Activity Location Approx. Date & Duration
Extended Hours for Station Box
Construction
Rebar, conduit, steel installations, and final
grading works
Beneath Eglinton Avenue and Eglinton TTC
Station
Underway through early 2021
Monday – Friday, 24 hours
Berwick Portal Construction
• Structural steel installations and architectural
works
Berwick Avenue and Eglinton TTC Station
Through 2021
• Berwick Ave closures subject to TTC approval
• Structural steel deliveries occur as early as 6:00
a.m.
TTC Eglinton Station Works
• North platform relocation works, escalator
installations and elevator construction
Eglinton TTC Station
(Elevator construction ongoing at 2200
Yonge St – former Smoke’s Poutinerie)
Periodically through 2021; subject to TTC
approval
Tunnel Ventilation Shaft Construction
Center of Yonge St between Eglinton Ave
and Roehampton Ave
Underway through early 2021
Concrete Works Throughout all station areas Through 2021
9. MOUNT PLEASANT STATION UPDATE
9
Activity Location Approx. Date & Duration
Excavation and Chipping Main Entrance site
Underway for approximately one (1)
week
Utility Reinstatement Works North and south sides of Eglinton Avenue Underway through 2021
Formwork, waterproofing, rebar, steel and
conduit installations
Secondary Entrance and Station Box (below
Eglinton Ave)
Underway through mid 2021
Activities will begin at the Main Entrance site
as early as January 18, 2021
Concrete Works
• Shotcrete application and concrete pours
Throughout all station areas Underway through 2021
Structural Steel Installations
• Welding of structural steel beams above
ground.
• Periodic use of a mobile crane within the 801 Mt
Pleasant Rd parking lot.
Secondary Entrance site and adjacent
parking lot at 801 Mt Pleasant Road.
Mid January 2021 for approximately
three (3) weeks.