SlideShare ist ein Scribd-Unternehmen logo
1 von 6
Downloaden Sie, um offline zu lesen
O.K NOT O.K
1) MECHANICAL	INSTALLATION
a) Check	the	Sufficient	free	space	around	the	unit
b)
Ensure	the	Drive	cabinets	are	installed	in	safe	dust	free	environment	and	the	room	
should	be	enough	to	handle	the	required	air	circulation	for	the	drives
c)
Check the frame, roof / canopy, component mounting plates, cable gland plates and
side doors for any damages during transport / erection and should as per GA and IGA
drawings
d)
Check the optional structure requirements such as anti-vibration pad, special
hooking	arrangements	etc.	if	any
e)
Ensure	the	Lifting	angles	are	removed.
f)
Check	that	the	cabinet	parts	are	clean	and	dust	free.
g)
Check that each shipping section was erected with correct type of joining
arrangements	like	side	plates,	channels,	connecting	bus	bar	(AC,	DC	and	PE)	etc.	
h) The	ambient	operating	conditions	are	allowed
i) The	unit	is	properly	fastened	to	the	floor	and	wall
k) The	cooling	air	is	able	to	flow	freely	and	cooling	air	volume	is	sufficient
2)
Bus	bars
a)
Check	visually	that	bus	bar	support	insulators	are	undamaged.
b)
Check	that	all	bus	bar	connections	/	joints	are	tightened.	(Note	that	all	bolts	are	
tightened	with	correct	torque	are	marked	in	factory	before	dispatch.	Visual	Checking	
of	the	mark	is	sufficient)
c)
Ensure	sufficient	clearance	between	bus	bars	after	erection	and	ensure	no	foreign	
materials	on	busbars
3)
Electrical	components
a)
Check	that	the	quantity,	make,	type	and	rating	of	components	are	as	per	BOM.	
Check	visually	that	the	components	are	not	damaged
b)
Check	that	all	the	components	are	marked	with	visible	labels.	If	any	label	missing	
please	arrange	the	same
c)
Check	that	all	modules	are	according	to	the	BOM	with	correct	option	codes
d)
Check	that	any	physical	damages	in	the	modules
e)
Check	drive	modules	are	mounted	properly	/	inserted	inside	plug	connectors	
securely	for	full	contact	with	plug	connector
4)
ELECTRICAL	INSTALLATION
a) The	inverter	is	grounded	properly
b) The	AC	line	voltage	matches	the	nominal	output	voltage	of	the	inverter	
c) The	AC	transformer	is	suitable	for	use	with	the	inverter
d) The	insulation	of	the	assembly	is	sufficent
e) The	AC	power	system	is	an	IT	(ungrounded)	system
f) The	AC	power	cable	connections	at	L1,L2	and	L3	and	their		tightening	torques	are	OK
g)
The	DC	power	cable	connections	at	UDC+	and	UDC-	and	their	tightening	torques	are	
OK
h) The	power	cables	are	routed	away	from	other	cables
i)
The	auxiliary	power	supply	cable	connection	at	Q10	and	their	tightening	torques	are	
Ok
CUSTOMER
EQUIPMENT DETAILS
SITE
INVERTER ERECTION CHECK LIST
SR NO
CHECK POINT
STATUS
k)
The	external	control	connections	to	the	inverter	are	OK		(including	emergency	stop,	
feildbus	etc.)
l)
The	cable	connections	at	the	junction	box	(option+K479)	and	their	tightening	torque	
are	OK
m) The	EMC	filter	(option	+E216)	is	correctly	installed,if	present
n)
There	are	no	tools,	foreign	objects	or	dust	from	drilling	inside	the	modules	or	the	
cabinet
o) All	shrouds	and	covers	are	in	place
5)
Cabling	and	wiring
a)
Check	that	Field	(Customer	side)	analog	signal	cables	like	PT100	are	wired	with	
shielded	cable.	Also	check	those	shields	are	properly	earthed	at	one	end.	Earth	Loop	
should	be	avoided
b)
Check	that	all	Field	cables	enough	in	length	and	stress	free.	The	cables	should	be	
with	proper	cable	gland	and	tightened	with	Gland	plate
c)
Check	that	all	fiber	optic	cables	are	not	damaged,	connectors	not	to	be	broken,	not	
routed	against	sharp	edges	or	bare	live	parts	and	bending	radius	of	the	FO	cables	is	
bigger	than	35	mm.
d)
Check,	by	gentle	pulling	the	cables,	that	their	connections	to	component	terminals	
are	tight	enough
e)
Check	that	short	links	on	TB’s	and	loop	chaining	are	done	according	to	scheme
6)
Earthing	and	Mechanical	Operating	Tests
a)
Check	that	the	panels	are	dual	earthed.		Welding	of	earth	bars	with	panel	is	not	
recommended.	(Please	note	there	may	be	a	separate	Power	and	Electronic	earthing	
practice	in	some	plants)
b)
Check	the	functionality	of	all	switches	by	closing	and	opening	them
c)
Check	that	fuses	are	placed	tightly	in	the	middle	of	the	fuse	socket	/	fuse	base.
d)
Check	that	the	doors	for	open	and	close	without	rubbing	or	noise	when	open	and	close.	
e)
