Find the simple interest rate per year required to accumulate the
same amount money in 5 years at 15% per year compound interest
The time taken for the money to triple the simple interest of
10% per year is close to
An investment of $10,000 ten years ago has accumulated to 25,000 now. Find the
compound ROR earned on the investment closest to
You deposit $1000 now and you want the account to have a
value as close to $8740 as possible in year 20. Assume the
account earns interest at 10%per year. The year which you
must make a deposit of 1000$
A manufacturer of tygon tubing wants to have
30,000 available 10 years from now
The present worth of $1000 in year 1 and amounts increasing
by $50 per year through year 5 at an interest rate of 10% per
year is closest to
Find the present worth and annual worth of $5000 in year 1
and amounts increasing by 9% per year through year 15. Use
an interest rate of 10% per year
A Dubai sewage company trying is trying to
decide among three alternatives
UAE engineering company is trying to decide between
microprocessors to manufacture. The cost associated with
each microprocessors are shown below
RAK toy company manufactures hover boards. They are
planning to expand their business units and have come up with
2 alternatives. Calculate the future worth of these two. I = 10%
The HCT university lab is a research contractor with NASA for
in-space fuel cell systems that are hydrogen and methanol
based. During the lab research, three equal service machines
to be evaluated. 200 at the end of the year
Two alternatives have been examined on the
basis of their capital cost using I=12%
Bob, a philanthropist is not sure what ROR his gifts
may realise once donated to his favorite charity.
Find the capitalized cost of a present worth of
300,000 annual cost 35000, periodic costs 75,000
5 years. I = 12%
AlAin computer company designs and sells signal
machines. The company is trying to decide on
wether to buy
BHP manufacturing is considering of a
machine for 500,000

More Related Content

What's hot

Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf18010YeashRahman
 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single ProjectNafis Ahmad
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3bAbdulaziz AlSuwaidi
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3bAbdulaziz AlSuwaidi
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysisMohsin Siddique
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Managerial Economics (Chapter 3 - Demand and Supply)
Managerial Economics (Chapter 3 - Demand and Supply)Managerial Economics (Chapter 3 - Demand and Supply)
Managerial Economics (Chapter 3 - Demand and Supply)Nurul Shareena Misran
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of moneyBibek Paudyal
 
Costs Of Production Micro Economics ECO101
Costs Of Production Micro Economics ECO101Costs Of Production Micro Economics ECO101
Costs Of Production Micro Economics ECO101Sabih Kamran
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy Sebghatullah Karimi
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Engineering Economy 17th Edition Sullivan Solutions Manual
Engineering Economy 17th Edition Sullivan Solutions ManualEngineering Economy 17th Edition Sullivan Solutions Manual
Engineering Economy 17th Edition Sullivan Solutions ManualVeronicaIngramss
 

What's hot (20)

Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf
 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single Project
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Managerial Economics (Chapter 3 - Demand and Supply)
Managerial Economics (Chapter 3 - Demand and Supply)Managerial Economics (Chapter 3 - Demand and Supply)
Managerial Economics (Chapter 3 - Demand and Supply)
 
Operations research
Operations researchOperations research
Operations research
 
Chapter-4 Time value of money
Chapter-4  Time value of moneyChapter-4  Time value of money
Chapter-4 Time value of money
 
Costs Of Production Micro Economics ECO101
Costs Of Production Micro Economics ECO101Costs Of Production Micro Economics ECO101
Costs Of Production Micro Economics ECO101
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Engineering Economy 17th Edition Sullivan Solutions Manual
Engineering Economy 17th Edition Sullivan Solutions ManualEngineering Economy 17th Edition Sullivan Solutions Manual
Engineering Economy 17th Edition Sullivan Solutions Manual
 

Viewers also liked

Методические указания по решению инженерных кейсов Лига по горному делу
Методические указания по решению инженерных кейсов Лига по горному делуМетодические указания по решению инженерных кейсов Лига по горному делу
Методические указания по решению инженерных кейсов Лига по горному делуАндрей Изюмников
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)Abdulaziz AlSuwaidi
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting3prem
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04rajeevgupta
 
Topic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment CreteriaTopic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment Creteriashengvn
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problemsvarsha nihanth lade
 
Cost classification
Cost classificationCost classification
Cost classificationpankajmaini
 
case study-capital budgeting
case study-capital budgetingcase study-capital budgeting
case study-capital budgetinginfinite_7
 
75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgetingvarsha nihanth lade
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)tutor2u
 
Capital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on financeCapital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on financeBabasab Patil
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniquesVJTI Production
 
Chapter 09 Capital Budgeting
Chapter 09 Capital BudgetingChapter 09 Capital Budgeting
Chapter 09 Capital BudgetingAlamgir Alwani
 

