SlideShare a Scribd company logo
1 of 15
Submitted By:
Mr. ASIF ALI (K13EL-49)
Mr. ALI MUHAMMAD (K13EL-19)
Mr. MOUZAM ALI (K13EL-37)
MEHRAN UNIVERSITY OF ENGINEERINGTECHNOLOGY
SZAB CAMPUS KHAIRPURMIR’S
(15 DAYS INTERNSHIP REPORT)
ACKNOWLEDGMENT
‘In the name of Allah, the most Gracious, the most merciful’
“All praises for Almighty Allah, who guides us in darkness and helps us in difficulties
and due respect for Holy Prophet (Peace be upon him) who enables us to recognize our
creator.”
First, we would like to thanks Almighty Allah who gave us strength to complete
challenging tasks & His blessings that He provided me confidence, guidance & strength
to complete this report. The journey has not finished yet and we pray to Him to show us
the straight path & help us more in future as we nothing without His blessings.
Writing an internship report appeared to be a great experience for us. It added a lot to us
knowledge. Completion of internship report is not an easy task. It requires continuous
hard work. Completion of this report would have not been possible without the support of
all staff of HR department to whom I interacted and concerned field department. We would like
to thanks especially Mr. MUZAMIL SALEEM (GM), Mr. ANWER SAHB (DPM) Mr.
FARHAN AHMED (senior plant manager) , Mr. AB,RAZAQUE (senior power house
manager) and other engineers and field workers to their practical guidance and personal interest
by which we become able to complete this task.
Very special thank to all our dear teachers that build our personality and enable us to do
some creative work be a successful person in practical life. We are responsible for errors and
mistakes presented in the report and a positive and constructive criticism will always be greeted
warmth.
SECTION NO:01 WARPING
SECTION:02 SIZING
SIZING
WARPING
SECTION WARPING
&SIZING(H-SHAPPED
CRIAL) & 800 SPEED
DIRECT WARPING
(H-SHAPPEDCRIAL)
BENGER WARPING(1200
SPEED)
CHINNA WARPING
(700 SPEED)
KUCUKER WARPING(1200 SPEED)
BEST AUTOMATIC SYSTEM
SIZING
KUCKER SIZING BEN SIZING
SECTION:03 WEAVING
Weaving is a method of textile production in which two distinct sets of yarns or threads are
interlaced at right angles to form a fabric or cloth. Similar methods are knitting, felting,
and braiding or plaiting. The longitudinal threads are called the warp and the lateral threads are
the weft or filling. In Afroze there are 72 looms are used each having same working.
LOOM:
A loom is a device used to weave cloth and tapestry. The basic purpose of any loom is to hold
the warp threads under tension to facilitate the interweaving of the weft threads. The precise
shape of the loom and its mechanics may vary, but the basic function is the same Toyota 710
loom used in an industry.
SENSORSUSED IN LOOM:
Different sensors are used in loom as,
(1) Feeler sensor: which sense when thread breaks.
(2) Metal sensor: which sense beam if it will be in front of it then it sense in working
condition otherwise not.
(3) Proximity sensor: it counts number of turns.
(4) Balloon sensor: it sense how much thread is used.
MOTORS USED IN LOOM:
(1) induction motor 1pahse and 3phase
(2) Servo motor
(3) Stepper motor
(1) Induction motor:
Introduction;
One of the most common electrical motor used in most applications which is known as
induction motor. This motor is also called as asynchronous motor because it runs at a
speed less than its synchronous speed.
Induction motors are easier to maintain and cheaper.
Working principle:
It has two main parts stator and rotor, stator is stationary part where rotor is rotating part
also stator having thin lamination, when a AC supply is provided to stator of I.M a
rotating magnetic field produces which cuts rotor, according to faradays law an emf
induces in rotor loop which produces its own field so, both stator and rotor field interacts
with each other and force produces which moves it. Where rotor speed is less then stator
speed.
Applications in textile:
Used in different places such as, in loom to drive it, drier etc.
(2) Servo motor:
This is nothing but a simple electrical motor , controlled with the help of servomechanism. If the
motor as controlled device, associated with servomechanism is dc motor, then it is commonly
known DC Servo Motor. If the controlled motor is operated by AC, it is called AC Servo Motor.
