21. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
22. CABC ( Crushed aggregate base course )
Earthworks
Mixing Plant
Testing Compaction
Site Trial
28. Prime Coat Site Trials
Roads&Pavings
Bituminous Prime Coat shall
consist of supplying and applying
bituminous material to a previously
prepared and approved base
course in accordance with the
Specification to ensure a bond
between this surface and the
overlying course.
62. ILS Glide Path Antenna
Miscellaneous Provides radio vertical guidance to an aircraft approaching and
landing on a runway
63. DVOR Ground Station
Miscellaneous Omni Directional Radio Range (VOR) is a radio navigation system for aircrafts, so
an aircraft can determine their position and stay on course.
64. Airfield Lights - Substation
Miscellaneous
Contains switchgear, protection and control equipment
65. Airfield Lights - Substation
Miscellaneous
Contains switchgear, protection and control equipment
66. Airfield Lights – Taxi Guidance Signs
Miscellaneous
Taxi guidance signs provide direction and
information to taxiing aircraft.
67. Concrete Slipform Paving
Roads&Pavings
Brief Description
Horizontal slip forming for concrete pavement. The process
consists of placing and spreading low slump concrete on the
ground in front of a paver that slips over the concrete and
extrudes strips of slabs.
Slipform Concrete Paver
Spreader
Texturing
& Curing
83. Cable Laying
ⓒ David H Moloney
Cable Drum Stand Cable pulled on rollers
Cable Winch
Cable Drum Unloading Cable on rollers Cable Testing prior to Backfilling
Miscellaneous
84. Horizontal Directional Drilling
Pipework
Brief Description
Horizontal Directional Drilling under a taxiway.
Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
96. Concrete Delivery Order - RecordConcrete
Brief Description
It is important to record orders for
concrete deliveries.
The form can be adapted for
other materials e.g.
reinforcement.
99. Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
105. Excavation for Underground Pump stationEarthworks
Brief Description
Faces of excavation Stepped &
Well-point Dewatering used.
106. Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
109. Stakeholders Engagement
Method of Work Plan (MOWP)
A Method of Working Plan (MOWP) is prepared when the normal operation of an aerodrome is
disrupted through aerodrome works and the risk to aircraft operations is increased. Stakeholders
likely to be significantly affected by the proposed works will be given the opportunity to participate
in the planning process.
The MOWP will clearly set out the following: • the scope of work and the stages of carrying out
the work; • how the works are to be carried out and the restrictions on the works organisation; •
how the aircraft operators and pilots will be told, through NOTAM, of the restrictions to aircraft
operations at each stage of the work; • identify any changes necessary to aerodrome markings
and lights as the works progress; • drawings to illustrate work arrangements and changes to
declared distances, taxiing routes, etc.; and • identify persons responsible for the works and those
accountable for ensuring safety of the aerodrome facilities to aircraft operations.
Airport Stakeholders
Operations G.M.
Technical Services G.M
Senior Aviation Manager
Chief Fire Officer
Project Manager
Sr. Maintenance Manager
Operations Reediness Team Leader
Certification & Compliance Manager
Airfield Duty Manager
Airport Duty Manager
HSE Specialist
DGSAS, Director of Airports
DGSAS, Aerodrome Certification
CAA Air Traffic Control –Tower
CAA Chief of Tower
Police
Ground Handling Agent
Airport Refueller Companies
114. Working Airside to Upgrade Taxiway
Asphalt Pavement Laid on Existing Concrete Pavement Temporary Gate and Fence
Excavation Planing at Runway tie-inFill –Crushed Aggregate Rake sealant
out of Joints
117. Temporary Contractors Site Facilities
ⓒ David H Moloney
Brief Description
Site Offices, Camp Accommodation for
1,250 workers, Canteen, Recreation,
Fabrication shops, Stores, Plant Yard. In five
locations along the route.
118. Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
124. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
125. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
134. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
140. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
150. Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
151. Existing Underground Utilities
ⓒ David H Moloney
Earthworks
Brief Description
Before digging
establish the location
and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
158. Safety Documents
Health,Safety&Environment
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
159. Safety Documents
Health,Safety&Environment
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
166. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
180. Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
181. Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Project
Quantity for each month of the Project
ⓒ David H Moloney
Brief Description
Histograms shows resources etc. for each month of a project.
184. Primary Substation-
Chiller Plant
Pump House
IRRIGATIONWATER TANKS
IrrigationPump House-
POTABLE/FIRE WATER TANK
Programme using Timeline & 3D Images
Airport Central Utility Yard
195. Airport Roof Truss
ⓒ David H Moloney
StructuralSteel
Brief Description
Roof Truss 190 tonne in weight. Sections welded together on
trestles and the truss is lifted into position.
206. Roof Covering
ⓒ David H Moloney
StructuralSteel
Brief Description
Sequence is
Fix bottom sheet
Fix Vapour barrier
Fix Top Hat section and clips
Fit Insulation
Fix top sheet