SlideShare a Scribd company logo
1 of 13
Human Failures Involved
in Accidents
Flixborough Disaster, 1974
Three Mile Island, 1979
Space Shuttle Challenger, 1986
Chernobyl, 1986
King’s Cross Underground Fire, 1987
Flixborough Disaster, 1974
Staffing • The works engineer had left early in the year and had
not yet been replaced.
• At the time the bypass line was being planned and
installed, there was no engineer on site with the
qualifications to perform a proper mechanical design,
or to provide critical technical review on related
issues. There were chemical and electrical engineers
on staff, but no other mechanical engineers.
Flixborough Disaster, 1974
Lack of
Hazard
Identification
• In the opinion of the investigators, the urgency to resume
production distracted staff from the sort of critical consideration
of their plans that could have identified the hazards involved
(i.e., they did not intentionally establish an unsafe condition
but, rather, failed to fully assess the significance of what they
were doing).
Work Load • The fact that the works manager position was vacant also shifted
workload to remaining staff, contributing to the distractions
discussed above. The report implies that company management
was not aware of the effect of the short staffing on the
performance of the facility staff involved in the modification.
Flixborough Disaster, 1974
Lack of
Knowledge
• While calculations were made to confirm that the 20-inch pipe could
withstand the normal working pressure, no consideration was given to the
bending moments or hydraulic thrusts that would be imposed on the assembly
due to its dogleg configuration . There was no reference made to vendor
manuals for the expansion bellows, nor to relevant British Standards.
Lack of
Quality
Assurance
• There were no quality assurance checks made on the fabrication or
installation of the assembly other than a leak check at approximately 130 psi
(for comparison, the relief valves [RVs] on the reactor system were set to
open at approximately 155 psi). Applicable British Standards required that the
assembly be tested at a pressure of 1.3x 105 the system design pressure,
which would have been above the RV set pressure.
Three Mile Island, 1979
Lack of
Knowledge
• The event that occurred in 1979, caused by two workers who
made a mistake cleaning valves with air pressure hoses,
resulted in much change for nuclear safety in the world.
Lack of
Training
• Workers in the control room faced a situation that they had not
prepared for in any of their training, and were forced to make
decisions on the spot. Additionally, there were flaws in the
control panel that caused the workers to be unaware that a
valve had been left open.
Three Mile Island, 1979
Design
Deficiencies
• The loss of normal feed water which is an anticipated
operating occurrence leads to the opening of the pressurizer
relief valve which is an other anticipated operating
occurrence;
• A break in the steam phase of the pressurizer is not
considered. There is no procedure to identify and manage
this event and the operating staff is not trained for it;
• The actuation of the emergency core cooling system does not
actuate a complete containment building isolation.
Three Mile Island, 1979
Multiple latent
deficiencies
(organization, m
aintenance,
quality, ...
• The pressurizer relief valve had been known to be leaking for a
while but the repair work was postponed so increasing the
probability of a jammed open valve and depriving the
operators of a way to identify the valve situation: the
temperature of the pressurizer relief line;
• The closed connecting valves of the steam generators auxiliary
feed water system added a complete loss of feed water system
to the complete loss of emergency core cooling system and
focused the attention of the operating team;
• An effluent tank was leaking;
• The iodine filters in the auxiliary building had poor efficiency.
Space Shuttle Challenger,1986
Inadequate
Design
• The O-Ring was a rubber seal component in the solid rocket booster (SRB),
its purpose was to stop leaks. Due to extremely cold temperature on the
day of launch, the O-Ring lost its elastic property and became brittle
(inflexible), allowing a leak and resulting in explosion.
lack of
understanding
• During the conference call with the management team and the
engineering team, the management team did not seem to understand
that a failure in the O rings system would result into fatalities and the
engineers also did stand against the launch and refusing that the launch
would take place as the life of 7 astronauts have a very big chance of
being lost they issued a recommendation that the launch shouldn’t
happen, instead of recommending they should of used another world in
order to express the severity of the problem
Space Shuttle Challenger,1986
Faulty
Judgement
• managers decided to launch despite record low temperatures
and ice on launch pad
Management
Problems
• NASA managers had known since 1977 that the design of the
SRBs contained a potentially catastrophic flaw in the O-rings,
but they had failed to address this problem properly.
• NASA managers also disregarded warnings from engineers
about the dangers of launching posed by the low temperatures
of that morning, and failed to adequately report these
technical concerns to their superiors.
Chernobyl, 1986
Wrong
Procedure
• Correct procedure was down the reactor to 700-MW but it
was down to 200 MW. At this Power reactor became unstable.
Lack of
Knowledge
• Operator error was probably due to their lack of knowledge
of nuclear reactor physics and engineering, as well as the
lack of experience and training. Personnel had an
insufficiently detailed understanding of technical procedures
involved with the nuclear reactor, and knowingly ignored
regulations to speed test completion
Chernobyl, 1986
Inadequate
Design
• The reactor had a dangerously large positive void coefficient.
The void coefficient is a measurement of how a reactor
responds to increased steam formation in the water coolant.
Most other reactor designs have a negative coefficient, i.e.
the nuclear reaction rate slows when steam bubbles form in
the coolant, since as the vapor phase in the reactor
increases, fewer neutrons are slowed down. Faster neutrons
are less likely to split uranium atoms, so the reactor
produces less power (a negative feed-back)
King’s Cross Underground Fire, 1987
Lack of
Training
• The staff was not properly trained for emergency fire.
• Many times fire had been detected most of time due to
smokers, dropping cigarette butts and matches.
Unclean
Escalators
• Lack of cleaning of wooden escalators causes flammable
mixture of lubricating oil and dirt ( tickets, hair, Pouches)
• This flammable mixture got ignited due to smokers cigarette
butts.
King’s Cross Underground Fire, 1987
Design of
Escalators
• Wooden escalators ignited quickly.
• Inclination of Escalators help in Trench effect.
• No fire detection system was present.