Servomechanism:
A servo system mainly consists of three basic components
(1) A controlled device
(2) An output sensor
(3) A feedback system
This is an automatic closed loop control system. Here instead of controlling a device by applying
the variable input signal, the device is controlled by a feedback signal generated by comparing
output signal and reference input signal. When reference input signal or command signal is
applied to the system, it is compared with output reference signal of the system produced by
output sensor, and a third signal produced by a feedback system. This third signal acts as an
input signal of controlled device.
Advantages:
 Works on some angle
 Good accuracy
 Works both reverse and forward
 Servo amplifier also used
 High frequency on stator side
2. Stepper motor:
A stepper motor is a type of DC motor that rotates in steps. When electrical signal is
applied to it, the motor rotates in steps and the speed of rotation depends on the rate at
which the electrical signals are applied and the direction of rotation is dependent on the
pattern of pulses that is followed. A stepper motor is made up of a rotor, which is
normally a permanent magnet and it is, as the name suggests the rotating component of
the motor. A stator is another part which is in the form of winding.
(a)Humidity plant:
ROOM AIR (Return fan) AIR PASS (Shivering room)
WEAVING (through supply fan having 26 to 27 degree cooling according to need)
4. PROCESSING:
(a) Bleaching:
There are 4 washing chambers in each portion has powder ,soap and detergents mixture which is
used for cleaning purpose ,after that it will be washed and then it move to drier portion where
inside it there is hot steam used. Where also flow sensors are used to sense flow of water inside
washing portion.
(b)Drier:
It is used to dry product after bleaching and washing ,cylinder drier (beneger company) ,it has
four zones ,having steam pressure of 4bar,and temperature of 100 degree C, in which total 25
induction motors used from which 23 are 0.75 KW and 2 motors are 5.5kw ,where dancer
(potentiometer) is used to balance speed of motors. Also invertors are used for 0.75 KW motors
as easily rotate them forward and reverse.
5. POWER PLANT:
There are four alternators are used each having rating of one MW.
(a):
 Step no: 01 In fuel there is mixture of 20% of natural gas and 80% of air.
20% natural gas
80% Air
Pressure of gas is used in current is 1513 mbar. Mbar meter is also used to measure
actual pressure.
 Step no:02 Union valve:
Is used to control the flow of fuel, also flinch used to connect valve on both sides of pipes.
 Step no: 03 Filter: are used to make fuel pure from dust and other particles.
Mbar
 Step no: 04 Gas pressure gauge
Psi
 Step no: 05 Fuel pressure filter:
It is used to finally measure pressure of fuel. Then move through flexible pipes.
(1) Power
mode:
individually
each generator
(2) Sink
mode:
all generators
equal
distribution of
load
 Step no: 06 Turbo charges:(mixture)
It used to make mix natural gas and air properly then make equal distribution of fuel
(gas) in pipes to Alternator; also it performs the function of exhaust.
 Step no: 07 Starting of Engine :
Initially what happens generator is moved through starting motor ( through a 12v battery
source) when its speed reached to 150 t0 200 rpm’s then motor is removed and fire or
ignition is provided to burn fuel (10000v are needed to start fire),and generator starts.
MODES OF OPERATION
(b) :Cable rating :
Qno: If power is 1KW then what will be the rating of cable?
Ans: by using the real power formula we can find the carrying capacity of cable
P=VICOSⱺ
I=P/VCOSⱺ
=1000/400*0.85
I=1.8 A
and cable rating will be 1mm =1.8 ladder tray
(c) Power Tray
Pufrated tray
These trays are used to carry cables where ladder tray is used in open environment as rain
water does not stop upon it, where ladder tray is used in closed environment.
(d) Switch gear:
One of the basic functions of switchgear is protection, which is interruption of short-
circuit and overload fault currents while maintaining service to unaffected
circuits. Switchgear also provides isolation of circuits from power supplies. it is designed
on basis of ampere rating. then in last it is distributed in different sections of textile where
