COMMUNICATION
ON SITE
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
COMMUNICATION
ON SITE-BRE GUIDE
Every year defects in the UK construction
industry cost at least £20 billion to repair
or rebuild
Some of the defects are as the result issues
such as:
 Poor communication;
 Poorly detailed drawing;
 Incorrect instructions or technical information
not being available on time;
COMMUNICATION
ON SITE
 Meeting types and frequencies;
 Method's of drawing transfer;
 Use and control of revised drawings, or
unconfirmed drawings;
 Reporting and tracking of defects;
 Lack of knowledge in detecting defects on
time.
COMMUNICATION
ON SITE-DEFERNT PHASES
Phase-1 Communication on site
 Who should accept and check deliveries of materials
to the site.
 Employment of a site engineers, clerk of work,
supervisors or securities.
 Setting their communication responsibilities and
methods.
 Setting the authority of the Clerk of Works to instruct
operatives.
 Communication with, and supervision of sub-
contractors.
COMMUNICATION
ON SITE
Drawing provision and distribution
 The role of accurate drawings in producing
good quality work.
 Careful attention must be paid as to:
 how drawings are going to be produced;
 Checked;
 distributed.
COMMUNICATION
ON SITE
The following points must be considered:
 provide drawings as complete as possible;
 at all relevant stages;
 with high accuracy;
 remove older version drawing immediately;
 make sure everyone involved with the project
knows about the new version.
COMMUNICATION
ON SITE
 ensure drawings are adequately detailed,
 and mistakes are all picked up before site
work starts.
 The drawings with high presentation-could
be produced to help building work
progress smoothly. Drawings such as:
 colour coded
 by trade or element
 laminated
 small or large sized.
COMMUNICATION
ON SITE
 The correct level of information is needed on
any drawing, for it to be successfully built
from.
 Where the drawings to be kept? It is going to
be in the site office?
 How to prepare and return amended
drawings back to site as quickly as possible.
 Is there a role for the manufacturers to help
prepare drawings?
COMMUNICATION
ON SITE
Single points of contact
 Consideration should be given to appointing
defined, single points of contact at suppliers,
design offices and contractors.
 This should help to avoid delays, confusion
and duplication of effort.
COMMUNICATION
ON SITE
Trade supervisors
 Assuming that the size of the project requires
a supervisor on site for each trade.
 This often brings benefits to the project
communication and the quality of build.
 Ensure that the role of the supervisor links
with the project requirements.
 Is the supervisor required only to schedule
work for the operatives?
COMMUNICATION
ON SITE
 Or is he/she directly involved with "setting
out", examination of drawings and quality of
build.
 To be effective, the trade supervisor must
have authoritarian style of management.
 May be a problem as the position can be
considered as not bering "operative" or
"management".
COMMUNICATION
ON SITE
Phase 2: Pre-start meeting
 The project manager should ensure that a pre-start or
"kick off" meeting is held.
 There are several benefits to site communication
which may arise from such a meeting,
Including the following:
 It allows people to get to know each other;
 This is likely to lead to better communication and less
confrontational attitudes as the work progresses.
COMMUNICATION
ON SITE
 It provides the opportunity to decide on how
communication will operate through out the
organization.
 It provides the opportunity to define points of contact
at each level.
 It can be used to ensure that all people have the
contact details for every person working on the
project.
 Ensuring all relevant people attend the kick off
meeting.
This may include:
 project management team;
 major suppliers.
COMMUNICATION
ON SITE
Technical literature and advice
 Large numbers of best practice information
and documents are accessible on the
internet on:
 Design
 material selection
 Construction
COMMUNICATION
ON SITE
 They are also available from a variety of
sources including the following:
 Manufacturers
 Construction site communication-guidance
 British Standards Institution
 BRE
 MCIOB
 RICS
 ETC
COMMUNICATION
ON SITE
Building regulatory authorities such
as:
Office of the Deputy Prime Minister,
Scottish Executive;