More Related Content

What's hot (11)

Deepwater Horizon Case Slides
Deepwater Horizon Case SlidesDeepwater Horizon Case Slides
Deepwater Horizon Case Slides
 
Boiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singaporeBoiler explosion at exxon mobil singapore
Boiler explosion at exxon mobil singapore
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Plan B
Plan BPlan B
Plan B
 
Three Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspectThree Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspect
 
automation
automationautomation
automation
 
Boiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridgedBoiler safety 11 28 2011 abridged
Boiler safety 11 28 2011 abridged
 
Velocys1
Velocys1Velocys1
Velocys1
 
Accident de fukushima
Accident de fukushimaAccident de fukushima
Accident de fukushima
 
Cavitation effect
Cavitation effectCavitation effect
Cavitation effect
 
Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014 Blueproof Update to FEU May 2014
Blueproof Update to FEU May 2014
 

Similar to Human failures involved in accidents

Read the incident scenario, and write a response that is at least th.docx
Read the incident scenario, and write a response that is at least th.docxRead the incident scenario, and write a response that is at least th.docx
Read the incident scenario, and write a response that is at least th.docx
niraj57
 
Write about the following ethics case studies1. Hyatt Regency Walk.pdf
Write about the following ethics case studies1. Hyatt Regency Walk.pdfWrite about the following ethics case studies1. Hyatt Regency Walk.pdf
Write about the following ethics case studies1. Hyatt Regency Walk.pdf
arjuntelecom26
 
An analysis of the Fukushima Nuclear Power Plants
An analysis of the Fukushima Nuclear Power PlantsAn analysis of the Fukushima Nuclear Power Plants
An analysis of the Fukushima Nuclear Power Plants
Raja Mitra
 
Catherine OwensRead the incident scenario, and write a response th.docx
Catherine OwensRead the incident scenario, and write a response th.docxCatherine OwensRead the incident scenario, and write a response th.docx
Catherine OwensRead the incident scenario, and write a response th.docx
michelljubborjudd
 

Similar to Human failures involved in accidents (20)

novNikezicPresentationNikezicPresentation
novNikezicPresentationNikezicPresentationnovNikezicPresentationNikezicPresentation
novNikezicPresentationNikezicPresentation
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Chernobyl Timeline
Chernobyl TimelineChernobyl Timeline
Chernobyl Timeline
 
Lessons Learnt from Root Cause Analysis of Gulf.pptx
Lessons Learnt from Root Cause Analysis of Gulf.pptxLessons Learnt from Root Cause Analysis of Gulf.pptx
Lessons Learnt from Root Cause Analysis of Gulf.pptx
 
moc0828011.pdf
moc0828011.pdfmoc0828011.pdf
moc0828011.pdf
 
Tank Overflow Protection and Surge Mitigation
Tank Overflow Protection and Surge MitigationTank Overflow Protection and Surge Mitigation
Tank Overflow Protection and Surge Mitigation
 
3 Mile island.pdf
3 Mile island.pdf3 Mile island.pdf
3 Mile island.pdf
 
Chernobyl nuclear accident
Chernobyl nuclear accidentChernobyl nuclear accident
Chernobyl nuclear accident
 
Mac Lecture
Mac LectureMac Lecture
Mac Lecture
 
Challenger space-shuttle-incident
Challenger space-shuttle-incidentChallenger space-shuttle-incident
Challenger space-shuttle-incident
 
Engineers responsibility for safety
Engineers responsibility for safetyEngineers responsibility for safety
Engineers responsibility for safety
 
