JSA-Piling or Concreting for Foundations & Building

JSA-Piling or Concreting for Foundations & Building
Sr. Activity Potential Hazards Control Measures
1.
Mobilization of equipment &
Materials
1.Involvement of unskilled personnel
2.Piling machine hit with plant/equipment & structures
3.Unauthorised/ uninspected equipment/tools at site
4.Personnel injury/property damage
5.Overhead structures/pipe racks
6.Slip, Trip & Fall
7.Inclement weather condition
 Trained & skilled staff to be authorized for working
 Ensure JSA briefing & Daily TBT to all workforce before commencing the
activity
 Use of authorized & designated routes
 Only inspected Equipment/Tools must be allowed at the worksite
 Use the right tools for the right job
 Ensure safe transportation of equipment/materials at the worksite
 Avoid throwing of materials
 All of the materials to be secured while its transportation to work site
 Ensure a safe distance of piling machine from overhead structures/pipe racks
 Water sprinkling to be carried out on regular biases to avoid dust
 Take care of overhead structure/pipe racks
 Keep access/walkways always clear from any obstruction
 Stop work in case of any inclement weather conditions (rain, storm, fog etc.)
 Restrict movement of heavy vehicles/equipment in rain/fog
2. Piling with Piling Machine 1.Uncertified piling Machine & Operator,
2.Personnel hit by the movement of the piling machine,
3.Working in live areas
4.Sling broken, load drop
5.Slip, Trip & Fall
6.Inclement weather condition
7.Fire & explosion
 Pile machine & its operator should be certified
 Banks man should be available at the site to control the movement of heavy
vehicles/equipment
 Keep away all unauthorized people during movement of heavy vehicle/equipment
 Be careful of nearby live areas
 Ensure Close HSE monitoring /supervision
 Ensure proper & inspected accessories being used for drilling
 Ensure that drilling bit is properly fixed with locking pins
 Keep away during the drilling operation
 the working area should properly be barricaded
JSA-Piling or Concreting for Foundations & Building
Project/Facility: Reference No:
Client: Date of Assessments:
Assessed by: Date of Next Assessment:
Reviewed by: Approved by:
Activity: JSA-Piling or Concreting for Foundations & Building
Emergency Plans. Standard PPE’s: First aid kit must be present at the worksite and the HSE personnel will be the first response in case of emergency, ERPs &
Emergency contact numbers to be in place at the job location
Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In case of any new hazard
identified by any of the working team members during the job, the JSA review process should be carried on.
JSA-Piling or Concreting for Foundations & Building
 Ensure proper stacking of all materials at the site
 Keep access/walkways always clear from any obstruction
 Ensure proper housekeeping of the workplace all the time
 Stop work in case of any inclement weather conditions (rain, storm, fog etc.)
 Restrict movement of heavy vehicles/equipment in rain/fog
 Ensure availability of inspected fire extinguishers at site
 Conduct proper gas test before start job
 Flame arrestor to be installed in all vehicles/equipment
3. Lowering of Steel Cage
structure & Concreting of
piles
1.Personnel hand injury while handling with steel
2.People under a suspended load
3.Unbalancing of load
4.Miscommunication between operator & signalman
5.Improper signalling during lowering of the steel cage
structure
6.Inappropriate PPE’s/Tools during concrete work
7.Skin contact with concrete or other chemicals
 Ensure the Involvement of skilled labour
 Ensure use of proper PPE’s
 Deliver TBT before commencing work
 Ensure use of inspected & colour coded hand tools & rigging accessories
 The area should be properly barricaded during lifting operations
 Ensure proper stacking of all materials at the worksite
 Maintain good housekeeping all the time
 Use of appropriate PPE’s during concrete
 Ensure use of inspected tools for the right job
 Availability of freshwater at site
4. Working at night shift hours 1.Poor visibility at night hours
2.Vehicles/equipment hit with people, equipment or
structure
3.Slip, trip & fall
 Ensure proper lighting arrangement for late-night working hours
 Careful movement of vehicles/equipment in night hours
 Place refection tapes at hard barriers, structures
 Banks men should wear high visibility reflection vests
 No working should be allowed in poor lighting conditions
 Ensure proper housekeeping to avoid tripping
1 von 2

Recomendados

risk assessment - pile cap.pdf von
risk assessment - pile cap.pdfrisk assessment - pile cap.pdf
risk assessment - pile cap.pdfmydl2
592 views4 Folien
JHA HEAVY LIFTING OF VESSEL.pdf von
JHA HEAVY LIFTING OF VESSEL.pdfJHA HEAVY LIFTING OF VESSEL.pdf
JHA HEAVY LIFTING OF VESSEL.pdfHaroon AbdulRahim
12 views11 Folien
HAZARD IDENTIFICATION RISK ASSESSMENT 561 KWH BASF DAHEJ GUJARAT.pdf von
HAZARD IDENTIFICATION RISK ASSESSMENT 561 KWH  BASF DAHEJ GUJARAT.pdfHAZARD IDENTIFICATION RISK ASSESSMENT 561 KWH  BASF DAHEJ GUJARAT.pdf
HAZARD IDENTIFICATION RISK ASSESSMENT 561 KWH BASF DAHEJ GUJARAT.pdfMohsinKhan281076
255 views6 Folien
Methodstatement welding von
Methodstatement weldingMethodstatement welding
Methodstatement weldingAanand Subi
10.9K views9 Folien
Mawaz CV von
Mawaz CVMawaz CV
Mawaz CVMawaz Akhter
240 views5 Folien
update 20feb1 von
update 20feb1update 20feb1
update 20feb1CHRISTOPHER Rickie CHRISTIE
149 views6 Folien

