,000m)  40 working levels & 55km of underground development HORNE PROJECT MAIDEN RESOURCE ESTIMATE
  • 11. TSXV: FPC | WWW.FALCORES.COM | 11 ENV_B ENV_C ENV_D NSR Assumptions and Parameters  Maiden resource of 2.8 Moz AuEq at 3.4 g/t  Opportunity to increase the resource:  Conservative NSR & base metal payabilities  Silver content not considered Commodity Payable Metal Metal Price ($US) Gold 87% $1,300.00 Copper 65% $3.30 Zinc 37% $0.95 Resource Class Cut-off (NSR $C) Tonnes (Millions) AuEq (g/t) Au (g/t) Cu (%) Zn (%) Contained AuEq (Moz) Contained Au (Moz) Contained Cu (Mlbs) Contained Zn (Mlbs) Inferred >50 67.6 2.48 1.8 0.17 0.72 5.4 4.0 261 1,073 >60 50.4 2.75 2.1 0.19 0.73 4.5 3.3 214 814 >70 35.9 3.07 2.3 0.21 0.72 3.5 2.7 168 573 >80 25.3 3.41 2.6 0.23 0.70 2.8 2.2 131 393 >90 17.9 3.77 3.0 0.26 0.69 2.2 1.7 102 272 >100 12.8 4.17 3.4 0.28 0.67 1.7 1.4 79 190 >110 9.5 4.57 3.7 0.30 0.66 1.4 1.1 63 138 Exchange Rate: CAD/USD = 1.05 HORNE PROJECT RESOURCE ESTIMATE – UPSIDE OPPORTUNITIES
  • 12. TSXV: FPC | WWW.FALCORES.COM | 12 HORNE PROJECT HORNE 5 PRELIMINARY ECONOMIC ASSESMENT TEAM  Luc Lessard, Eng.,  Former COO, Vice-President of Engineering & Construction for Osisko , IAMGOLD and Cambior  Francois Vezina, Eng., MBA, Mine Development  Former Mine Manager Osisko and Agnico-Eagle; Technical Services Manager for Agnico-Eagle (LaRonde II, Pinos Altos, Kittilä)  Director – Mining, Osisko Mining Group  Christian Laroche, Eng., Processing & Metallurgy  Metallurgical engineer with 15 years experience in plant design, engineering, feasibility, construction and commissioning  Director – Metallurgy, Osisko Mining Group  InnovExplo, Mineral Resource Evaluation, Modelling and Mine Development  Est. 2003, Independent Canadian mining consulting firm  SGS Lakefield, Metallurgy  Est. 1941, recognized world-wide as a premier testing and consulting facility  BBA, Mill Design  Est. 1979, Independent Canadian consulting engineering firm  Golder, Tailings Management  Est. 1961, Independent Canadian consulting engineering firm  WSP, Surface infrastructure and Environment  Est. 1959, Independent Canadian consulting engineering firm
  • 13. TSXV: FPC | WWW.FALCORES.COM | 13 Goldex (Agnico-Eagle) Young-Davidson (AuRico) LaRonde (Agnico-Eagle) Horne 5 ** (Falco) Resource Grade (g/t AuEq) 1.8 2.8 5.1 3.4 Mining Method Long hole Transverse long hole Longitudinal Retreat / Transverse Open Stoping Transverse long hole ** Depth (m) 800 - 1,500 750 - 1,500 2,000-3,000 600 - 2,300 Stope Size 15-38 x 30 x 50 20-25 x 20 x 30 5-25 x 15 x 30 38 x 15 x 15 ** Mining Rate 5,100 tpd 8,000 tpd * 7,200 tpd >10,000 tpd ** Operating Cost/NSR $41/t * $53.50/t * $95/t Under review Annual Production (koz) 71,000 * 200,000 * 230,000 * Under review * Projected life-of-mine (LOM) ** Horne 5 tonnes and grades per 43-101 report; balance is conceptual Horne 5 $80 NSR Cutoff in Maiden 43-101 Resource Estimate Under Review Source: Company website and filings COMPARABLE MINE ANALYSIS HIGH MARGIN POTENTIAL
  • 14. TSXV: FPC | WWW.FALCORES.COM | 14  16,000m surface drill program  9 holes, 9 wedge holes  Metallurgical testing  Updated NI 43-101  Primary objectives of confirmation drilling:  Upgrade resource category from Inferred to Indicated  Confirm metallurgical parameters (improve payability)  Confirm historic silver grades of >15 g/t  Targeted Results  Increase tonnes by >30%  Increase AuEq to >3.5 Moz  $3.7M cost; Completion by H2 2015 N S HORNE PROJECT CONFIRMATORY DRILL PROGRAM – HORNE 5