it is required.
(e) Cooling of generator:
cooling is provided to generator through water. where water pumps are used to circulate
water through it ,where it takes heat from different portions of generator and then that hot
water goes to heat exchanger and becomes cool so, such process continue.
Figure: block diagram power plant.
FIRE ALARAM SYSTEM
A fire alarm system is number of devices working together to detect and warn people
through visual and audio appliances when smoke, fire, carbon monoxide or other
emergencies are present. These alarms may be activated from smoke detectors, and
heat detectors.
Types of fire alarm system
(1) Conventional fire alarm systems:
Conventional fire alarm systems and its components are all wired to the same
cable that connects them to a fire alarm control panel that displays a signal when
one of the components is activated. These types of systems are inexpensive and
work well in small facilities. The main problem with conventional fire alarm
systems is that when a fire alarm component produces a signal and it appears on
the control panel there is no way to know which component it is in the building.
(2) Addressable fire alarm system:
Addressable fire alarm systems are the most modern type of system and its
components have individual unique identifiers. When one of the system’s
components is initiated it displays a signal on the fire alarm control panel that
indicates the component’s address. Large facilities are typically equipped with
these systems because they can quickly pinpoint the address of the fire alarm
component that sent the signal. This saves a lot of time because it eliminates the
need to search for the component that produced the signal.
In each zone there are 18 devices used total 42 zones , each operates on 24.5V
,where 16-20 ft distance between each alarm and having height of 15ft.
Conclusion:
 We had a great learning and training experience at Afroze Textile Industries for
our academic program of Electrical ENGINEERING at MEHRAN
UNIVERSITY of Engineering And Technology SZAB CAMPUS
KHAIRPURMIR’S
 We physically visited industrial utilities like steam boiler, RO plant, oil boiler,
power house, air compressor, chiller plant which work on those basic
thermodynamics principles and laws which we have studied in theories,
 Working on them physically on the industrial scale was really so demanding for
us.
 We had a real world working and have work from, experiences which we had
never been exposed to, in our isolated academic life at university.
 We learned the coordination in planning of production order of different buyers to
make the buyers happy and how to take the necessary steps in modifying the
machines to cover any halts in the machines during a run.
 We learned that how electrical engineers do take actions in maintaining a
harmonious flow in the production line by the properly govern the maintenance of
machines and by designing new efficient plants and by modifying the existing
plants to reduce the time consumption, cost, break downs of the production line.
 They also increase by the same way the quality, and more diversified product
which can change the market.
 We learned how to work in a team and how to work under the higher authorities.
SUGGESTIONS:
We saw that Afroze Textile Industry has to depend upon the water tankers a little bit
which are expensive, not a true solution, dealing with them is nasty.
1. We suggest that they should consider reconfiguring the waste water plant RO,
which has the water storage capacity of 500,000 gallons, this will eventually be
good for environment, production, and profitable I guess.
ENERGY CRISIS:
In spite of having fully owned 3MWatt power plant a froze is still facing power shutdown
on Sundays due to natural Gas strike by the govt. this cause an effective loss to the
production and profit of the industry.
1. We recommend the industry to install solar power systemon the roofs and make
use of it in conjunction with N.gas power plant.
2. We also recommend that industry should encourage the govt. for the use of Thar
coal in producing energy for the betterment of this sector.
3. We also recommend that industry should overcome power losses in terms of
power efficient machines and good lubrication and insulations of machines.