Check	the	door	defeat	function.	When	fuse	switch	or	disconnecting	switch	is	closed,	
the	cabinet	door	cannot	be	opened.
7) Start-Up	Preparation
a)
Make	sure	that	the	panel	is	safe	to	connect	voltage
b)
Keep all switches and breakers of the panel in OFF position and do the necessary
short	links	if	required
c)
Ensure that nobody is working on the unit or circuits that are associated to the panel
to	be	test	like	inter	panels,	shipping	section,	motor	etc.
d)
Keep	all	cabinet	doors	in	close	before	power	up
e)
Ensure	auxiliary	voltages	available	for	backcharging	and	control	testing
f) Status	of	Grid	voltage	availability	and	readiness	for	energising
g) Status	of	panel	earthing	and	earth	pits
h) Status	of	DC	power	connections	readiness
Consultant	Engineer
Client	Engineer
Acceptance Date
Contractor	Engineer
O.K NOT	O.K
1) AVAILABILITY	OF	DOCUMENTATION
a) Erection	drawings	including	OGA				
b) Erection	/	Maintenance	Manual
c) Transport	packing	list		
2) RECEIPT	OF	TRANSFORMER
a) Externally	inspected	damage	(if	any)	
b) Gas	pressure	on	receipt	(Where	applicable)
c) Oil	level	(in	case	of	oil	filled	transformer)
d) Unit	correctly	positioned		
3) RECEIPT	OF	ACCESSORIES	
a) All	materials	stored	correctly		
b) Packing	Cases	inspected,	damage	if	any	
c) Marshalling	box	inspected,	damage	if	any	
d) Control	panels	(RTCC)inspected	damage	if	any		
e) Materials	received	corresponded	to	Advise	note	
f) Any	shortages	/	wrong	supply	
g) Materials	comply	with	shipping	specification	
h) Remark	(if	any)
4) ERECTION	
a) Transport	rollers	mounted	
b) Conservator	mounted	
c)
Buchholz	relay	and	oil	surge	relay	mounted	(arrow	
marked	should	be	towards	conservator)	
d) Breather	mounted	and	duly	charged	
e) HV	Bushings	mounted	
f) LV	Bushing	mounted	
Sr.	No. Check	Point
Status
TRANSFORMER	ERECTION	CHECK	LIST	
Customer:-
Equipment	Details:-
Site:-
g) Tertiary	Bushing	mounted	(if	applicable)	
h) HV	neutral	Bushing	mounted	
i) LV	Neutral	Bushing	mounted				
j) Bushing	installed	at	correct	angles			
k) Diaphragm	checked			
l) MOLG	mounted			
m) Radiator	mounted			
n) Fans	mounted			
o) Pressure	Relief	valves	mounted			
p) Alignment	of	all	pipe	work			
q) OLTC	Conservator	mounted				
r) Heat	Exchangers	assembled	with	pipe	work			
s) Topping	up	of	transformer	oil			
t) Leakage	observed	after	24	hrs.(if	any)		
u) Rating	Diagram	and	identification	plate	fitted				
v) Control	panel	(RTCC)	aligned	
w) Control	panel	(OLTC)	aligned
4) OIL	FILLING	
a) All	bushing	oil	level			
b) Tap	changer	selector	oil	level			
c) Diverter	switch	oil	level			
d) Auxiliary	unit	oil	level			
e) Radiator,	Headers	oil	filled			
f) Transformer	/	OLTC	Conservator	oil	tight			
g) Complete	transformer	oil	tight			
h) All	air	release	plug	vented			
i) Valves	in	service	position			
j) All	drain	/	filter	valves	blanked		
5) MULTICORE	CABLE		
a) All	tray	work	adequately	secured
b) All	cables	adequately	tied/clipped	back	to	tray
c) Cables	glaned	correctly	
6) BREATHERS	
a) Transformer	silica	gel	breather	satisfactory				
b) Tap	changer	silica	gel	breather	satisfactory	
c) Dry	breather	correctly	installed	
7) FANS	
a) Fans	rotate	freely	&	quickly
b) Pumps	installed	for	correct
c) Flow	indication	visible	
8) CONTROL	PANELS	
a) Cable	termination	&	Glanning
9) Cleaning	and	touch	up	of	painting	
Consultant	Engineer
Client	Engineer
DateAcceptance
Contractor	Engineer
O.K NOT	O.K
1)
SCB	Assembly	/	Installation
a) Mounting	Structure's	verticality,	alignment,	GI	coating
b) Casting	of	mounting	structure	and	pile	cap	above	G.L
c) Clerance	between	bottom	of	SMB	and	G.L.
d) Overall	visual	aspect	(damages,	Scratches)
e) Box	Fixation	and	assembly
d) SCB	allocation	(ID	Vs	allocation)
f) Cleaning	of	the	interior	of	the	panel	box
g) Labelling/Numeration	of	SCB	as	per	drawing
2)
Equipment
a) Input	NHI	Fuse	status	(Input	Fuses)
b) Surge	Arrestor	Flag
c) DC	switch	operational
3)
Electrical	Connections
a) Ground	connectivity	to	GI	strip,	cable	and	connections
b) DC	output,	cable	and	connections
c) String	input,	cable	and	connections
d) Gland	tighting
e) Protection	against	direct	contact
f) All	connection	tightness
g) Cable	Labelling	(Inputs,	Outputs,	Auxiliary,	communication	cables)
4)
Documentation
a) SCB's	SLD	&	String	Layout
Client	Engineer
Acceptance Date
Contractor	Engineer
Consultant	Engineer
Sr.	No. Check	Point
Status
SCB	ERECTION	CHECK	LIST	
Customer:-
Equipment	Details:-
Site:-