  • 15. TSXV: FPC | WWW.FALCORES.COM | 15 HORNE PROJECT CONFIRMATORY DRILL PROGRAM – INITIAL RESULTS ($0 NSR) Hole_ID From (m) To (m) Length (m) Au (g/t) Ag (g/t) Cu (%) Zn (%) Au_Eq_ With Silver (g/t) Au_Eq_ Without Silver (g/t) Au (g/t) Cu (%) Zn (%) Au_Eq_ Without Silver (g/t) 2015 vs 2014 % H5-15-01 1,110 1,141 31.2 2.03 10.16 0.46 0.04 3.00 2.85 2.26 0.30 0.10 2.82 0.9% H5-15-01-Atw 1,105 1,142 36.7 0.88 4.51 0.27 0.06 1.45 1.38 2.18 0.35 0.12 2.85 (51.5%) H5-15-02 1,001 1,102 100.9 1.32 29.46 0.11 1.94 2.93 2.48 1.14 0.11 1.19 1.92 29.4% H5-15-02-Atw 1,002 1,089 87.0 1.43 28.61 0.13 1.47 2.82 2.39 1.25 0.12 1.41 2.16 10.6% H5-15-03B 1,248 1,365 116.7 0.50 15.51 0.06 1.00 1.34 1.11 0.79 0.06 0.67 1.23 (9.7%) H5-15-03Dtw 1,255 1,390 134.4 0.55 15.44 0.08 1.10 1.46 1.23 0.82 0.06 0.70 1.28 (3.7%) Total 506.9 0.96 19.39 0.13 1.17 2.05 1.76 1.14 0.12 0.83 1.76 0.4% Grade % Difference (15.6%) 8.8% 39.8% 0.4% 2015 Diamond Drill Hole Results Weighted Average of 2014 Raw Assays within a 15 m radius cylinder around DDH New Drill Hole DataNew Drill Hole DataHistorical Raw Assay Data Hole_ID Length (m) Au_Eq_With Silver (g/t) Au_Eq Without Silver (g/t) Au_Eq Without Silver (g/t) 2015 Results vs Historical Data H5-15-01 31.2 3.00 2.85 2.82 0.9% H5-15-01-Atw 36.7 1.45 1.38 2.85 (51.5%) H5-15-02 100.9 2.93 2.48 1.92 29.4% H5-15-02-Atw 87.0 2.82 2.39 2.16 10.6% H5-15-03B 116.7 1.34 1.11 1.23 (9.7%) H5-15-03Dtw 134.4 1.46 1.23 1.28 (3.7%) Total 506.9 2.05 1.76 1.76 0.4%
  • 16. TSXV: FPC | WWW.FALCORES.COM | 16 600m HORNE PROJECT CONFIRMATORY DRILL PROGRAM – HORNE 5 ENV_A Targets (Zones)  All within the Main Envelope (ENV_A)  At least one in each High Grade Zones  Two in the two major high grade zones (HG_A and HG_B)  HG_A targeted a silver-zinc rich zone HG_A HG_B HG_E HG_C HG_D High Grade Zones Main Envelope 1000 ft E 305 m W 1000 ft E 305 m W H5-15-01 H5-15-02 H5-15-03
  • 17. TSXV: FPC | WWW.FALCORES.COM | 17 1110.4m Mineralized Zones Hole H5-15-01 HORNE PROJECT 2015 DRILL PROGRAM – HORNE 5
  • 18. TSXV: FPC | WWW.FALCORES.COM | 18 Highly Prospective Land in a Top Jurisdiction  13 former mines on 740 km2 of Falco properties  Over 80 years of data archives  Great land package with several high potential green and brown field prospects LAND PACKAGE DOMINANT POSITION IN ESTABLISHED CAMP Balmoral 700 km Lake Shore Gold 182 km Niogold 125 km Eastmain Resources 125 km Eagle Hill 124 km St. Andrews Goldfields 120 km Integra Gold 30 km Falco Resources 740+ km
  • 19. TSXV: FPC | WWW.FALCORES.COM | 19 Background Previously Untested  Cu-Zn-Au property, located 25km northwest of Rouyn-Noranda  One of the most significant VMS properties in the Camp Lithogeochemically similar to Horne Complex rocks  Falco identified near-surface conductors related to stratigraphy with the chemical characteristics of Horne Complex  Over 2km of laterally extensive exhalative sequence, akin to VMS systems  Several Zn-rich anomalies Consistent with lateral placement to VMS mineralization Distribution Map of High Probability “Horne Type” Samples Rimo Horne Complex RIVIERE MOUILLEUSE (RIMO) SIMILAR SIGNATURE TO HORNE
  • 20. TSXV: FPC | WWW.FALCORES.COM | 20 RIVIERE MOUILLEUSE (RIMO) SIMILAR SIGNATURE TO HORNE  5,000 meter drilling program has commenced  2 drills  ~10 holes
  • 21. TSXV: FPC | WWW.FALCORES.COM | 21 Potential to increase Mineral Resources in the Horne Complex  11 gold targets within the shadow of the old mines  Identified potential Horne West extension at depth  Targeting 3 zones initially HORNE 5 PLUS PROGRAM ADDITIONAL TARGETS IN THE HORNE COMPLEX
  • 22. TSXV: FPC | WWW.FALCORES.COM | 22 Horne West Au g/t  Several near-surface mineralized zones close to Horne  Drilled by Noranda but smelter sought higher copper values  Would provide early cash flow during production ramp-up  Testing extensions Horne 5 Deposit Horne Mine Possible Extension HORNE 5 PLUS PROGRAM NEAR SURFACE TARGETS