Trade associations;
Insurance companies (e.g. Housing
Association Property Mutual
(HAPM).
COMMUNICATION
ON SITE
National House Building Council
(NHBC));
Consultants and research
organisations (e.g. Building
Research Establishment;
(BRE), Construction Industry
Research and Information
Association (CIRIA)).
COMMUNICATION
ON SITE
Provision of technical advice
 Arrangements should be made to provide
technical advice to site operatives. In
circumstances such as:
 If there is a complex detailing to be built
 Operatives are inexperienced;
 New materials/products are in use;
 Providing the best practice information
including the following:
COMMUNICATION
ON SITE
 Introducing technical issues into the standard
induction procedures.
 Sample panels and mock-ups.
 Best practice posters on display (e.g. in the site
canteen, head office).
 Manufacturers visit the site to demonstrate best
practice or new products.
 Manufacturers visit design team to introduce new
products.
 Supply operatives with relevant parts of good practice
guidance.
COMMUNICATION
ON SITE
Upwards feedback
 Establish means by which
information can be effectively fed
back up through the formal
management structure.
 Two key areas where this can be
particularly important are as
follows:
COMMUNICATION
ON SITE
1. operatives to site office (e.g.
reporting on an incorrect drawing);
2. Site office to head office (e.g.
where an incorrect detail is
discovered;
3. this should be reported back to the
design office and the drawings
corrected).
COMMUNICATION
ON SITE
Project Meetings
 The success of formal meetings (e.g. the
monthly progress meeting) is helped by being
structured, including the following:
 Chairperson
 Agenda
 Set start and finish times
 Minutes recorded.
COMMUNICATION
ON SITE
Keep people informed at all time.
Advice all people involved across
the whole construction project.
Take care and time with
communication.
Communication must be
"supported" (i.e. ensure that
someone given an instruction).
COMMUNICATION
ON SITE
Has the back up, resources and
knowledge to complete the task
properly.
Make sure the method of
communication used is the most
appropriate.
COMMUNICATION
ON SITE
 Make sure the message is clear and all
people who need to know are informed.
 Provide instructions as early as possible,
 Do not assume that actions identified in a
memo, fax or e-mail will always have been
carried out.
 Always follow up to see if the message is
received and followed,
 Find a productive way to check if any one has
been forgotten to get the message,
COMMUNICATION
ON SITE
 Some sort of follow up or checking may
still be necessary.
 Learn from previous projects that you
have been involved with where the
communication was either particularly
good or bad.
 Learn from mistakes.
 Suggest improvement and follow up.
COMMUNICATION
ON SITE
New communication technology
 The use of new technology to help
communication should be considered.
Consider full benefits of items such as:
1. mobile phones
2. two way radios
3. digital cameras
4. on site internet- on site and at the head
office intranet
5. e-mail
COMMUNICATION
ON SITE
 For example, drawings can be e-mailed
between the site office and the architect, as
can digital photographs of defects and
progress.
 The internet can be used to access
information such as:
 Building Standards
 good practice guidance
 documentation.
COMMUNICATION
ON SITE
 On large scale construction projects the use
of project "intranet" systems has been shown
to be valuable.
 These systems are based on project wide
access via a network of personal computers
to electronic ("virtual") project documents
such as:
 Drawings
 Specifications
 correspondence.
Subcontractor BSubcontractor A
Web Browser
General
Contractor
Web Browser
Web Browser
XML XML
XML
Message
Agent
Message
Agent
Message
Agent
Platform: IBM PC
OS: Window 2000 Professional
FTP server: IIS 5.0
Platform: IBM PC
OS: Linux
FTP server: WuFTP
Platform: IBM PC
OS: Window 2000 Professional
FTP server: IIS 5.0
Data
Synchronization
Subcontractor BSubcontractor A
Web Browser
General
Contractor
Web Browser
Web Browser
XML XML
XML
Message
Agent
Message
Agent
Message
Agent
Message
Agent
Message
Agent
Message
Agent
Platform: IBM PC
OS: Window 2000 Professional
FTP server: IIS 5.0
Platform: IBM PC
OS: Linux
FTP server: WuFTP
Platform: IBM PC
OS: Window 2000 Professional
FTP server: IIS 5.0
Data
Synchronization

