Project TardisMAIN WAREHOUSE RACKING INSTALLATION
CREATED BY DAVE GRAYSON
14TH NOVEMBER 2014.
1
Project Management Plan
(P.M.P.)
 Project Sponsor: Dave Grayson
 Project Members:
 Project Managers-Dave Wilkins/Steve Broad
 I.T.-Chris Fowles
 Maintenance-Garry Hall
 Goods In-Marcus Dale
 Purchasing-Brian Wade
 MHE-Marcus Dale/Supplier
 P.I. –John Longsden
 Racking/Sprinklers-Andy Manktelow/Supplier
 H&S-Donna Saville
2
Background
 As the business continues to expand at a significant rate the need for
warehousing space has become business critical during 2014.
 This has lead to a makeshift extension of the warehouse via stillage purchase
and storage on site, 4 hire trailers used as storage and Sims being used as a
third party storage warehouse. This has lead to increased cost totalling £26.5k at
the time of writing for third party storage and £280per week for trailer hire.
 Other additional costs include the need to do increased hours, overtime, shift
work in order to keep the warehouse flowing to cope with both inbound and
outbound peaks.
 As part of the remedy for the main site there is to be an extension built to
accommodate office and canteen space. This will enable additional floor
space to become available in the main warehouse that is to be filled with long
pallet and euro storage racking This project covers the additional racking build.
 This work cannot physically start until the new extension has been built.
3
In Scope
 Once the extension is built and ready to occupy then there will need to
be a move from the existing Trade Counter/Showroom/Works
Office/Canteens/Stationary office and Drilling and Returns area.
 The existing warehouse floor will then need to have VNA log on wires
installed for the relevant 11 aisles of extended racking.
 Once complete there will be a major build of euro and cantilever
racking in the newly created space.
 There will also be modifications made to the old Trade
Counter/Showroom mez which will then become a new work area for
carrier /secondary ops returns and drilling.
 These new areas will require sprinkler coverage.
 Phase 1 will require P&D’s to supply the increased location capacity
and expected growth in volumes as well as regular replen/de van
single sku pallets from our satellite warehouse.
4
In Scope
 The euro racking will be scoped out for MTM; roller racking;1245 panels storage
etc.
 Create a nominated secondary Ops team and Team Leader to run it.
 Purchase any relevant MHE trucks for the supply of product to the mez floor.
 Reconfigure the warehouse once the new locations are in place to provide a)
new pick slots for new ranges and b) moving fast moving product to the front
end of the warehouse and slow/non moving stock to the furthest point in the
warehouse.
 Remove the cantilever racking adjacent to the goods out bays to replace the
current euro X aisle. Absorb the lost euro locations in the new extended aisles.
This will increase the marshalling area on the outbound bays.
 Achieve all this whilst the business continues to operate on a daily basis, where
possible. There is an expectation that there will be additional out of hours work
required during some parts of the project.
5
Out of Scope
 Supplying backfill labour to other parts of the business during this
project. There is a huge challenge here to complete this project at
the same time as normal trading which will stretch operational
resource to its limit.
 In aisle picking sequencing reconfiguration for the existing aisles and
pick faces. This will need to be done post project Go Live.
6
Expected Outcome
 To provide a medium /long term solution to the warehouse space
issue-especially the long pallet locations.
 Enable the main warehouse to operate more safely and efficiently.
 Enable the company to introduce more new ranges into its sales
portfolio by increasing pick face availability and bulk storage
capacity.
 Provide exceptional delivery service standards to both internal
customers and external customers.
 To eliminate third party storage costs and have the main warehouse
as a picking and short lead time stock holding warehouse.
7
C.D.P.
Jul-06 Jul-13 Jul-20 Jul-27 Aug-03 Aug-10 Aug-17 Aug-24 Aug-31 Sep-07 Sep-14 Sep-21 Sep-28
Move existing offices
Make ready T/Count Mez
Demolish current drilling area
Move drilling and carier
Lay VNA long in wiring
Rollback or Build racking
Install P&D's
Install Sprinklers
Install RF hardware
Commision/Test MHE/RF
H&S Risk Assess
Project Meeting
Migrate Stock into locations
Go Live
Operational KPI's
PIR Meeting
8
Capex Budget
Budget Actual Diff +/-
Cost £ Cost £
Demolition of offices/drilling
Make ready T/Counter
IT RF hardware installation
Racking
Sprinklers
VNA floor log on wires
MHE purchase
Manitenance Work
IT hardware/software
Stock transfer
Out of hours working
9
Risks
 There are some key members of the current operational team who will be taken
out of the mainstream operational day, at times, until the project is complete.
Backfill will be required by less experienced staff which could have an impact
on the main warehouse service levels
 Costs going over budget
 The extension build overshoots the start of July which means this project also
being delayed. That would encroach into October and November-traditionally
our two busiest months of the year.
 New ranges being introduced into the business due to a major increase in sales
demand before this option is up and running.
 With a major demolition and racking build alongside probability of maintenance
work there are likely to be a lot of contractors on site. These must be controlled
properly or could pose a H&S risk.
 Failure to complete the project on time due to a project overshoot on tasks
involved will have the same ramifications as per the failure to start on time.
10
Governance
 Periodic project meeting, (as per CDP)-all.
 Weekly review of the CDP-between Project Manager and Project
Sponsor.
 Weekly budget review between Project Manager and Project
Sponsor
 Weekly update to the Director’s from the Project Sponsor.
 Operational KPI’s post Go Live.
11
Project Sign Off /Closure
 All project team members will be required to sign off that their area
is closed off.
 A final close out meeting will be held to review both success and
also any lessons that can be learnt for future projects. (Post
Implementation Review meeting.)
 Final sign off will then be done by the Project Sponsor/Directors.
12