Read the incident scenario, and write a response that is at least th.docx
Read the incident scenario, and write a response that is at least th.docxRead the incident scenario, and write a response that is at least th.docx
Read the incident scenario, and write a response that is at least th.docx
 
Write about the following ethics case studies1. Hyatt Regency Walk.pdf
Write about the following ethics case studies1. Hyatt Regency Walk.pdfWrite about the following ethics case studies1. Hyatt Regency Walk.pdf
Write about the following ethics case studies1. Hyatt Regency Walk.pdf
 
Nebraska
NebraskaNebraska
Nebraska
 
Flixborough case-history 0
Flixborough case-history 0Flixborough case-history 0
Flixborough case-history 0
 
Remediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrockRemediation of DNAPL in fractured bedrock
Remediation of DNAPL in fractured bedrock
 
Nuclear reconsidered
Nuclear reconsideredNuclear reconsidered
Nuclear reconsidered
 
An analysis of the Fukushima Nuclear Power Plants
An analysis of the Fukushima Nuclear Power PlantsAn analysis of the Fukushima Nuclear Power Plants
An analysis of the Fukushima Nuclear Power Plants
 
Catherine OwensRead the incident scenario, and write a response th.docx
Catherine OwensRead the incident scenario, and write a response th.docxCatherine OwensRead the incident scenario, and write a response th.docx
Catherine OwensRead the incident scenario, and write a response th.docx
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disaster
 

More from Basitali Nevarekar

More from Basitali Nevarekar (19)

Topic5 organizational factors
Topic5 organizational factorsTopic5 organizational factors
Topic5 organizational factors
 
Topic 04 risk mangement
Topic 04 risk mangementTopic 04 risk mangement
Topic 04 risk mangement
 
Topic 3 swiss cheese model
Topic 3 swiss cheese modelTopic 3 swiss cheese model
Topic 3 swiss cheese model
 
Topic 02 human and organizational factors in process industry
Topic 02 human and organizational factors in process industryTopic 02 human and organizational factors in process industry
Topic 02 human and organizational factors in process industry
 
Designing the task
Designing the taskDesigning the task
Designing the task
 
Human factors in risk management
Human factors in risk managementHuman factors in risk management
Human factors in risk management
 
human factor loop
human factor loophuman factor loop
human factor loop
 
Control methods
Control methodsControl methods
Control methods
 
Manufacturing of fly-ash brick
Manufacturing of fly-ash brickManufacturing of fly-ash brick
Manufacturing of fly-ash brick
 
Re-Refining of used lubricating oil
Re-Refining of used lubricating oilRe-Refining of used lubricating oil
Re-Refining of used lubricating oil
 
bio filters for pollution control
bio filters for pollution controlbio filters for pollution control
bio filters for pollution control
 
cross flow filtration
cross flow filtrationcross flow filtration
cross flow filtration
 
Production of 5-HMF
Production of 5-HMFProduction of 5-HMF
Production of 5-HMF
 
membrane reactor for gas separation
membrane reactor for gas separationmembrane reactor for gas separation
membrane reactor for gas separation
 
Membrane Separation techniques
Membrane Separation techniquesMembrane Separation techniques
Membrane Separation techniques
 
Magnetic refrigeration
Magnetic refrigerationMagnetic refrigeration
Magnetic refrigeration
 
Arsenic removal from drinking water
Arsenic removal from drinking waterArsenic removal from drinking water
Arsenic removal from drinking water
 
Self healing polymer technology
Self healing polymer technologySelf healing polymer technology
Self healing polymer technology
 
Photocatalytic membrane Reactor
Photocatalytic membrane ReactorPhotocatalytic membrane Reactor
Photocatalytic membrane Reactor
 

Recently uploaded

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 

Recently uploaded (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Human failures involved in accidents