More Related Content

What's hot

Stenter machine & heat set
Stenter machine & heat setStenter machine & heat set
Stenter machine & heat setMizan Rahman
 
Carding,card clothing,grinding, autoleveller.pdf
Carding,card clothing,grinding, autoleveller.pdfCarding,card clothing,grinding, autoleveller.pdf
Carding,card clothing,grinding, autoleveller.pdfGoldentuch
 
Projectile weaving
Projectile weavingProjectile weaving
Projectile weavingFuad Ahmed
 
Garment printing
Garment printingGarment printing
Garment printingSiva M
 
Find out the production of lap former machine in kg
Find out the production of lap former machine in kgFind out the production of lap former machine in kg
Find out the production of lap former machine in kgAmit Biswas
 
Auro textile Trainning report
Auro textile Trainning reportAuro textile Trainning report
Auro textile Trainning reportJAGMOHAN Raj
 
Industrial Textile Processing
Industrial Textile ProcessingIndustrial Textile Processing
Industrial Textile ProcessingAzmir Latif Beg
 
Finishing 1: Padding Mangles Stentering machine
Finishing 1: Padding Mangles    Stentering machineFinishing 1: Padding Mangles    Stentering machine
Finishing 1: Padding Mangles Stentering machineVijay Prakash
 
Study on cost effectiveness of silk dyeing with acid dyes and basic dyes
Study on cost effectiveness of silk dyeing with acid dyes and basic dyesStudy on cost effectiveness of silk dyeing with acid dyes and basic dyes
Study on cost effectiveness of silk dyeing with acid dyes and basic dyesMd. Ariful Islam
 
Industrial Attachment on Chandra Spinning Mills Ltd.
Industrial Attachment on Chandra Spinning Mills Ltd.Industrial Attachment on Chandra Spinning Mills Ltd.
Industrial Attachment on Chandra Spinning Mills Ltd.Amanuzzaman Aman
 

What's hot (20)

Stenter machine & heat set
Stenter machine & heat setStenter machine & heat set
Stenter machine & heat set
 
Carding,card clothing,grinding, autoleveller.pdf
Carding,card clothing,grinding, autoleveller.pdfCarding,card clothing,grinding, autoleveller.pdf
Carding,card clothing,grinding, autoleveller.pdf
 
Projectile weaving
Projectile weavingProjectile weaving
Projectile weaving
 
Garment printing
Garment printingGarment printing
Garment printing
 
Process control and yarn quality in spinning woodhead publishing-karthik
Process control and yarn quality in spinning woodhead publishing-karthikProcess control and yarn quality in spinning woodhead publishing-karthik
Process control and yarn quality in spinning woodhead publishing-karthik
 
Yarn spining...
Yarn spining...Yarn spining...
Yarn spining...
 
Find out the production of lap former machine in kg
Find out the production of lap former machine in kgFind out the production of lap former machine in kg
Find out the production of lap former machine in kg
 
Yarn dyeing faults
Yarn dyeing faultsYarn dyeing faults
Yarn dyeing faults
 
Auro textile Trainning report
Auro textile Trainning reportAuro textile Trainning report
Auro textile Trainning report
 
Carding (1)
Carding (1)Carding (1)
Carding (1)
 
Warping
WarpingWarping
Warping
 
Warping phpapp3648
Warping phpapp3648Warping phpapp3648
Warping phpapp3648
 
carding
cardingcarding
carding
 
Circular knitting machine parts & function
Circular knitting machine parts & functionCircular knitting machine parts & function
Circular knitting machine parts & function
 
Industrial Textile Processing
Industrial Textile ProcessingIndustrial Textile Processing
Industrial Textile Processing
 
Finishing 1: Padding Mangles Stentering machine
Finishing 1: Padding Mangles    Stentering machineFinishing 1: Padding Mangles    Stentering machine
Finishing 1: Padding Mangles Stentering machine
 
Study on cost effectiveness of silk dyeing with acid dyes and basic dyes
Study on cost effectiveness of silk dyeing with acid dyes and basic dyesStudy on cost effectiveness of silk dyeing with acid dyes and basic dyes
Study on cost effectiveness of silk dyeing with acid dyes and basic dyes
 
Industrial Attachment on Chandra Spinning Mills Ltd.
Industrial Attachment on Chandra Spinning Mills Ltd.Industrial Attachment on Chandra Spinning Mills Ltd.
Industrial Attachment on Chandra Spinning Mills Ltd.
 