Viewers also liked (16)

Методические указания по решению инженерных кейсов Лига по горному делу
Методические указания по решению инженерных кейсов Лига по горному делуМетодические указания по решению инженерных кейсов Лига по горному делу
Методические указания по решению инженерных кейсов Лига по горному делу
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
Topic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment CreteriaTopic 1 Npv And Other Investment Creteria
Topic 1 Npv And Other Investment Creteria
 
ROI, NPV and PP
ROI, NPV and PPROI, NPV and PP
ROI, NPV and PP
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems
 
Cost classification
Cost classificationCost classification
Cost classification
 
case study-capital budgeting
case study-capital budgetingcase study-capital budgeting
case study-capital budgeting
 
75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)
 
Capital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on financeCapital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on finance
 
Capital budgeting techniques
Capital budgeting techniquesCapital budgeting techniques
Capital budgeting techniques
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Chapter 09 Capital Budgeting
Chapter 09 Capital BudgetingChapter 09 Capital Budgeting
Chapter 09 Capital Budgeting
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 

Similar to Case study questions Engineering Economics

Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solutionHaris Hassan
 
Review materials for engineering economics
Review materials for engineering economicsReview materials for engineering economics
Review materials for engineering economicsAditya Nugroho
 
Question 1. You can earn $40 in interest on a $1,000 deposit for.docx
Question 1. You can earn $40 in interest on a $1,000 deposit for.docxQuestion 1. You can earn $40 in interest on a $1,000 deposit for.docx
Question 1. You can earn $40 in interest on a $1,000 deposit for.docxmakdul
 
Bethesda Mining Company
Bethesda Mining CompanyBethesda Mining Company
Bethesda Mining CompanyPeachy Essay
 
Capital budgeting problems
Capital budgeting problemsCapital budgeting problems
Capital budgeting problemsNaveen Loyola
 
Homework chapter-5
Homework chapter-5Homework chapter-5
Homework chapter-5Omar Cesar
 
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.Dr. Trilok Kumar Jain
 
Presentation on Time value of money (Lecture 2).pptx
Presentation on Time value of money (Lecture 2).pptxPresentation on Time value of money (Lecture 2).pptx
Presentation on Time value of money (Lecture 2).pptxmhsmncumbatha
 
Fin 515-week-3-problem-set
Fin 515-week-3-problem-setFin 515-week-3-problem-set
Fin 515-week-3-problem-setaagnaa
 
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docx
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docxQUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docx
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docxniraj57
 
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docx
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docxAssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docx
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docxfredharris32
 
Presentation Case Tri Star - Final
Presentation Case Tri Star - FinalPresentation Case Tri Star - Final
Presentation Case Tri Star - FinalSpencer Cheung
 
Complete the math problems below. Show your work. Need today 17 .docx
Complete the math problems below.  Show your work.  Need today 17 .docxComplete the math problems below.  Show your work.  Need today 17 .docx
Complete the math problems below. Show your work. Need today 17 .docxmaxinesmith73660
 
pay back period question.pdf
pay back period question.pdfpay back period question.pdf
pay back period question.pdfzohaibanwar20
 
Interest Factors.pptx .
Interest Factors.pptx                       .Interest Factors.pptx                       .
Interest Factors.pptx .Athar739197
 

Similar to Case study questions Engineering Economics (20)

Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
 
Review materials for engineering economics
Review materials for engineering economicsReview materials for engineering economics
Review materials for engineering economics
 
Question 1. You can earn $40 in interest on a $1,000 deposit for.docx
Question 1. You can earn $40 in interest on a $1,000 deposit for.docxQuestion 1. You can earn $40 in interest on a $1,000 deposit for.docx
Question 1. You can earn $40 in interest on a $1,000 deposit for.docx
 
Bethesda Mining Company
Bethesda Mining CompanyBethesda Mining Company
Bethesda Mining Company
 
Capital budgeting problems
Capital budgeting problemsCapital budgeting problems
Capital budgeting problems
 
Capital budgeting problems
Capital budgeting problemsCapital budgeting problems
Capital budgeting problems
 
Homework chapter-5
Homework chapter-5Homework chapter-5
Homework chapter-5
 
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
 
Hw1
Hw1Hw1
Hw1
 
Presentation on Time value of money (Lecture 2).pptx
Presentation on Time value of money (Lecture 2).pptxPresentation on Time value of money (Lecture 2).pptx
Presentation on Time value of money (Lecture 2).pptx
 
Fin 515-week-3-problem-set
Fin 515-week-3-problem-setFin 515-week-3-problem-set
Fin 515-week-3-problem-set
 
