Examples of Lean Reports and Visibility EladAmit September 2010
Cumulative Flow Diagram (a.k.a. CFD) Purpose:Visually depict our work queues and completion trends to allow us to find and fix bottlenecks as well as predict completion velocity
Cumulative Flow Diagram (a.k.a. CFD) End Report: Stacked area chart showing per stage, the total estimate for the items in that stage Y-axis total estimate of items X-axis Time (tick per day)
Cumulative Flow Diagram (a.k.a. CFD) Example (Day 13): Backlog – 5 Selected – 1 Develop Ongoing – 2 Develop Done – 1 Deploy – 1 Live - 4
Cumulative Flow Diagram (a.k.a. CFD) Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per typeNote: in case of requirement, need to aggregate the estimates from the tasks Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)
Process Control Chart Purpose:Identify outliers in our process to focus improvement initiatives and reduce special cause variation
Process Control Chart End Report: A dot on the chart is a work item which finished on that date. Ex: the dot at the end of the arrow was finished on November 20th and took 20 days to complete Y-axis Actual chronological time it took an item X-axis Time (tick per day)
Process Control Chart End Report: The upper control limit (mean +3 std.dev.) Outliers (anything above the upper control limit) clearly marked The mean cycle time for all of the items in the report The lower control limit (mean -3 std.dev.)
Process Control Chart Parameters: What portion of the process we want to measure the cycle time for (e.g. from defined to development done, from start of development to testing) Item Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per type Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)
Process Control Chart RebasingNeed to allow rebasing of mean, upper and lower control limits to allow the chart to account for changes (e.g. more employees, changes in development processes) Rebasing points due to changes
Average Cycle Time Purpose:Identify trends in our delivery velocity
Process Control Chart End Report: Line chart with average cycle time per day Y-axis Average cycle time for all items finished on said day X-axis Time (tick per day)
Process Control Chart Parameters: What portion of the process we want to measure the cycle time for (e.g. from defined to development done, from start of development to testing) Item Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per type Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)
Thank You and Good Luck 

More Related Content

Similar to Elad Amit - Examples of Lean Reports and Visibility

Problem solving tools 112411
Problem solving tools 112411Problem solving tools 112411
Problem solving tools 112411
Khriztel NaTsu
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
WanBK Leo
 
Nandyal_20150513_1145_1230.original.1431384030
Nandyal_20150513_1145_1230.original.1431384030Nandyal_20150513_1145_1230.original.1431384030
Nandyal_20150513_1145_1230.original.1431384030
Raghav Nandyal
 
iv. minggu keempat
iv. minggu keempativ. minggu keempat
iv. minggu keempat
Isna Aryanty
 
Power point operations management i (1)
Power point operations management i (1)Power point operations management i (1)
Power point operations management i (1)
ocagnen
 

Similar to Elad Amit - Examples of Lean Reports and Visibility (20)

Problem solving tools 112411
Problem solving tools 112411Problem solving tools 112411
Problem solving tools 112411
 
unit 3 software requirement and analysis-1.ppt
unit 3 software requirement and analysis-1.pptunit 3 software requirement and analysis-1.ppt
unit 3 software requirement and analysis-1.ppt
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
Simple Process Mapping Techniques
Simple Process Mapping TechniquesSimple Process Mapping Techniques
Simple Process Mapping Techniques
 
Lead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail PresentationLead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail Presentation
 
Nandyal_20150513_1145_1230.original.1431384030
Nandyal_20150513_1145_1230.original.1431384030Nandyal_20150513_1145_1230.original.1431384030
Nandyal_20150513_1145_1230.original.1431384030
 
iv. minggu keempat
iv. minggu keempativ. minggu keempat
iv. minggu keempat
 
Managing projects by data
Managing projects by dataManaging projects by data
Managing projects by data
 
FME World Tour 2015 - FME & Data Migration Simon McCabe
FME World Tour 2015 -  FME & Data Migration Simon McCabeFME World Tour 2015 -  FME & Data Migration Simon McCabe
FME World Tour 2015 - FME & Data Migration Simon McCabe
 
GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1GanttChart for ClearQuest 1.4 and 1.3.1
GanttChart for ClearQuest 1.4 and 1.3.1
 
GanttChart for IBM Rational ClearQuest ver 1.3.1
GanttChart for IBM Rational ClearQuest ver 1.3.1GanttChart for IBM Rational ClearQuest ver 1.3.1
GanttChart for IBM Rational ClearQuest ver 1.3.1
 
Monitoring with Prometheus
Monitoring with PrometheusMonitoring with Prometheus
Monitoring with Prometheus
 
Togaf 9 template architecture roadmap
Togaf 9 template   architecture roadmapTogaf 9 template   architecture roadmap
Togaf 9 template architecture roadmap
 
Power point operations management i (1)
Power point operations management i (1)Power point operations management i (1)
Power point operations management i (1)
 
Flow process chart
Flow process chartFlow process chart
Flow process chart
 
Click, View & Do! - English
Click, View & Do! - EnglishClick, View & Do! - English
Click, View & Do! - English
 
Value stream mapping - Future State
Value stream mapping - Future StateValue stream mapping - Future State
Value stream mapping - Future State
 
Process Charts and Process Sequence Charts: Tools for Process Improvement
Process Charts and Process Sequence Charts: Tools for Process ImprovementProcess Charts and Process Sequence Charts: Tools for Process Improvement
Process Charts and Process Sequence Charts: Tools for Process Improvement
 
Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
General Performance Testing Overview
General Performance Testing OverviewGeneral Performance Testing Overview
General Performance Testing Overview
 

More from AgileSparks

More from AgileSparks (20)

What Do Agile Leaders Do by Kurt Bittner
What Do Agile Leaders Do by Kurt Bittner What Do Agile Leaders Do by Kurt Bittner
What Do Agile Leaders Do by Kurt Bittner
 
Distributed Teams by Kevin Goldsmith
Distributed Teams by Kevin GoldsmithDistributed Teams by Kevin Goldsmith
Distributed Teams by Kevin Goldsmith
 
A Back-End Approach to Customer Driven by Adi Gostynski
A Back-End Approach to Customer Driven by Adi GostynskiA Back-End Approach to Customer Driven by Adi Gostynski
A Back-End Approach to Customer Driven by Adi Gostynski
 
Jira Portfolio by Elad Ben-Noam
Jira Portfolio by Elad Ben-NoamJira Portfolio by Elad Ben-Noam
Jira Portfolio by Elad Ben-Noam
 
Agile Hiring at Scale by Yon Bergman
Agile Hiring at Scale by Yon Bergman Agile Hiring at Scale by Yon Bergman
Agile Hiring at Scale by Yon Bergman
 
Are We Really Using Our Resources in The Most Effective Way? by Perry Yaqubo...
Are We Really Using Our Resources in The Most Effective Way?  by Perry Yaqubo...Are We Really Using Our Resources in The Most Effective Way?  by Perry Yaqubo...
Are We Really Using Our Resources in The Most Effective Way? by Perry Yaqubo...
 
Honest Experimentation by Jonathan Bertfield
 Honest Experimentation by Jonathan Bertfield Honest Experimentation by Jonathan Bertfield
Honest Experimentation by Jonathan Bertfield
 
Pango Journey to an Agile Cloud by Yaniv Kalo
Pango Journey to an Agile Cloud by Yaniv KaloPango Journey to an Agile Cloud by Yaniv Kalo
Pango Journey to an Agile Cloud by Yaniv Kalo
 
ClickSoftware Agile Tranistion by Meny Duek
ClickSoftware Agile Tranistion by Meny DuekClickSoftware Agile Tranistion by Meny Duek
ClickSoftware Agile Tranistion by Meny Duek
 
Augury's Journey Towards CD by Assaf Mizrachi
Augury's Journey Towards CD by Assaf Mizrachi Augury's Journey Towards CD by Assaf Mizrachi
Augury's Journey Towards CD by Assaf Mizrachi
 
Kubernetes is Hard! Lessons Learned Taking Our Apps to Kubernetes by Eldad Assis
Kubernetes is Hard! Lessons Learned Taking Our Apps to Kubernetes by Eldad AssisKubernetes is Hard! Lessons Learned Taking Our Apps to Kubernetes by Eldad Assis
Kubernetes is Hard! Lessons Learned Taking Our Apps to Kubernetes by Eldad Assis
 
Creating a Culture of Ownership and Trust with Visibility and Transparency by...
Creating a Culture of Ownership and Trust with Visibility and Transparency by...Creating a Culture of Ownership and Trust with Visibility and Transparency by...
Creating a Culture of Ownership and Trust with Visibility and Transparency by...
 