Warping
WarpingWarping
Warping
 
Draw frame
Draw frameDraw frame
Draw frame
 

Similar to AFROZE TEXTILE INDUSTRIES

AUTOMATIC WHITEBOARD CLEANER
AUTOMATIC WHITEBOARD CLEANERAUTOMATIC WHITEBOARD CLEANER
AUTOMATIC WHITEBOARD CLEANERFahim Mahmud
 
Presentation on stenter machine
Presentation on stenter machinePresentation on stenter machine
Presentation on stenter machineEmran Ali
 
Iaetsd electric road cleaner
Iaetsd electric road cleanerIaetsd electric road cleaner
Iaetsd electric road cleanerIaetsd Iaetsd
 
Noida Metro Rail Corporation
Noida Metro Rail CorporationNoida Metro Rail Corporation
Noida Metro Rail CorporationAnkit Chaudhary
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdfKhalidAyaz3
 
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...IJSRD
 
Unit 2 updated sensors used in the automotive IE -.pptx
Unit 2 updated sensors used in the automotive IE -.pptxUnit 2 updated sensors used in the automotive IE -.pptx
Unit 2 updated sensors used in the automotive IE -.pptx15SweekarChougale
 
engineering and utilities report
engineering and utilities reportengineering and utilities report
engineering and utilities reportHassan Bilal
 
Me761 a lecture-4 cnc
Me761 a lecture-4 cncMe761 a lecture-4 cnc
Me761 a lecture-4 cncAshok Mannava
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)99sunilkumar
 
Power generation using speed breaker
Power generation using speed breakerPower generation using speed breaker
Power generation using speed breakerHitesh Sahu
 
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurement
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurementCh. no. 6 miscellaneous measurement sound, speed and humidity measurement
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurementAmol Kokare
 
railway workshop jodhpur
railway workshop jodhpurrailway workshop jodhpur
railway workshop jodhpurkalumutha
 
railway workshop jodhpur
railway workshop jodhpur railway workshop jodhpur
railway workshop jodhpur kalumutha
 
UNIT-V-IC Engine Performance.pptx
UNIT-V-IC Engine Performance.pptxUNIT-V-IC Engine Performance.pptx
UNIT-V-IC Engine Performance.pptxsanjaisrinivaas
 

Similar to AFROZE TEXTILE INDUSTRIES (20)

AUTOMATIC WHITEBOARD CLEANER
AUTOMATIC WHITEBOARD CLEANERAUTOMATIC WHITEBOARD CLEANER
AUTOMATIC WHITEBOARD CLEANER
 
Presentation on stenter machine
Presentation on stenter machinePresentation on stenter machine
Presentation on stenter machine
 
Iaetsd electric road cleaner
Iaetsd electric road cleanerIaetsd electric road cleaner
Iaetsd electric road cleaner
 
Noida Metro Rail Corporation
Noida Metro Rail CorporationNoida Metro Rail Corporation
Noida Metro Rail Corporation
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
 
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...
Test Rig for Measurement of Spark Advance Angle and Ignition System Using AT8...
 
internship report-KEl
internship report-KElinternship report-KEl
internship report-KEl
 
Servo 2.0
Servo 2.0Servo 2.0
Servo 2.0
 
J D J
J D JJ D J
J D J
 
Unit 3-4-a
Unit 3-4-aUnit 3-4-a
Unit 3-4-a
 
Unit 2 updated sensors used in the automotive IE -.pptx
Unit 2 updated sensors used in the automotive IE -.pptxUnit 2 updated sensors used in the automotive IE -.pptx
Unit 2 updated sensors used in the automotive IE -.pptx
 
engineering and utilities report
engineering and utilities reportengineering and utilities report
engineering and utilities report
 
Me761 a lecture-4 cnc
Me761 a lecture-4 cncMe761 a lecture-4 cnc
Me761 a lecture-4 cnc
 
60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)60015688 ashish-loco-summer (1)
60015688 ashish-loco-summer (1)
 
Power generation using speed breaker
Power generation using speed breakerPower generation using speed breaker
Power generation using speed breaker
 