Más contenido relacionado

Similar a JSA-Piling or Concreting for Foundations & Building

Project von
ProjectProject
ProjectKhurram Shahzad
176 views25 Folien
Turn Key Group Services - OHS Toolkit von
Turn Key Group Services - OHS ToolkitTurn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS Toolkitturnkeygroupservices
1.1K views37 Folien
Plant ; equipment dismantling of scaffold von
Plant ; equipment dismantling of scaffoldPlant ; equipment dismantling of scaffold
Plant ; equipment dismantling of scaffoldBimal Chandra Das
211 views3 Folien
Lifting equipment at work von
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
5.2K views36 Folien
AHU.pdf von
AHU.pdfAHU.pdf
AHU.pdfSyedMoazzamAliAli1
35 views6 Folien
LPG Chloride treaters foundation execution_Rev.00.pdf von
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfJESUSBASILIOANTONIO
12 views6 Folien

Similar a JSA-Piling or Concreting for Foundations & Building (20)

Lifting equipment at work von Paul Smith
Lifting equipment at workLifting equipment at work
Lifting equipment at work
Paul Smith5.2K views
LPG Chloride treaters foundation execution_Rev.00.pdf von JESUSBASILIOANTONIO
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
Construction safety lecture-3 von Saleem Malik
Construction safety  lecture-3Construction safety  lecture-3
Construction safety lecture-3
Saleem Malik1.4K views
150 Question Answers | Occupational Health & Safety von Muhammad Usman
150 Question Answers | Occupational Health & Safety150 Question Answers | Occupational Health & Safety
150 Question Answers | Occupational Health & Safety
Muhammad Usman24.8K views
Safety protocols of construction site.pptx von Zeeshan Yousaf
Safety protocols of construction site.pptxSafety protocols of construction site.pptx
Safety protocols of construction site.pptx
Zeeshan Yousaf8 views
Demolition of existing boiler house von AnatoliZ
Demolition of existing boiler houseDemolition of existing boiler house
Demolition of existing boiler house
AnatoliZ3.8K views
Excavations von FFSafety
ExcavationsExcavations
Excavations
FFSafety1.7K views
Jha rock drill use and maintenance romo von nafable
Jha rock drill use and maintenance romoJha rock drill use and maintenance romo
Jha rock drill use and maintenance romo
nafable1.2K views
hot works for construction of temporary facilities von Fãrük Ñäzmî
hot works for construction of temporary facilitieshot works for construction of temporary facilities
hot works for construction of temporary facilities
Fãrük Ñäzmî923 views

Último

Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc... von
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...csegroupvn
8 views210 Folien
Pitchbook Repowerlab.pdf von
Pitchbook Repowerlab.pdfPitchbook Repowerlab.pdf
Pitchbook Repowerlab.pdfVictoriaGaleano
6 views12 Folien
sam_software_eng_cv.pdf von
sam_software_eng_cv.pdfsam_software_eng_cv.pdf
sam_software_eng_cv.pdfsammyigbinovia
10 views5 Folien
DESIGN OF SPRINGS-UNIT4.pptx von
DESIGN OF SPRINGS-UNIT4.pptxDESIGN OF SPRINGS-UNIT4.pptx
DESIGN OF SPRINGS-UNIT4.pptxgopinathcreddy
21 views47 Folien
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx von
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptxlwang78
180 views19 Folien
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth von
BCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for GrowthBCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for Growth
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for GrowthInnomantra
15 views4 Folien

Último(20)

Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc... von csegroupvn
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
Design of Structures and Foundations for Vibrating Machines, Arya-ONeill-Pinc...
csegroupvn8 views
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx von lwang78
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
lwang78180 views
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth von Innomantra
BCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for GrowthBCIC - Manufacturing Conclave -  Technology-Driven Manufacturing for Growth
BCIC - Manufacturing Conclave - Technology-Driven Manufacturing for Growth
Innomantra 15 views
Créativité dans le design mécanique à l’aide de l’optimisation topologique von LIEGE CREATIVE
Créativité dans le design mécanique à l’aide de l’optimisation topologiqueCréativité dans le design mécanique à l’aide de l’optimisation topologique
Créativité dans le design mécanique à l’aide de l’optimisation topologique
LIEGE CREATIVE8 views
Unlocking Research Visibility.pdf von KhatirNaima
Unlocking Research Visibility.pdfUnlocking Research Visibility.pdf
Unlocking Research Visibility.pdf
KhatirNaima10 views
Design of machine elements-UNIT 3.pptx von gopinathcreddy
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptx
gopinathcreddy37 views
Design_Discover_Develop_Campaign.pptx von ShivanshSeth6
Design_Discover_Develop_Campaign.pptxDesign_Discover_Develop_Campaign.pptx
Design_Discover_Develop_Campaign.pptx
ShivanshSeth649 views
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf von AlhamduKure
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdfASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf
ASSIGNMENTS ON FUZZY LOGIC IN TRAFFIC FLOW.pdf
AlhamduKure8 views
Integrating Sustainable Development Goals (SDGs) in School Education von SheetalTank1
Integrating Sustainable Development Goals (SDGs) in School EducationIntegrating Sustainable Development Goals (SDGs) in School Education
Integrating Sustainable Development Goals (SDGs) in School Education
SheetalTank19 views
Web Dev Session 1.pptx von VedVekhande
Web Dev Session 1.pptxWeb Dev Session 1.pptx
Web Dev Session 1.pptx
VedVekhande17 views

JSA-Piling or Concreting for Foundations & Building

  • 1. JSA-Piling or Concreting for Foundations & Building Sr. Activity Potential Hazards Control Measures 1. Mobilization of equipment & Materials 1.Involvement of unskilled personnel 2.Piling machine hit with plant/equipment & structures 3.Unauthorised/ uninspected equipment/tools at site 4.Personnel injury/property damage 5.Overhead structures/pipe racks 6.Slip, Trip & Fall 7.Inclement weather condition  Trained & skilled staff to be authorized for working  Ensure JSA briefing & Daily TBT to all workforce before commencing the activity  Use of authorized & designated routes  Only inspected Equipment/Tools must be allowed at the worksite  Use the right tools for the right job  Ensure safe transportation of equipment/materials at the worksite  Avoid throwing of materials  All of the materials to be secured while its transportation to work site  Ensure a safe distance of piling machine from overhead structures/pipe racks  Water sprinkling to be carried out on regular biases to avoid dust  Take care of overhead structure/pipe racks  Keep access/walkways always clear from any obstruction  Stop work in case of any inclement weather conditions (rain, storm, fog etc.)  Restrict movement of heavy vehicles/equipment in rain/fog 2. Piling with Piling Machine 1.Uncertified piling Machine & Operator, 2.Personnel hit by the movement of the piling machine, 3.Working in live areas 4.Sling broken, load drop 5.Slip, Trip & Fall 6.Inclement weather condition 7.Fire & explosion  Pile machine & its operator should be certified  Banks man should be available at the site to control the movement of heavy vehicles/equipment  Keep away all unauthorized people during movement of heavy vehicle/equipment  Be careful of nearby live areas  Ensure Close HSE monitoring /supervision  Ensure proper & inspected accessories being used for drilling  Ensure that drilling bit is properly fixed with locking pins  Keep away during the drilling operation  the working area should properly be barricaded JSA-Piling or Concreting for Foundations & Building Project/Facility: Reference No: Client: Date of Assessments: Assessed by: Date of Next Assessment: Reviewed by: Approved by: Activity: JSA-Piling or Concreting for Foundations & Building Emergency Plans. Standard PPE’s: First aid kit must be present at the worksite and the HSE personnel will be the first response in case of emergency, ERPs & Emergency contact numbers to be in place at the job location Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In case of any new hazard identified by any of the working team members during the job, the JSA review process should be carried on.
  • 2. JSA-Piling or Concreting for Foundations & Building  Ensure proper stacking of all materials at the site  Keep access/walkways always clear from any obstruction  Ensure proper housekeeping of the workplace all the time  Stop work in case of any inclement weather conditions (rain, storm, fog etc.)  Restrict movement of heavy vehicles/equipment in rain/fog  Ensure availability of inspected fire extinguishers at site  Conduct proper gas test before start job  Flame arrestor to be installed in all vehicles/equipment 3. Lowering of Steel Cage structure & Concreting of piles 1.Personnel hand injury while handling with steel 2.People under a suspended load 3.Unbalancing of load 4.Miscommunication between operator & signalman 5.Improper signalling during lowering of the steel cage structure 6.Inappropriate PPE’s/Tools during concrete work 7.Skin contact with concrete or other chemicals  Ensure the Involvement of skilled labour  Ensure use of proper PPE’s  Deliver TBT before commencing work  Ensure use of inspected & colour coded hand tools & rigging accessories  The area should be properly barricaded during lifting operations  Ensure proper stacking of all materials at the worksite  Maintain good housekeeping all the time  Use of appropriate PPE’s during concrete  Ensure use of inspected tools for the right job  Availability of freshwater at site 4. Working at night shift hours 1.Poor visibility at night hours 2.Vehicles/equipment hit with people, equipment or structure 3.Slip, trip & fall  Ensure proper lighting arrangement for late-night working hours  Careful movement of vehicles/equipment in night hours  Place refection tapes at hard barriers, structures  Banks men should wear high visibility reflection vests  No working should be allowed in poor lighting conditions  Ensure proper housekeeping to avoid tripping