13. Next Question for you all to solve
Annual consumption: 1600 units
Cost of material: Rs 40 per unit
Ordering cost: Rs 50
Carrying cost : 10%
14.
15.
16.
17.
18. Practice sum for Reorder
level.
Given
Minimum usage 100 units per week
Normal usage 200 units per week
Maximum usage 300 units per week
Re-order period 4 to 6 weeks
Calculate Reorder level:
Ans: RoL= Maximum usage*maximum time
= 300*6 = 1800 units
19. Next question for you to solve
The following information is available in respect of component DP 5:
Budgeted consumption- maximum 1,500 units per month
Budgeted consumption- minimum 800 units per month
Estimated delivery period Maximum 4 months and minimum 2 months
You are required to calculate Re-order level
20. ReOrdering level= Maximum consumption *
Lead Time [maximum]
Ordering level= 1,500 * 4
Ordering level= 6,000 Units per week
21.
22. Problem sum on Minimum level
From the following calculate (i) Re-ordering Level and (ii) Minimum Level
Minimum usage 100 units per week Normal usage 200 units per week
Maximum usage 300 units per week Re-order period 4 to 6 weeks
Solution:
(i) Re-ordering Level
Re-ordering level= Maximum consumption * Lead Time [maximum]
Re-ordering level= 300 * 6
Re-ordering level= 1,800 Units per week
Minimum Level
Minimum level= Reorder level – (Average consumption x lead time [Average])
Minimum level= 1,800 – (200 x 5)
Minimum level= 1,000 Units per week
23. Next sum to solve
Maximum consumption 400 units per week Average consumption 300 units
per week
Minimum consumption 250 units per week
24. Solution:
(i) Ordering Level
Ordering level= Maximum consumption * Lead Time [maximum]
Ordering level= 400 * 6
Ordering level= 2,400 Units per week
(ii) Minimum Level
Minimum level= Reorder level – (Average consumption x lead time [Average])
Minimum level= 2,400 – (300 x 5)
Minimum level= 900 Units per week
25.
26. Maximum demand: 200 per week
Average demand: 160 per week
Minimum demand: 145 per week
Maximum lead time: 2 weeks
Average lead time: 1.5 weeks
Minimum lead time: 1.35 weeks
Re-order quantity per order: 500 dinner sets
Safety stock: 184 dinner sets
Required: Compute maximum level of stock
Solution
*Reorder level = (Maximum usage × Maximum lead time) + Safety stock
= (200 units × 2 days) + 184 units
= 400 units + 184 units
= 584 units
Maximum Level of Stock = Reorder level + Reorder quantity – (Minimum usage × Minimum lead time)
= Reorder quantity – (Minimum usage × Minimum lead time)
= *584 units + 500 units – (145 units × 1.35 days)
= 584 units + 500 units – 196 units
= 1,084 units – 196 units
= 888 units
27. Next Question for you to solve.
Minimum consumption per week = 3,000 units
Maximum consumption per week = 4,500 units
Economic order quantity (EOQ) = 14,000 units
Normally, 3,500 units of threads are consumed on a weekly basis and it takes
around 20 - 25 days of ordering period to get the new supply of threads from the
supplier.
28. Solution:
Re-order level = Maximum weekly consumption x Maximum re-order period = 4,500 x
25 = 112,500
Maximum level = Re-ordering level + EOQ – (Minimum consumption x Minimum re-
order period) = 112,500 + 14,000 – (3,000 x 20) = 126,500 – 60,000 = 66,500 Units
From the calculation done above, it is clear that the maximum level of stock that can
be kept in the store department is 66,500 units.
29.
30. Daily Consumption = 100 to 200 units
Maximum re-order period for emergency purchase = 5 days
Danger Level = ?
Solution,
Normal consumption: 100+200/2 = 300/2 = 150 units
Danger Level = Normal consumption x Maximum re-order period for emergency
purchase
= 150 x 5
750 units.
31. In a factory component A is used as follows:
Normal usage – 50 kg per week
Minimum usage – 25 kg per week
Maximum usage – 75 kg per week
Re-order quantity 300 kg.
Re-order period 4 to 6 weeks.
Calculate for component A:
(i) Re-order level,
(ii) Maximum level.
(iii) Minimum level; and
(iv) Average stock level.
32. (i) Re-order level = Maximum usage × Maximum period
= 75 × 6 = 450 kg
(ii) Maximum level = Re-order level + Re-order quantity – (Minimum usage ×
Minimum time)
= 450 + 300 – (25 × 4) = 650 kg.
(iii) Minimum level = Reorder level – (Normal usage × Average time)
= 450 – (50 × 5) = 200 kg.
(iv) Average stock level = Maximum level + Minimum level/2
= (650 + 200/2)kg = 425 kg.