Emission-Control-Sensors-pptx.pptx
Emission-Control-Sensors-pptx.pptxEmission-Control-Sensors-pptx.pptx
Emission-Control-Sensors-pptx.pptx
 
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurement
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurementCh. no. 6 miscellaneous measurement sound, speed and humidity measurement
Ch. no. 6 miscellaneous measurement sound, speed and humidity measurement
 
railway workshop jodhpur
railway workshop jodhpurrailway workshop jodhpur
railway workshop jodhpur
 
railway workshop jodhpur
railway workshop jodhpur railway workshop jodhpur
railway workshop jodhpur
 
UNIT-V-IC Engine Performance.pptx
UNIT-V-IC Engine Performance.pptxUNIT-V-IC Engine Performance.pptx
UNIT-V-IC Engine Performance.pptx
 

AFROZE TEXTILE INDUSTRIES

  • 1. Submitted By: Mr. ASIF ALI (K13EL-49) Mr. ALI MUHAMMAD (K13EL-19) Mr. MOUZAM ALI (K13EL-37) MEHRAN UNIVERSITY OF ENGINEERINGTECHNOLOGY SZAB CAMPUS KHAIRPURMIR’S (15 DAYS INTERNSHIP REPORT)
  • 2.
  • 3. ACKNOWLEDGMENT ‘In the name of Allah, the most Gracious, the most merciful’ “All praises for Almighty Allah, who guides us in darkness and helps us in difficulties and due respect for Holy Prophet (Peace be upon him) who enables us to recognize our creator.” First, we would like to thanks Almighty Allah who gave us strength to complete challenging tasks & His blessings that He provided me confidence, guidance & strength to complete this report. The journey has not finished yet and we pray to Him to show us the straight path & help us more in future as we nothing without His blessings. Writing an internship report appeared to be a great experience for us. It added a lot to us knowledge. Completion of internship report is not an easy task. It requires continuous hard work. Completion of this report would have not been possible without the support of all staff of HR department to whom I interacted and concerned field department. We would like to thanks especially Mr. MUZAMIL SALEEM (GM), Mr. ANWER SAHB (DPM) Mr. FARHAN AHMED (senior plant manager) , Mr. AB,RAZAQUE (senior power house manager) and other engineers and field workers to their practical guidance and personal interest by which we become able to complete this task. Very special thank to all our dear teachers that build our personality and enable us to do some creative work be a successful person in practical life. We are responsible for errors and mistakes presented in the report and a positive and constructive criticism will always be greeted warmth.
  • 4. SECTION NO:01 WARPING SECTION:02 SIZING SIZING WARPING SECTION WARPING &SIZING(H-SHAPPED CRIAL) & 800 SPEED DIRECT WARPING (H-SHAPPEDCRIAL) BENGER WARPING(1200 SPEED) CHINNA WARPING (700 SPEED) KUCUKER WARPING(1200 SPEED) BEST AUTOMATIC SYSTEM SIZING KUCKER SIZING BEN SIZING
  • 5. SECTION:03 WEAVING Weaving is a method of textile production in which two distinct sets of yarns or threads are interlaced at right angles to form a fabric or cloth. Similar methods are knitting, felting, and braiding or plaiting. The longitudinal threads are called the warp and the lateral threads are the weft or filling. In Afroze there are 72 looms are used each having same working. LOOM: A loom is a device used to weave cloth and tapestry. The basic purpose of any loom is to hold the warp threads under tension to facilitate the interweaving of the weft threads. The precise shape of the loom and its mechanics may vary, but the basic function is the same Toyota 710 loom used in an industry.
  • 6. SENSORSUSED IN LOOM: Different sensors are used in loom as, (1) Feeler sensor: which sense when thread breaks. (2) Metal sensor: which sense beam if it will be in front of it then it sense in working condition otherwise not. (3) Proximity sensor: it counts number of turns. (4) Balloon sensor: it sense how much thread is used. MOTORS USED IN LOOM: (1) induction motor 1pahse and 3phase (2) Servo motor (3) Stepper motor (1) Induction motor: Introduction; One of the most common electrical motor used in most applications which is known as induction motor. This motor is also called as asynchronous motor because it runs at a speed less than its synchronous speed. Induction motors are easier to maintain and cheaper. Working principle: It has two main parts stator and rotor, stator is stationary part where rotor is rotating part also stator having thin lamination, when a AC supply is provided to stator of I.M a rotating magnetic field produces which cuts rotor, according to faradays law an emf induces in rotor loop which produces its own field so, both stator and rotor field interacts with each other and force produces which moves it. Where rotor speed is less then stator speed. Applications in textile: Used in different places such as, in loom to drive it, drier etc.
