SlideShare a Scribd company logo
1 of 2
Salford City College
Eccles Sixth Form Centre
BTec Level 3
Extended Diploma in Creative Media Production
Games Design
Final Major Project
Schedule
Review date: 06.02.13
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
w/b 04.02.13 Task 1 - FMP Launch
Meeting
w/b 11.02.13 Half-Term
w/b 18.02.13 Book meeting slot
with project manager.
Finish Task 2 and 3 by
today.
Review Schedule and
Production Log
w/b 25.02.13 Task 1, 2 completed Task 4: Pitch must
take place by this
week.
Begin to generate
ideas. Collect images
etc.
Gather More images
for task 3 and describe
what my map with me
like.
Gather More images
for task 3 and describe
what my map with me
like.
Review Schedule and
Production Log
w/b 04.03.13 Review Schedule and
Production Log
Finish ideas
generation and give
first idea.
Finish Ethical,
Contractual and
Budget Before here.
Finish Ethical,
Contractual and
Budget Before here.
Review Schedule and
Production Log
w/b 11.03.13 Start Pre- Production Start Pre- Production Start Pre- Production Continue Building a
project pack for Pre-
Production, including
things needed and
wage/ budgets.
Continue Building a
project pack for Pre-
Production, including
things needed and
wage/ budgets.
Continue Building a
project pack for Pre-
Production, including
things needed and
wage/ budgets.
Review Schedule and
Production Log
w/b 18.03.13 Finish Pre-Production
Before the end of this
week.
Finish Pre-Production
Before the end of this
week.
Finish Pre-Production
Before the end of this
week.
Finish Pre-Production
Before the end of this
week.
Finished Pre
Production.
Start Production,
building the map,
starting with the roads
then building the
detail up.
Review Schedule and
Production Log
25.03.13 Easter Review Schedule and
Production Log
01.04.13 Easter Review Schedule and
Production Log
w/b 08.04.13 Start Production,
building the map,
starting with the roads
then building the
detail up.
Start Production,
building the map,
starting with the roads
then building the
Start Production here. Start Production here. Start Production here. Review Schedule and
Production Log
w/b 15.04.13 Building the Main
Outline of the map.
Roads, Turns, etc.
Building the Main
Outline of the map.
Roads, Turns, etc.
Starting to build
Buildings. Houses, Car
parks, Factories,
Shops.
Completing the first
part of the map.
Continuing adding
extra details to the
map.
Starting to build
Buildings. Houses, Car
parks, Factories,
Shops.
Review Schedule and
Production Log
w/b 22.04.13 Continuing to build
Buildings. Houses, Car
parks, Factories,
Shops.
Continuing to build
Buildings. Houses, Car
parks, Factories,
Shops.
Continuing to build
Buildings. Houses, Car
parks, Factories,
Shops.
Task 6: Completed by
now.
Task 6: Completed by
now.
Review Schedule and
Production Log
w/b 29.04.13 Task 6: Completed by
now.
Task 6: Completed by
now.
Task 6: Completed by
now.
Task 6: Completed by
now.
Task 6: Completed by
now.
Review Schedule and
Production Log
w/b 06.05.13 Task 6: Completed by
now.
Task 7: Completed by
now
Task 7: Completed by
now
Task 7: Completed by
now
Review Schedule and
Production Log
w/b 13.05.13 Review Schedule and
Production Log
w/b 20.05.13 Task 8: Evaluation will
take place no later
than the beginning of
this week.
Finish a draft map
build, and start a fly
though as back up.
Finish a draft map
build, and start a fly
though as back up.
The render.
Render Failed, Create
presentation
showcasing the map
with rendered screen
shots
DEADLINE
Complete the draft
map, and fly through,
create screen shots of
important parts of the
map and evaluate the
project completed.
Make sure all tasks are
completed, and
upload all to Moodle/
blog.

More Related Content

More from ConnahTilley

Computer risk assessment
Computer risk assessmentComputer risk assessment
Computer risk assessmentConnahTilley
 
Class risk assessment
Class risk assessmentClass risk assessment
Class risk assessmentConnahTilley
 
Task 2 map pack reviews
Task 2   map pack reviewsTask 2   map pack reviews
Task 2 map pack reviewsConnahTilley
 
Task 5 budget and wages upload
Task 5   budget and wages uploadTask 5   budget and wages upload
Task 5 budget and wages uploadConnahTilley
 
Creature, Birds and Reptiles
Creature, Birds and ReptilesCreature, Birds and Reptiles
Creature, Birds and ReptilesConnahTilley
 
Creature sketchbook pages
Creature sketchbook pagesCreature sketchbook pages
Creature sketchbook pagesConnahTilley
 
Figurative Artist Research
Figurative Artist ResearchFigurative Artist Research
Figurative Artist ResearchConnahTilley
 
Creature sketchbook pages
Creature sketchbook pagesCreature sketchbook pages
Creature sketchbook pagesConnahTilley
 
Figurative Artist Paintings
Figurative Artist PaintingsFigurative Artist Paintings
Figurative Artist PaintingsConnahTilley
 
Figurative artist paintings
Figurative artist paintingsFigurative artist paintings
Figurative artist paintingsConnahTilley
 
