Item Description Formula Formula Description Remarks
BAC Budget at Completion - - Originally Estimated Budget at Completion
PV Planned Value %Estimated work till DOD* BAC %Estimated work till the Date of Data multiplied by BAC Also Known as BCWS or Budgeted Cost Work Scheduled
EV Earned Value %Accomplished work till DOD* BAC %Accomplished work till the Date of Data multiplied by BAC Also Known as BCWP or Budgeted Cost Work Performed
AC Actual Cost Actual Cost incurred for Work Accomplished - Also Known as ACWP or Actual Cost Work Performed
SV Schedule Variance SV= EV-PV How much more/less work has been accomplished compared to what was planned -
CV Cost Variance CV= EV-AC How much more/less has the accomplished work cost compared to what was planned -
SPI Schedule Performance Index SPI = EV/PV How does the work being completed compare to what was planned in the schedule -
CPI Cost Performance Index CPI = EV/AC How much is the work being accomplished costing compared to what was planned -
EAC Estimate at Completion EAC = BAC/CPI
Budget at Completion Divided by Cost Performance Index Also can be calculated Thru EAC = AC +
((BAC – EV) / CPI)
This formula used only if no variances from BAC or the project
will continue with same spending rate.
EAC Estimate at Completion EAC = AC + Bottom-up ETC Sum of Actual Cost incurred till DOD plus new estimates of remaining work
This Formula used if the estimates were fundamentally
followed.
EAC Estimate at Completion EAC = AC + (BAC – EV) Sum of Actual Cost incurred till DOD plus (Budget at Completion minus Earned Value)
This formula used only in atypical/asymetrical condition; means
CPI and SPI will remain the same.
EAC Estimate at Completion EAC = AC + ((BAC – EV)/(SPI*CPI)) Sum of Actual Cost incurred till DOD plus ((Budget at Completion minus Earned Value)/(SPI*CPI))
This formula used only in typical/symetrical condition; means
CPI and SPI will be changed and remaining budget will be
modified according to performance.
ETC Estimate to Complete ETC = EAC – AC Expected total cost minus actual cost till DOD -
VAC Variance at Completion VAC = BAC – EAC The difference between the originally estimated BAC and a newly calculated EAC
How much over or under budget will we be at the end of the
project
TCPI
To Complete Performance Index
Based on BAC
TCPI|BAC = (BAC – EV) / (BAC – AC) -
The required level of performance must future project work
meet in order to meet the budget (BAC)
TCPI
To Complete Performance Index
Based on EAC
TCPI|BAC = (BAC – EV) / (EAC – AC) -
The required level of performance must future project meet in
order to meet the project’s cost based on past performance
(EAC)
Compiled By: Essam Mohamed Lotfi, PMP, CCP
Email: esam_mese@hotmail.com
LinkedIn: ae.linkedin.com/in/essamlotffy/
Earned Value Calculations

More Related Content

What's hot

Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
constructioninside
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Vivek Prakash
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costs
Anatoly Ryabukha
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
harwoodr
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Praveen Malik, PMP
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
Iftikhar Anjum
 

What's hot (20)

PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Pmp formulas pmbok6
Pmp formulas pmbok6Pmp formulas pmbok6
Pmp formulas pmbok6
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Pmp formulas pmbok5
Pmp formulas pmbok5Pmp formulas pmbok5
Pmp formulas pmbok5
 
Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
Project Management 3.2 cost_exo
Project Management 3.2 cost_exoProject Management 3.2 cost_exo
Project Management 3.2 cost_exo
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costs
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
Daily payments record
Daily payments recordDaily payments record
Daily payments record
 
Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
Rena CV
Rena CVRena CV
Rena CV
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project Management
 
The Benefits of using Earned Value Management
The Benefits of using Earned Value ManagementThe Benefits of using Earned Value Management
The Benefits of using Earned Value Management
 
PPP05 - Creating Preventive Maintenance Schedules
PPP05 - Creating Preventive Maintenance Schedules PPP05 - Creating Preventive Maintenance Schedules
PPP05 - Creating Preventive Maintenance Schedules
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 

Similar to Evm.calculations.Summary sheet

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 

Similar to Evm.calculations.Summary sheet (20)

Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
EVMS Gold Card
EVMS Gold CardEVMS Gold Card
EVMS Gold Card
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 

More from Essam Lotffy, PMP®, CCP®

More from Essam Lotffy, PMP®, CCP® (18)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Recently uploaded

Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 

Recently uploaded (16)

Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

Evm.calculations.Summary sheet

  • 1. Item Description Formula Formula Description Remarks BAC Budget at Completion - - Originally Estimated Budget at Completion PV Planned Value %Estimated work till DOD* BAC %Estimated work till the Date of Data multiplied by BAC Also Known as BCWS or Budgeted Cost Work Scheduled EV Earned Value %Accomplished work till DOD* BAC %Accomplished work till the Date of Data multiplied by BAC Also Known as BCWP or Budgeted Cost Work Performed AC Actual Cost Actual Cost incurred for Work Accomplished - Also Known as ACWP or Actual Cost Work Performed SV Schedule Variance SV= EV-PV How much more/less work has been accomplished compared to what was planned - CV Cost Variance CV= EV-AC How much more/less has the accomplished work cost compared to what was planned - SPI Schedule Performance Index SPI = EV/PV How does the work being completed compare to what was planned in the schedule - CPI Cost Performance Index CPI = EV/AC How much is the work being accomplished costing compared to what was planned - EAC Estimate at Completion EAC = BAC/CPI Budget at Completion Divided by Cost Performance Index Also can be calculated Thru EAC = AC + ((BAC – EV) / CPI) This formula used only if no variances from BAC or the project will continue with same spending rate. EAC Estimate at Completion EAC = AC + Bottom-up ETC Sum of Actual Cost incurred till DOD plus new estimates of remaining work This Formula used if the estimates were fundamentally followed. EAC Estimate at Completion EAC = AC + (BAC – EV) Sum of Actual Cost incurred till DOD plus (Budget at Completion minus Earned Value) This formula used only in atypical/asymetrical condition; means CPI and SPI will remain the same. EAC Estimate at Completion EAC = AC + ((BAC – EV)/(SPI*CPI)) Sum of Actual Cost incurred till DOD plus ((Budget at Completion minus Earned Value)/(SPI*CPI)) This formula used only in typical/symetrical condition; means CPI and SPI will be changed and remaining budget will be modified according to performance. ETC Estimate to Complete ETC = EAC – AC Expected total cost minus actual cost till DOD - VAC Variance at Completion VAC = BAC – EAC The difference between the originally estimated BAC and a newly calculated EAC How much over or under budget will we be at the end of the project TCPI To Complete Performance Index Based on BAC TCPI|BAC = (BAC – EV) / (BAC – AC) - The required level of performance must future project work meet in order to meet the budget (BAC) TCPI To Complete Performance Index Based on EAC TCPI|BAC = (BAC – EV) / (EAC – AC) - The required level of performance must future project meet in order to meet the project’s cost based on past performance (EAC) Compiled By: Essam Mohamed Lotfi, PMP, CCP Email: esam_mese@hotmail.com LinkedIn: ae.linkedin.com/in/essamlotffy/ Earned Value Calculations