  • 7. (2) Servo motor: This is nothing but a simple electrical motor , controlled with the help of servomechanism. If the motor as controlled device, associated with servomechanism is dc motor, then it is commonly known DC Servo Motor. If the controlled motor is operated by AC, it is called AC Servo Motor. Servomechanism: A servo system mainly consists of three basic components (1) A controlled device (2) An output sensor (3) A feedback system This is an automatic closed loop control system. Here instead of controlling a device by applying the variable input signal, the device is controlled by a feedback signal generated by comparing output signal and reference input signal. When reference input signal or command signal is applied to the system, it is compared with output reference signal of the system produced by output sensor, and a third signal produced by a feedback system. This third signal acts as an input signal of controlled device. Advantages:  Works on some angle  Good accuracy  Works both reverse and forward  Servo amplifier also used  High frequency on stator side
  • 8. 2. Stepper motor: A stepper motor is a type of DC motor that rotates in steps. When electrical signal is applied to it, the motor rotates in steps and the speed of rotation depends on the rate at which the electrical signals are applied and the direction of rotation is dependent on the pattern of pulses that is followed. A stepper motor is made up of a rotor, which is normally a permanent magnet and it is, as the name suggests the rotating component of the motor. A stator is another part which is in the form of winding. (a)Humidity plant: ROOM AIR (Return fan) AIR PASS (Shivering room) WEAVING (through supply fan having 26 to 27 degree cooling according to need) 4. PROCESSING: (a) Bleaching: There are 4 washing chambers in each portion has powder ,soap and detergents mixture which is used for cleaning purpose ,after that it will be washed and then it move to drier portion where inside it there is hot steam used. Where also flow sensors are used to sense flow of water inside washing portion.
  • 9. (b)Drier: It is used to dry product after bleaching and washing ,cylinder drier (beneger company) ,it has four zones ,having steam pressure of 4bar,and temperature of 100 degree C, in which total 25 induction motors used from which 23 are 0.75 KW and 2 motors are 5.5kw ,where dancer (potentiometer) is used to balance speed of motors. Also invertors are used for 0.75 KW motors as easily rotate them forward and reverse. 5. POWER PLANT: There are four alternators are used each having rating of one MW. (a):  Step no: 01 In fuel there is mixture of 20% of natural gas and 80% of air. 20% natural gas 80% Air Pressure of gas is used in current is 1513 mbar. Mbar meter is also used to measure actual pressure.  Step no:02 Union valve: Is used to control the flow of fuel, also flinch used to connect valve on both sides of pipes.  Step no: 03 Filter: are used to make fuel pure from dust and other particles. Mbar  Step no: 04 Gas pressure gauge Psi  Step no: 05 Fuel pressure filter: It is used to finally measure pressure of fuel. Then move through flexible pipes.
  • 10. (1) Power mode: individually each generator (2) Sink mode: all generators equal distribution of load  Step no: 06 Turbo charges:(mixture) It used to make mix natural gas and air properly then make equal distribution of fuel (gas) in pipes to Alternator; also it performs the function of exhaust.  Step no: 07 Starting of Engine : Initially what happens generator is moved through starting motor ( through a 12v battery source) when its speed reached to 150 t0 200 rpm’s then motor is removed and fire or ignition is provided to burn fuel (10000v are needed to start fire),and generator starts. MODES OF OPERATION (b) :Cable rating : Qno: If power is 1KW then what will be the rating of cable? Ans: by using the real power formula we can find the carrying capacity of cable P=VICOSⱺ I=P/VCOSⱺ =1000/400*0.85 I=1.8 A and cable rating will be 1mm =1.8 ladder tray (c) Power Tray Pufrated tray