5 own figurative artists
5 own figurative artists5 own figurative artists
5 own figurative artistsConnahTilley
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project CharterConnahTilley
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project CharterConnahTilley
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project CharterConnahTilley
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project CharterConnahTilley
 

More from ConnahTilley (20)

App Concept
App ConceptApp Concept
App Concept
 
Computer risk assessment
Computer risk assessmentComputer risk assessment
Computer risk assessment
 
Class risk assessment
Class risk assessmentClass risk assessment
Class risk assessment
 
Task 2 map pack reviews
Task 2   map pack reviewsTask 2   map pack reviews
Task 2 map pack reviews
 
Task 5 budget and wages upload
Task 5   budget and wages uploadTask 5   budget and wages upload
Task 5 budget and wages upload
 
Presentation2
Presentation2Presentation2
Presentation2
 
Presentation1
Presentation1Presentation1
Presentation1
 
Creature, Birds and Reptiles
Creature, Birds and ReptilesCreature, Birds and Reptiles
Creature, Birds and Reptiles
 
Creature sketchbook pages
Creature sketchbook pagesCreature sketchbook pages
Creature sketchbook pages
 
Creature Research
Creature ResearchCreature Research
Creature Research
 
Figurative Artist Research
Figurative Artist ResearchFigurative Artist Research
Figurative Artist Research
 
Creature sketchbook pages
Creature sketchbook pagesCreature sketchbook pages
Creature sketchbook pages
 
Figurative Artist Paintings
Figurative Artist PaintingsFigurative Artist Paintings
Figurative Artist Paintings
 
Figurative artist paintings
Figurative artist paintingsFigurative artist paintings
Figurative artist paintings
 
5 own figurative artists
5 own figurative artists5 own figurative artists
5 own figurative artists
 
First Year Pages
First Year PagesFirst Year Pages
First Year Pages
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project Charter
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project Charter
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project Charter
 
Unit 67 Project Charter
Unit 67 Project CharterUnit 67 Project Charter
Unit 67 Project Charter
 

FMP_Schedule_24052013

  • 1. Salford City College Eccles Sixth Form Centre BTec Level 3 Extended Diploma in Creative Media Production Games Design Final Major Project Schedule Review date: 06.02.13 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b 04.02.13 Task 1 - FMP Launch Meeting w/b 11.02.13 Half-Term w/b 18.02.13 Book meeting slot with project manager. Finish Task 2 and 3 by today. Review Schedule and Production Log w/b 25.02.13 Task 1, 2 completed Task 4: Pitch must take place by this week. Begin to generate ideas. Collect images etc. Gather More images for task 3 and describe what my map with me like. Gather More images for task 3 and describe what my map with me like. Review Schedule and Production Log w/b 04.03.13 Review Schedule and Production Log Finish ideas generation and give first idea. Finish Ethical, Contractual and Budget Before here. Finish Ethical, Contractual and Budget Before here. Review Schedule and Production Log w/b 11.03.13 Start Pre- Production Start Pre- Production Start Pre- Production Continue Building a project pack for Pre- Production, including things needed and wage/ budgets. Continue Building a project pack for Pre- Production, including things needed and wage/ budgets. Continue Building a project pack for Pre- Production, including things needed and wage/ budgets. Review Schedule and Production Log w/b 18.03.13 Finish Pre-Production Before the end of this week. Finish Pre-Production Before the end of this week. Finish Pre-Production Before the end of this week. Finish Pre-Production Before the end of this week. Finished Pre Production. Start Production, building the map, starting with the roads then building the detail up. Review Schedule and Production Log 25.03.13 Easter Review Schedule and Production Log 01.04.13 Easter Review Schedule and Production Log
  • 2. w/b 08.04.13 Start Production, building the map, starting with the roads then building the detail up. Start Production, building the map, starting with the roads then building the Start Production here. Start Production here. Start Production here. Review Schedule and Production Log w/b 15.04.13 Building the Main Outline of the map. Roads, Turns, etc. Building the Main Outline of the map. Roads, Turns, etc. Starting to build Buildings. Houses, Car parks, Factories, Shops. Completing the first part of the map. Continuing adding extra details to the map. Starting to build Buildings. Houses, Car parks, Factories, Shops. Review Schedule and Production Log w/b 22.04.13 Continuing to build Buildings. Houses, Car parks, Factories, Shops. Continuing to build Buildings. Houses, Car parks, Factories, Shops. Continuing to build Buildings. Houses, Car parks, Factories, Shops. Task 6: Completed by now. Task 6: Completed by now. Review Schedule and Production Log w/b 29.04.13 Task 6: Completed by now. Task 6: Completed by now. Task 6: Completed by now. Task 6: Completed by now. Task 6: Completed by now. Review Schedule and Production Log w/b 06.05.13 Task 6: Completed by now. Task 7: Completed by now Task 7: Completed by now Task 7: Completed by now Review Schedule and Production Log w/b 13.05.13 Review Schedule and Production Log w/b 20.05.13 Task 8: Evaluation will take place no later than the beginning of this week. Finish a draft map build, and start a fly though as back up. Finish a draft map build, and start a fly though as back up. The render. Render Failed, Create presentation showcasing the map with rendered screen shots DEADLINE Complete the draft map, and fly through, create screen shots of important parts of the map and evaluate the project completed. Make sure all tasks are completed, and upload all to Moodle/ blog.