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docx
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docxQUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docx
QUESTION `1. [6 + 8  = 14 Marks.]a) This is a two pe.docx
 
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docx
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docxAssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docx
AssetsLiabilitiesTotal Reserves$50,000Demand Deposits$18.docx
 
Presentation Case Tri Star - Final
Presentation Case Tri Star - FinalPresentation Case Tri Star - Final
Presentation Case Tri Star - Final
 
Complete the math problems below. Show your work. Need today 17 .docx
Complete the math problems below.  Show your work.  Need today 17 .docxComplete the math problems below.  Show your work.  Need today 17 .docx
Complete the math problems below. Show your work. Need today 17 .docx
 
Investment analysis
Investment analysisInvestment analysis
Investment analysis
 
Bus 401 week 3 quiz version c
Bus 401 week 3 quiz version cBus 401 week 3 quiz version c
Bus 401 week 3 quiz version c
 
pay back period question.pdf
pay back period question.pdfpay back period question.pdf
pay back period question.pdf
 
Interest Factors.pptx .
Interest Factors.pptx                       .Interest Factors.pptx                       .
Interest Factors.pptx .
 
ipptchap008.ppt
ipptchap008.pptipptchap008.ppt
ipptchap008.ppt
 

More from Abdulaziz AlSuwaidi

Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)Abdulaziz AlSuwaidi
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)Abdulaziz AlSuwaidi
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Abdulaziz AlSuwaidi
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2Abdulaziz AlSuwaidi
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Abdulaziz AlSuwaidi
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1 Abdulaziz AlSuwaidi
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)Abdulaziz AlSuwaidi
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Abdulaziz AlSuwaidi
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 

More from Abdulaziz AlSuwaidi (17)

Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)
 
Lo4b(arif)
Lo4b(arif)Lo4b(arif)
Lo4b(arif)
 
Lo4a(arif)
Lo4a(arif)Lo4a(arif)
Lo4a(arif)
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)
 
2. ethical theories part 2 (1)
2.  ethical theories part 2 (1)2.  ethical theories part 2 (1)
2. ethical theories part 2 (1)
 
1. ethical theories part 1
1. ethical theories part 11. ethical theories part 1
1. ethical theories part 1
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1
 
lo 2 handout 1 (2) PART 2
 lo 2 handout 1 (2) PART 2 lo 2 handout 1 (2) PART 2
lo 2 handout 1 (2) PART 2
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1
 
Lo 2 b factors
Lo 2 b   factorsLo 2 b   factors
Lo 2 b factors
 
Lo 2 a key terminologies
Lo 2 a   key terminologiesLo 2 a   key terminologies
Lo 2 a key terminologies
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 

Recently uploaded

Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 

Recently uploaded (20)

Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 

Case study questions Engineering Economics

  • 1. Find the simple interest rate per year required to accumulate the same amount money in 5 years at 15% per year compound interest
  • 2. The time taken for the money to triple the simple interest of 10% per year is close to
  • 3. An investment of $10,000 ten years ago has accumulated to 25,000 now. Find the compound ROR earned on the investment closest to
  • 4. You deposit $1000 now and you want the account to have a value as close to $8740 as possible in year 20. Assume the account earns interest at 10%per year. The year which you must make a deposit of 1000$
  • 5. A manufacturer of tygon tubing wants to have 30,000 available 10 years from now
  • 6. The present worth of $1000 in year 1 and amounts increasing by $50 per year through year 5 at an interest rate of 10% per year is closest to
  • 7. Find the present worth and annual worth of $5000 in year 1 and amounts increasing by 9% per year through year 15. Use an interest rate of 10% per year
  • 8. A Dubai sewage company trying is trying to decide among three alternatives
  • 9. UAE engineering company is trying to decide between microprocessors to manufacture. The cost associated with each microprocessors are shown below
  • 10. RAK toy company manufactures hover boards. They are planning to expand their business units and have come up with 2 alternatives. Calculate the future worth of these two. I = 10%
  • 11. The HCT university lab is a research contractor with NASA for in-space fuel cell systems that are hydrogen and methanol based. During the lab research, three equal service machines to be evaluated. 200 at the end of the year
  • 12. Two alternatives have been examined on the basis of their capital cost using I=12%
  • 13. Bob, a philanthropist is not sure what ROR his gifts may realise once donated to his favorite charity.
  • 14. Find the capitalized cost of a present worth of 300,000 annual cost 35000, periodic costs 75,000 5 years. I = 12%
  • 15.
  • 16.
  • 17.
  • 18. AlAin computer company designs and sells signal machines. The company is trying to decide on wether to buy
  • 19. BHP manufacturing is considering of a machine for 500,000