  • 11. These trays are used to carry cables where ladder tray is used in open environment as rain water does not stop upon it, where ladder tray is used in closed environment. (d) Switch gear: One of the basic functions of switchgear is protection, which is interruption of short- circuit and overload fault currents while maintaining service to unaffected circuits. Switchgear also provides isolation of circuits from power supplies. it is designed on basis of ampere rating. then in last it is distributed in different sections of textile where it is required. (e) Cooling of generator: cooling is provided to generator through water. where water pumps are used to circulate water through it ,where it takes heat from different portions of generator and then that hot water goes to heat exchanger and becomes cool so, such process continue. Figure: block diagram power plant.
  • 12. FIRE ALARAM SYSTEM A fire alarm system is number of devices working together to detect and warn people through visual and audio appliances when smoke, fire, carbon monoxide or other emergencies are present. These alarms may be activated from smoke detectors, and heat detectors. Types of fire alarm system (1) Conventional fire alarm systems: Conventional fire alarm systems and its components are all wired to the same cable that connects them to a fire alarm control panel that displays a signal when one of the components is activated. These types of systems are inexpensive and work well in small facilities. The main problem with conventional fire alarm systems is that when a fire alarm component produces a signal and it appears on the control panel there is no way to know which component it is in the building. (2) Addressable fire alarm system: Addressable fire alarm systems are the most modern type of system and its components have individual unique identifiers. When one of the system’s
  • 13. components is initiated it displays a signal on the fire alarm control panel that indicates the component’s address. Large facilities are typically equipped with these systems because they can quickly pinpoint the address of the fire alarm component that sent the signal. This saves a lot of time because it eliminates the need to search for the component that produced the signal. In each zone there are 18 devices used total 42 zones , each operates on 24.5V ,where 16-20 ft distance between each alarm and having height of 15ft.
  • 14. Conclusion:  We had a great learning and training experience at Afroze Textile Industries for our academic program of Electrical ENGINEERING at MEHRAN UNIVERSITY of Engineering And Technology SZAB CAMPUS KHAIRPURMIR’S  We physically visited industrial utilities like steam boiler, RO plant, oil boiler, power house, air compressor, chiller plant which work on those basic thermodynamics principles and laws which we have studied in theories,  Working on them physically on the industrial scale was really so demanding for us.  We had a real world working and have work from, experiences which we had never been exposed to, in our isolated academic life at university.  We learned the coordination in planning of production order of different buyers to make the buyers happy and how to take the necessary steps in modifying the machines to cover any halts in the machines during a run.  We learned that how electrical engineers do take actions in maintaining a harmonious flow in the production line by the properly govern the maintenance of machines and by designing new efficient plants and by modifying the existing plants to reduce the time consumption, cost, break downs of the production line.  They also increase by the same way the quality, and more diversified product which can change the market.  We learned how to work in a team and how to work under the higher authorities.
  • 15. SUGGESTIONS: We saw that Afroze Textile Industry has to depend upon the water tankers a little bit which are expensive, not a true solution, dealing with them is nasty. 1. We suggest that they should consider reconfiguring the waste water plant RO, which has the water storage capacity of 500,000 gallons, this will eventually be good for environment, production, and profitable I guess. ENERGY CRISIS: In spite of having fully owned 3MWatt power plant a froze is still facing power shutdown on Sundays due to natural Gas strike by the govt. this cause an effective loss to the production and profit of the industry. 1. We recommend the industry to install solar power systemon the roofs and make use of it in conjunction with N.gas power plant. 2. We also recommend that industry should encourage the govt. for the use of Thar coal in producing energy for the betterment of this sector. 3. We also recommend that industry should overcome power losses in terms of power efficient machines and good lubrication and insulations of machines.