3. EGLINTON STATION UPDATE
3CENTRAL WEST WORKS MONTHLY MEETING
Activity Location Approx. Date & Duration
Extended Hours for Station Box
Construction
Excavation, rebar, conduit and
micropile installation
Beneath the TTC box
Underway through 2020
Monday β Friday, 24 hours
Berwick Portal Construction/TTC
Eglinton Station Works
Delivery of escalator truss and north
platform relocation preparatory works
Eglinton TTC Station
Periodically through 2020; subject to
TTC approval
Next scheduled closure(s):
β’ November 14-15, 2020
Tunnel Ventilation Shaft Construction
Center of Yonge St between Eglinton
Ave and Roehampton Ave
Underway through December 2020
Elevator Construction
2200 Yonge St (former Smokeβs
Poutinerie)
Underway through December 2020
Structural Steel Deliveries
Northeast corner of Yonge St and
Eglinton Ave
As early as 6:00 a.m. Monday β Sunday
for two (2) weeks
7. MOUNT PLEASANT STATION UPDATE
7INSERT FOOTER
Activity Location Approx. Date & Duration
Tunnel Segment Demolition and Removal Station Box and Entrances Complete!
Deep Excavation and Chipping Underneath the Station Roof
Underway for approximately two (2)
weeks
Utility Reinstatement Works
North and South sides of Eglinton
Avenue
Underway through 2021
Waterproofing, rebar, steel and conduit
installations
Secondary Entrance and Station Box Underway through 2021
Concrete Works Secondary Entrance and Station Box Underway through 2021
Above Ground Construction of the
Secondary Entrance
β’ Structural Steel Installations
North side of Eglinton Avenue, east of
Mount Pleasant Road
Expected to start late Winter 2020
and continue through to 2021
10. RECORD BREAKING ACHIEVEMENT:
MT PLEASANT STATION COMPLETES THE LARGEST CONCRETE POUR ON THE PROJECT!
10INSERT FOOTER
Last Saturday, Mt Pleasant Station completed the largest concrete pour on the project to-date. The team poured 1700 m3 of concrete in 11
hours, forming two of the station inverts and track beds.