More Related Content

Similar to 016 communication in construction sector

Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdf
Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdfUnleashing Innovation Advancing MEP Projects with 3D Modeling.pdf
Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdfMarsBIM1
 
A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.iFieldsmart Technologies
 
Communications Management Plan
Communications Management PlanCommunications Management Plan
Communications Management PlanJonathan Reid
 
043 integrating risk management
043 integrating risk management043 integrating risk management
043 integrating risk managementdrdej19
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Blog top 5 reasons construction document management delivers winning projects...
Blog top 5 reasons construction document management delivers winning projects...Blog top 5 reasons construction document management delivers winning projects...
Blog top 5 reasons construction document management delivers winning projects...iFieldsmart Technologies
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfiFieldsmart Technologies
 
A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.iFieldsmart Technologies
 
Arc411 management assignment
Arc411 management assignmentArc411 management assignment
Arc411 management assignment2gueso06
 
2.10 communication management 1
2.10 communication management 12.10 communication management 1
2.10 communication management 1reddvise
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseOlivia Wilson
 
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...iFieldsmart Technologies
 
Bim4T: Building Information Modelling for Tender in the construction industry.
Bim4T: Building Information Modelling for Tender in the construction industry.Bim4T: Building Information Modelling for Tender in the construction industry.
Bim4T: Building Information Modelling for Tender in the construction industry.carlobughi
 
Why Architects Need Design Collaboration Platforms in Preconstruction.pdf
Why Architects Need Design Collaboration Platforms in Preconstruction.pdfWhy Architects Need Design Collaboration Platforms in Preconstruction.pdf
Why Architects Need Design Collaboration Platforms in Preconstruction.pdfiFieldsmart Technologies
 
Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communicationarshriz
 

Similar to 016 communication in construction sector (20)

Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdf
Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdfUnleashing Innovation Advancing MEP Projects with 3D Modeling.pdf
Unleashing Innovation Advancing MEP Projects with 3D Modeling.pdf
 
A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.
 
Communications Management Plan
Communications Management PlanCommunications Management Plan
Communications Management Plan
 
043 Integrating Risk Management
043 Integrating Risk Management043 Integrating Risk Management
043 Integrating Risk Management
 
043 integrating risk management
043 integrating risk management043 integrating risk management
043 integrating risk management
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Blog top 5 reasons construction document management delivers winning projects...
Blog top 5 reasons construction document management delivers winning projects...Blog top 5 reasons construction document management delivers winning projects...
Blog top 5 reasons construction document management delivers winning projects...
 
Technical Report
Technical ReportTechnical Report
Technical Report
 
Services of Burgeon Construction
Services of Burgeon Construction Services of Burgeon Construction
Services of Burgeon Construction
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdf
 
A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.A guide to construction RFIs including construction management software.
A guide to construction RFIs including construction management software.
 
SPIROS TSOUMANIS-CV
SPIROS TSOUMANIS-CVSPIROS TSOUMANIS-CV
SPIROS TSOUMANIS-CV
 
Arc411 management assignment
Arc411 management assignmentArc411 management assignment
Arc411 management assignment
 
MDA csp
MDA cspMDA csp
MDA csp
 
2.10 communication management 1
2.10 communication management 12.10 communication management 1
2.10 communication management 1
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
 
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...
Leveraging Construction Field Reports and iFieldSmart Technologies for Improv...
 
Bim4T: Building Information Modelling for Tender in the construction industry.
Bim4T: Building Information Modelling for Tender in the construction industry.Bim4T: Building Information Modelling for Tender in the construction industry.
Bim4T: Building Information Modelling for Tender in the construction industry.
 