  • 23. TSXV: FPC | WWW.FALCORES.COM | 23  Glencore will retain its back-in right to acquire a 65% interest on any base metal deposit containing more than 350,000 tonnes copper metal equivalent after presentation of a NI 43-101 compliant resource, under the following conditions:  paying Falco three times the project-specific exploration and development expenditures;  paying Falco three times the Rouyn regional base metal exploration expenditures up to a maximum of $20 million;  Glencore must complete a compliant feasibility study, within a specified period and at no cost to Falco;  Falco will retain a 35% interest; receive a 6-month financing period subsequent to a production decision; and will participate in a JV management committee where unanimous agreement is required on critical mining decision  The back-in right does not apply to any gold deposit, defined as a deposit where the value of gold and silver are three times greater than the value of base metals, using 6-month average metal prices at closing as defined at the date of the agreement. As such, gold deposits are solely to the Falco account.  Glencore retains a 1-2% NSR on all metals on mineral claims transferred to Falco. Where historic royalties exist, the combined royalty is capped at 3 to 4%. In areas with no prior royalties, the NSR is capped at 2%.  Glencore has the right to explore for and exploit smelter materials (e.g. flux) in all areas. Should smelter materials be mined from the Falco properties, Falco will receive a royalty of $0.50 per tonne plus 50% of any gold which may be recovered  Glencore retains their rights of first refusal for custom milling and smelting of base metal production GLENCORE AGREEMENT TERMS OF THE AGREEMENT
  • 24. TSXV: FPC | WWW.FALCORES.COM | 24 FALCO RESOURCES VALUE PROPOSITION – EV / RESOURCES $7 $8 $14 $28 $3 $9 $13 $13 $16 $22 $24 $5 $6 $12 $31 $8 $23 $32 $64 $65 $67 $90 $139 PureGold Falco Niogold Eastmain PilotGold Almaden Corvus Integra Kaminak Dalradian Continental Lydian Midas WestKirkland Pretium TrueGold Asanko TMAC GuyanaGF Aureus Torex Rubicon Roxgold Resources PEA PFS / Feasibility Study - Not Yet Funded Fully Financed and In Construction / Ramp up PEA Average: $14 Fully Funded and in Construction / Ramp-Up Average: $61 Resource Average: $14 PFS / Feasibility - Not Yet Funded Average: $13 SOURCE: BMO, FACTSET AND COMPANY FILINGS
  • 25. TSXV: FPC | WWW.FALCORES.COM | 25 CORPORATE TIMELINE First Half of 2017 •Full Feasibility Study •Construction Decision 2016 •Significant Infill Drilling Program from surface •Initiate dewatering program 2nd Quarter 2016 •Initial Preliminary Economic Assessment November -December 2015 •New 43-101 Resource Estimate Summer & Fall 2015 •5,000 meter program on RIMO •7,800 meter program on Horne 5 plus •Metallurgy •Hydrology •Geotechnical •Environment •Engage with community and all stakeholders January to August 2015 •16,000 meters Confirmatory Drilling Program
  • 26. TSXV: FPC | WWW.FALCORES.COM | 26 Sean Roosen, Chairman  Chairman & CEO of Osisko Royalties Luc Lessard, President & CEO, Director  Former COO of Canadian Malartic Partnership  Former COO and Senior Vice-President of Engineering & Construction for Osisko Mining  Former Vice-President of Engineering & Construction for Iamgold  Former Executive Director of Engineering & Construction for Cambior Jim Davidson, Director  Co-Founder of Falco Resources  Former CFO of Western Minerals Group Claude Ferron, Director  Former COO of Xstrata Copper Canada Paul Henri-Girard, Director  Former Vice-President of Canadian Operations at Agnico Eagle Mines Luc Lessard, President & CEO, Director Vincent Metcalfe, CFO  Former mining investment banker Claude Bernier, Exploration Manager  Over 40 years of experience on various exploration projects Claude Léveillée, Vice-President Community Relations & Human Resources  Former Corporate Director, Human Resources/Organizational Development at Agnico Eagle Mines SENIOR LEADERSHIP TEAM Board of Directors Officers
  • 27. TSXV: FPC | WWW.FALCORES.COM | 27 Head Office Falco Resources Ltd. 1100, avenue des Canadiens-de-Montréal Bureau 300 Montréal, QC H3B 2S2 Tél. : +1.514.905.3162 Toll Free : +1.888.915.2009 Courriel : info@falcores.com Investor Inquiries Vincent Metcalfe, CFO Tel: +1.514.905.3162 Email: vmetcalfe@falcores.com CONTACT US