More Related Content

What's hot

TRL_A4brochure_CP
TRL_A4brochure_CPTRL_A4brochure_CP
TRL_A4brochure_CPPeter Hale
 
SERVICE MARKETING ON PORTS
SERVICE MARKETING ON PORTSSERVICE MARKETING ON PORTS
SERVICE MARKETING ON PORTSAMIR KHAN
 
Wärtsilä offshore oil and gas business
Wärtsilä offshore oil and gas businessWärtsilä offshore oil and gas business
Wärtsilä offshore oil and gas businessBusiness Finland
 
4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler ApplicationsKristy Marshall
 
Conexplo proppant management 2014 mendoza
Conexplo proppant management 2014 mendozaConexplo proppant management 2014 mendoza
Conexplo proppant management 2014 mendozaJuan Carlos Bonapace
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Iain McGregor
 
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with MinemaxKristy Marshall
 

What's hot (9)

TRL_A4brochure_CP
TRL_A4brochure_CPTRL_A4brochure_CP
TRL_A4brochure_CP
 
SERVICE MARKETING ON PORTS
SERVICE MARKETING ON PORTSSERVICE MARKETING ON PORTS
SERVICE MARKETING ON PORTS
 
Wärtsilä offshore oil and gas business
Wärtsilä offshore oil and gas businessWärtsilä offshore oil and gas business
Wärtsilä offshore oil and gas business
 
SWC - Revised 050716
SWC - Revised 050716SWC - Revised 050716
SWC - Revised 050716
 
4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications4. Joe Kraft, Minemax - Minemax Scheduler Applications
4. Joe Kraft, Minemax - Minemax Scheduler Applications
 
Conexplo proppant management 2014 mendoza
Conexplo proppant management 2014 mendozaConexplo proppant management 2014 mendoza
Conexplo proppant management 2014 mendoza
 
Dana Medway HR
Dana Medway HRDana Medway HR
Dana Medway HR
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax
2. Jonathan Nortier and Ali Sirkeci, AMC - Evaluate Your Options with Minemax
 

Similar to Project Tardis (5)