Why Architects Need Design Collaboration Platforms in Preconstruction.pdf
Why Architects Need Design Collaboration Platforms in Preconstruction.pdfWhy Architects Need Design Collaboration Platforms in Preconstruction.pdf
Why Architects Need Design Collaboration Platforms in Preconstruction.pdf
 
Improving IT Project Communication
Improving IT Project CommunicationImproving IT Project Communication
Improving IT Project Communication
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 

Recently uploaded (20)

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 

016 communication in construction sector

  • 2. COMMUNICATION ON SITE-BRE GUIDE Every year defects in the UK construction industry cost at least £20 billion to repair or rebuild Some of the defects are as the result issues such as:  Poor communication;  Poorly detailed drawing;  Incorrect instructions or technical information not being available on time;
  • 3. COMMUNICATION ON SITE  Meeting types and frequencies;  Method's of drawing transfer;  Use and control of revised drawings, or unconfirmed drawings;  Reporting and tracking of defects;  Lack of knowledge in detecting defects on time.
  • 4. COMMUNICATION ON SITE-DEFERNT PHASES Phase-1 Communication on site  Who should accept and check deliveries of materials to the site.  Employment of a site engineers, clerk of work, supervisors or securities.  Setting their communication responsibilities and methods.  Setting the authority of the Clerk of Works to instruct operatives.  Communication with, and supervision of sub- contractors.
  • 5. COMMUNICATION ON SITE Drawing provision and distribution  The role of accurate drawings in producing good quality work.  Careful attention must be paid as to:  how drawings are going to be produced;  Checked;  distributed.
  • 6. COMMUNICATION ON SITE The following points must be considered:  provide drawings as complete as possible;  at all relevant stages;  with high accuracy;  remove older version drawing immediately;  make sure everyone involved with the project knows about the new version.
  • 7. COMMUNICATION ON SITE  ensure drawings are adequately detailed,  and mistakes are all picked up before site work starts.  The drawings with high presentation-could be produced to help building work progress smoothly. Drawings such as:  colour coded  by trade or element  laminated  small or large sized.
  • 8. COMMUNICATION ON SITE  The correct level of information is needed on any drawing, for it to be successfully built from.  Where the drawings to be kept? It is going to be in the site office?  How to prepare and return amended drawings back to site as quickly as possible.  Is there a role for the manufacturers to help prepare drawings?
  • 9. COMMUNICATION ON SITE Single points of contact  Consideration should be given to appointing defined, single points of contact at suppliers, design offices and contractors.  This should help to avoid delays, confusion and duplication of effort.
  • 10. COMMUNICATION ON SITE Trade supervisors  Assuming that the size of the project requires a supervisor on site for each trade.  This often brings benefits to the project communication and the quality of build.  Ensure that the role of the supervisor links with the project requirements.  Is the supervisor required only to schedule work for the operatives?
  • 11. COMMUNICATION ON SITE  Or is he/she directly involved with "setting out", examination of drawings and quality of build.  To be effective, the trade supervisor must have authoritarian style of management.  May be a problem as the position can be considered as not bering "operative" or "management".
  • 12. COMMUNICATION ON SITE Phase 2: Pre-start meeting  The project manager should ensure that a pre-start or "kick off" meeting is held.  There are several benefits to site communication which may arise from such a meeting, Including the following:  It allows people to get to know each other;  This is likely to lead to better communication and less confrontational attitudes as the work progresses.
  • 13. COMMUNICATION ON SITE  It provides the opportunity to decide on how communication will operate through out the organization.  It provides the opportunity to define points of contact at each level.  It can be used to ensure that all people have the contact details for every person working on the project.  Ensuring all relevant people attend the kick off meeting. This may include:  project management team;  major suppliers.
  • 14. COMMUNICATION ON SITE Technical literature and advice  Large numbers of best practice information and documents are accessible on the internet on:  Design  material selection  Construction
