I worked with the Village of Elwood to prepare a Preliminary Park Plan for Deer Run Park. The challenge of this 37-acre linear park was to transform the space from industrial buffer to a neighborhood park.
This presentation illustrates the final Preliminary Plan as approved by the Park & Recreation Committee and Village Board including construction costs and implementation schedule.
2. Design Process
Design Process
Conducted 4 meetings with Parks and Recreation
Board
d
December 2009‐vsioning meeting
F b
February 2010‐presentation of initial concepts
t ti f i iti l t
March 2010‐general costing of preferred program
elements
April 2010‐selection of preferred design concept
Coordination meetings with technical design team
Applied for rezoning of park properties
Will modify OSLAD application based on Village Board
endorsement of concept plan
3. Influences on Park Design
Influences on Park Design
Existing site characteristics
g
Vision for Elwood park system
Parks and Recreation Board
Community input
Parks and Open Space Master
Plan
OSLAD requirements
4. Influences on Park Design
Influences on Park Design
Existing site characteristics
g
Vision for Elwood park system
Parks and Recreation Board
Community input
Parks and Open Space Master
Plan
OSLAD requirements
6. Preferred Program
Preferred Program
Recreation Beautification
Flexible field Landscaped plantings
Tot playground and buffers
Regulation softball Interpretive plantings
p p g
diamond and signage
Walking/running oval Park gateways and
Fitness stations
entry features
t f t
Amenities
Concessions facility
Picnic shelter(s)
Trail system
Parking
8. Initial Working Concept
Initial Working Concept
Keeps southern softball
diamond
Relocates parking towards
activity areas
i i
Includes a
concessions/picnic facility
Creates flexible lawn for
field sports and events
p
Places fitness stations in
southern portion
9. Initial Working Concept
Initial Working Concept
Substantial infrastructure
costs for concessions
facility
R l
Relocated parking removes
d ki
previous investment
Lack of visibility from
Mississippi Avenue
10. Preferred Concept
Preferred Concept
Shorter infrastructure
lines
Existing parking lot used
Activity areas are
centralized
A ti iti
Activities more visible
i ibl
from Mississippi Avenue
Regulation softball
diamond
New approach to fitness
pp
area
11. Preferred Concept
Preferred Concept
Shorter infrastructure
lines
Existing parking lot used
Activity areas are
centralized
A ti iti
Activities more visible
i ibl
from Mississippi Avenue
Regulation softball
diamond
New approach to fitness
pp
area
12. Preferred Concept‐Cost Impacts
Preferred Concept‐Cost Impacts
Cost savings: New cost items:
Parking lot removal
k l l Relocation of one
l f
$40,000 savings softball diamond
Parking lot $20,000
construction
i
$34,000 savings Optional cost items:
Sanitary sewer line Additional picnic shelter
$20,000 savings
Reduced grading work Lighting for softball
$40,000 savings
diamond and
concessions area
Hard court sports
13. Preferred Concept‐Conditions
Preferred Concept‐Conditions
Endorsed with
following condition: As
final costing is
developed, include the
following amenities as
f ll i ii
prioritized below:
1.
1 Additional picnic
shelter between
softball diamond and
open field
fi ld
2. Lighting for softball
diamond and
concessions
3. 2 tennis courts