UK Excellence article PICL & SGG Pisa(1)
UK Excellence article  PICL & SGG Pisa(1)UK Excellence article  PICL & SGG Pisa(1)
UK Excellence article PICL & SGG Pisa(1)Geoffrey Noble
 
Lungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase
 
Warehouse Restructuring10
Warehouse Restructuring10Warehouse Restructuring10
Warehouse Restructuring10John White
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...yusuf699644
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1Maricel Molina
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docxbrian157854
 
cv_eugene_engels 2015 attachment
cv_eugene_engels 2015 attachmentcv_eugene_engels 2015 attachment
cv_eugene_engels 2015 attachmentEugene van Brakel
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Carige Andrew
 
Intern Presentation (1)
Intern Presentation (1)Intern Presentation (1)
Intern Presentation (1)Joshua Bastian
 
F. King CV- Jan 2015
F. King CV- Jan 2015F. King CV- Jan 2015
F. King CV- Jan 2015Frank King
 

Similar to Project Tardis (5) (20)

Project Telstar
Project TelstarProject Telstar
Project Telstar
 
UK Excellence article PICL & SGG Pisa(1)
UK Excellence article  PICL & SGG Pisa(1)UK Excellence article  PICL & SGG Pisa(1)
UK Excellence article PICL & SGG Pisa(1)
 
Lungelo Mwelase P2 Report
Lungelo Mwelase P2 ReportLungelo Mwelase P2 Report
Lungelo Mwelase P2 Report
 
Warehouse Restructuring10
Warehouse Restructuring10Warehouse Restructuring10
Warehouse Restructuring10
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docx
 
cv_eugene_engels 2015 attachment
cv_eugene_engels 2015 attachmentcv_eugene_engels 2015 attachment
cv_eugene_engels 2015 attachment
 
project management UOC-1
project management UOC-1project management UOC-1
project management UOC-1
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 
Upload
UploadUpload
Upload
 
Projects
ProjectsProjects
Projects
 
Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16Andrew Carige_Resume_Detailed Version 25-02-16
Andrew Carige_Resume_Detailed Version 25-02-16
 
Intern Presentation (1)
Intern Presentation (1)Intern Presentation (1)
Intern Presentation (1)
 
Can off
Can offCan off
Can off
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
Perth metro
Perth metroPerth metro
Perth metro
 
F. King CV- Jan 2015
F. King CV- Jan 2015F. King CV- Jan 2015
F. King CV- Jan 2015
 

Project Tardis (5)