Weitere ähnliche Inhalte

Was ist angesagt?

Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Engineering Limited
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.Sheikh Nazmul Islam
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power PlantGensol Engineering Limited
 
Electrical Design
Electrical DesignElectrical Design
Electrical Designanjal3753
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationraiamitesh8
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Photovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsPhotovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsGavin Harper
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and TrackingATUL RAJ
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 

Was ist angesagt? (20)

Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality Management
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Grid tie solar power system
Grid tie solar power systemGrid tie solar power system
Grid tie solar power system
 
Electrical Design
Electrical DesignElectrical Design
Electrical Design
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
CUF vs PR
CUF vs PRCUF vs PR
CUF vs PR
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Photovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsPhotovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design Tools
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking1 MW solar Power plant project Scheduling and Tracking
1 MW solar Power plant project Scheduling and Tracking
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 

Andere mochten auch

Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
 
Transformer protection & maintenance
Transformer protection & maintenanceTransformer protection & maintenance
Transformer protection & maintenancePradeep Avanigadda
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Gensol Engineering Limited
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Gensol Engineering Limited
 
13 lv switchboard inspection guide
13   lv switchboard inspection guide13   lv switchboard inspection guide
13 lv switchboard inspection guideSơn Trà
 
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...JLanka Technologies (Pvt) Limited
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisSchneider Electric
 
