Easy Steps to Network
Construction and Critical Path
Determination
Project Management
Dr. Mahmoud Abbas Mahmoud
Asst. Prof...
Easy Steps to Network
Construction and Critical Path
Determination
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5A...
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
Note:
Practically, nodes numbering
can be start by (0) or (1).
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activit...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
E
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A
1
Dr. Mahmoud Abbas Mahmoud
Duration
(week)
Preceding
Activity
Activity
10-A
7-B
5AC
6AD
9B, CE
8DF
12D, EG
2
B
3
C
D
4
...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
Duration
(week)
Preceding
Activity
Activit...
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
How to...
Dr. Mahmoud Abbas Mahmoud
Remember that only a critical
activity can have a Zero Total
Float (TF)
Dr. Mahmoud Abbas Mahmoud
Therefore, we will calculate
the Total Floats for all
activities and each activity
has a ZERO To...
Total Float (TF) calculations
Dr. Mahmoud Abbas Mahmoud
TFij = (LC)j – (ES)i – Dij
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Du...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Critic...
Dr. Mahmoud Al-Naimi
Nächste SlideShare
Wird geladen in …5
×

Easy steps to network construction and critical path determination

5.847 Aufrufe

Veröffentlicht am

Project Management, Easy steps to network construction and critical path determination

Veröffentlicht in: Ingenieurwesen
  • Great projects with clear instructions. I've gotten an enormous feeling of accomplishment pride from making my own bookshelves and side tables. Thanks Ted! ▶▶▶ https://t.cn/A62Ye5eM
       Antworten 
    Sind Sie sicher, dass Sie …  Ja  Nein
    Ihre Nachricht erscheint hier
  • Grab 5 Free Shed Plans Now! Download 5 Full-Blown Shed Plans with Step-By-Step Instructions & Easy To Follow Blueprints! ☺☺☺ https://url.cn/I86oXShh
       Antworten 
    Sind Sie sicher, dass Sie …  Ja  Nein
    Ihre Nachricht erscheint hier
  • Ryan Shed Plans 12,000 Shed Plans and Designs For Easy Shed Building! ▶▶▶ https://url.cn/15NhsAEL
       Antworten 
    Sind Sie sicher, dass Sie …  Ja  Nein
    Ihre Nachricht erscheint hier
  • Dating for everyone is here: ❶❶❶ http://bit.ly/2F90ZZC ❶❶❶
       Antworten 
    Sind Sie sicher, dass Sie …  Ja  Nein
    Ihre Nachricht erscheint hier
  • Follow the link, new dating source: ❤❤❤ http://bit.ly/2F90ZZC ❤❤❤
       Antworten 
    Sind Sie sicher, dass Sie …  Ja  Nein
    Ihre Nachricht erscheint hier

Easy steps to network construction and critical path determination

  1. 1. Easy Steps to Network Construction and Critical Path Determination Project Management Dr. Mahmoud Abbas Mahmoud Asst. Prof. 2016
  2. 2. Easy Steps to Network Construction and Critical Path Determination Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG Example: For the activities given in the table: i) Draw the (AOA) network diagram. ii) Find the critical activities. iii) Find the critical path (CP). iv) Find project completion time. We will illustrate these steps with the following Example. Dr. Mahmoud Abbas Mahmoud
  3. 3. Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG
  4. 4. Note: Practically, nodes numbering can be start by (0) or (1). Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 1
  5. 5. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG
  6. 6. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2
  7. 7. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B
  8. 8. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3
  9. 9. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C
  10. 10. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D
  11. 11. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4
  12. 12. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E
  13. 13. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5
  14. 14. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F
  15. 15. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6
  16. 16. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G
  17. 17. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G ???????But (G) depend on both (D) and (E)
  18. 18. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G Use Dummy !
  19. 19. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G Dummy
  20. 20. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0
  21. 21. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 (AOA) Network Drawing is Completed
  22. 22. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Critical Path Calculations
  23. 23. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass:
  24. 24. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass: Calculating the Earliest Start Time (ES):
  25. 25. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass: Calculating the Earliest Start Time (ES): Earliest Start Time (ES)j=Max [ (ES)i + Dij ]
  26. 26. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 Earliest Start Time (ES) for Start Event = (0) NOTE: (ES) for any Start Event = (0)
  27. 27. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0
  28. 28. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 10[0+10]= 10 0
  29. 29. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 Max [(0+7) , (10+5)] = Max [7,15]= 15
  30. 30. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 [10+ 6]= 16
  31. 31. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 Max [(15+9) , (16+0)] = Max [24,16]= 24
  32. 32. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Max [(16+8) , (24+12)] = Max [24,36]= 36
  33. 33. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Therefore, Project completion time is: 36 weeks
  34. 34. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Backward Pass:
  35. 35. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36
  36. 36. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36
  37. 37. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC):
  38. 38. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC): Latest Completion Time (LC)i=Min [ (LC)j - Dij ]
  39. 39. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 24 36 36 36 – 12 = 24
  40. 40. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 24 16 24 24 36 36 Min [(36-8),(24-0)= Min[28,24] = 24
  41. 41. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 15 24 16 24 24 36 36 24 – 9 = 15
  42. 42. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 10 15 15 24 16 24 24 36 36 Min [(24-6),(15-5)= Min[18,10] = 10
  43. 43. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 0 10 10 15 15 24 16 24 24 36 36 Min [(15-7),(10-10)= Min[8, 0] = 0
  44. 44. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  45. 45. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 How to find the Critical Activities and the Critical Path ???
  46. 46. Dr. Mahmoud Abbas Mahmoud Remember that only a critical activity can have a Zero Total Float (TF)
  47. 47. Dr. Mahmoud Abbas Mahmoud Therefore, we will calculate the Total Floats for all activities and each activity has a ZERO Total Float (TF) will be a critical activity.
  48. 48. Total Float (TF) calculations Dr. Mahmoud Abbas Mahmoud TFij = (LC)j – (ES)i – Dij A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  49. 49. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity A B C D E F G Dummy
  50. 50. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy For activity A (1, 2) TF = 10 – 0 – 10 = 0*
  51. 51. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy
  52. 52. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy For activity B (1, 3) TF = 15 – 0 – 7 = 8
  53. 53. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy
  54. 54. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy For activity C (2, 3) TF = 15 – 10 – 5 = 0*
  55. 55. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy
  56. 56. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy For activity D (3, 4) TF = 24 – 10 – 6 = 8
  57. 57. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy
  58. 58. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy For activity E (3, 5) TF = 24 – 15 – 9 = 0*
  59. 59. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy
  60. 60. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy For activity F (4, 6) TF = 36 – 16 – 8 = 12
  61. 61. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy
  62. 62. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy For activity G (5, 6) TF = 36 – 24 – 12 = 0*
  63. 63. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy
  64. 64. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy For Dummy activity (4, 5) TF = 24 – 16 – 0 = 8
  65. 65. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy
  66. 66. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy The Critical Activities are: (A, C, E, G) Critical Path is: (A C E G) Project completion time is: 36 weeks