  • 1. Project TardisMAIN WAREHOUSE RACKING INSTALLATION CREATED BY DAVE GRAYSON 14TH NOVEMBER 2014. 1
  • 2. Project Management Plan (P.M.P.)  Project Sponsor: Dave Grayson  Project Members:  Project Managers-Dave Wilkins/Steve Broad  I.T.-Chris Fowles  Maintenance-Garry Hall  Goods In-Marcus Dale  Purchasing-Brian Wade  MHE-Marcus Dale/Supplier  P.I. –John Longsden  Racking/Sprinklers-Andy Manktelow/Supplier  H&S-Donna Saville 2
  • 3. Background  As the business continues to expand at a significant rate the need for warehousing space has become business critical during 2014.  This has lead to a makeshift extension of the warehouse via stillage purchase and storage on site, 4 hire trailers used as storage and Sims being used as a third party storage warehouse. This has lead to increased cost totalling £26.5k at the time of writing for third party storage and £280per week for trailer hire.  Other additional costs include the need to do increased hours, overtime, shift work in order to keep the warehouse flowing to cope with both inbound and outbound peaks.  As part of the remedy for the main site there is to be an extension built to accommodate office and canteen space. This will enable additional floor space to become available in the main warehouse that is to be filled with long pallet and euro storage racking This project covers the additional racking build.  This work cannot physically start until the new extension has been built. 3
  • 4. In Scope  Once the extension is built and ready to occupy then there will need to be a move from the existing Trade Counter/Showroom/Works Office/Canteens/Stationary office and Drilling and Returns area.  The existing warehouse floor will then need to have VNA log on wires installed for the relevant 11 aisles of extended racking.  Once complete there will be a major build of euro and cantilever racking in the newly created space.  There will also be modifications made to the old Trade Counter/Showroom mez which will then become a new work area for carrier /secondary ops returns and drilling.  These new areas will require sprinkler coverage.  Phase 1 will require P&D’s to supply the increased location capacity and expected growth in volumes as well as regular replen/de van single sku pallets from our satellite warehouse. 4
  • 5. In Scope  The euro racking will be scoped out for MTM; roller racking;1245 panels storage etc.  Create a nominated secondary Ops team and Team Leader to run it.  Purchase any relevant MHE trucks for the supply of product to the mez floor.  Reconfigure the warehouse once the new locations are in place to provide a) new pick slots for new ranges and b) moving fast moving product to the front end of the warehouse and slow/non moving stock to the furthest point in the warehouse.  Remove the cantilever racking adjacent to the goods out bays to replace the current euro X aisle. Absorb the lost euro locations in the new extended aisles. This will increase the marshalling area on the outbound bays.  Achieve all this whilst the business continues to operate on a daily basis, where possible. There is an expectation that there will be additional out of hours work required during some parts of the project. 5
  • 6. Out of Scope  Supplying backfill labour to other parts of the business during this project. There is a huge challenge here to complete this project at the same time as normal trading which will stretch operational resource to its limit.  In aisle picking sequencing reconfiguration for the existing aisles and pick faces. This will need to be done post project Go Live. 6
  • 7. Expected Outcome  To provide a medium /long term solution to the warehouse space issue-especially the long pallet locations.  Enable the main warehouse to operate more safely and efficiently.  Enable the company to introduce more new ranges into its sales portfolio by increasing pick face availability and bulk storage capacity.  Provide exceptional delivery service standards to both internal customers and external customers.  To eliminate third party storage costs and have the main warehouse as a picking and short lead time stock holding warehouse. 7
  • 8. C.D.P. Jul-06 Jul-13 Jul-20 Jul-27 Aug-03 Aug-10 Aug-17 Aug-24 Aug-31 Sep-07 Sep-14 Sep-21 Sep-28 Move existing offices Make ready T/Count Mez Demolish current drilling area Move drilling and carier Lay VNA long in wiring Rollback or Build racking Install P&D's Install Sprinklers Install RF hardware Commision/Test MHE/RF H&S Risk Assess Project Meeting Migrate Stock into locations Go Live Operational KPI's PIR Meeting 8
  • 9. Capex Budget Budget Actual Diff +/- Cost £ Cost £ Demolition of offices/drilling Make ready T/Counter IT RF hardware installation Racking Sprinklers VNA floor log on wires MHE purchase Manitenance Work IT hardware/software Stock transfer Out of hours working 9
  • 10. Risks  There are some key members of the current operational team who will be taken out of the mainstream operational day, at times, until the project is complete. Backfill will be required by less experienced staff which could have an impact on the main warehouse service levels  Costs going over budget  The extension build overshoots the start of July which means this project also being delayed. That would encroach into October and November-traditionally our two busiest months of the year.  New ranges being introduced into the business due to a major increase in sales demand before this option is up and running.  With a major demolition and racking build alongside probability of maintenance work there are likely to be a lot of contractors on site. These must be controlled properly or could pose a H&S risk.  Failure to complete the project on time due to a project overshoot on tasks involved will have the same ramifications as per the failure to start on time. 10
  • 11. Governance  Periodic project meeting, (as per CDP)-all.  Weekly review of the CDP-between Project Manager and Project Sponsor.  Weekly budget review between Project Manager and Project Sponsor  Weekly update to the Director’s from the Project Sponsor.  Operational KPI’s post Go Live. 11
  • 12. Project Sign Off /Closure  All project team members will be required to sign off that their area is closed off.  A final close out meeting will be held to review both success and also any lessons that can be learnt for future projects. (Post Implementation Review meeting.)  Final sign off will then be done by the Project Sponsor/Directors. 12