Solar Roof top Project proposal delhi
Solar Roof top Project proposal delhiSolar Roof top Project proposal delhi
Solar Roof top Project proposal delhiTarun Rathore
 
Electrical maintenance-1
Electrical maintenance-1Electrical maintenance-1
Electrical maintenance-1Vijay Raskar
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantVignesh Sekar
 
Solar product business plan
Solar product business planSolar product business plan
Solar product business planIndrajith Nair
 
wiring Part 3: wires & cables
wiring Part 3: wires & cableswiring Part 3: wires & cables
wiring Part 3: wires & cablesvigyanashram
 
K 12 school-safety_security_checklist_mc_donald_aaci
K 12 school-safety_security_checklist_mc_donald_aaciK 12 school-safety_security_checklist_mc_donald_aaci
K 12 school-safety_security_checklist_mc_donald_aaciJAMES E. McDONALD, PSNA
 

Andere mochten auch (20)

4. annexures
4. annexures4. annexures
4. annexures
 
Analysis of PVSyst Loss Diagram
Analysis of PVSyst Loss DiagramAnalysis of PVSyst Loss Diagram
Analysis of PVSyst Loss Diagram
 
Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in India
 
Transformer protection & maintenance
Transformer protection & maintenanceTransformer protection & maintenance
Transformer protection & maintenance
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 
Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects Engineering Drawings required for Solar Projects
Engineering Drawings required for Solar Projects
 
Guide to Solar Project Implementation
Guide to Solar Project ImplementationGuide to Solar Project Implementation
Guide to Solar Project Implementation
 
13 lv switchboard inspection guide
13   lv switchboard inspection guide13   lv switchboard inspection guide
13 lv switchboard inspection guide
 
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
 
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles AlvisPreventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
Preventive Maintenance Strategies for Power Distribution Systems- Charles Alvis
 
Solar Roof top Project proposal delhi
Solar Roof top Project proposal delhiSolar Roof top Project proposal delhi
Solar Roof top Project proposal delhi
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
Electrical maintenance-1
Electrical maintenance-1Electrical maintenance-1
Electrical maintenance-1
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
Wires & cables
Wires & cablesWires & cables
Wires & cables
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Solar product business plan
Solar product business planSolar product business plan
Solar product business plan
 
wiring Part 3: wires & cables
wiring Part 3: wires & cableswiring Part 3: wires & cables
wiring Part 3: wires & cables
 
K 12 school-safety_security_checklist_mc_donald_aaci
K 12 school-safety_security_checklist_mc_donald_aaciK 12 school-safety_security_checklist_mc_donald_aaci
K 12 school-safety_security_checklist_mc_donald_aaci
 

Ähnlich wie Erection Checklist for Solar Inverters, Solar Transformers & Solar String Combiner Box

158742585 packaged-type-ac-units
158742585 packaged-type-ac-units158742585 packaged-type-ac-units
158742585 packaged-type-ac-unitsbhattbhai
 
Vf19 plusspc rev3(3)
Vf19 plusspc rev3(3)Vf19 plusspc rev3(3)
Vf19 plusspc rev3(3)Tim Yao
 
244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdfmoumo1
 
02 custodie eng
02 custodie eng02 custodie eng
02 custodie engHai Pham
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467trorro
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467trorro
 
API 510 Practice Exam #5 CLOSE BOOK Questions.pdf
API 510 Practice Exam #5 CLOSE BOOK Questions.pdfAPI 510 Practice Exam #5 CLOSE BOOK Questions.pdf
API 510 Practice Exam #5 CLOSE BOOK Questions.pdfEmmanuelMatutu
 
Job aid valve replacement
Job aid   valve replacementJob aid   valve replacement
Job aid valve replacementJim Piechocki
 
Building design report
Building design reportBuilding design report
Building design reportJasonSalway2
 
Stainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxStainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxtoramansor
 
Airex Manufacturing Pro System Kit www.airexmfg.com
Airex Manufacturing Pro System Kit   www.airexmfg.comAirex Manufacturing Pro System Kit   www.airexmfg.com
Airex Manufacturing Pro System Kit www.airexmfg.comAirex Manufacturing Inc
 