Real Innovation is with Real Customers by Baat Enosh
Real Innovation is with Real Customers by Baat EnoshReal Innovation is with Real Customers by Baat Enosh
Real Innovation is with Real Customers by Baat Enosh
 
True Continuous Improvement with Toyota Kata by Jesper Boeg
True Continuous Improvement with Toyota Kata by Jesper BoegTrue Continuous Improvement with Toyota Kata by Jesper Boeg
True Continuous Improvement with Toyota Kata by Jesper Boeg
 
Homo-Adaptus Agile Worker by Lior Frenkel
Homo-Adaptus Agile Worker by Lior FrenkelHomo-Adaptus Agile Worker by Lior Frenkel
Homo-Adaptus Agile Worker by Lior Frenkel
 
Intel CHD Case Study by Ronen Ezra
Intel CHD Case Study by Ronen EzraIntel CHD Case Study by Ronen Ezra
Intel CHD Case Study by Ronen Ezra
 
Leading Innovation by Jonathan Bertfield
Leading Innovation by Jonathan BertfieldLeading Innovation by Jonathan Bertfield
Leading Innovation by Jonathan Bertfield
 
Organization architecture autonomy and accountability
Organization architecture autonomy and accountability Organization architecture autonomy and accountability
Organization architecture autonomy and accountability
 
Tribal Unity, Agile Israel 2017
Tribal Unity, Agile Israel 2017Tribal Unity, Agile Israel 2017
Tribal Unity, Agile Israel 2017
 
The mindful manager, Agile Israel 2017
The mindful manager, Agile Israel 2017The mindful manager, Agile Israel 2017
The mindful manager, Agile Israel 2017
 

Recently uploaded

Recently uploaded (20)

Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
 
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
Choosing the Right FDO Deployment Model for Your Application _ Geoffrey at In...
 
The UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, OcadoThe UX of Automation by AJ King, Senior UX Researcher, Ocado
The UX of Automation by AJ King, Senior UX Researcher, Ocado
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM Performance
 
UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2UiPath Test Automation using UiPath Test Suite series, part 2
UiPath Test Automation using UiPath Test Suite series, part 2
 
Designing for Hardware Accessibility at Comcast
Designing for Hardware Accessibility at ComcastDesigning for Hardware Accessibility at Comcast
Designing for Hardware Accessibility at Comcast
 
Demystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyDemystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John Staveley
 
ASRock Industrial FDO Solutions in Action for Industrial Edge AI _ Kenny at A...
ASRock Industrial FDO Solutions in Action for Industrial Edge AI _ Kenny at A...ASRock Industrial FDO Solutions in Action for Industrial Edge AI _ Kenny at A...
ASRock Industrial FDO Solutions in Action for Industrial Edge AI _ Kenny at A...
 
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
 
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya HalderCustom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
Custom Approval Process: A New Perspective, Pavel Hrbacek & Anindya Halder
 
WSO2CONMay2024OpenSourceConferenceDebrief.pptx
WSO2CONMay2024OpenSourceConferenceDebrief.pptxWSO2CONMay2024OpenSourceConferenceDebrief.pptx
WSO2CONMay2024OpenSourceConferenceDebrief.pptx
 
Salesforce Adoption – Metrics, Methods, and Motivation, Antone Kom
Salesforce Adoption – Metrics, Methods, and Motivation, Antone KomSalesforce Adoption – Metrics, Methods, and Motivation, Antone Kom
Salesforce Adoption – Metrics, Methods, and Motivation, Antone Kom
 
IESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIESVE for Early Stage Design and Planning
IESVE for Early Stage Design and Planning
 
Free and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
Free and Effective: Making Flows Publicly Accessible, Yumi IbrahimzadeFree and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
Free and Effective: Making Flows Publicly Accessible, Yumi Ibrahimzade
 
Buy Epson EcoTank L3210 Colour Printer Online.pptx
Buy Epson EcoTank L3210 Colour Printer Online.pptxBuy Epson EcoTank L3210 Colour Printer Online.pptx
Buy Epson EcoTank L3210 Colour Printer Online.pptx
 
The Metaverse: Are We There Yet?
The  Metaverse:    Are   We  There  Yet?The  Metaverse:    Are   We  There  Yet?
The Metaverse: Are We There Yet?
 
SOQL 201 for Admins & Developers: Slice & Dice Your Org’s Data With Aggregate...
SOQL 201 for Admins & Developers: Slice & Dice Your Org’s Data With Aggregate...SOQL 201 for Admins & Developers: Slice & Dice Your Org’s Data With Aggregate...
SOQL 201 for Admins & Developers: Slice & Dice Your Org’s Data With Aggregate...
 
Optimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through ObservabilityOptimizing NoSQL Performance Through Observability
Optimizing NoSQL Performance Through Observability
 
AI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří KarpíšekAI revolution and Salesforce, Jiří Karpíšek
AI revolution and Salesforce, Jiří Karpíšek
 
PLAI - Acceleration Program for Generative A.I. Startups
PLAI - Acceleration Program for Generative A.I. StartupsPLAI - Acceleration Program for Generative A.I. Startups
PLAI - Acceleration Program for Generative A.I. Startups
 

Elad Amit - Examples of Lean Reports and Visibility

  • 1. Examples of Lean Reports and Visibility EladAmit September 2010
  • 2. Cumulative Flow Diagram (a.k.a. CFD) Purpose:Visually depict our work queues and completion trends to allow us to find and fix bottlenecks as well as predict completion velocity
  • 3. Cumulative Flow Diagram (a.k.a. CFD) End Report: Stacked area chart showing per stage, the total estimate for the items in that stage Y-axis total estimate of items X-axis Time (tick per day)
  • 4. Cumulative Flow Diagram (a.k.a. CFD) Example (Day 13): Backlog – 5 Selected – 1 Develop Ongoing – 2 Develop Done – 1 Deploy – 1 Live - 4
  • 5. Cumulative Flow Diagram (a.k.a. CFD) Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per typeNote: in case of requirement, need to aggregate the estimates from the tasks Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)
  • 6. Process Control Chart Purpose:Identify outliers in our process to focus improvement initiatives and reduce special cause variation
  • 7. Process Control Chart End Report: A dot on the chart is a work item which finished on that date. Ex: the dot at the end of the arrow was finished on November 20th and took 20 days to complete Y-axis Actual chronological time it took an item X-axis Time (tick per day)
  • 8. Process Control Chart End Report: The upper control limit (mean +3 std.dev.) Outliers (anything above the upper control limit) clearly marked The mean cycle time for all of the items in the report The lower control limit (mean -3 std.dev.)
  • 9. Process Control Chart Parameters: What portion of the process we want to measure the cycle time for (e.g. from defined to development done, from start of development to testing) Item Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per type Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)
  • 10. Process Control Chart RebasingNeed to allow rebasing of mean, upper and lower control limits to allow the chart to account for changes (e.g. more employees, changes in development processes) Rebasing points due to changes
  • 11. Average Cycle Time Purpose:Identify trends in our delivery velocity
  • 12. Process Control Chart End Report: Line chart with average cycle time per day Y-axis Average cycle time for all items finished on said day X-axis Time (tick per day)
  • 13. Process Control Chart Parameters: What portion of the process we want to measure the cycle time for (e.g. from defined to development done, from start of development to testing) Item Filters: Work item type (e.g. requirement, task, defect)Only one type due to different stages per type Date range Customer Assignee Severity Priority Etc...(preferably have the ability to filter on any attribute of the selected work item type)