  • 15. COMMUNICATION ON SITE  They are also available from a variety of sources including the following:  Manufacturers  Construction site communication-guidance  British Standards Institution  BRE  MCIOB  RICS  ETC
  • 16. COMMUNICATION ON SITE Building regulatory authorities such as: Office of the Deputy Prime Minister, Scottish Executive; Trade associations; Insurance companies (e.g. Housing Association Property Mutual (HAPM).
  • 17. COMMUNICATION ON SITE National House Building Council (NHBC)); Consultants and research organisations (e.g. Building Research Establishment; (BRE), Construction Industry Research and Information Association (CIRIA)).
  • 18. COMMUNICATION ON SITE Provision of technical advice  Arrangements should be made to provide technical advice to site operatives. In circumstances such as:  If there is a complex detailing to be built  Operatives are inexperienced;  New materials/products are in use;  Providing the best practice information including the following:
  • 19. COMMUNICATION ON SITE  Introducing technical issues into the standard induction procedures.  Sample panels and mock-ups.  Best practice posters on display (e.g. in the site canteen, head office).  Manufacturers visit the site to demonstrate best practice or new products.  Manufacturers visit design team to introduce new products.  Supply operatives with relevant parts of good practice guidance.
  • 20. COMMUNICATION ON SITE Upwards feedback  Establish means by which information can be effectively fed back up through the formal management structure.  Two key areas where this can be particularly important are as follows:
  • 21. COMMUNICATION ON SITE 1. operatives to site office (e.g. reporting on an incorrect drawing); 2. Site office to head office (e.g. where an incorrect detail is discovered; 3. this should be reported back to the design office and the drawings corrected).
  • 22. COMMUNICATION ON SITE Project Meetings  The success of formal meetings (e.g. the monthly progress meeting) is helped by being structured, including the following:  Chairperson  Agenda  Set start and finish times  Minutes recorded.
  • 23. COMMUNICATION ON SITE Keep people informed at all time. Advice all people involved across the whole construction project. Take care and time with communication. Communication must be "supported" (i.e. ensure that someone given an instruction).
  • 24. COMMUNICATION ON SITE Has the back up, resources and knowledge to complete the task properly. Make sure the method of communication used is the most appropriate.
  • 25. COMMUNICATION ON SITE  Make sure the message is clear and all people who need to know are informed.  Provide instructions as early as possible,  Do not assume that actions identified in a memo, fax or e-mail will always have been carried out.  Always follow up to see if the message is received and followed,  Find a productive way to check if any one has been forgotten to get the message,
  • 26. COMMUNICATION ON SITE  Some sort of follow up or checking may still be necessary.  Learn from previous projects that you have been involved with where the communication was either particularly good or bad.  Learn from mistakes.  Suggest improvement and follow up.
  • 27. COMMUNICATION ON SITE New communication technology  The use of new technology to help communication should be considered. Consider full benefits of items such as: 1. mobile phones 2. two way radios 3. digital cameras 4. on site internet- on site and at the head office intranet 5. e-mail
  • 28. COMMUNICATION ON SITE  For example, drawings can be e-mailed between the site office and the architect, as can digital photographs of defects and progress.  The internet can be used to access information such as:  Building Standards  good practice guidance  documentation.
  • 29. COMMUNICATION ON SITE  On large scale construction projects the use of project "intranet" systems has been shown to be valuable.  These systems are based on project wide access via a network of personal computers to electronic ("virtual") project documents such as:  Drawings  Specifications  correspondence.
  • 30. Subcontractor BSubcontractor A Web Browser General Contractor Web Browser Web Browser XML XML XML Message Agent Message Agent Message Agent Platform: IBM PC OS: Window 2000 Professional FTP server: IIS 5.0 Platform: IBM PC OS: Linux FTP server: WuFTP Platform: IBM PC OS: Window 2000 Professional FTP server: IIS 5.0 Data Synchronization Subcontractor BSubcontractor A Web Browser General Contractor Web Browser Web Browser XML XML XML Message Agent Message Agent Message Agent Message Agent Message Agent Message Agent Platform: IBM PC OS: Window 2000 Professional FTP server: IIS 5.0 Platform: IBM PC OS: Linux FTP server: WuFTP Platform: IBM PC OS: Window 2000 Professional FTP server: IIS 5.0 Data Synchronization