Technical specification EEE
Technical specification EEETechnical specification EEE
Technical specification EEEAmit Kumar
 
Proforma for collection of data during training
Proforma for collection of data during trainingProforma for collection of data during training
Proforma for collection of data during trainingBhaskar Naidu
 

Ähnlich wie Erection Checklist for Solar Inverters, Solar Transformers & Solar String Combiner Box (18)

158742585 packaged-type-ac-units
158742585 packaged-type-ac-units158742585 packaged-type-ac-units
158742585 packaged-type-ac-units
 
Vf19 plusspc rev3(3)
Vf19 plusspc rev3(3)Vf19 plusspc rev3(3)
Vf19 plusspc rev3(3)
 
Mechanical
Mechanical Mechanical
Mechanical
 
244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf
 
02 custodie eng
02 custodie eng02 custodie eng
02 custodie eng
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467
 
Ansi Gptc Z380.1 2009 192 467
Ansi Gptc Z380.1   2009 192 467Ansi Gptc Z380.1   2009 192 467
Ansi Gptc Z380.1 2009 192 467
 
API 510 Practice Exam #5 CLOSE BOOK Questions.pdf
API 510 Practice Exam #5 CLOSE BOOK Questions.pdfAPI 510 Practice Exam #5 CLOSE BOOK Questions.pdf
API 510 Practice Exam #5 CLOSE BOOK Questions.pdf
 
Control valves MCQ
Control valves MCQControl valves MCQ
Control valves MCQ
 
Installation mechanical
Installation mechanicalInstallation mechanical
Installation mechanical
 
Taiyaba rashid acp
Taiyaba rashid acpTaiyaba rashid acp
Taiyaba rashid acp
 
Job aid valve replacement
Job aid   valve replacementJob aid   valve replacement
Job aid valve replacement
 
Building design report
Building design reportBuilding design report
Building design report
 
Stainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docxStainless Steel Threaded&Welding Joint.docx
Stainless Steel Threaded&Welding Joint.docx
 
Airex Manufacturing Pro System Kit www.airexmfg.com
Airex Manufacturing Pro System Kit   www.airexmfg.comAirex Manufacturing Pro System Kit   www.airexmfg.com
Airex Manufacturing Pro System Kit www.airexmfg.com
 
Technical specification EEE
Technical specification EEETechnical specification EEE
Technical specification EEE
 
Api 510-closed-1[1]
Api 510-closed-1[1]Api 510-closed-1[1]
Api 510-closed-1[1]
 
Proforma for collection of data during training
Proforma for collection of data during trainingProforma for collection of data during training
Proforma for collection of data during training
 

Mehr von Gensol Engineering Limited

Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Gensol Engineering Limited
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Gensol Engineering Limited
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Gensol Engineering Limited
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Gensol Engineering Limited
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019Gensol Engineering Limited
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Gensol Engineering Limited
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Gensol Engineering Limited
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Gensol Engineering Limited
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol Engineering Limited
 
Electric Vehicle & Integration with Renewable Energy
Electric Vehicle & Integration with Renewable Energy Electric Vehicle & Integration with Renewable Energy
Electric Vehicle & Integration with Renewable Energy Gensol Engineering Limited
 

Mehr von Gensol Engineering Limited (20)

Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019
 
List of successful bidders 11.03.2019
List of successful bidders 11.03.2019List of successful bidders 11.03.2019
List of successful bidders 11.03.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Module Price Trend Analysis
Module Price Trend AnalysisModule Price Trend Analysis
Module Price Trend Analysis
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18
 
Floating Solar PV - An Introduction
Floating Solar PV -  An Introduction Floating Solar PV -  An Introduction
Floating Solar PV - An Introduction
 
Electric Vehicle & Integration with Renewable Energy
Electric Vehicle & Integration with Renewable Energy Electric Vehicle & Integration with Renewable Energy
Electric Vehicle & Integration with Renewable Energy
 

Kürzlich hochgeladen

Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 

Kürzlich hochgeladen (20)

Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 

Erection Checklist for Solar Inverters, Solar Transformers & Solar String Combiner Box