  • 1. Human Failures Involved in Accidents Flixborough Disaster, 1974 Three Mile Island, 1979 Space Shuttle Challenger, 1986 Chernobyl, 1986 King’s Cross Underground Fire, 1987
  • 2. Flixborough Disaster, 1974 Staffing • The works engineer had left early in the year and had not yet been replaced. • At the time the bypass line was being planned and installed, there was no engineer on site with the qualifications to perform a proper mechanical design, or to provide critical technical review on related issues. There were chemical and electrical engineers on staff, but no other mechanical engineers.
  • 3. Flixborough Disaster, 1974 Lack of Hazard Identification • In the opinion of the investigators, the urgency to resume production distracted staff from the sort of critical consideration of their plans that could have identified the hazards involved (i.e., they did not intentionally establish an unsafe condition but, rather, failed to fully assess the significance of what they were doing). Work Load • The fact that the works manager position was vacant also shifted workload to remaining staff, contributing to the distractions discussed above. The report implies that company management was not aware of the effect of the short staffing on the performance of the facility staff involved in the modification.
  • 4. Flixborough Disaster, 1974 Lack of Knowledge • While calculations were made to confirm that the 20-inch pipe could withstand the normal working pressure, no consideration was given to the bending moments or hydraulic thrusts that would be imposed on the assembly due to its dogleg configuration . There was no reference made to vendor manuals for the expansion bellows, nor to relevant British Standards. Lack of Quality Assurance • There were no quality assurance checks made on the fabrication or installation of the assembly other than a leak check at approximately 130 psi (for comparison, the relief valves [RVs] on the reactor system were set to open at approximately 155 psi). Applicable British Standards required that the assembly be tested at a pressure of 1.3x 105 the system design pressure, which would have been above the RV set pressure.
  • 5. Three Mile Island, 1979 Lack of Knowledge • The event that occurred in 1979, caused by two workers who made a mistake cleaning valves with air pressure hoses, resulted in much change for nuclear safety in the world. Lack of Training • Workers in the control room faced a situation that they had not prepared for in any of their training, and were forced to make decisions on the spot. Additionally, there were flaws in the control panel that caused the workers to be unaware that a valve had been left open.
  • 6. Three Mile Island, 1979 Design Deficiencies • The loss of normal feed water which is an anticipated operating occurrence leads to the opening of the pressurizer relief valve which is an other anticipated operating occurrence; • A break in the steam phase of the pressurizer is not considered. There is no procedure to identify and manage this event and the operating staff is not trained for it; • The actuation of the emergency core cooling system does not actuate a complete containment building isolation.
  • 7. Three Mile Island, 1979 Multiple latent deficiencies (organization, m aintenance, quality, ... • The pressurizer relief valve had been known to be leaking for a while but the repair work was postponed so increasing the probability of a jammed open valve and depriving the operators of a way to identify the valve situation: the temperature of the pressurizer relief line; • The closed connecting valves of the steam generators auxiliary feed water system added a complete loss of feed water system to the complete loss of emergency core cooling system and focused the attention of the operating team; • An effluent tank was leaking; • The iodine filters in the auxiliary building had poor efficiency.
  • 8. Space Shuttle Challenger,1986 Inadequate Design • The O-Ring was a rubber seal component in the solid rocket booster (SRB), its purpose was to stop leaks. Due to extremely cold temperature on the day of launch, the O-Ring lost its elastic property and became brittle (inflexible), allowing a leak and resulting in explosion. lack of understanding • During the conference call with the management team and the engineering team, the management team did not seem to understand that a failure in the O rings system would result into fatalities and the engineers also did stand against the launch and refusing that the launch would take place as the life of 7 astronauts have a very big chance of being lost they issued a recommendation that the launch shouldn’t happen, instead of recommending they should of used another world in order to express the severity of the problem
  • 9. Space Shuttle Challenger,1986 Faulty Judgement • managers decided to launch despite record low temperatures and ice on launch pad Management Problems • NASA managers had known since 1977 that the design of the SRBs contained a potentially catastrophic flaw in the O-rings, but they had failed to address this problem properly. • NASA managers also disregarded warnings from engineers about the dangers of launching posed by the low temperatures of that morning, and failed to adequately report these technical concerns to their superiors.
  • 10. Chernobyl, 1986 Wrong Procedure • Correct procedure was down the reactor to 700-MW but it was down to 200 MW. At this Power reactor became unstable. Lack of Knowledge • Operator error was probably due to their lack of knowledge of nuclear reactor physics and engineering, as well as the lack of experience and training. Personnel had an insufficiently detailed understanding of technical procedures involved with the nuclear reactor, and knowingly ignored regulations to speed test completion
  • 11. Chernobyl, 1986 Inadequate Design • The reactor had a dangerously large positive void coefficient. The void coefficient is a measurement of how a reactor responds to increased steam formation in the water coolant. Most other reactor designs have a negative coefficient, i.e. the nuclear reaction rate slows when steam bubbles form in the coolant, since as the vapor phase in the reactor increases, fewer neutrons are slowed down. Faster neutrons are less likely to split uranium atoms, so the reactor produces less power (a negative feed-back)
  • 12. King’s Cross Underground Fire, 1987 Lack of Training • The staff was not properly trained for emergency fire. • Many times fire had been detected most of time due to smokers, dropping cigarette butts and matches. Unclean Escalators • Lack of cleaning of wooden escalators causes flammable mixture of lubricating oil and dirt ( tickets, hair, Pouches) • This flammable mixture got ignited due to smokers cigarette butts.
  • 13. King’s Cross Underground Fire, 1987 Design of Escalators • Wooden escalators ignited quickly. • Inclination of Escalators help in Trench effect. • No fire detection system was present.